Tunnel. Immersed Tunnels

Similar documents
Construction Technology B (CON4313)

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

Ground Freezing for Tunnel, Shafts, and Adits

Experts in tunneling with Tunnel Boring Machines

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

TRANSPORTATION RESEARCH FORUM March A State-of-the-Art of Underground Construction In Urban Areas

Boletín Geotécnico Artículo

TBM rescue projects using shafts and ground freezing

WORK IN PROGRESS. Technical Note. Technical description of key issues of Tunnel solutions. 1. Introduction

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Introduction to Tunnel Construction

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

What is SFT? OÜ ANKURTUNNEL Tõnu Ader FinEst Link Final Conference on 7th of February

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

WHY THE CHANNEL TUNNEL WAS BUILT

An introduction to. pipe jacking

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

Pipe Jacking. Japan Sewage Works Association

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

Performance review of a pipe jacking project in Hong Kong

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK

Tabulated overview of the obligation to submit the use and occupancy notice or building design documentation and to apply for use and occupancy permit

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

POSTER PAPER PROCEEDINGS

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

Concrete Pipe Jacking

Large-diameter bored piles and Large-hole drillings Applications

Compaction and Jet Grouting

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION

Shieldhall Tunnel construction of the first shaft, service chamber, cut and cover and the tunnel boring machine launch chamber at Craigton

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

SELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley

introduction Introduction to Bridge and Tunnel Engineering Characteristics of ideal bridge Ideal location Factors affecting bridge type Classification

6 Preliminary Assessment of Construction Method and Constructability Issues

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

Design Data 4. Jacking Concrete Pipe

MIAH, INC SEABED TRENCHING OVERVIEW. P.O. Box 3685 Salem, OR (503) FAX# (503)

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Tel: Neil: Tony: Website:

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

Design Data 4M. Jacking Concrete Pipe

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

The Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions

BREAKTHROUGH AND BURIAL OF TBMS ON THE BRISBANE AIRPORT LINK PROJECT

4th International Engineering and Construction Conference - July 28, 2006

Risk Management of the Restoration of Shanghai Metro Line 4

Section WATER LINE IN TUNNELS

Grouting Bilfinger Spezialtiefbau GmbH

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

Description of Phase 2 Modified Design

Hallandsås Ridge Tunnel, Sweden

2 Technology of closed-face tunnelling machines

Promoters. Presentation. Tunnel. Tim Smart Head of Engineering & Operations. 20 th October

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

Promoters Tunnel Presentation

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

South-to-North Water Diversion( middle route ) China Institute of Water Resources and Hydropower Research(IWHR)

Hardrock Tunnel Boring Machines

Topic 3: 1 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt

TBM Performance and Development State in Korea

Singapore Safety Day. Keller civil works team for a large petrochemical project, Malaysia

Principles for Tunnel Design

Geotechnical and civil engineering contractors

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

Ground Movement Analysis of Pipe Roof Construction in Soft Clay

Design of Izmir Bay Crossing Bridge

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling

SECTION A1 EXCAVATION AND BACKFILL GENERAL

IMPACTS OF TUNNELS IN THE UK. Non-technical summary

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

Gautrain construction update

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

TBM Selection and Specification

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

POSTER PAPER PROCEEDINGS

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!


Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Section TUNNEL GROUT. A. Mix design requirements, testing, furnishing, and production of grout for:

Introduction to Utilidors, Power Distribution and Communication Systems in Cold Regions

Brief Discussion on Application of Guided Boring Non-excavation Technology in Repair of Sewage Pipes Mei-Di SHAN1,a,*, Feng ZHOU2,b

Forensics by Freezing

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

3 rd Edition of the ITA Tunnelling Awards - the winners 2017!

Transcription:

Tunnel Tunnels are underground spaces, usually, in a tubular shape with substantial lengths. They can either be man-made or natural and can be used as passageways, storages, carriageways and utility ducts. They can also be used for mining, water supply, sewerage, flood prevention, civil defense, and many other purposes. Man-made tunnels can be constructed in numerous ways. Shallow tunnels are usually constructed by burying tunnel structures in trenches dug for the purpose. This is a preferred method of tunnelling as long as space is available and the operation will not cause disturbance to surface activities. Otherwise, tunnels can be constructed by boring through the ground. Short tunnels are usually bored manually or by using light machines, such as roadheader, backhoe, etc. If the ground is too hard to bore, drill-and-blast method is frequently used. For long tunnels, it is more economical and much faster to use tunneling boring machines (TBM) which work on full face at the same time. In uniform massive rock formations without fissures or joints, tunnels can be bored without any temporary supports to hold up the tunnel crowns. However, more than frequently, temporary supports are required because of the presence of fissures and joints in the rock mass. Figure 1 shows the temporary supports for a 4-lane highway tunnel. In recent years, it has become popular to spray a layer of shotcrete to serve as the primary lining to protect the newly exposed surface and to support the tunnel crowns as well. The shotcrete is frequently reinforced by steel meshes and, if necessary, braced by steel lattices. In soft ground, it has become popular to use shield machines for boring and reinforced concrete segments, see Figure 2, for lining. The largest shield machine ever, 14.14m in diameter, was used in constructing the Tokyo Trans-Bay Highway (Tokyo Wan Aqua-Line) between Kawasaki City and Kisarazu City of Japan (completed in 1997). There are various types of shield machines available to serve different purposes. Figure 3 shows the multi-face shield machine first used in constructing the Osaka Business Park Station of No. 7 Subway Line of Osaka, Japan (completed in 1995). The machine is 17m in width and 7.5m in height and has three cutters which operated independently. Theoretically, the two side cutters can be detached from the center cutter upon the completion of station excavation leaving the center cutter to continue boring towards the next station. However, this technique was not used in this particular case and the machine was used for constructing the Osaka Business Park Station only. Immersed Tunnels For tunnels to be constructed across waters, an alternative to boring is to lay tunnel boxes directly on the pre-prepared seabed. These boxes, made of either steel or reinforced concrete, are prepared in dry docks and sealed at their ends by the use of bulkheads. They will float as the docks are flooded and will be towed to the site by tugboats. The boxes are then flooded to allow them to sink to the seabed after they are properly positioned. Usually, immersed tunnels are buried in shallow trenches dug for

the purpose and covered by ballast so they will not be affected by the movement of the water. The joints between sections of the tunnel will be made watertight by using rubber gaskets and water is pumped out for the tunnel to be ready for services. Among the numerous immersed tunnels, the newly completed one (3510m) for φresund Link between Denmark and Sweden is second to the cross-bay tunnel (5825m) for the Bay Area Rapid Transit of San Francisco in length. Micro-tunnels Small size tunnels, such as sewer lines and water mains, are usually installed by jacking steel or concrete pipes into the ground as illustrated in Figure 4. The soil core inside the tubes can be removed manually or by using moles, which are essentially small shield tunneling machines. The alignment of the pipes is continuously monitored and adjusted. With the moles guided by computerized navigation system, it is possible to align pipes to a precision within 100mm regardless of length. This technique has been used for jacking pipes as large as 2m or so in diameter for distances more than 100 meters. Pipes with smaller sizes can be jacked to distances of more than 300 meters. Special Tunneling Techniques Auxiliary measures are frequently required to ensure the safety of tunnels during boring in soft ground. In the early days, compressed air was a popular choice. It is seldom used nowadays because improper decompression may cause aeroembolism (diver s disease) to workers. Instead, grouting and ground freezing are now favored. In the Central Artery Project (scheduled to be completed in 2004) in Boston, ground freezing is carried out to permit three tunnels to be bored under the railway tracks leading to Boston's South Station Railway Terminal. There are a total of roughly 1,600 freezing pipes installed to depths varying from 13.7m (45 feet) to 16.8m (55 feet) and the volume of frozen soil is more than 60,000 cubic meters. This could be the largest undertaking of this nature. An underpass, scheduled to be completed in the year 2001, is being constructed beneath the Taipei International Airport by using the Endless-Self-Advancing method patterned by Uemura Engineering Co., Ltd of Japan (Moh et al, 1999). As illustrated in Figure 5, to minimize ground settlements and to ensure the safety of air traffic, interlocked steel pipes are first jacked into the ground to form a protective shelter. The soil core inside the shelter is excavated for 400mm per lift. Concrete segments are moved consecutively in sequence into the space created, one by one, by jacking against the segments behind. Each time only one segment is jacked forward and the jacking force is taken by the frictional resistance acting on all the rest of segments. Cables are anchored to the first and the last segments so the force acting on the last segment can be transmitted to the segments in front of the one being jacked. The movements of segments resemble the movements of centipedes and, in theory, there is no limit on the length of tunnel to be installed. The Longest Tunnels The longest tunnel of any kind is the New York City West Delaware water supply tunnel (completed in 1944). It runs for 105 miles from the Rondout Reservoir into the

Hillview Rreservoir in Yonkers, New York. The longest rail tunnel is Seikan Tunnel (53.6km) in Japan (completed in 1985). The longest road tunnel is Saint Gotthard Tunnel (16.9 km) in Switzerland (completed in 1980). The title will be taken over by Laerdal Tunnel (24.5 km) in Norway in the year 2001 upon its completion. The longest undersea tunnel is the Channel Tunnel (49.4 km of which 38 km is undersea) across the English Strait. It runs from Folkestone on the Britain side to Calais on the France side. There are two running tunnels plus one service tunnel in the center, 7.6m and 4.8m in internal diameter, respectively. The Tunnel was officially inaugurated on May 6, 1994 when Her Majesty the Queen of England and President Mitterrand of France became the first official passengers to pass by train between the two countries. Eurotunnel has a concession from the British and French governments to run the Tunnel until 2052. Shuttle trains will carry up to 180 cars, or 120 cars together with 12 coaches. Freight shuttles can carry 28 lorries. It will take 35 minutes to cross the strait. References Moh, Z. C., Hsiung, K. I., Huang, P. C. and Hwang, R. N., (1999) Underpass beneath Taipei International Airport, Proc., Conference on New Frontiers and Challenges, 8~12 November, Bangkok, Thailand Za-Chieh Moh and Richard N. Hwang

Figure 1 Temporary Supports to a 4-lane Road Tunnel ( Courtesy of RESA Engineering Corporation) Figure 2 Reinforced Concrete Lining for a Tunnel

Figure 3 Multi-face Shield Tunneling Machine ( Courtesy of Hitachi Zosen Corporation ) Slurry Treatment Plant Control Unit Pipe being installed Mole Jack Figure 4 Micro-tunneling and Pipe Jacking Technique

Jacks Figure 5 Endless-Self-Advancing Tunneling Technique