Guidelines for Scaffolding near Service Lines. Version 1 March 2014

Similar documents
Electricity Safety (Electric Line Clearance) Regulations 2010

Safety: Role of a. Safety Observer. 30 th March th MARCH 2011 ISSUE 3 UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

Field Instruction. All Horizon Power workers who work in and around excavations.

CPCCLSF3001A Licence to erect, alter and dismantle scaffolding intermediate level

VICTORIAN SERVICE & INSTALLATION RULES MANAGEMENT COMMITTEE

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10

High voltage for apparatus under Safe Access Rules and statutory regulations is defined as being greater than 1000V ac or 1500V dc.

Fall Prevention For Scaffolders

SAFE WORK METHOD STATEMENT

Contractor s Guide to Applying for Permit to Dig/Excavate

Customer Connection Guide. Document number SOP Issue number 9 Status Approver

ELECTRIC LINE CLEARANCE PLAN

Network Safeworking Rules and Procedures

Scaffolding Procedures

METERING GUIDE PART 1 METERING GENERAL

CONTRACTOR WHS HAZARD STANDARD TRAFFIC MANAGEMENT EXTERNAL USE ONLY

OSHA Subpart V: Power Transmission and Distribution. Cleveland State University Work Zone Safety and Efficiency Transportation Center

Engineering Recommendation G81 Part 7 Issue

Skills and Training Guideline

Consequences Workers put in dangerous positions Fall

WHS Management Plans

SAFE WORK METHOD STATEMENT

Building over or close to a public sewer

Guideline for the erection of Supaloc Steel Trusses Pre- Delivery preparation by the supplier Installing Supaloc Steel roof trusses...

Electrical Safety Management Plan (ESMP)

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

Demolition Safety!!!!

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation.

Ensure your own actions reduce risks to health and safety

NTW.1 Network Utilities

Code of Engineering Practice for Works on, Near or Adjacent to the Luas Light Rail System

Jemena Electricity Networks (Vic) Ltd

HANDING-OVER CERTIFICATE - SCAFFOLDING

Specifications for the Secondary Installation of Communication Equipment on MLGW Transmission Structures

BP OIL -- TOLEDO REFINERY

Apply for Working at Heights Permit

Human Resources Team People & Organisational Development. On-Call and Call out Policy

JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) CS-OHS-11

GUIDANCE ON THE SELECTION OF APPROPRIATE WORK EQUIPMENT FOR WORK AT HEIGHT ACTIVITIES WITHIN A COLD STORE ENVIRONMENT

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National

Construction Material Processors Association Inc.

Design Governance Rules BOP325.23

Copies of the written program may be obtained at Where are copies of this written plan kept? (Insert building/room, etc.).

your guide to completing an application for a new or replacement water connection from your property to an existing water main

What you need to know about 6 Star. 6 Star. for new homes, home renovations, alterations, additions and relocations

Supervision of Trainees Holding a Limited Certificate

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES

GUIDELINES FOR MANAGING MOBILE PLANT NEAR PEDESTRIANS ON ROADWORK SITES

ComEd Customer Requirements for Proper Installation of Metering Equipment Residential and Commercial Customers

Bridge Strikes from Road Vehicles or Waterborne Vessels

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

C D M R e g u l a t i o n s

Insulation and Building Treatments (Cavity Wall Insulation) Qualification Specification

Guide to Alterations and Work at Premises We Rent Out

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

1 August 2017 United Energy Ring Fencing Strategy

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision

For the 2008 Code, the minimum clear distances were revised to reflect an accurate metric conversion (also known as a soft conversion).

ELECTRO-FENCE. Fence Protection System. System Manual. EF_System_V1.1

Health & Safety Policy Estate Services

Specifications for Residential Overhead Electric Service Installation

Control of Equipment on Masts, Towers and Rooftops BOP018.8

SHE 002 Method Statements and Risk Assessments

Contractor Induction Manual

Supervision Guideline for Electrician to Lineworker Apprentices

Weekly Operating Notice, Periodical Operating Notice and the Sectional Appendix

Walking & Working Surfaces / Back Safety and Ergonomics

Preventing Electrocutions:

Supervision of Persons who are not Limited Certificate Holders

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1.

CAL/OSHA ELECTRICAL HIGH VOLTAGE

Clearances and conductor spacings and a safe access for a.c. switchyards

BUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS. March 2014

Eurobitume UK. Site Inspection for Delivery of Bitumen

EFFECTIVE DATE: November 1, 2011, unless a later date is cited at the end of a section. [ NMAC - Rp,

STATEMENT OF METHODOLOGY AND CHARGES FOR CONNECTION TO SP DISTRIBUTION LTD AND SP MANWEB PLC S ELECTRICITY DISTRIBUTION SYSTEMS

219 Make sure your own actions reduce risks to health and safety

3. GENERAL INFORMATION AND REQUIREMENTS

The safe management and control of Temporary Works

CONSTRUCTION ENVIRONMENTAL HEALTH & SAFETY EXHIBIT EQUIPMENT SAFETY

Click on the relevant state and open the OHS authority website.

Education Infrastructure Service. Asbestos Management Process

Safety barrier to a deck located adjacent to a retaining wall at Oraka Beach Road, Mahia

Overview SEMPW306. Deal with incidents and contingencies within the railway environment

DOMESTIC ELECTRICAL INSTALLATION PERIODIC INSPECTION REPORT (FOR A SINGLE DWELLING) B ADDRESS AND DETAILS OF THE INSTALLATION Address: SPECIMEN

RIS RIS-1800-ENE. Rail Industry Standard for Network and Depot Interface Management Isolation Documentation. Rail Industry Standard

Section 2: Underground

Cranes and Derricks Standard Summary. April, 2010

Basic Service. This Section provides information regarding a. Introduction

Level 2 NVQ Diploma in Associated Industrial Services Occupations Passive Fire Protection (Construction)

HOW TO SAFELY REMOVE ASBESTOS

ANDREW DEANE Richard Wengle Architect Inc. Development planning comments were not received at the time this agenda was printed.

Assessment. Challenge Assessment for Restricted Certificate of Competence. Advanced Scaffolding Elementary Scaffolding.

Ecological Mitigation and Management Plan

Vegetation Management Plan

Leasing of Railway Land

TI/131 TECHNICAL ADVICE ON THE SITING OF CLASS 1 TYPE OIL STORAGE INSTALLATIONS FOR SINGLE FAMILY DWELLINGS

Loss Prevention Standard

How to Become an Accredited Service Provider (ASP) Andrew Loukopoulos

Transcription:

Guidelines for Scaffolding near Service Lines Version 1 March 2014

Erecting, dismantling and use of scaffold near service lines This guideline has been developed to provide guidance for the erection, dismantling and use of scaffolding near insulated service cables/lines. For those situations where the scaffold is also within 4.6 metres of overhead powerlines refer to the ESV document, Guidelines for Scaffolding near Overhead Powerlines. The movement of scaffolding components near powerlines can put workers in a dangerous or hazardous situation and the risks must be controlled. Energy Safe Victoria (ESV) and WorkSafe Victoria consider the skill set of an ESV Spotter (required for mobile plant) is not adequate to control No Go Zone risks associated with scaffolding work. A service cable or line, as defined by the Electrical Safety (Installations) Regulations 2009 is the final span or section of a low voltage aerial line or underground line that is part of the supply network of a major electricity company that is connected to a point of supply. If the erected scaffold or erection/dismantling process causes scaffold components to come within 4.6 metres of any service line (Service Line No Go Zone) then assessment and discussion with the power distribution company is necessary before the work can proceed. The power company may issue a Permit To Work (PTW) or provide advice on clearance distances if a PTW is not necessary. Image 1: Plan view of No Go Zones with regard to service lines. Work shall be carried out under the conditions detailed in a PTW that has been issued by the power distribution Company. The PTW issued by the power distribution company may require the scaffolding company to have a competent person to act as an observer to monitor the actual scaffolding erection /dismantling work and compliance with the PTW conditions. The observer must have no other Page 2 of 5

duties while they are monitoring the works and be authorised to stop work immediately if they observe that workers or scaffold components are likely to come within an unsafe distance of the service line or if any of the conditions set out in the PTW are not being met. The power distribution company may charge for the works they undertake to provide safe access (eg de-energisation, cable relocation, installing insulation on cables) through an agreed contractual arrangement. Power Distribution Company Assessment for PTW The considerations from the power distribution company when assessing if a PTW is required will depend on a number of factors, including the following: the finished erected position of the scaffold in relation to the service line, insulation condition of the service line, integrity of service line attachment points, the nature or type of work that is proposed to be completed from the scaffold. The power company shall provide written approval to the applicant/representative that the erection, dismantling or use of scaffolding can be undertaken without a PTW, providing the highest point of the scaffold is not higher than: A. 1.5 m above the point at which the service line attaches to the building and no scaffolding components are placed above the service cable or closer than: B. 1.5 metres horizontally to the service line or its point of attachment to the building and C. 3.7 metres below the service line Image 2: Diagrammatic representation of when a PTW may not be required. Note: Any time where the erection, dismantling and use of scaffolding is closer than 1.5 metres horizontally, or closer than 3.7metres below the service line, or anywhere above the service line then a PTW shall be required and other conditions may need to be applied. Page 3 of 5

General requirements when using scaffold near service lines 1. A Safe Work Method Statement (SWMS) must be completed prior to the commencement of any scaffolding work near service lines and state the controls that will be implemented to ensure the workers or scaffold components do not come within an unsafe distance of the service lines. The SWMS should include what actions are required in the event of an accidental contact with service lines & powerlines. 2. Persons undertaking scaffolding erection/dismantling work above or closer than 4.6 metres to the overhead service line (No Go Zone), shall seek the permission of the power company before the work commences. Work shall be carried out in accordance with any conditions listed on the PTW and the SWMS. 3. Service lines should be de-energised when erecting, altering or dismantling scaffolding within the No Go Zone. However, depending on specific site and equipment conditions and if other risk controls can be applied, work may be undertaken while the service lines are energised, only after a Permit To Work (PTW) has been issued by the power company. 4. The PTW is location and task specific and will only apply for a specific period of time. This means that separate PTW s could be required for the a. erection of the scaffold, b. work from the scaffold, c. dismantling of the scaffold. 5. The power company may require a suitably competent person to observe the work being undertaken to ensure contact and or damage does not occur to the service line and attachments. The competence of this person is such that they.. a. understand how the specific scaffolding is erected and b. understand how the components are assembled and c. have suitable vision and communication to be able to observe and warn against any hazardous situation d. understand the conditions detailed in the PTW e. understand the SWMS controls and how these will ensure that the PTW conditions are maintained and complied with. f. have no other duties whilst observing the work 6. In some circumstances hoarding or shade cloth may be required to be secured to the face and or ends of the scaffold as a barrier. a. Hoarding can be 9mm marine ply, 12mm C/D construction ply, concrete form ply or similar. Shade cloth must be of an industrial grade; b. Fitted sheets of hoarding/shade cloth need to be installed in a manner to minimise the gaps, this will prevent inadvertent protrusion of materials that may contact live conductors. Effective risk management controls shall be applied with regard to any gaps in the structure. c. Permit conditions may require the hoarding / shade cloth to have the top edge extend above the work platform adjacent to the electrical line 7. Where erected scaffolding encloses a service line, the service line would generally be de-energised during the erection/ dismantling of the scaffold. Note: Power companies may choose to vary this condition when other specific risk controls are being applied. 8. Insulated service lines can be re-energised and remain in service through an erected scaffold with the addition of mechanical protection and or barriers as specified by the PTW conditions. Page 4 of 5

No Go Zone requirements for scaffold erection near service lines Distance from scaffold to service lines < 300mm 300 to 1500mm 1501 to 4600 mm De-energise PTW SWMS service line SWMS Competent Person PTW Mechanical *(PTW & mechanical SWMS protection on service line Competent Person protection on service line) * The power company may advise that a PTW is not required after assessing the condition of the service line and has determined that the work being undertaken can be completed safely. How to find your distribution company 1. You should be able to identify the electricity distribution company from the electricity bill for the property or 2. Go to the web site link below and type in the suburb and the distribution company/s for that area will be displayed along with the contact phone number. In some areas there may be more that one distribution company that supplies the suburb. This will be resolved by discussion with one of the companies. http://jemena.com.au/outages/find-my-distributor.aspx Contact numbers for distribution company enquiries. (No Go Zone) CitiPower 13 12 80 Jemena 13 16 26 Powercor 13 24 12 SP AusNet 13 17 99 United Energy 13 20 99 Warning: Printed copies of this document MAY NOT BE THE LATEST. The most up-to-date version is located on the ESV Website. Page 5 of 5