APPENDIX H. Stabilization Measure Fact Sheets

Similar documents
EC-04 ROLLED EROSION CONTROL PRODUCTS (RECP)

Erosion Control Blankets

EC-7 GEOTEXTILES AND MATS. Objectives. Potential Alternatives

SECTION 806 WATER COURSE AND SLOPE EROSION PROTECTION

Suitable Applications Where concentrated flow of surface runoff must be conveyed down a slope in order to prevent erosion.

SECTION EROSION CONTROL MATTINGS AND COMPONENTS

ARMORMAX ENGINEERED EARTH ARMORING SOLUTIONS

Best Management Practice (BMP) Guidance Manual

ROLLED EROSION CONTROL PRODUCTS (RECP)

APPENDIX C DURING CONSTRUCTION BMP TABLES

Index. outlet protection Rev. 12/93

Earth Dikes and Drainage Swales

TEMPORARY STREAM DIVERSION

Rock Sock (RS) Rock Sock height.

WATER QUALITY. Our Focus Today. Erosion Control Technologies & Solutions. What is Soil Erosion. Federal Regulations

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads

EROSION CONTROL GENERAL NOTES EC JAN 2017 C.B.

Erosion Control Solutions

Brush layering construction

SECTION EROSION AND SEDIMENTATION CONTROLS

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

Common Construction-Site BMPs Quick Reference Guide

Diversion Dikes. Fe=0.95

STREAM STABILIZATION PLAN

CITY OF URBANA CLASS 2 EROSION CONTROL PERMIT STANDARD DETAILS

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

Temporary Watercourse Crossing: Fords

THE EVOLUTION OF EROSION CONTROL TECHNOLOGY. Welcome! Pete Hanrahan, CPESC E. J. Prescott, Inc. Gardiner, Maine

IN T R A / M IN T R A M

PART 1 GENERAL REQUIREMENTS

The Construction General Permit and Erosion Prevention and Sedimentation Control

Temporary Watercourse Crossing: Culverts

ITEM 750 ROCK FILTER DAMS

Temporary Stream Crossing

Temporary Stream Crossing

Tips with Creation of your Erosion and Sediment Control Plan

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives

P R E M I E R M A N U F A C T U R E R O F E R O S I O N C O N T R O L P R O D U C T S

Sediment Control Practices

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Figure Inlet protection (Source: Minnesota DOT)

PROJECT SCREENING MATRIX: A User s Guide

LINED WATERWAY OR OUTLET (Feet) Code 468

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

Slide Presentation. Exercise (if there s time) Field Demonstration. Various Pollutants of Concern: Why Use BMPs? 10/02/2013

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

York County STORMWATER LUNCH & LEARN

GRASS-LINED CHANNEL (acre) CODE 840

ACTIVITY: Silt Fence ES 14

Erosion Control State Standards Sampling of Material Innovations

BMP-5. A temporary sediment barrier consisting of a synthetic filter fabric stretched across and attached to supporting posts and entrenched.

Your Guide to Natural Erosion Control and Revegetation Solutions. BioNet. Natural Solutions for Natural Problems.

ROLLED EROSION CONTROL. systems brochure

BMP-17. To provide for the conveyance of concentrated surface runoff water to a receiving channel or system without damage from erosion.

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies

Case Study 5. Willow Creek Concrete Plank Ford

Organic Filter Tubes. Fe= (Depends on soil type)

Section Soil Erosion Protection Tender No. [ ] Page 1

Post Construction Erosion Controls

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.

Lake Lorelei Property Owners Association Rip Rap Standards Recommendations. Revision 0 February 2018

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

Properly constructing and maintaining a road drainage system is the most effective ways to reduce flood damage

Case Study 15. Moonlight Crossing Concrete Box Vented Ford

Flexamat Erosion Control Mat

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 836 SEEDING AND EROSION CONTROL WITH TURF REINFORCING MAT January 18, 2013

Chapter 10. Conduit Outlet Structures Introduction General Layout Information

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Slash Water Bar Video

MATERIAL SPECIFICATION Manufactured Ditch Checks

Training on Roads for Water and Resilience

I. Detailed alternatives for stabilization

Flexamat Tied Concrete Block Mats

BMP 6.4.4: Infiltration Trench

Filter Tube Barriers (Instream)

Turf Reinforcement Mats

METROPOLITAN UTILITIES DISTRICT No Page: 1 of 10

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

GREEN SHORELINE PROJECTS ON LONG ISLAND

A Complete Retaining Wall Solution >

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C

EROSION AND SEDIMENT CONTROL

Inlet Protection. Fe= (Depends on soil type)

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

E&S BMP DESIGN. Working Toward a Better Conclusion

Specifications for the Selection and Application of Erosion Control Blanket on Slopes or Channels

Fabric Drop Inlet Protection

TDOT DESIGN DIVISION DRAINAGE MANUAL CHAPTER V ROADSIDE DITCHES & STREAMS

TEMPORARY SEDIMENT TRAP CODE

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

Non-Vegetative Stabilization

Sediment Retention Fiber Roll (SRFR) General Usage and Installation Guidelines

Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [2]

WQ-08 ENHANCED DRY SWALE

Chapter 5.5 Inlets, Outlets, and Flow Control

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site.

Development of transition mat scour protection design methodology and comparison to the state-of-the-practice

Transcription:

APPENDIX H Stabilization Measure Fact Sheets

Prepared for The Boeing Company 5800 Woolsey Canyon Road, MC: 033-T436 Canoga Park, CA 91304-1148 Appendix H Stabilization Measure Fact Sheets Prepared by 6701 Center Drive West Suite 550 Los Angeles, CA 90045 Project Number SB0363R September 21, 2011

CONTENTS 1. Erosion Control Blanket (Bank Stabilization)... H3 1.1 Site Suitability... H3 1.2 Design Considerations... H3 1.3 Construction Considerations... H4 1.4 Maintenance and Operations... H4 2. Turf Reinforcement Mat (Bank Stabilization)... H5 2.1 Site Suitability... H5 2.2 Design Considerations... H6 2.3 Construction Considerations... H6 2.4 Maintenance and Operations... H6 3. Riprap Check Structures (In-Stream Grade Control)... H7 3.1 Site Suitability... H7 3.2 Design Considerations... H8 3.3 Construction Considerations... H8 3.4 Maintenance and Operations... H8 4. Energy Dissipation Riprap... H9 4.1 Site Suitability... H9 4.2 Design Considerations... H10 4.3 Construction Considerations... H10 4.4 Maintenance and Operations... H10 5. Vegetated Riprap (Bank Stabilization)... H11 5.1 Site Suitability... H11 5.2 Design and Construction Considerations... H11 5.3 Maintenance and Operations... H12 6. References... H13 H2

1. EROSION CONTROL BLANKET (BANK STABILIZATION) Erosion Control Blankets (ECBs) are a temporary rolled erosion control product consisting of flexible nets or mats, manufactured from both natural and synthetic materials, which can be brought to a site, rolled out, and fastened down on a slope. ECBs are typically manufactured of fibers such as straw, wood, excelsior, coconut, or a combination, and then stitched to or between geosynthetic or woven natural fiber netting. Various grades of biodegradable fibers and netting can be specified depending on required durability and environmental sensitivity (Salix, 2004). Erosion Control Blanket Placed at Boeing SSFL; Geosyntec, 2010 ECBs are primarily used for short-term protection of slopes and stream banks for: Prevention of surficial soil erosion Protection for new vegetation Reduction of flow velocities Stabilization of disturbed areas Considerations related to suitability, design, construction, and operations and maintenance of ECBs are included in the sections below. Erosion Control Blanket from E-SenSS; Salix, 2004 1.1 Site Suitability ECBs are used for temporary slope and channel protection and should not be planned for long-term use. Additionally, ECBs should not be used for applications involving high stresses and scour conditions. Refer to Table II in the Restoration, Mitigation, and Monitoring Plan (RMMP) for stability thresholds for ECBs. In addition to the stability thresholds, ECB site selection should include consideration of the following: ECBs are not suitable for excessively rocky sites ECBs are not suitable where vegetation mowing will occur ECBs are not suitable for areas with heavy foot traffic 1.2 Design Considerations There are a variety of ECB material types. This fact sheet includes biodegradable materials only. Nondegradable material blankets are considered turf reinforcement mats (TRMs) and are described in the TRM fact sheet. Refer to manufacturer information to determine what material type is ideal for the application the ECB is slated for. H3

Organic or biodegradable materials are ideal for areas where revegetation is planned to provide permanent slope stabilization. Biodegradable materials may be suited for low-velocity or high-velocity situations, depending on the material type. Low velocity materials include looser-weave natural vegetative fibers, and typically have a one to two season lifetime. These should be used for slopes of moderate grade and length and are not designed for severe conditions. High velocity materials include high-strength and denser nettings or meshes, and have a one to five season lifetime. These ECBs may be used for steeper slopes and higher velocities. Biodegradable ECB materials include: Jute Excelsior (curled wood fiber) Straw Wood Fiber Coconut Fiber Blanket or Mesh Straw Coconut Fiber Blanket Vegetation is recommended to stabilize the channel and to keep the ECB in place. Vegetation can be included in the ECB design as follows: Live pole cuttings, crimping, and seeding can be used to secure ECB in addition to manufacturer recommended staples Fascine bundles can be utilized to breakup long slopes Fiberschines can be utilized for toe of slope stabilization 1.3 Construction Considerations ECBs should be installed as described below such that damage to channels and streambanks during installation is minimized. Preparation of site: Grade and shape the area of installation Remove rocks, clods, vegetation and other obstructions prior to placement of ECB to ensure direct contact with soil Loosen top 2-3 inches of soil to promote vegetative growth Seed the area prior to placement of ECB for revegetation according to landscaping plans ECBs must be anchored in place by one of the following practices: U-shaped wire staples, minimum 11 gauge wire steel with 8 inch legs and 2 inch crown Metal stake pins of 0.188 inch diameter steel with 1.5 inch steel washer at head of pin, 8 inches in length Triangular wooden stakes Staples and metal stakes should be installed flush with soil surface 1.4 Maintenance and Operations Maintenance requirements for ECBs are included in Table VII in Section 6 of the RMMP. Also refer to manufacturer instructions for specific operations related to different ECB materials. H4

2. TURF REINFORCEMENT MAT (BANK STABILIZATION) Turf Reinforcement Mats (TRMs) are similar to Erosion Control Blankets (ECBs), but they are permanent, designed to resist shear and tractive forces, and are usually specified for banks subjected to flowing water. They are designed to enhance the natural ability of vegetation to protect against erosion. The mats are composed of ultraviolet (UV) stabilized polymeric fibers, filaments, and/or nettings, integrating together to form a three-dimensional matrix. As such, vegetated TRMs can resist higher tractive forces than either vegetation or TRMs can alone (Salix, 2004). TRMs are largely used for long-term or permanent applications pertaining to the following: Prevention of channel and streambank soil erosion Protection of soil from scouring forces Enhancement of vegetative development and growth Reduction of flow velocities TRMs do not lose efficacy when soil boundaries shift or subside following installation (Salix, 2004). Photos of Turf Reinforcement Mats from E-Senss; Salix, 2004 Considerations related to suitability, design, construction, and operations and maintenance of TRMs are included in the sections below. 2.1 Site Suitability TRMs are designed for long-term slope stability and vegetation establishment purposes. While TRMs can withstand higher velocities than ECBs, they should not be used for applications involving high stresses and scour conditions. Refer to Table II in the RMMP for TRM stability thresholds. Note: TRMs will protect vegetation, but may delay establishment due to lower soil temperatures. H5

2.2 Design Considerations TRMs typically consist of polypropylene, polyethylene, nylon, or other non-degradable synthetic materials. There are a variety of TRM types, including those listed below. Refer to manufacturer information to determine what material type is ideal for the application the TRM is slated for. Non-biodegradable and synthetic materials used for TRM applications include: Plastic netting Plastic mesh Synthetic fiber with netting Bonded synthetic fiber Combination synthetic and biodegradable materials Vegetation is recommended to be included to stabilize the channel and to keep the TRM in place. Vegetation can be incorporated into the TRM design as follows: Live pole cuttings, crimping, and seeding can be used to secure TRM in addition to manufacturer recommended staples Fascine bundles can be utilized to breakup long slopes Fiberschines can be utilized for toe of slope stabilization 2.3 Construction Considerations Installation of TRMs should be conducted as described in the lists below. Preparation of site: Grade and shape the area of installation Remove rocks, clods, vegetation and other obstructions prior to placement of TRM to ensure direct contact with soil TRMs can be installed after seeding the underlying soil or can be installed below soil fill, which is then seeded TRMs must be anchored in place by one of the following practices: U-shaped wire staples, minimum 11 gauge wire steel with 6-12+ inch legs Metal stake pins of 0.188 inch diameter steel with 1.5 inch steel washer at head of pin, 8 inches in length Staples and metal stakes should be installed flush with soil surface See manufacturer guidelines for required anchor size and installation TRMs should be installed such that damage to channels and streambanks during installation is minimized. 2.4 Maintenance and Operations Maintenance requirements for TRMs are included in in Table VIII in Section 6 of the RMMP. Also refer to manufacturer instructions for specific operations related to different TRM materials. H6

3. RIPRAP CHECK STRUCTURES (IN-STREAM GRADE CONTROL) Riprap check structures (also called check dams) are ramps or low weirs with aprons made from riprap or small boulders. Check structures allow for a smaller effective slope of the channel, reducing the velocity of flows. They are typically installed in series. The structures are built by placing rock fill within an existing channel, keying the structure into the bed and bank if the channel is erosive, and maintaining a low flow point at the center of the structure. They are constructed such that the upstream slope of the rock fill is steeper than the downstream slope. Wellconstructed riprap check structures can prevent or retard channel bed erosion and upstream progression of "knickpoints" and headcuts, reduce shear stresses on potentially erosive banks located immediately upstream, as well as provide pool habitats for sedimentation and aquatic biota. Check structures can be installed for temporary or permanent purposes. Applications include: Temporary grade control in eroding channels that will be filled or stabilized at a later date. Riprap Check Structure photos from E-SenSS; Salix, 2004 Erosion prevention in temporary channels where a non-erodible lining is not practicable. Temporary erosion protection in vegetated channels as vegetation is getting established. Permanent grade control in small open channels with constructed spillway and hardened riprap apron Considerations related to suitability, design, construction, and operations and maintenance of check structures are included in the sections below. 3.1 Site Suitability Check structures can be used for both temporary and permanent applications for a range of slope features. Refer to Table II in the RMMP for check structure stability thresholds. In addition to the parameters listed above, check structure site selection should include consideration of the following: Check structures should not be used in already-vegetated channels, as damage to plant life may occur H7

Check structures should not be used in streams with extended base flows 3.2 Design Considerations Check structures will result in a reduced effective slope, which will slow down flows but will also reduce the capacity of the system. Capacity should be calculated with the reduced slope to determine that it is sufficient. If needed, the ditch or swale into which check structures are being installed may be widened. Generally, the toe of the upstream check structure should be constructed at the same elevation as the top of the downstream structure. The center of the check structure should be lower to direct flows to the middle of the channel. The check structures should be sized such that high flows travel safely over the check damage without upstream flooding or damage to the structure. Small pools will form between check structures in series. Backwater from a downstream check structure should reach the toe of the check structure directly upstream. Riprap check structures are typically constructed of 8 to 12 inch rocks. 3.3 Construction Considerations Considerations should be taken during construction to maximize the efficiency of the check structures and reduce damage to the channel. Riprap or boulders should be installed mechanically or by hand. The check structure must span the entire width of the channel. If installed in series, the first check structures should be installed approximately 16 feet from culvert outlets, then at regularly spaced intervals thereafter. For steep slopes and high flows, the following measures should be taken to reinforce the check structures: Non-woven geotextile fabric should be installed under and around the check dam to prevent erosion around the structure. Structure sections should be keyed into the channel banks and bottom. Extended rock aprons may need to be installed upstream or downstream of the structure. 3.4 Maintenance and Operations Maintenance requirements for check structures are included in in Table VI in Section 6 of the RMMP. H8

4. ENERGY DISSIPATION RIPRAP Energy dissipation riprap includes both loose riprap stones and hardened (grouted) riprap. These measures can be used for erosion protection at the outlets of culverts, conduits, or channels, as well as protection on channel banks. Loose riprap outlet protection consists of an apron of placed riprap stone located at the outlet of a concentrated discharge, as described above. Riprap aprons can be used to reduce surface water velocity and dissipate energy of flow exiting a storm drain pipe before it flows into erodible receiving channels. A benefit of utilizing loose riprap, as opposed to grouted riprap or gabions, is that the material can potentially fall into scour holes that may be created from high discharge events, thus making it a more adaptive measure. Grouted riprap consists of riprap mixed with concrete grout which fills the interstitial space between the stones. It is a hardened stabilization measure which is appropriate to use when the anticipated design velocities and shear stresses are higher than the stability thresholds associated with vegetated measures, such as ECBs and TRMs, and loose riprap. Grouted riprap is used primarily for energy dissipation at the outlets of culverts, conduits, or channels. Grouted riprap can also be used to reinforce the bed and banks of channels susceptible to erosion. When utilized for outlet energy dissipation, grouted riprap aprons should be designed with sufficient toe down so that bed scour does not undermine the structure. 4.1 Site Suitability Loose riprap; http://www.p2pays.org/ref/02/01524/urbst95.jpg Grouted riprap; http://www.fs.fed.us/eng/pubs/html/wr_p/99771804/images/fig11.jpg Energy dissipation riprap should be used where discharge velocities are erosive and can be used for a variety of flow conditions. Stability thresholds are included in Table II in the RMMP. In addition, the following points should be taken into consideration: Energy dissipation riprap may negatively impact the channel habitat If subjected to freeze and thaw, grouted riprap may erode H9

4.2 Design Considerations Depth of flow, roughness, gradient, side slopes, discharge rate, and velocity should be considered in the design of the energy dissipation. The sizing of the riprap structure is dependent on the forces expected at the culvert outlet. Where flows are conveyed in open channels such as ditches and swales, use the estimated discharge rate for selecting the apron length and rock size. Design flows should be same as the culvert or channel design flow but should be at least equivalent to the 5 year flow for temporary structures planned for one rainy season, or to the 10 year peak flow for temporary structures planned for two or three rainy seasons. Other design considerations include: Larger diameter stone is heavier and can resist higher shear stresses without movement. Durable, angular rock provides the best erosion control results. Inadequate drainage can lead to water build-up behind grouted riprap, resulting in breakage of grouted riprap. 4.3 Construction Considerations Considerations should be taken during construction to maximize the efficiency of the check structures and reduce damage to the channel. Filter fabric should be installed prior to placement of loose or grouted riprap. Secure filter fabric into place by keying fabric into slope. Riprap or boulders should be installed mechanically or by hand; rocks should not be dumped into the energy dissipation riprap location. Riprap apron should be aligned with the receiving channel and should be installed straight throughout its length. 4.4 Maintenance and Operations Typically, maintenance of energy dissipation riprap is not intensive, other than after large storms and high flows. High flows can wash away rock and leave area susceptible to erosion, and riprap should be repaired immediately after such events to ensure that the riprap is operating properly. Refer to Table X in Section 6 of the RMMP for other maintenance activities. H10

5. VEGETATED RIPRAP (BANK STABILIZATION) Vegetated riprap is a layer of stone and/or boulder armoring that is vegetated using pole planting, brushlayering, and livestaking techniques. The goal of this method is to increase the stability of the bank, while simultaneously establishing riparian growth within the rock and overhanging the water, to provide shade, water quality benefits, and wildlife habitat. Vegetative riprap combines the widely accepted, resistive and continuous rock revetment techniques with deeplyplanted biotechnical techniques. Vegetation has the added benefit of potentially increasing bank tensile strength due to roots, stems, and branches (Salix, 2004). Also refer to the Energy Dissipation fact sheet for more information about riprap systems. 5.1 Site Suitability Vegetated riprap is appropriate for high-velocity sites, and adding vegetation allows for ecological benefits. For stability thresholds for vegetated riprap, see Table II in the RMMP. Vegetated Riprap; both from E-SenSS (Salix 2004) In addition, the following points should be taken into consideration: Vegetation can reduce stream flow capacity, so this approach should not be used if flow capacity is of concern. 5.2 Design and Construction Considerations There are a variety of riprap vegetation methods. Vegetation methods are summarized below (Salix, 2004): Willow Bundles: This installation method requires installing long poles and branches between riprap. While simple, the cuttings that are not in contact with soil will not become established, reducing the vegetative benefit. Bent Poles: This method may be used with filter fabric and involves planting of live willow logs or poles in riprap. Poles may vary in length from five to sixty feet. Brushlayering and Pole Planting: This method allows for the most immediate ecological benefits, but it is the most complex. This involves pole planting through riprap as well as installing brush at an opposing angle to poles to provide added structural support while poles are becoming established. H11

If riprap needs to be revegetated, the following method may be used: Joint or Live Stake Planted Riprap: This method involves planting of live wood stakes into preexisting riprap. 5.3 Maintenance and Operations Typically, maintenance of vegetated riprap is not intensive, other than after large storms and high flows. High flows can wash away rock and leave the area susceptible to erosion, and riprap should be repaired immediately after such events to ensure that the riprap is operating properly. Refer to Table IX in Section 6 of the RMMP for other maintenance activities. H12

6. REFERENCES California Department of Transportation (Caltrans), 2003. Construction Site Best Management Practices Manual. California Department of Transportation (Caltrans), 2006. Construction Site BMP Fact Sheet: Cellular Confinement System. California Stormwater Quality Association (CASQA), 2003. California Stormwater Quality Association Stormwater Best Management Practice Handbook: Construction. January, 2003. Hanes Geocomponents, 2008. Terracell: Design Guidelines for Erosion Control. Denver, CO Urban Drainage and Flood Control District, 2010. Urban Storm Drainage Criteria Manual: Volume 3, Best Management Practices. November 2010. Salix Applied Earthcare (Salix), 2004. E-SENSS Manual: Environmentally-Sensitive Streambank Stabilization. U.S Environmental Protection Agency (USEPA), 2007. National Management Measures to Control Nonpoint Source Pollution from Hydromodification. July 2007. H13