EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities

Similar documents
TEMPORARY FACILITIES

Section: TABLE OF CONTENTS Temporary Facilities. 04.A General B Access and Haul Roads

EM385 Construction Safety and Health Certification Course Section 14 Material Handling, Storage, and Disposal

EM385 Construction Safety and Health Certification Course Section 23 Demolition

EM385 Construction Safety and Health Certification Course Section 2 - Sanitation

SECTION 200 CLEARANCES

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision

References. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A

Barricades. Preparer: Owner: Approver: EHS Specialist EHS Team Leader Site Director J. Walker (Electronic Signature on File)

2600SEG135 SAFETY STANDARD FOR INDUSTRIAL LADDERS AND STAIRCASES IN BUILDINGS

PROGRAM OVERVIEW WALKING/WORKING SURFACE INDUSTRIAL SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

PRIVATE ROAD AND DRIVEWAY STANDARDS Development Standard #1 (Rev 7/18)

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SECTION 503 TEMPORARY PAVEMENT RESTORATION

Section 7: Specifications

1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY

SECTION PORTLAND CEMENT CONCRETE

Iron Ore Company of Canada Health, Safety & Environment

SAFEGUARDS DURING CONSTRUCTION

Model Safety Program

Section 1 OBC FADS /13 Access to Parking Areas

ICC/NSSA STANDARD FOR THE DESIGN AND CONSTRUCTION OF STORM SHELTERS ICC

Electric Service Standards

Review of Plans and Specs from a Constructability Perspective

Water Pollution Control for Work in Sensitive Areas

IM 0291(108)0 UNION COUNTY INDEX OF SHEETS. Index of Sheets. Estimate of Quantities. Table of Fence Quantities. Details for Right-of-Way Fence

PADMOUNT EQUIPMENT LOCATIONS / CLEARANCES

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

STANDARD PRACTICE INSTRUCTION

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION ASPHALT PAVING AND SURFACING

Risk Control at United Fire Group

T a b l e o f C o n t e n t s

SECTION TEMPORARY FACILITIES AND CONTROLS

Savard Labor & Marine Staffing, Inc. Fall Prevention Program Rev3/14

DIVISION 07 THERMAL AND MOISTURE PROTECTION ROOFING

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

53.27 MAINTENANCE AND PREPARATION OF GRAVEL SURFACE ROADS AND SNOW REMOVAL AND ICE CONTROL ON GRAVEL AND PAVED SURFACES

Worksite Safety Update Promoting safety in road construction

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS

PIP STE05501 Fixed Ladders and Cages Design Guide

Chapter WAC Construction Work

Gas meter clearances and service installation requirements

SECTION EARTHWORK

New Jersey Turnpike Authority

MONTEZUMA COUNTY COLORADO ROAD AND BRIDGE STANDARD SPECIFICATIONS

SOIL TRACKING PREVENTION DEVICE TYPE A

Allen & Sherriff Architects, Inc Yonge Street, S202, Richmond Hill, Ontario L4C 5K9 Tel: Fax: File Ref.

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES

Reliant Holdings Ltd Safety Management System

CONCRETE TILE PAVERS

RHINO-STOP Modular Vehicle Impact Barriers

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

SPECIAL SPECIFICATION 3289 High Friction Surface Treatment

Roadway Surfaces and Traffic Control Elements

Effective Date: 10-January Table of Contents

Series - 1

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting:

Health & Safety Policy and Procedures Manual SECTION 8 FALL PROTECTION PROGRAM

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

FOR HISTORICAL REFERENCE ONLY

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

Environmental Codes of Practice. Sewage Interception Pipeline

Zoning Permits 11-1 ZONING PERMITS

City of Logan Sanitary Sewer Design Standards

ASPEN LAKES DEVELOPMENT CORP.

City of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements

Fall Protection Program For Working on Flat Roofs

Guardrail Clamping System. Installation Instructions

Subdivision 1 Responsibility of the Owner

Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011

Draft. Not yet Approved

TITLE 17 REFUSE AND TRASH DISPOSAL REFUSE

SECTION STAINLESS STEEL WALL PANELS

Section 7 Roadway GENERAL REQUIREMENTS I. TYPICAL SECTION...7-1

DIVISION 4100 SITEWORK

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

AS The External Waterproofing Membranes Standard

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SECTION TRENCHING & BACKFILLING

SECTION STORMWATER POLLUTION PREVENTION

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

SUBDIVISION SECTION STREET DESIGN MANUAL

SECTION GENERAL EXCAVATION

ATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

2007 Title 24 Accessibility Code Updates and ADA Issues

SECTION EARTHWORK

WOOD I-JOIST AWARENESS GUIDE

Fall Protection Safety Program and Training Materials

Special Specification 6148 Inverted Profile Pavement Marking (Audible)

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

B STEEL BEAM GUIDE RAIL - OPSS 552

B STEEL BEAM GUIDE RAIL - OPSS 721

Transcription:

EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities

OSHAcademy Course 500 Study Guide EM 385 SAFETY AND HEALTH CERTIFICATION COURSE SECTION 4 Edited by: Steven Geigle, M.A., CET, CSHM Copyright 2013 Geigle Safety Group, Inc. All rights reserved. No portion of this text may be reprinted for other than personal use. Any commercial use of this document is strictly forbidden. The source for this study guide is USACE 385 1 1, including Change 7 July 2012. The course is designed to be studied off line as a tool for preparation to successfully complete the OSHAcademy Course 500 final exam. OSHAcademy Occupational Safety and Health Training A division of Geigle Safety Group, Inc. 1915 NW Amberglen Parkway, Suite 400 Beaverton, Oregon 97006 www.oshatrain.org instructor@oshatrain.org 971.217.8721 Disclaimer: The content of this study guide is for training purposes only. Federal law prohibits public employees and agencies from endorsing any product, service or enterprise. See 5 CFR Section 2635.702; DoD Joint Ethics Regulations Section 3 209 and Section 3 300. This training is not recognized, approved, nor endorsed by any person or agency of local, state, or federal government. OSHAcademy is not affiliated with the U.S. Dept of labor, Occupational Safety and Health Administration (OSHA) or any other local, state, or federal government agency.

BEFORE you read through this section, review the study questions at the end of this section. HUNT for the answers to the questions as you read through the section. Doing this will make the training a little more interesting and help assure a high score on the course final exam! 04.A GENERAL 04.A.01 Plans for the layout of temporary construction buildings, facilities, fencing, and access routes and anchoring systems for temporary structures shall be submitted to and approved by the GDA. > See 09.A.19 for temporary building spacing requirements; Section 11 for temporary power distribution approval requirements; and Section 24 for temporary ramp, trestle, scaffold, and platform approval requirements. 04.A.02 The design and construction of temporary structures shall consider the following loadings (Reference American Society of Civil Engineers (ASCE) 7 98): a. Dead and live loads; b. Soil and hydrostatic pressures; c. Wind loads; d. Rain and snow loads; e. Flood and ice loads; and f. Seismic forces. 04.A.03 Trailers and other temporary structures used as field offices, as personnel housing, or for storage shall be anchored with rods and cables or by steel straps to ground anchors. The anchor system shall be designed to withstand winds and must meet applicable state or local standards for anchoring mobile trailer homes. 04.A.04 Fencing and warning signs. a. Temporary project fencing (or a substitute acceptable to the GDA and delineated in the APP) shall be provided on all projects located in areas of active use by members of the public, including those areas in close proximity to family housing areas and/or school facilities. b. Fencing shall extend from grade to a minimum of 48 in (1.2 m) above grade and shall have a maximum mesh size of 2 in (50 mm). Fencing shall remain rigid/taut with a minimum of 200 lbs (.9 kn) of force exerted on it from any direction with less than 4 in (100 mm) of deflection. c. Signs warning of the presence of construction hazards and requiring unauthorized persons to keep out of the construction area shall be posted on the fencing. At minimum, signs shall be posted every 150 ft (45.7 m). Fenced sides of projects that are less than 150 ft (45.7 m) shall, at minimum, have at least one warning sign. > See also Section 8.

d. Depending upon the nature and location of the project site, the GDA may determine that fencing is not required. This will be based on a risk analysis of public exposure and other project specific considerations, and will be included in the applicable AHA. In those locations where the GDA has determined fencing is not required, signs, warning of construction hazards, shall be conspicuously posted. 04.A.05 Temporary Work Camps (Floating plants excluded). a. All sites used for temporary work camps shall be adequately drained. They shall not be subject to periodic flooding nor located within 200 ft (61 m) of swamps, pools, sink holes, or other surface collections of water unless adequate mosquito control methods have been implemented. The sites shall be graded, ditched, and rendered free from depressions in which water may become a nuisance. b. Sites shall be sized to prevent overcrowding of necessary structures. c. The grounds and open areas surrounding the shelters shall be maintained free of rubbish, debris, waste paper, garbage, or other refuse. d. Shelters will provide protection from the elements, and each room used for sleeping purposes shall contain at least 50 ft2 (4.6 m2) of floor space for each occupant and at least 7 ft 6 in (2.3 m) ceilings. e. Beds, cots, or bunks, and suitable storage facilities (such as wall lockers for clothing and personal articles) shall be provided in every room used for sleeping purposes. Beds shall be spaced not closer than 36 in (91.4 cm) both laterally and end to end and shall be elevated at least 12 in (30.4 cm) from the floor. Double decked bunk beds shall be spaced not fewer than 48 in (121.9 cm) both laterally and end to end with a minimum space of not fewer than 27 in (68.5 cm) between the upper and lower bunk. Triple deck bunks are prohibited. f. Floors shall be constructed of wood, asphalt, or concrete. Wooden floors shall be of smooth and tight construction. Floors shall be kept in good repair. g. All wooden floors shall be elevated not less than 1 ½ ft (0.45 m) above the ground level at all points to prevent dampness, permit free circulation of air beneath, and for easier and safer maintenance. h. Living quarters shall be provided with windows that may be opened for purposes of ventilation. i. All exterior openings shall be effectively screened with 16 mesh material and screen doors shall be equipped with self closing devices. j. Temporary sleeping quarters shall be heated, cooled, ventilated, lighted, and maintained in a clean and safe condition. k. Sleeping quarters must comply with applicable provisions of the National Fire Protection Agency (NFPA) 101 Life Safety Code. 04.A.06 Unless otherwise indicated, throughout this manual, lumber dimensions are given in nominal sizes.

04.B ACCESS/HAUL ROADS 04.B.01 Access/haul roads shall be designed in accordance with current engineering criteria. Prior to construction, the Contractor shall provide the GDA with a copy of the Access/Haul Road plan for review and acceptance. Work on the haul road shall not commence until the GDA has accepted the plan. The plan shall address the following items: a. Equipment usage, traffic density, and hours of operation; b. Road layout and widths, horizontal and vertical curve data, and sight distances; c. Sign and signalperson requirements, road markings, and traffic control devices; d. Drainage controls; e. Points of contact between vehicles and the public, and safety controls at these points of contact; f. Maintenance requirements, including roadway hardness and smoothness and dust control; and g. Hazards adjacent to the road, such as bodies of water, steep embankments, etc. 04.B.02 No employer shall move, or cause to be moved, any equipment or vehicle upon an access or haul road unless the roadway is constructed and maintained to safely accommodate the movement of the equipment or vehicle involved. 04.B.03 When road levels are above working levels, berms, barricades, or curbs shall be constructed to prevent vehicles overrunning the edge or end of embankment. Berms/curbs shall be constructed to one half the diameter of the tires of the largest piece of equipment using the roadway. 04.B.04 Roadways shall have a crown and ditches for drainage. Water shall be intercepted before reaching a switch back or large fill and be led off. 04.B.05 Haul roads shall be constructed to widths suitable for safe operation of the equipment at the travel speeds proposed by the Contractor and accepted by the GDA. 04.B.06 All roads, including haul roads, shall be posted with maximum speed limits. 04.B.07 An adequate number of turn outs shall be provided on single lane roads with two way traffic. When turnouts are not practical, the Contractor shall provide a traffic control system to prevent accidents.

04.B.08 Whenever possible, use a right hand traffic pattern on two way haul roads. 04.B.09 Curves. a. All curves shall have open sight lines and as great a radius as practical. b. Vehicle speed shall be limited on curves so that vehicles can be stopped within one half the visible distance of the roadway. c. The design of horizontal curves shall consider vehicle speed, roadway width and surfacing, and super elevation. 04.B.10 Grades. a. When necessary, based on grade and machine and load weight, machines shall be equipped with retarders to assist in controlling downgrade descent. b. Truck haul roads should be kept to less than a 10% grade. There should be no more than 400 ft (121.9 m) of grade exceeding 10%. c. The maximum allowable grade shall not exceed 12%. 04.B.11 Lighting shall be provided as necessary. 04.B.12 Traffic control lights, barricades, road markings, signs, and signalpersons for the safe movement of traffic shall be provided in accordance with the DOT Federal Highway Administration's Manual on Uniform Traffic Control Devices and this Section. 04.B.13 Roadway hardness, smoothness, and dust control shall be used to maintain the safety of the roadway. 04.B.14 All roads shall be maintained in a safe condition and eliminate or control dust, ice, and similar hazards. 04.B.15 The deposition of mud and or other debris on public roads shall be minimized to the extent possible and in accordance with local requirements.

SECTION STUDY QUESTIONS BEFORE you read through this section, review the section study questions below. HUNT for the answers to the questions as you read through the section. Doing this will make the training a little more interesting and help assure a high score on the course final exam! 1. Trailers and other temporary structures used as field offices must: 2. Temporary project fencing shall extend from grade to above grade. 3. Signs warning of the presence of construction hazards and requiring unauthorized person to keep out shall be posted at every feet of fencing. 4. Depending upon the nature and location of the project site, the GDA may determine that temporary project fencing is not required. 5. The design and construction of temporary structures shall consider all of the following loading, EXCEPT: 6. Trailers and other temporary structures used as field offices, as personnel housing, or for storage shall be anchored with rods and cables or by steel straps to ground anchors. 7. All sites used for temporary work camps shall not be subject to periodic flooding nor located within (61 m) of swamps, pools, sink holes, or other surface collections of water unless adequate mosquito control methods have been implemented. 8. Whenever possible, use a traffic pattern on two way haul roads. 9. Truck haul roads should be kept to less than a grade, and the maximum allowable grade shall not exceed. 10. To maintain the safety of the roadway, all of the following will be used, EXCEPT: