Negatively Geared Ore Reserves - A Major Peril of the Break-Even Cut Off Grade Julian Poniewierski

Similar documents
Underground Ore Reserve growth at Prominent Hill extends mine life to 2030

MINERAL RESOURCES & MINERAL RESERVES STATUS AS AT 31 DECEMBER 2015 Tim Rowland Group Competent Person 11 th April 2016 Market Presentation

Copper Silver Gold. TSX-V, Nasdaq First North: FIL filo-mining.com. Corporate Presentation July, 2017

QUARTERLY PRODUCTION REPORT: KANMANTOO PRODUCTION AHEAD OF YTD GUIDANCE

Copper Silver Gold. TSX-V, Nasdaq First North: FIL filo-mining.com. Corporate Presentation October, 2017

Ravenswood Expansion Project Update

OZ MINERALS. JP Morgan Melbourne Mining Day. Terry Burgess, Managing Director and CEO. Melbourne 16 October 2009 OZMINERALS.COM

Confidence in Carrapateena project grows

Australia s leading explorer in Mexico

Quality, Diverse Group of Mining Assets. February 2018

EXCO S PROJECT PIPELINE

Copper Mountain Announces Robust Preliminary Economic Assessment Results for New Ingerbelle

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves

Sierra Metals Exploration Update Call

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 31 MARCH 2016

Evaluation of Grade Engineering using Enterprise Optimization. Michael Scott, Nick Redwood

Sierra Metals Updates Mineral Resource and Reserve Estimate for Bolivar Mine, Mexico

Maiden Ore Reserve for Camel Creek JV

For personal use only

Malachite Resources AGM. November For personal use only. Malachite Resources Limited

EXCO S PROJECT PIPELINE. Unlocking the Value

Hot Chili and CMP sign Non-Binding Letter of Intent on Second Copper Project

AGM - Lorena Gold Project

SECOND QUARTER REPORT 15 JULY 2014

MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES

PRESENTATION MINING 2010 RESOURCES CONVENTION - BRISBANE

Diversified Australian Producer

RESOURCE GOLD PTY. LTD.

Increasing Net Present Value by a Third at an Operating Sublevel Cave Mine Using Draw Strategy Optimisation. Presented by Alex Campbell

KANMANTOO COPPER MINE: STRATEGY AND OPPORTUNITY SA GOVERNMENT COPPER SUMMIT GREG HALL IIIII CEO & MANAGING DIRECTOR 6 MAY 2015

Azure Minerals Ltd ASX Code:

SA Mining and Exploration Conference Adelaide Convention Centre 11 DECEMBER 2015

SIERRA METALS REPORTS A 53.5% INCREASE IN NI COMPLIANT MINERAL RESERVES AT ITS YAURICOCHA MINE, PERU

ALACER GOLD ANNOUNCES FOURTH QUARTER MINE PRODUCTION AND 2012 GUIDANCE

Boliden to acquire Kevitsa Finnish nickel-copper-gold-pgm mine from First Quantum. 10 March 2016

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX:

PROUDLY POSITIONED AS AN AUSTRALIAN MINER ASX:MLX. November 2017 AGM Presentation

Thalanga Project Ore Reserve and Mineral Resource Statement (as at 1 December 2017)

Seizing Opportunity and Building Value

AVINO SILVER & GOLD MINES LTD.

CMZ. Advancing The Zafranal Project. Bruce L. Turner Executive Director, Compañía Minera Zafranal 6 March 2017 Peru Day PDAC 2017

Health and Safety. Update: No LTI at Prestea Open Pits. 5.65M man hours worked with no LTI

For personal use only

For personal use only

TRANS-SIBERIAN GOLD PLC

For personal use only

TRANS-SIBERIAN GOLD PLC

Updated Investor Presentation

For personal use only KANMANTOO MINE: MINING WITHIN OUR COMMUNITY GREG HALL IIIII CEO & MANAGING DIRECTOR 13 APRIL 2015

Commenting on the approval of the development of the Mt Carlton Project Conquest Executive Chairman, Jake Klein commented:

Q PRODUCTION REPORT

N E W S R E L E A S E

N E W S R E L E A S E

White Dam Gold Project Dump Leach

For personal use only

2013 Ore Reserve estimates Increased Ore Reserves at Ban Houayxai

For personal use only

ARM COPPER. Thando Mkatshana Chief Executive: ARM Copper and ARM Coal. Vale/ARM joint venture 50% 50% Refining. Flash/ Isa smelt smelting

OMITIOMIRE OXIDE COPPER FEASIBILITY STUDY

Hot Chili Commences Scoping Study on Productora Copper Project, Chile

INV METALS ANNOUNCES ROBUST PRELIMINARY FEASIBILITY STUDY AT LOMA LARGA

For personal use only

Whittle Integrated Strategic Planning. Service Offering. Optimising open pit & underground mining businesses.

FIRST MAJESTIC SILVER CORP.

Niblack Project Poised For Development

Thalanga Operations Ore Reserve and Mineral Resource Statement

Sandspring Resources Positive Pre Feasibility Study for Toroparu demonstrates 2.6 year payback on initial 1.32 g/t gold grade

June 2017 Quarterly Report Presentation and Webcast 28 July 2017

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME

Gum Creek Gold Project Free Milling Scoping Study

For personal use only

Fourth Quarter Production Report. for the three months ended 31 December 2017

Hidden Valley PNG s Newest Mine Briefing for Analysts

Q PRODUCTION REPORT GUIDANCE MET FOR 2017

Second drill rig to accelerate major drilling program at Productora

On The Road To Silver & Gold Mining In Mexico

Orezone Announces Updated Feasibility Study to Incorporate a Phase II High-Grade Sulphide Expansion

VALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE

Newmont Reports 2017 Reserves and Resources; Reserve additions replace depletion, Resources increase

Bank of America Merrill Lynch 2017 Global Metals, Mining & Steel Conference. Andrew Cole Managing Director & CEO

FEASIBILITY STUDY CONFIRMS KALKAROO COPPER-GOLD PROJECT. Highlights

For personal use only

For personal use only

ASX ANNOUNCEMENT. CMP to Purchase Additional Stake in Productora for US$1.5 Million. Sprott Loan to be Reduced and Extended by 12 Months

Whittle Integrated Strategic Planning. Services. From mineral resource to cash flow. Improve cash flow profile

The global Mineral Resource estimate now stands at Mt grading at 1.19 g/t Au for 1,328,500 contained gold ounces.

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT

QUADRA ANNOUNCES THIRD QUARTER 2009 PRODUCTION RESULTS

TEPAL PROJECT MEXICO Corporate update

Dittmer G r old P roject

AVINO ANNOUNCES FOURTH QUARTER AND FULL YEAR 2017 PRODUCTION RESULTS FROM ITS AVINO PROPERTY

Transitioning from Explorer to Miner

CORPORATE PRESENTATION JULY 2017

For personal use only

Southern Cross Goldfields Ltd

Prominent Hill 2011 Annual Mineral Resource and Ore Reserve Statement

MINING DILUTION: VARIABLE VERSUS FIXED FACTOR

CU-RIVER MINING AUSTRALIA

For personal use only

PROUDLY POSITIONED AS AN AUSTRALIAN MINER ASX:MLX. Corporate Update

Transcription:

Negatively Geared Ore Reserves - A Major Peril of the Break-Even Cut Off Grade Julian Poniewierski March 2016 AusIMM Project Evaluation 2016, Adelaide.

Hands Up - What would you prefer: Of following Ore Reserve options: (both profitable) (a) 100 Mt @ 0.4% Cu (900 Mlb copper) (b) 45 Mt @ 0.6% Cu (600 Mlb copper) It appears that most CEOs choose (a) 2

Hands Up - What would you prefer: Of following Project options: NPV = 152 M$ or 77 M$ 3

Hands Up - What would you prefer: Of following Ore Reserve/Project options: (a) 100 Mt @ 0.4% Cu NPV = 77 M$ (b) 45 Mt @ 0.6% Cu NPV = 152 M$ Same project, different cut-off grade. 250 Mt total material, $3/lb Cu, typical OP costs, i=8%, pre-tax 4

My Proposition: Significant negative value tonnages in Ore Reserves have compounded Mining Company financial problems. Like a negatively geared investment house, in a falling property market, negatively geared ore reserves have magnified the loss when commodity prices have dropped. 5

Introduction Break-even Cut-Off Grade Usually excludes costs NOT associated with processing decision ( ore not rock costs) Excluded costs have to be covered by difference between break-even grade and actual value of a mined grade. If accepted definition is material that pays for itself, then it should pay for itself when it is by itself 6

Introduction Break-even Cut-Off Grade Inherent Risk in break-even COG Ore Reserves Risk magnified when negative value tonnages included Ken Lane s theories of COG selection for NPV maximisation, now 52 years old (published 1964 ). Brian Hall s Hill of Value now 13 years old. (2003) Industry still stuck on BE-COG; so let s - at least - get it right 7

Distribution of Value In a typical ore reserve using a break-even cut-off grade, a lot of ore is marginal. Data from real example open pit. Typical. 8

Distribution of Value Real Tonnage Distribution by $/t Value (typical): 9

Distribution of Value Value Proportion Distribution by $/t Value: 10

Distribution of Value Cumulative Tonnage vs. Cumulative Value: Bottom 27% of tonnes only 6% value Top 27% of tonnes 60% Value Same Tonnage, Same Work, 10 times the value A lot of material is mined & milled for Practice Bin Cum % Tonnes Cum % Value <0 0% 0% 0-5 27% 6% 5-10 55% 22% 10-15 73% 40% 15-20 82% 52% 20-25 87% 63% 25-30 92% 73% 30-35 95% 82% 35-40 97% 87% 40-45 98% 91% 45-50 99% 94% 11

Implication of an Error Tonnage Distribution Change in with a 5$/t Error: 55% of material ΣValue = 0 Non break-even calculation costs to still be paid for 12

What a $5/t Error Looks Like Gold: 1600 A$/oz: 0.10 g Au recovered /tonne (1150 US$/ oz and 0.72 USD:AUD) Copper: 2.40 US$/lb: 0.10 % (recovered Cu) 4.50 US$/lb: 0.05 % (recovered Cu) Rounding Error 13

The Leverage Effect of an Error Consider following two ore reserves: A: -5 $/t COV B: +5 $/t COV 100 Mt 735 M$ 7.35 $/t 45 Mt 735 M$ 16.3 $/t NPV of A: 77 M$ NPV of B: 152 M$ Pre-tax; 8%; 250 Mt TMM; 5 Mtpa Mill, Typical OP mining, processing & treatment costs

The Leverage Effect of an Error After a 15$/t equivalent price fall: A: -5 $/t COV B: +5 $/t COV 100 Mt -765 M$ -7.35 $/t 45 Mt 60 M$ 1.34 $/t A fell 2.2 times more in value than B M$ 1500 vs M$ 634

Types of $5/t Errors Recovery Errors Fixed Recovery Lab Data vs. Real Data. Ignoring Data Median vs. the Mean Cost Omissions & Errors 16

Fixed Recovery Error Fixed Recovery = Using Project Average Recovery for Average Head Grade for all Tonnes down to BEG: e.g. 85% @ 1.5 g/t & 85% @ 0.3 g/t Example Gold Mine #1 (real): Reserve Head Grade = 2.2 g/t Au Mill Recovery = 94.0% COG = 0.9 g/t (controlled by a physical limit) 17

Fixed Recovery Error Example Gold Mine #1 (real): Recovery varies by Head Grade Fixed Tails Grade often a better Estimate of Recovery 94.0% of 2.2 g/t Au tails grade = 0.13 g/t JV partner wanted to Increase Ore Reserves (market value perception) 18

Fixed Recovery Error Example Gold Mine #1 (real): New Ore Reserve with COG @ 0.4 g/t & 94% recovery: 94% Recovery @ 0.4 g/t Tails grade = 0.02 g/t (Note world s best gold plant has a tails grade around 0.04-0.05 g/t) [NB: implies 0.38 g/t recovered] 0.13 g/t Tails grade for 0.4 g/t 67% Recovery. If Require 0.38 g/t recovered gold for break-even then at 0.13 g/t tails grade, break-even COG = 0.5 g/t (not 0.4) Remember: 0.1 g/t; $5/t maybe 20-30% of Ore Reserve with negative value 19

Fixed Recovery Error OK Fixed Tail may underestimate true recovery. Nobody goes broke making more money than they thought 20

Reality Bites (Laboratory vs. Real Mill Performance) Example Gold Mine #1 again: 21

Reality Bites (Laboratory vs. Real Mill Performance) Example Gold Mine #1 again: Actual average = 0.25 g/t break-even of 0.6 g/t 0.2 g/t error: Now maybe 40-60% of Ore Reserve negative value 22

Ignoring Data Error More common than you would (should) think: 23

Ignoring Data Error Gold Mine #2: Using 0.11 g/t Fixed Tail for Ore Reserves No-one had analysed the available data: Remember: 0.1 g/t; $5/t maybe 20-30% of Ore Reserve with negative value 24

Means, Medians & Modes The FLAW of Averages : 25

Means, Medians & Modes Common Error: Assuming Modal or Median Value as the Correct value; rather than the Mean value Distributions of Values are usually Skewed 26

Chapter navigator (to add Insert, Header & Footer, Footer and apply) Means, Medians & Modes Example Raisebore drill & move time data (Kidd Creek) Median = 11.5 Mean = 13.6 (18% ) so fixed costs (labour) 18% higher & stope turn over slower. 27

Means, Medians & Modes Common Error is Assuming Modal or Median Value as the Correct value; rather than the Mean value Distributions of Values are usually Skewed Imagine a project made up of dozens (hundreds?) of such errors? Skewed distributions: Mean of Sum Sum of Means 28

Simple Cost Errors & Omissions More common than you would (should) think: Real Data OP Gold mine #3: Reasons for increase included: Logistics: Access Road Mill Parts Cyanide underestimated Power cost increases Year X Year X+1 G&A 5$Mpa 12$Mpa % Increase 1.28 $/t 3.56 $/t 178% Mining 2.24 $/t 2.28 $/t 2% Milling 8.92 $/t 11.90 $/t 33% Total: 12.44 $/t 17.74 $/t 43% Remember: $5/t, maybe 20-30% of Ore Reserve with negative value 29

Simple Cost Errors & Omissions Nothing is ever wrong in the design is it? 30

Simple Cost Errors & Omissions And some-times things can get worse: 31

Clues to Look For Discussed issues. Things don t gel: Historical Quarterly Total Costs vs. Head Grade 32

Clues to Look For Discussed issues. Things don t gel: Historical Trend 33

Clues to Look For Discussed issues. Things don t gel: Ore Reserve Grade 34

Clues to Look For Discussed issues. Things don t gel: Most Likely Total Costs from Historical Trends 35

Clues to Look For Discussed issues. Things don t gel: Ore Reserve Price 36

Clues to Look For Discussed issues. Things don t gel: Historical Trend Total Costs for Ore Reserve Grade >> Ore Reserve Price 37

Other Clues to Look For Misaligned Executive KPIs e.g. Size of Reserves Management Strong on spin Low on technical detail 38

Other Clues to Look For Corners Cut: 39

Conclusions Errors/Omissions in Break-Even COG calculation Negative geared ore reserves Increased project/company risk profile Experience can avoid some of errors: Benchmarking of Data Don t ignore data; Don t ignore experience "A conclusion is the place where you got tired of thinking." Steven Wright 40

Thank you