Minimizing Storm Damage To Operating Houses on Movable Bridges

Similar documents
Insurance Property Risk Engineering GAPS. WaterWorks

Insurance Property Risk Engineering GAPS. WaterWorks

ICC/NSSA STANDARD FOR THE DESIGN AND CONSTRUCTION OF STORM SHELTERS ICC

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist

Section X - Miscellaneous

Section 32 - Miscellaneous

WIND, WATER & SALT BEST PRACTICES AND CODE REQUIREMENTS FOR DESIGN IN A TROPICAL ENVIRONMENT

Full-Scope Commissioning for High-Quality Buildings

2004 MASTER FORMAT SECTION Façade Panels

KEEPING UP WITH I-CODES

Field Planning and Data Collection Practices for Conducting Detailed Natural Hazard Vulnerability Assessments of Campus Structures

MEP Seismic & Wind Provisions of ASCE Prepared for the 2017 Rochester Engineering Symposium Richard Sherren, P.E.

Property Condition Assessment

Storm Damage Repair Requirements

TEXAS A&M ENGINEERING

CONSTRUCTION MATERIALS

Damaged Buildings and Health Facility Evaluations

Business License Application

ICC-SRCC LISTING. DIVISION: PLUMBING Section: Residential Solar Domestic Water Heater System

9th Edition Residential Volume with MA Amendments - Flood Standards Only DRAFT. 9th Edition Massachusetts Residential Code Requirements in Floodplains

FOR GENERATING SYSTEMS

Water Management & Damage Prevention: A Guide for Homeowners

SECTION ADDENDUM NUMBER ONE

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School

ADJUSTABLE PIPING SUPPORT PRODUCT BROCHURE

1 AND 2 FAMILY DWELLING REQUIREMENTS

ADJUSTABLE PIPING SUPPORT PRODUCT BROCHURE

VMA C (Revision 2)

: Plan Review and Project Services

Chapter UNIFORM CODES FOR CONSTRUCTION BUILDING CODE

APPLICATION AND CERTIFICATE FOR PAYMENT

Reclaimed Water Treatment, Distribution, Pumping and Storage Engineering Report Form

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

SECTION ROOF MOUNTED ATTIC EXHAUST VENT

2015 Virginia Building Code Changes As Related to Flood Items. September 27, 2018 Southwest Virginia VFMA Workshop

Roof System. and Considerations. Environment friendly e-library

IBHS Shutter Selection Guide

SECTION ELECTRICAL POWER ATTIC EXHAUST VENTILATOR

SILVER LINE BUILDING PRODUCTS. Series 1700 Heavy Commercial Aluminum Double Hung. HC65 48 x84 / HC50 60 x96 Replacement Window

3 Season Porch Windows

Maintaining Building Envelope Integrity. Is Your Leak REALLY a Roof Leak?

CLEAR CREEK COUNTY BUILDING DEPARTMENT PERMIT PROCEDURES AND REQUIREMENTS FOR COMMERCIAL AND MULTI-FAMILY DEVELOPMENTS

FEMA P-1019 Emergency Power Systems for Critical Facilities. ASFPM May 4, 2017 David K Low, PE DK Low & Associates

PERMIT APPLICATION REQUIREMENTS NEW RESIDENTIAL (SFD) POOL

City of South Pasadena COMMUNITY IMPROVEMENT

SECTION TURBINE VENTILATORS

COMPLETE REVISION October Process Industry Practices Civil. PIP CVC01017 Plant Site Data Sheet

Building Inspection Report

City of Grosse Pointe Park Sanitary Sewer System Inflow and Infiltration Investigation Smoke Testing

Retail Effects of ANSI/ASHRAE/IES Standard

INSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process.

Tohono O odham Nation. Adoption of Building Codes

Department of Public Safety and Corrections Uniform Construction Code Council. Uniform Construction Code (LAC 55:VI.301)

Bridge Maintenance Painting Projects Design and Management Considerations

PERMIT APPLICATION REQUIREMENTS

ICC-SRCC LISTING. DIVISION: PLUMBING Section: Residential Solar Domestic Water Heater System

DISASTER PREPAREDNESS CHECKLIST

Elastomeric Protected Membrane Roofing Fluid-Applied Protected Membrane Roofing. Restoration Coating System (RCS) over Cap Sheet

Aurora Genmounts Install LT Installation Manual

ICC/NSSA STANDARD FOR THE DESIGN AND CONSTRUCTION OF STORM SHELTERS

KOCHVILLE TOWNSHIP REQUIRED INFORMATION FOR CONSTRUCTION PLAN REVIEW COMMERCIAL AND MULTI-FAMILY

Nassau County Building Department

Exhibit A Library Shell Construction

Committee Input No NFPA [ New Section after ]

DESIGNING SAFE ROOMS AND SAFE HOMES WITH LOGIX.

2014 Advanced FBC Fifth Edition Chapter 15 Florida Specific Review

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 08 - OPENINGS. A. This Section includes fixed and operable aluminum-framed windows.

Encapsulated, Sealed & Closed Crawlspace Installation Manual

D. Provide UL-approved assemblies for pipes and ducts passing through fire-rated floors, walls, or partitions as required.

G R E E N H O U S E D E S I G N M A N U F A C T U R I N G FEATURED GREENHOUSE PACKAGES

WeatherSmart Air Barrier Installation Guide

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

CEILING MOUNTED ARTICULATING JIB CRANE

Understanding IBC Wind Load Requirements for Generating Systems

Showing Only Sections Changed 6 th Edition FBC (2017) from 5 th Edition FBC (2015) [changes shown with underline and strike-through]

Borough of Doylestown Building and Zoning Department

CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013

Design & Construction Standards, Revised January

PRE-FABRICATED HOUSING

Administration Building Needs Assessment

Central Station Air Handler Specification

ACP Greater Tampa Bay Mitigation as a Precursor to Recovery

ROOF OWNER'S OPERATION AND MAINTENANCE MANUAL

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

CLEAR CREEK COUNTY BUILDING DEPARTMENT REQUIREMENTS FOR A SINGLE FAMILY RESIDENCE

NATIONWIDE SAN ANTONIO SALES & SERVICE CENTER

REHABILITATION STANDARDS CHECKLIST

Commercial Remodel Permit

A. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials

Mills Elementary School Site Summary

SECTION ORNAMENTAL ALUMINUM RAILINGS PART 1 - GENERAL 1.01 SUMMARY

DuPont Tyvek Wall Underlay Install Guide

COVER SHEET ELEVATION SHEET SECTION DETAILS (MECHANICALLY ASSEMBLY) SECTION DETAILS (WELDED ASSEMBLY)

APPENDIX 6 (not yet reviewed by UCCS) STRUCTURAL ANALYSIS/VIBRATION CRITERIA

SECTION LATCHWAYS CONSTANT FORCE POSTS

2. DEFINITIONS. American Association of State Highway and Transportation Officials.

2018 Manufactured Homes and Factory Built Housing

TABLE OF CONTENTS. (Δ = Rev 06/08)

2015 I-Code Highlights

Transcription:

Minimizing Storm Damage To Operating Houses on Movable Bridges Brett M. Brabham, P.E. Louisiana Department of Transportation and Development Bridge Design Section

Introduction 150 Movable Bridges (Excluding Railroad) Vast majority have Operating Houses New Operating Houses cost between $400k to $500k Not included in this estimate is $120k of electrical equipment

Codes and Regulations AASHTO has minimal information concerning the construction of Operating Houses Louisiana has adopted National and State codes for the construction of buildings

Code Requirements for Buildings in Louisiana International Building Code National Fire Protection Association (NFPA) Code Louisiana Plumbing Code The American Society of Heating, Refrigerating and Air- Conditioning Engineers (ASHRAE)

International Building Code Load Requirements 1. Snow Loads

Snow Load Map

International Building Code Load Requirements 1. Snow Loads 2. Flood Loads

Flood Loads Flood Elevations are determined by the Federal Emergency Management Agency (FEMA) Local Jurisdiction

International Building Code Design Flood Conditions All new construction of buildings, structures, and portions of buildings including substantial improvement and restoration of substantial damage to buildings and structures, shall be designed and constructed to resist the effects of flood hazards and flood loads.

International Building Code Design Flood Conditions Substantial Damage damage of any origin sustained by a structure to its before-damaged condition would equal or exceed 50% of the market value of the structure before the damage occurred.

What is the criteria for Determining Flood Zones? Area with a flood plain subject to a 1% or greater chance of flooding in any year; or Area designated as a flood hazard area on a community s flood hazard map, or otherwise legally designated.

Bayou Liberty Bridge Former Operating House House Design Elevation is 5. The 100 year Flood Elevation is 7.12.

Bayou Liberty Bridge New Operating House New Operating House Elev. 15.00

Existing Structures Below the 100 Year Flood Plain without Substantial Damage? Flood Resistant Materials

Flood Resistant Materials Use items which water will have little or no effect.

Existing Structures in Flood Zones without Substantial Damage? Flood Resistant Materials Raise items off the floor

Existing Structures in Flood Zones without Substantial Damage? Flood Resistant Materials Raise items off the floor Protective walls

Protective Walls Keep visibility in mind. Provide a bilge Pumping System.

International Building Code Load Requirements 1. Snow Loads 2. Flood Loads 3. Wind Loads

Wind Load Map

Wind Load Building Connections

Roofing Systems Built-up Roofing Systems Metal Roofing Systems

Roofing Systems The most important component in regards to wind-related storm damage. Ensure the wall/ceiling to roof connections can withstand the wind loads.

Roofing Systems

Roofing Systems The most important Component in regards to Wind Related Storm Damage. Ensure the wall/ceiling to roof connections can withstand the wind loads. Ensure that the roof panels/ shingles are installed as per the manf. Recommendations.

Roofing Systems

Roofing Systems Cont. Written Manufacturer s Warranties Corrosion resistant materials including fasteners.

Roofing Systems Consider your environment High Humidity Salt Spray

Roofing Systems Cont. Written Manufacturer s Warranties Corrosion resistant materials including fasteners. Make sure the roof drains properly.

Roofing Systems

Roofing Systems Cont. Written Manufacturer s Warranties Corrosion resistant materials including fasteners. Make sure the roof drains properly. Make sure all items attached to the roof are properly installed such as fans, rooftop units, etc.

Roofing Systems

Window Systems Storefront Systems Individual Windows

Window Systems Must meet IBC wind loads in the building location. Corrosion resistant materials including fasteners. In areas with a wind load of 120 mph or greater, the windows must be large missile impact rated.

Window Systems Cont. Must be installed as per the manufacturer s recommendations.

Window Systems

Window Systems Cont. Must be installed as per the manufacturer s recommendations. Glass must be shatterproof as per AASHTO requirements.

Miscellaneous Components Window Units External Ductwork External Piping

Window Units Make sure the air conditioning unit is secured to the building.

External Ductwork Make sure the ductwork is secured to handle the wind loads in the area.

External Ductwork Although the ductwork was securely mounted to the roof, damage occurred due to the ductwork itself failing.

External Piping Avoid using PVC piping exposed above ground. Piping should be rigidly supported to the bridge with marine grade fasteners.

Summary Know your location within the state prior to designing the building. Know the building elevation for both Flood and Wind Load Design. Use materials based on your environment. Make sure all building connections and components meet wind load requirements. Secure all external items to resist the wind/flood loads in the location of the Operating House.

Questions?