CCR Rule Report: Initial Inflow Design Flood Control System Plan For Ash Basin B At Brayton Point Power Station

Similar documents
ENVIRONMENTAL ENGINEERING LAND SURVEYING

CHOLLA POWER PLANT FLY ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_InflowFlood_002_

ENVIRONMENTAL ENGINEERING LAND SURVEYING

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

Inflow Design Flood Control System Plan for Louisa Generating Station CCR Impoundment. MidAmerican Energy Company

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

CHOLLA POWER PLANT BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_Inflowflood_003_

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

CCR Certification: Initial Written Post-Closure Plan (d) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD

APPENDIX III Hydrologic and Hydraulic Evaluations

CCR Certification: Initial Inflow Design Flood Control System Plan for the

CCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

CCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

Inflow Design Flood Control System Plan

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

Run-on and Run-off Control System Plan

Inflow Design Flood Control System Plan

Coal Combustion Residuals Inflow Design Flood Control System Plan

CCR Annual Inspection (b) for the West Ash Pond at the F. B. Culley Generating Station. Revision 0

Initial Inflow Design Flood Control System Plan Holding Pond

Inflow Design Flood Control System Plan Plant McDonough-Atkinson Ash Pond 3 (AP-3) and Ash Pond 4 (AP-4)

Initial Inflow Design Flood Control System Plan

INITIAL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN Sibley CCR Landfill Sibley Generating Station East Johnson Rd Sibley, Missouri

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

Via October Mr. William Neal, P.E. Technological Specialist DTE Electric Company One Energy Plaza Detroit, MI 48226

D. B. Wilson Station CCR Landfill

Inflow Design Flood Control System Plan

Pond Closure - Case Study[TP1]

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

CCR Certification: Initial Written Post-Closure Plan (d) for the East Ash Pond at the F.B. Culley Generating Station.

Via October Mr. William Neal, P.E. Technological Specialist DTE Electric Company One Energy Plaza Detroit, MI 48226

Green Station CCR Surface Impoundment

CCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

CCR Rule Operating Criteria Closure Plan

CCR Annual Inspection (b) for the Ash Pond at the San Miguel Plant. Revision 0

CCR Certification: Amended Inflow Design Flood Control System Plan for the. East Ash Pond. at the. F.B. Culley Generating Station.

HAZARD POTENTIAL CLASSIFICATION REPORT

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that

D.E. KARN GENERATING FACILITY BOTTOM ASH POND HAZARD POTENTIAL CLASSIFICATION ASSESSMENT REPORT. Assessment Report. Pursuant to 40 CFR 257.

CCR Certification: Initial Inflow Design Flood Control System Plan for the. East Ash Pond. at the. F.B. Culley Generating Station.

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS

Run-on and Run-off Control System Plan

WELSH POWER PLANT ASH LANDFILL. Run-on and Run-off Control System Plan

Coal Combustion Residuals (CCR) Run-on and Run-off Control System Plan

Initial Inflow Design Flood Control System Plan

STRUCTURAL STABILITY ASSESSMENT

Inflow Design Flood Control System Plan

McElroy s Run Impoundment Initial Hazard Potential Classification Assessment Report

McElroy s Run Impoundment Coal Combustion Residual Annual Report

INITIAL HAZARD POTENTIAL CLASSIFICATION ASSESSMENT REPORT

McElroy s Run Impoundment Structural Stability Assessment Report

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS

TABLE OF CONTENTS LEGAL NOTICE

Inflow Design Flood Control System Plan

LANDFILL POST-CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS

Stantec Consulting Services Inc Lebanon Road, Cincinnati, OH 45241

Inflow Design Flood Control System Plan

CCR Certification: Initial Inflow Design Flood Control System Plan for the

Site Description. CCR Rule Initial Inflow Design Flood Control System Plan (cont.) 2

STRUCTURAL STABILITY ASSESSMENT

Upper Lightning Lake Water Level Management Environmental Assessment Worksheet. Attachment D Design Report for Upper Lightning Lake

ALLIANT ENERGY WISCONSIN POWER AND LIGHT COLUMBIA ENERGY CENTER CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT. January 15, 2016

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2

STRUCTURAL STABILITY ASSESSMENT. Bremo Power Station CCR Surface Impoundment: North Ash Pond STRUCTURAL STABILITY ASSESSMENT

Application for a Dam Permit Ash Basin No. 1

ALLIANT ENERGY WISCONSIN POWER AND LIGHT NELSON DEWEY GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT MCDONOUGH ASH POND 1 (AP-1) GEORGIA POWER COMPANY

CVEN 339 Summer 2009 Final Exam. 120 minutes allowed. 36 Students. No curve applied to grades. Median 70.6 Mean 68.7 Std. Dev High 88 Low 24.

Inflow Design Flood Control System Plan

Northern Indiana Public Service Company (NIPSCO) 2723 East 1500 North, Wheatfield, Indiana USA Golder Associates Inc.

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT MCMANUS ASH POND A (AP-1) 40 CFR (c)(1)(i)-(xii)

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio

TVA Colbert Fossil Facility Ash Disposal Pond 4

CLOSURE PLAN. CFR (b) Document No. GERS Stingy Run Flyash Pond. Gavin Plant Cheshire, Ohio. October, 2016

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

INSPECTION REPORT. Third Annual RCRA CCR Unit Inspection Report January 2018 WASTE DISPOSAL AREA SURFACE IMPOUNDMENT

ALLIANT ENERGY INTERSTATE POWER AND LIGHT OTTUMWA GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

INITIAL HAZARD POTENTIAL CLASSIFICATION ASSESSMENT REPORT. Fly Ash Impoundment KCP&L Greater Missouri Operations Company Sibley Generating Station

Harrison Landfill Run-on and Run-off Control System Plan

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY

CCR DESIGN CRITERIA DEMONSTRATION MITCHELL LANDFILL MITCHELL POWER GENERATION PLANT MARSHALL COUNTY, WEST VIRGINIA. Prepared For:

Coal Combustion Residuals Unit Structural Stability Assessment

CCR Certification: Initial Structural Stability Assessment (d)

North Omaha Ash Landfill Run-on and Run-off Control System Plan

INFLOW DESIGN FLOOD CONTROL PLAN

Report Issued: July 26, 2017 Revision 1

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station

Transcription:

Submitted to Brayton Point Energy, LLC 1 Brayton Point Rd., Somerset, MA 02725 Submitted by AECOM 1001 Highlands Plaza Drive West Suite 300 St. Louis, MO 63110 CCR Rule Report: Initial Inflow Design Flood Control System Plan For Ash Basin B At Brayton Point Power Station

AECOM CCR Rule Report: Initial Inflow Design Flood Control System Plan for Ash Basin B at the Brayton Point Power Station 1-1 1 Introduction This Coal Combustion Residual (CCR) Rule Report documents that the initial inflow design flood control system plan for Ash Basin B at the Brayton Point Energy, LLC Brayton Point Power Station meets the requirements specified in 40 Code of Federal Regulations (CFR) 257.82. Ash Basin B is located near Somerset, Massachusetts in Bristol County, approximately 0.1 miles northeast of the Brayton Point Power Station, in an area known as the Ash Basin Complex. Ash Basin B is used to manage bottom ash discharge water at the Brayton Point Power Station. Ash Basin B is an existing CCR surface impoundment as defined by 40 CFR 257.53. The CCR Rule requires that the initial inflow design flood control system plan for an existing CCR surface impoundment be prepared by October 17, 2016. The plan must document how the inflow design flood control system has been designed and constructed to meet the requirements of 40 CFR 257.82 and be supported by appropriate engineering calculations. The owner or operator of the CCR unit must obtain a certification from a qualified professional engineer stating that the inflow design flood control system meets the requirements of 40 CFR 257.82. The owner or operator must prepare an inflow design flood control system plan every five years.

AECOM CCR Rule Report : Initial Inflow Design Flood Control System Plan for Ash Basin B at the Brayton Point Power Station 2-1 2 Initial Inflow Design Flood Control System Plan 40 CFR 257.82 (a) The owner or operator of an existing CCR surface impoundment must design, construct, operate, and maintain an inflow design flood control system as specified in paragraphs (a)(1) and (2) of this section. (1) The inflow design flood control system must adequately manage flow into the CCR unit during and following the peak discharge of the inflow design flood specified in paragraph (a)(3) of this section. (2) The inflow design flood control system must adequately manage flow from the CCR unit to collect and control the peak discharge resulting from the inflow design flood specified in paragraph (a)(3) of this section. (3) The inflow design flood is: (i) For a high hazard potential CCR surface impoundment,, the probable maximum flood; (ii) For a significant hazard potential CCR surface impoundment,, the 1,000-year flood; (iii) For a low hazard potential CCR surface impoundment,, the 100-year flood; or (iv) For an incised CCR surface impoundment, the 25-year flood. (b) Discharge from the CCR unit must be handled in accordance with the surface water requirements under 257.3-3. Analyses completed for the initial inflow design flood control system plan of Ash Basin B are described in the following subsections. Data and analysis results in the following subsections are based on spillway design information shown on design drawings, construction information, topographic surveys, information about operational and maintenance procedures provided by Brayton Point Energy, LLC, and field measurements collected by AECOM. The analysis approach and results of the hydrologic and hydraulic analyses are presented in the following subsections. Ash Basin B is an incised CCR surface impoundment, as defined by 40 CFR 257.53. Therefore, in accordance with 40 CFR 257.82(a)(3)(iv), the Inflow Design Flood (IDF) is the 25-year flood. 2.1 Initial Inflow Design Flood Control Systems ( 257.82(a)) An initial inflow design flood control system plan, supported by a hydraulic and hydrologic analysis, was developed for Ash Basin B by evaluating the effects of a 24-hour duration design storm for the 25-year IDF using a hydraulic HydroCAD (Version 10) computer model and a starting water surface elevation of 22.0 feet. The computer model evaluated Ash Basin B s ability to collect and control the 25-year IDF under existing operational and maintenance procedures. Rainfall data for the 25-year IDF was obtained from the Northeast Regional Climate Center (NRCC). The NRCC rainfall depth is 6.04 inches. The HydroCAD model results for Ash Basin B indicate that the CCR unit has sufficient storage capacity and spillway structures to adequately manage (1) flow into the CCR unit during and following the peak discharge of the 25-year IDF and (2) flow from the CCR unit to collect and control the peak discharge resulting from the 25- year IDF. The peak water surface elevation is 22.1 feet during the IDF, and the minimum crest elevation of Ash Basin B is 23.7 feet. Therefore, overtopping is not expected. Based on this evaluation, Ash Basin B meets the requirements in 257.82(a).

AECOM CCR Rule Report : Initial Inflow Design Flood Control System Plan for Ash Basin B at the Brayton Point Power Station 2-2 2.2 Discharge from the CCR Unit ( 257.82(b)) 40 CFR 257.82(b) provides that the discharge from the CCR unit must be handled in accordance with the surface water requirements under 40 CFR 257.3-3, which states the following: (a) For purposes of section 4004(a) of the Act, a facility shall not cause a discharge of pollutants into waters of the United States that is in violation of the requirements of the National Pollutant Discharge Elimination System (NPDES) under section 402 of the Clean Water Act, as amended. (b) For purposes of section 4004(a) of the Act, a facility shall not cause a discharge of dredged material or fill material to waters of the United States that is in violation of the requirements under section 404 of the Clean Water Act, as amended. (c) A facility or practice shall not cause non-point source pollution of waters of the United States that violates applicable legal requirements implementing an areawide or Statewide water quality management plan that has been approved by the Administrator under section 208 of the Clean Water Act, as amended. (d) Definitions of the terms Discharge of dredged material, Point source, Pollutant, Waters of the United States, and Wetlands can be found in the Clean Water Act, as amended, 33 U.S.C. 1251 et seq., and implementing regulations, specifically 33 CFR part 323 (42 FR 37122, July 19, 1977). The handling of discharge was evaluated by reviewing design drawings, operational and maintenance procedures, conditions observed in the field by AECOM, and the inflow design flood control system plan developed per 257.82(a). Based on this evaluation, Ash Basin B does not discharge into waters of the United States. Discharge from Ash Basin B is channeled to Ash Basin A, which is then pumped to the Brayton Point Station for use as sluice water, or is diverted to the onsite wastewater treatment plant. Hydraulic and hydrologic analyses performed as part of the initial inflow design flood control system plan found Ash Basin B adequately manages outflow during the 25- year IDF, as overtopping of the Ash Basin B crest is not expected. Therefore, discharge into waters of the United States is not expected during normal or 25-year IDF conditions, and Ash Basin B meets the requirements in 257.82(b).

About AECOM AECOM (NYSE: ACM) is a global provider of professional technical and management support services to a broad range of markets, including transportation, facilities, environmental, energy, water and government. With nearly 100,000 employees around the world, AECOM is a leader in all of the key markets that it serves. AECOM provides a blend of global reach, local knowledge, innovation, and collaborative technical excellence in delivering solutions that enhance and sustain the world s built, natural, and social environments. A Fortune 500 company, AECOM serves clients in more than 100 countries and has annual revenue in excess of $19 billion. More information on AECOM and its services can be found at www.aecom.com. 1001 Highlands Plaza Drive West Suite 300 St. Louis, MO 63110 1-314-429-0100