A Comparison of Actual vs. Predicted Leachate Generation

Similar documents
Action Leakage Rate Calculation

Practical Considerations for CCR Facility Design, Operations, and Maintenance

LANDFILL CLOSURE PLAN. Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

Run-on and Run-off Control System Plan

Coal Combustion Product Risk Assessment Using a Probabilistic Cost Modeling Approach

CLOSURE PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

Pond Closure - Case Study[TP1]

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

2015 ANNUAL ENGINEERING INSPECTION REPORT PLUM POINT ENERGY STATION CLASS 3N LANDFILL PERMIT NO S3N AFIN:

Leachate Management Plan

Bioreactor Landfill Design

2016 ANNUAL STRUCTURAL STABILITY INSPECTION REPORT

Closure Plan Limited Purpose Landfill TransAlta Centralia Mine

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

World of Coal Ash Lexington April 2013

Closure of Unlined CCR Impoundments: Working with State and Federal Agencies to Develop a Mutually Acceptable Solution

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD

Initial Closure Plan Phase 1 Module 1 Phase 1 Module 2 Phase 1 Module 3. Columbia Dry Ash Disposal Facility. Wisconsin Power and Light Company

Colon Mine Site Structural Fill

CCP Annual Inspection Report

CCP Annual Inspection Report

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

Brickhaven No.2 Mine Tract A Structural Fill

Leachate Management Leachate Control and Collection

CCR Impoundment Closure: Reshaping your Ash! 2017 MWCC Technical Conference

CCR DESIGN CRITERIA DEMONSTRATION MITCHELL LANDFILL MITCHELL POWER GENERATION PLANT MARSHALL COUNTY, WEST VIRGINIA. Prepared For:

Evaluation of Groundwater Protectiveness of Potential Surface Impoundment Closure Options

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station)

Appendix B Addendum 1 - Revisions to the Operation and Training Plan (dated November 2015) for the Indian River County Class I Landfill

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

Evaluation of Drainage Layer Alternatives for Proposed Landfill Liner at the E.W. Brown Generating Station

RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN

Cell 2 Composite Liner Design Certification

Ardaman & Associates, Inc. Geotechnical, Environmental, and Materials Consultants A Tetra Tech Company

Environmental Factors Associated With Decommissioning That Can Impact Cost, Schedule and Reuse Options

Coal Combustion Residuals Inflow Design Flood Control System Plan

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL

ET COVER SYSTEM IN ARID ENVIRONMENTS

Las Pulgas Landfill Phase I Clean Closure Marine Corps Base Camp Pendleton, Ca

ACTION LEAKAGE RATE GUIDELINE. Prepared by:

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

On behalf of Green Meadow, LLC and Charah, Inc., HDR provides the enclosed Addendum 3 regarding the permit application entitled:

APPENDIX III Hydrologic and Hydraulic Evaluations

Coal Combustion Residual Landfill Annual Inspection Report Corrective Actions Resolution. Boardman Generating Facility

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

ENVIRONMENTAL ENGINEERING LAND SURVEYING

ATTACHMENT B EVALUATION OF POTENTIAL LEAKAGE THROUGH CATEGORY 1 LANDFILL, CALL 4 LINING SYSTEM

Inspection Report. Re: Keystone Ash Disposal Site Annual CCR Unit Inspection Report No. 1

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company

Consulting Engineers and Scientists. Closure Plan. Submitted by: GEI Consultants, Inc Voyager Drive Green Bay, Wisconsin

2017 Annual Landfill Inspection

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio

TECHNICAL MEMORANDUM

Technical Memorandum

An Economic Approach to Dewatering Coarse- Grained Coal Combustion Residuals

Coal Combustion Residuals Landfill Closure and Post-Closure Plans

Landfill Operations to Improve Installation of Cap and Gas Collection

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

2015 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

Pleasants Power Station Landfill Coal Combustion Residual 2017 Annual Report

CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN. Pursuant to 40 CFR

Closure Plan Ash Disposal Area PGE Boardman Power Plant

December 19, GEI Project No Mr. Tim Muehlfeld, P.E. WEC Business Services, LLC 333 W. Everett Street, A231 Milwaukee, Wisconsin 53203

NC2 Ash Disposal Area Run-on and Run-off Control System Plan

Upland Landfill Waste Discharge Application 7295 Gold River Highway Campbell River, British Columbia

Memorandum. MIDS Work Group Barr Engineering Company

CCR Rule Operating Criteria Closure Plan

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

Run-on and Run-off Control System Plan

ENVIRONMENTAL ENGINEERING LAND SURVEYING

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

GCL Chemical Compatibility Testing with CCR Landfill Leachate

WELSH POWER PLANT ASH LANDFILL. Run-on and Run-off Control System Plan

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO S3N AFIN:

HOLLOW ROCK FACILITY 2016 ANNUAL LANDFILL INSPECTION REPORT FOR COAL COMBUSTION RESIDUALS (CCR) EXISTING LANDFILL

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION

Inflow Design Flood Control System Plan Plant McDonough-Atkinson Ash Pond 3 (AP-3) and Ash Pond 4 (AP-4)

AMERICAN ELECTRIC POWER (SWEPCO)

Pond Closures: Solving a Complicated Puzzle

RETENTION BASIN EXAMPLE

This annual inspection report has been prepared to meet the requirements of 40 CFR (b).

June 2017 C.3 Workshop Sizing Example. Section II.B Sizing Volume-Based Treatment Measures based on the Adapted CASQA Stormwater BMP Handbook Approach

storage There are three basic systems for storing liquid SYSTEM DESCRIPTIONS

4.0 ENVIRONMENTAL IMPACT ANALYSIS 4.10 UTILITIES -- WASTEWATER

Gainesville Regional Utilities Deerhaven Generating Station

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for:

VISUAL SITE INSPECTION REPORT

Transcription:

2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ A Comparison of Actual vs. Predicted Leachate Generation Cedric H. Ruhl, PE 1 and Chris Jordan, EI 2 1 Amec Foster Wheeler Environment & Infrastructure, Inc., 14424 Albemarle Point Place, Suite 115, Chantilly, Virginia 20151 2 Amec Foster Wheeler Environment & Infrastructure, Inc., 2801 Yorkmont Road, Suite 100, Charlotte, North Carolina 28208 CONFERENCE: 2017 World of Coal Ash (www.worldofcoalash.org) KEYWORDS: CCR, landfill, leachate, double-liner system INTRODUCTION Coal combustion residual (CCR) landfill leachate is often treated at on-site CCR surface impoundments, but federal and state regulations are driving owners to close these impoundments, therefore requiring alternative, more costly treatment methods. The quantity of leachate for treatment influences the cost, so accurate leachate generation estimates are essential for developing a useful cost-benefit analysis of alternative treatment options. Landfill design engineers often use the Hydrologic Evaluation of Landfill Performance (HELP) 1 model to estimate generation rates and design leachate collection and removal systems (LCRS). The HELP model typically overestimates generation 3, which leads to conservative LCRS designs but potentially inappropriate leachate treatment options. Measured leachate and leakage generation rates at a double-lined landfill facility in the United States southeast was reviewed and compared to historical rainfall events, landfill operations practices, and predicted leachate generation rates. BACKGROUND The landfill facility consists of a double-lined landfill that is permitted to receive CCR wastes. The landfill is partially located over an inactive ash basin. Proposed landfill development will occur in five phases. Phase 1, Cells 1 and 2 encompassing an area of 7.9 hectares (19.5 acres) were constructed in 2009 and began operations in 2011. The landfill was constructed with a leachate collection system (LCS), leakage detection system (LDS), and double liner system. The double liner system consists of the following (from bottom to top): Compacted subgrade; 46 cm (18-in) soil liner with a maximum hydraulic conductivity of 1x10-5 cm/s; Geosynthetic clay liner; Secondary geomembrane (60-mil textured HDPE geomembrane);

LDS geocomposite drainage layer; Primary geomembrane (60-mil textured HDPE geomembrane); LCS geocomposite drainage layer; and 61-cm (24-in) protective cover. Landfill Cells 1 and 2 are adjacent, contiguously lined, and separated by an intercell berm. Each cell has the following pump system: Low-flow LCS pump (151 liters/minute; 40 gallons/minute); High-flow LCS pump (1,457 liters/minute; 385 gallons/minute); and LDS pump (151 liters/minute; 40 gallons/minute). The Cell 1 and Cell 2 sump pumps (six total) discharge into a common force main pipe which discharges to an ash basin. The landfill also incorporates chimney drains that convey contact water at the top area of the landfill to the leachate collection system. A typical chimney drain is shown in Figure 1. Figure 1 Typical chimney drain The Permit to Operate for Cells 1 and 2 was received on March 7, 2011. Based on annual waste placement records between July 2011 and June 2015, waste placement began in July 2011 and occurred intermittently until March 2014. No waste was placed in the landfill between March 2014 and June 2015. A history of waste placement over time is shown in Chart 1.

MEASURED LCS AND LDS FLOW VOLUMES Cumulative LCS and LDS flow quantities were automatically electronically recorded from flowmeter readings at a frequency of numerous times per day for the following systems: Cell 1 low-flow LCS pump; Cell 1 high-flow LCS pump; Cell 1 LDS pump; Cell 2 low-flow LCS pump; Cell 2 high-flow LCS pump; and Cell 2 LDS pump. The LCS and LDS quantity readings were initially greater than zero and were intermittently reset due to power surges, maintenance, or other factors. Data processing initially consisted of summarizing the cumulative leachate and leakage quantities on a daily basis, zeroing the initial quantity, reconciling readings following power surges or maintenance, and interpolating daily leachate readings for sections of missing data. The cumulative daily LCS and LDS data by cell and pump was then consolidated into monthly values of LCS and LDS collected for the landfill facility (Cells 1 and 2). Cumulative measured LCS and LDS volume vs. time are shown in Charts 2A and 2B, respectively.

MEASURED RAINFALL Daily rainfall was recorded from an on-site rain gauge. Daily rainfall data was consolidated into monthly values of cumulative rainfall similar to the leachate and leakage data. Cumulative rainfall vs. time is shown in Chart 3.

ESTIMATED LCS FLOW, RUNOFF, AND LDS FLOW RATES The HELP model 1 was used to estimate LCS flow, runoff, and LDS flow rates for a 25- year timespan for three assumed waste heights as shown in Table 1. Case Waste Depth (ft) Waste Depth (m) Average Annual LCS Drainage (mm/yr) LCS Flow Average Annual LCS Drainage (cm/s) Table 1 - HELP Model Results Runoff Average Annual Runoff (mm/yr) Average Annual Runoff (cm/s) Average Annual Leakage (mm/yr) LDS Flow Average Annual Leakage (cm/s) Case 1 0 0 402.388 1.28E-06 19.977 6.33E-08 15.076 4.78E-08 Case 2 10 3 94.580 3.00E-07 251.417 7.97E-07 42.515 1.35E-07 Case 3 80 24 37.893 1.20E-07 251.417 7.97E-07 23.280 7.38E-08 The estimated LCS flow consists of the infiltration through the waste mass that is collected by the lateral drainage layer. Estimated infiltration vs. waste height from this data is shown in Chart 4.

As shown above, the relationship between estimated infiltration and waste height can be approximated as the average of logarithmic and power best-fit curves. The HELP model also estimates runoff generated. The landfill utilizes chimney drains; therefore, the majority of the runoff will be conveyed to the sump and managed as leachate. Estimated runoff vs. waste height is shown in Chart 5.

As shown above, the relationship between estimated runoff and waste height is constant above a certain height of waste. The estimated LDS flow consists of the estimated leakage through the primary geomembrane that is collected by the leak detection layer. The estimated LDS flow vs. waste height is shown in Chart 6. The relationship between LDS flow and waste height was assumed to have a linear relationship based on estimated LDS flow rates above a waste height of 3 meters. ESTIMATED LANDFILL PROPERTIES The HELP model outputs described above were used to estimate relationships between LCS flow, runoff, and LDS flow and waste height. The waste height over time was estimated using a stepwise process described as follows: 1. Obtain the length and width of the landfill base by approximating the landfill footprint as a square; 2. Estimate the relationship between landfill height and surface area by making appropriate reductions based on sideslope; 3. Estimate the relationship between cumulative airspace volume and landfill height by using the average area method; 4. Estimate the relationship between waste capacity (mass) and landfill height by using the airspace utilization factor; 5. Utilize annual landfill waste reports to estimate cumulative mass of landfilled material; and

6. Convert from cumulative waste mass per time to landfill height per time by using the relationship estimated in Step 4. Step 1: Landfill Cells 1 and 2 have areas of 4.0 hectares (9.9 acres) and 3.9 hectares (9.6 acres) respectively, for a cumulative area of 7.9 hectares (19.5 acres). Assuming a square footprint, the equivalent landfill base width is 281 meters x 281 meters (921 ft x 921 ft). Step 2: The landfill will have 3H:1V sideslopes and will utilize tack-on benches and downdrains for stormwater drainage. Graded benches are not proposed. The relationship between landfill height and surface area was estimated by reducing the equivalent base length by two times the sideslope times the height in question. For example, the surface area at a waste height of 3 meters would be (281 m 2 x 3 x 3 meters) = (263 m) 2 = 69,169 m 2 = 6.92 hectare (17.10 ac). Step 3: The cumulative airspace volume at various waste heights was estimated by using the average area method. For example, the cumulative airspace at a waste height of 3 meters would be 3 m x (69,169 m 2 + 79,000 m 2 )/2 = 222,254 m 3 (294,786 cy). Step 4: The airspace utilization factor (AUF) is the ratio of mass of waste placed divided by volume of airspace utilized including waste and cover volumes. The AUF is 1,076 kg/m 3 (1,814 lbs/cy) based on a previous study. The cumulative waste capacity (mass) at various waste heights was estimated by multiplying the AUF by the cumulative airspace volume (Step 3) at various waste heights. For example, the cumulative waste capacity at a waste height of 3 meters would be 222,254 m 3 x 1,076 kg/m 3 = 239,145,304 kg (267,371 tons). The relationship between estimated waste height and landfill capacity is shown in Chart 7.

Step 5: The mass of material placed in the landfill is recorded on a monthly basis and reported annually to the state regulatory agency. The cumulative mass of waste placed per month was calculated from the incremental mass of waste placed per month which was obtained from the annual reports. Step 6: The height of the landfill for a given month was estimated by using the equation derived in Step 4 as shown in Chart 8. ESTIMATED LCS AND LDS FLOW VOLUMES

Estimated LCS flow volumes over time were calculated based on the estimated landfill height at a point in time (Chart 8) to calculate the area of the active face of the landfill. The contribution of LCS flow from infiltration was assumed to occur over the entire landfill footprint (7.9 hectares); the contribution of LCS flow from runoff was assumed to occur over the active face of the landfill (less than 7.9 hectares for landfill heights greater than 0 m). LDS flow was assumed to occur over the entire landfill footprint. Cumulative estimated LCS and LDS volume over time are shown in Charts 9A and 9B, respectively.

COMPARING MEASURED AND ESTIMATED LCS AND LDS VOLUME Measured and estimated LCS and LDS volume over time are shown in Charts 10A and 10B, respectively. The estimated LCS volume was surprisingly close to the measured LCS volume. The estimated LDS volume was significantly higher than the measured LDS volume.

RELATIONSHIP BETWEEN MEASURED LCS AND LDS FLOWS, AND RAINFALL Measured and estimated cumulative LCS and LDS volume and cumulative rainfall vs. time are shown in Charts 11A and 11 B, respectively. The graphs indicate a correlation between cumulative rainfall and LCS flow, there appears to be less correlation between cumulative rainfall and LDS flow.

Measured and estimated incremental (monthly) LCS and LDS volume and incremental (monthly) rainfall over time are shown in Charts 12A and 12B, respectively. The graphs indicate a correlation between incremental rainfall and LCS flow, there appears to be less correlation between incremental rainfall and LDS flow. Unit LCS and LDS flows per centimeter of rainfall vs. time are shown in Charts 13A and 13B, respectively.

No waste was placed in the landfill between March 2014 and June 2015. The graphs indicated that LCS flow per centimeter of rainfall was relatively consistent over this time period. LDS flow per centimeter of rainfall decreased asymptotically over the same time period. CONCLUSIONS The HELP model generally overestimates the contribution of leachate from percolation 3. However, the combined HELP model predictions of infiltration and runoff accurately

predicted LCS flows at the subject facility over the time period reviewed. We note that the HELP model annual precipitation was estimated to be 108 cm (42 inches) per year and the average actual measured rainfall at the site was 117 cm (46 inches). The contribution of flow from surface water runoff (i.e. chimney drains) exceeded infiltration flows. A study performed by Baucom and Ruhl 2 concluded that the use of chimney drains is an appropriate way to account for the surface runoff from build-out landfill grades and will increase the LCS flows coming from the landfill. The data indicate a strong correlation between LCS flow and rainfall. LCS flows generally increase during months of increased rainfall as shown in Chart 12A, and the LCS flow per centimeter of rainfall was relatively consistent during periods of landfill inactivity (Chart 13A). There does not appear to be a similar correlation between LDS flows and rainfall or LDS flow per centimeter of rainfall (Charts 12B and 13B, respectively). Similar studies should be performed on other landfills in other geographic areas and at different stages in the landfill lifecycle process to determine whether the conclusions described in this paper are applicable for other facilities or are only applicable to the facility studied. REFERENCES [1] Hydrologic Evaluation of Landfill Performance (HELP) Model, Version 3.07, developed by Paul R. Schroeder, Waterloo Hydrogeologic Inc. [2] Baucom, Kyle and Ruhl, Cedric. CCP Landfill Leachate Generation and Leachate Management, 2013 World of Coal Ash, Lexington, 2013. Lexington, KY. [3] Albright, William H. et. al. Alternative Cover Assessment Project Phase 1 Report, Desert Research Institute, October 2002.