Cokato Lake (86-263) Wright County. Hydrologic Investigation

Similar documents
Exploring the Possibilities At Prado Dam

San Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

John H. Kerr Dam and Reservoir Virginia and North Carolina (Section 216)

Upper Lightning Lake Water Level Management Environmental Assessment Worksheet. Attachment D Design Report for Upper Lightning Lake

DES MOINES RIVER RESERVOIRS WATER CONTROL PLAN UPDATES IOWA ASCE WATER RESOURCES DESIGN CONFERENCE

Hydrologic Study Report for Single Lot Detention Basin Analysis

A Hydrologic Study of the. Ryerson Creek Watershed

2002 Water Quality Monitoring Report

A Tale of Two Dams and a dry river. November 1, 2011 Planning, Resources and Technology Committee Mojave Water Agency

Report for 2001SD1941B: Alternative Conservation Practices to Improve Soil and Water Quality

SECTION III: WATERSHED TECHNICAL ANALYSIS

Water Supply Reallocation Workshop

CENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT

Prior Lake Stormwater Management & Flood Mitigation Study

Song Lake Water Budget

Current Water Management Practices for Kerr Reservoir

Background Information on the. Peace River Basin

2003 Water Quality Monitoring Report

July 31, 2012

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

Draft Application for New License for Major Water Power Project Existing Dam

Reservoir Drought Operations

Camp Far West Hydroelectric Project Relicensing

SECTION IV WATERSHED TECHNICAL ANALYSIS

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

Hydrologic, Hydraulic, and Ecological Modeling Issues and Implementation for the Blind River Fresh Water Diversion Project

5/25/2017. Overview. Flood Risk Study Components HYDROLOGIC MODEL (HEC-HMS) CALIBRATION FOR FLOOD RISK STUDIES. Hydraulics. Outcome or Impacts

Project Summary: - Hydrologic Models. - LiDAR Based - 10 Synthetic Events - No Historic Events - 100yr Runoff is Largest - Assumes Even Rainfall

Technical Memorandum. Hydraulic Analysis Smith House Flood Stages. 1.0 Introduction

Sea Level Rise and Recurrent Flooding Update

EFFECT OF RAINGAGE DENSITY ON RUNOFF SIMULATION MODELING by ABSTRACT

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION

An Investigation into the 2012 drought on Apalachicola River. Steve Leitman, Bill Pine and Greg Kiker

ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT

Jacobi, Toombs, and Lanz, Inc.

Reservoir on the Rio Boba

Section 4. Mono Basin Tributaries: Lee Vining, Rush, Walker, and Parker Creeks. Monitoring Results and Analysis For Runoff Season

FISHER RIVER INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT

Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

Outline. Regional Overview Mine Study Area. Transportation Corridor Study Area. Streamflow Low Flow Peak Flow Snow Small Pools.

Prepared for: City of Jeffersonville. November Prepared by

The Impacts of Climate Change on Portland s Water Supply

Spring Forecast Based Operations, Folsom Dam, California

SEWRPC Staff Memorandum

Appendix I. Dworshak Operations

Wapato Access Feasibility Study

16 September Water Management Wilmington District. US Army Corps of Engineers BUILDING STRONG

Modeling the Middle and Lower Cape Fear River using the Soil and Water Assessment Tool Sam Sarkar Civil Engineer

..Title Receive Report on Salinas Valley Water Conditions for the Third Quarter of Water Year

OVERLAND RESERVOIR. Prepared for: Overland Ditch and Reservoir Company Redlands Mesa Road Hotchkiss, CO 81419

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

Brannen Lake Storage Feasibility Potential Effects on Water Levels

Relicensing Study 3.8.1

Continuous Simulation Example Problem

Irrigation modeling in Prairie Ronde Township, Kalamazoo County. SW Michigan Water Resources Council meeting May 15, 2012

Status Report. Work to Date on the Development of the VARQ Flood Control Operation at Libby Dam and Hungry Horse Dam. January 1999.

SOURCE WATER MONITORING

San Luis Obispo Creek Watershed Hydrologic Model Inputs

Hydrologic Calibration:

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

AS A COURTESY, PLEASE TURN OFF CELL PHONES AND PAGERS WHILE MEETING IS IN PROGRESS.

APPENDIX 4 ARROYO MODELING

Wood Canyon Emergent Wetland Project. City of Aliso Viejo 12 Journey, Suite 100 Aliso Viejo, CA 92656

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

Section 6: Stormwater Improvements

MIDAS CREEK PROJECT. FINAL DESIGN REPORT SKR Hydrotech 4/11/2012

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

Folsom Dam Water Control Manual Update

DEVELOPMENT OF A HYDRO-GEOMORPHIC MODEL FOR THE LAGUNA CREEK WATERSHED

Analysis of Vermillion River Stream Flow Data (Dakota and Scott Counties, Minnesota)

Water Supply Board Briefing. Water Operations Department March 22, 2016

CALSIM II Sacramento River Basin Hydrology Enhancements

CLAY STREET BRIDGE REPLACEMENT

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

NON-TREATY STORAGE AGREEMENT

Pajaro River Watershed Flood Prevention Authority. Phase 3 and 4a. Pajaro River Watershed Study

Rainwater Harvesting

Climate and Land Use Consequences to 100-Year Flooding

APPENDIX F RATIONAL METHOD

Appendix C Baseline Tatelkuz Lake Levels

Culvert Sizing procedures for the 100-Year Peak Flow

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar

Lecture 9A: Drainage Basins

Engineering Report Preliminary Floodplain Study. Executive Summary

DICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON

Welcome STEP 1: STEP 2: STEP 3:

RUNOFF VOLUMES FOR ANNUAL OPERATING PLAN STUDIES

Watershed Response to Water Storage. 8/1/2012 Paul Wymar Scientist Chippewa River Watershed Project

Assessment of Agricultural Flood Damages Along the James River in South Dakota

DRAINAGE STUDY CROWS LANDING INDUSTRIAL BUSINESS PARK. Stanislaus County. Prepared by:

Technical Memorandum No Basis of Comparison

Case Studies in Hazard Class Reductions Implementation of NY s Guidance for Dam Hazard Classification

Restoring Wreck Pond Inlet Jenna Krug, Habitat Restoration Coordinator

CHOLLA POWER PLANT BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_Inflowflood_003_

Activity Calculating Property Drainage

IMPACT OF CLIMATE CHANGE ON WATER AVAILABILITY AND EXTREME FLOWS IN ADDIS ABABA

Gain-Loss Study of Lower San Pedro Creek and the San Antonio River, San Antonio, Texas, May October 1999

Chehalis Basin Strategy Causes of Extreme Flooding. October 11, 2016 Policy Workshop

Transcription:

Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005

Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Problem Statement In recent years, heavy rainfall has caused high lake level conditions on Cokato Lake. Members of the lake association feel that high water problems will continue due to recent culvert changes within the watershed, and continued growth within the city of Cokato. The lake association would like the Department to improve the outlet to accommodate the increase in water coming into the lake. The existing outlet structure, which is owned by the DNR Division of Fisheries, was constructed in 1965. The Surface Water Unit within DNR Waters was requested to conduct a hydrologic evaluation of Cokato Lake and its watershed, with an emphasis on the specific concerns raised by the lake association. Cokato Lake is located in southwestern Wright County, approximately two miles north of the city of Cokato. Cokato Lake outlets directly to the North Fork Crow River, which is slightly more than a mile downstream of the lake outlet as the crow flies. Background Information Watershed: Cokato Lake, 582 acres in size, has a total watershed area of 29,300 acres (Figure 1). The corresponding watershed to lake area ratio is 50:1. Three larger lakes are located within the Cokato Lake watershed, including Smith, Shakopee and Byron Lakes. The total area tributary to those three lakes is 4,870 acres, or 9.1% of the total watershed area of Cokato Lake. The amount of runoff contributed by these three subwatersheds to Cokato Lake would be expected to be relatively minor, compared to the remainder of the watershed. Excluding those three subwatersheds, the direct watershed of Cokato Lake is 24,400 acres; the corresponding watershed to lake area ratio using this value is still a very high 42:1. 1

Figure 1: Cokato Lake Watershed 2

Soils: The Wright County Soil Survey, published by the then Soil Conservation Service, indicates that the general soil association within the Cokato Lake watershed is the Lester- Hayden-Peat Association. This soil association is the largest in Wright County and is generally described as consisting of.rolling areas. Slopes are generally short and irregular. Peat bogs and marshes occur. The association includes many large and small lakes. Both the Lester and Hayden soils are generally well drained and have a loam surface layer and clay loam subsoil. Peat soils are found in most of the depressions. Land cover: A land cover map, based on early-1990s aerial photographs, and tabulated percentages for the Cokato Lake watershed are shown below (Figure 2). Figure 2. Land Cover Acres Percent Urban and Rural Development 1466 5.0 Cultivated Land 22,254 76.0 Hay/Pasture/Grassland 2514 8.6 Brushland 77 0.3 Forested 1155 3.9 Water 1362 4.7 Bog/Marsh/Fen 447 1.5 Mining 20 0.1 3

Three quarters of the land within the Cokato Lake watershed is in agricultural production. Considerable agricultural drainage improvements have occurred within the watershed. Much of Sucker Creek, the primary tributary to Cokato Lake, was channelized with the establishment of Joint County Ditch No. 15. Additional private drainage activity has also occurred, both open ditch and subsurface drains. Surface drainage improvements in particular will tend to increase both the volume and rate at which runoff reaches Cokato Lake. Recorded Lake Levels Figure 3a is a plot of all available recorded lake levels for Cokato Lake. The Ordinary High Water (OHW) level and the runout elevation (lowest point on the crest of the outlet dam) are also shown on this graph. The total range of recorded lake levels is 2.7 feet. Unfortunately, water levels were not recorded during recent highwater events. However, two highwater marks from the summer of 2002 flood were recently surveyed (970.7 and 970.9). The lake levels reached in 2002 far exceeded the recorded range of lake levels. (All elevations in this report reference feet above mean sea level 1929 adjustment.) Cokato Lake (86-263) 967.5 967.0 Recorded Lake Levels OHW Runout Elevation (MSL) 966.5 966.0 965.5 965.0 964.5 964.0 Jan-55 Sep-57 Jun-60 Mar-63 Dec-65 Sep-68 Jun-71 Mar-74 Nov-76 Aug-79 May-82 Feb-85 Nov-87 Aug-90 May-93 Jan-96 Oct-98 Jul-01 Apr-04 Figure 3a. Recorded Lake Levels A lake level gage was re-installed on Cokato Lake during the spring of 2004. Only a handful of readings have been obtained to-date. But the current gage reader did capture the lake level response following a 2.5 June rainfall event. As shown in Figure 3b, Cokato Lake rose 0.94 feet and receded to pre-storm levels within three weeks. 4

Cokato Lake (86-263) Recorded Lake Levels Lake Level (MSL) 967.5 967.0 966.5 966.0 965.5 965.0 964.5 964.0 Runout 20-May 23-May 26-May 29-May 1-Jun 4-Jun 7-Jun 10-Jun 13-Jun 16-Jun 19-Jun 22-Jun 25-Jun 28-Jun 1-Jul 2004 Figure 3b. June 2004 recorded lake levels. Recent rainfall Central Minnesota, including Wright County has received its share of heavy rainfall during the last few years. Three significant summer rainstorm events affected Wright County during 2002 and 2003. A summary of these storms including a map showing rainfall totals may be found at the DNR Climatology Office website: http://www.climate.umn.edu/doc/flashflood.htm. An excerpt for the June 2002 event is included as Figure 4. Refer back to Figure 1 to help locate Cokato Lake and its watershed. Figure 4. Heavy June 2002 Rainfall. 5

Hydraulic and Hydrologic Analyses Commonly used hydraulic and hydrologic engineering analytical techniques were used as part of this study. Two computer simulation models developed by the U.S. Army Corps of Engineers were instrumental in this study HEC-RAS and HEC-HMS. HEC-RAS (Hydrologic Engineering Center River Analysis System) was used to compute flow and water levels over the outlet dam and downstream channel. HEC-HMS (- Hydrologic Modeling System) was used to compute the rate and volume of runoff entering Cokato Lake and then routing that inflow through Cokato Lake and its outlet. Summaries of the results of these analyses are incorporated into the following discussion. Outlet A lake s outlet, including dam and downstream channel, is a primary factor to evaluate when dealing with lake levels concerns. The outlet controls the rate at which water can leave a given lake. The outlet has no control on the amount of water entering a lake. A recent photo of the Cokato Lake dam is shown below. Figure 5. Cokato Lake Dam A DNR Waters field crew completed a survey of the Cokato Lake outlet channel, including the 25 th Street and County Road 4 culverts on March 2, 2005. These data provided the basis for developing an HEC-RAS model for the Cokato Lake outlet. The key product of this model is the relationship of how outflow from Cokato Lake varies with changing lake levels. This relationship was first developed for existing conditions. The simulation results confirm that the dam does control outflow during lower flow conditions. As lake levels, and therefore outflow increases, the downstream channel becomes the primary control (beginning at a flow rate of approximately 500 6

cubic feet per second). The culvert under 25 th Street SW does restrict outflow from Cokato Lake during high flow conditions. Two alternatives to increase outflow were evaluated using the HEC-RAS model. The first alternative assumed that the higher portions of the outlet dam were lowered approximately eight inches to the elevation of the existing low notch. When the photograph in Figure 6 was taken, the lake level was below high portions of the dam crest and water was only flowing through the low notch in the dam. The 2 nd alternative assumed that a second culvert (w/ same dimensions) was added to 25 th St. SW crossing, without any modification to the existing dam. The computed lake level outflow rating curve for existing conditions and the two alternatives is shown as Figure 6. Cokato Lake Outflow Rating Curve Lake Level 973 972 971 970 969 968 967 966 965 Existing Conditions Alt. 1 - low ered dam Alt. 2-2nd culvert @ 25th St. 964 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 Figure 6. Outflow Rating Curve Outflow (cubic feet per second) The next step is to determine how the improved outflow conditions will affect lake levels on Cokato Lake, which required the use of the 2 nd Corps of Engineers computer simulation model (HEC-HMS). The HEC-HMS model parameters were first estimated using the recorded rainfall and lake level data for June 2004. The parameters were then adjusted for the summer of 2002 event, such that the computed peak lake level essentially matched the surveyed highwater mark (970.7 / 971.0). Once the HEC-HMS model was calibrated to the 2002 event, the model was rerun using the two alternative outflow rating curves shown in Figure 7. The results are tabulated below: 7

Cokato Lake Computed Lake Levels - Existing Conditions and Two Outlet Alternatives Starting Peak Lake Level Lake Level Lake Level Bounce Existing Conditions 965.31 970.89 5.58 ft. Alt. 1: lower entire 965.02 970.71 5.69 dam crest to elevation of the low notch Alt. 2: add 2 nd culvert 965.31 970.62 5.31 at 25 th Street SW Development within the City of Cokato The city of Cokato comprises approximately five percent of the total watershed of Cokato Lake. Aerial photographs from the early 1990s and 2003 were reviewed to identify instances of newer development within the city. Commercial expansion along the U.S. Highway 12 corridor appears to be the primary activity that would be expected increase runoff to Cokato Lake. There has also been new residential development, primarily in the southeast quadrant of the city. The increased amount of imperious surface roads, driveways and rooftops of the residential development - would also tend to increase runoff, but to a lesser extent than commercial development. Figure 7 includes both aerial photographs. The red boxes highlight those areas of the city interpreted to be newer commercial development, including parking lots. The yellow boxes indicate areas of new residential development. The total area of each development type are as follows: Commercial development: Residential development: 61.0 acres; 0.25% of the direct watershed 36.2 acres; 0.15% of the direct watershed The HEC-HMS model was used to gain a sense of the impact on peak lake levels due to the expanding urban development with the city of Cokato. The model parameter used to compute the amount of runoff was adjusted to account for an additional 100 acres of urban development. With the assumption of additional runoff from the City of Cokato, the computed peak lake level for the summer of 2002 event increased by 0.02 feet. 8

Figure 7a early 1990s aerial photograph Figure 7b 2003 aerial photograph 9

County Road 4 Culvert Another issue raised by the lake association was the new County Road 4 culvert, immediately east of Cokato Lake. The portion of the Cokato Lake watershed draining through this culvert is highlighted on Figure 1. This subwatershed represents 1.6% of the direct watershed to Cokato Lake. This author understands that an older set of 3 24 diameter culverts at this road crossing were recently replaced by Wright County with a single 48 culvert. A very simple comparison is to look at the total cross sectional area 9.4 square feet (old) vs. 12.6 square feet (new). While not a true measure of the respective hydraulic capacity, this comparison would suggest that the new culvert has approximately one-third more capacity than the old culvert crossing. The change in culvert will not increase the total volume of runoff reaching Cokato Lake for a given storm event. But the larger culvert will affect the timing. Due to their close proximity to the lake, the old set of culverts to would have had to store water for several days in order serve as an effective flood damage reduction measure (refer back to Figure 3b). The culvert change would be expected to change the runoff timing by a matter of several hours, not the days required to effect a measurable change in lake levels. Conclusions The very large watershed to lake area ratio is the overriding factor causing periodic high levels on Cokato Lake. Lowering the crest of the outlet dam would result in lower peak lake levels, but the total lake level bounce would remain essentially the same. A lower dam crest would also result in lower lake levels during normal to dry climatic conditions. The existing culvert under the 25 th St. NW does restrict outflow during flood conditions. However, doubling the capacity the hydraulic capacity of the road crossing reduced the peak simulated lake level for the 2002 event by less than 2 inches. Neither the new development within the city of Cokato, nor the new culvert on County Road 4 measurably increased flooding conditions on Cokato Lake. The extensive drainage network throughout the watershed has likely had a far greater impact. No one person, agency or action is to blame for the high lake levels experienced on Cokato Lake during the last few years, nor are there easy solutions to minimizing future high lake levels. A comprehensive program to identify, evaluate and implement a wide variety of measures to slow down and reduce runoff from throughout the entire watershed is the only realistic option to achieving a measurable benefit. Prepared by: Jim Solstad DNR Waters jim.solstad@dnr.state.mn.us 10