DYNAMIC SIMULATION FOR DESIGN IMPROVEMENTS, COST REDUCTION AND OPERATIONAL STABILITY IN LNG PLANT DESIGN

Similar documents
DYNAMICS OF BASELOAD LIQUEFIED NATURAL GAS PLANTS ADVANCED MODELLING AND CONTROL STRATEGIES

LARGE CAPACITY LNG TRAINS TRAINS GNL DE GRANDE CAPACITE

MLNG DUA DEBOTTLENECKING PROJECT

BASIC DESIGN OF PYEONGTAEK LNG RECEIVING TERMINAL-II OF KOREA GAS CORPORATION LA CONCEPTION DE BASE DU TERMINAL METHANIER PYEONGTAEK-II

PROPANE PRECOOLING CYCLES FOR INCREASED LNG TRAIN CAPACITY CYCLES DE PREREFROIDISSEMENT AU PROPANE POUR DES CAPACITES AUGMENTEES DE PRODUCTION DE GNL

TURBO-EXPANDER TECHNOLOGY DEVELOPMENT FOR LNG PLANTS DEVELOPPEMENT DE LA TECHNOLOGIE DES TURBO- EXPANSEURS POUR LES CENTRALES DE GNL

Enhancement of LNG Propane Cycle through Waste Heat Powered Absorption Cooling

OPTIMUM COMPRESSOR CONTROLS FOR CLOSED LOOP REFRIGERATION

Synergies between process energy efficiency and relief loads

GASTECH 2OO2. Doug Yates, LNG Operations Coordinator, Phillips Petroleum Company

Applying Dynamic Process Simulations Toward Flaring Reduction

Dynamic Simulation: a Tool for Advanced Design and Operating Behaviour Prediction

Gastech Singapore October Capital Cost and Efficiency Data for the ZR-LNG Dual Methane Expander Liquefaction Technology

CONVERTING DOMINION COVE POINT LNG INTO BIDIRECTIONAL FACILITY

MITIGATION OF SEASONAL PRODUCTION LOSS FOR THREE PARALLEL 4.7MMTPA

The following sub-systems are provided and the integration of these is described below:

Reliquification of Boil of Gas by using BOG Compressor

ENERGY MANAGEMENT INITIATIVE AT PETRONAS LNG COMPLEX

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET

Preface to the First Edition Preface to the Second Edition. Acknowledgment

Efficacité supérieure Coût inférieur Plus grande fiabilité et robustesse. PO-6.1

UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT

CO 2 RECOVERY FROM CO 2 REMOVAL UNIT AT GL1Z PLANT

ADVANCED PROCESS CONTROL QATAR GAS ONE YEAR EXPERIENCE

COMPARISON OF ENERGY EFFICIENCY BETWEEN VARIABLE AND FIXED SPEED SCROLL COMPRESSORS IN REFRIGERATING SYSTEMS

Low Emissions gas turbine solutions

Appendix 1-A Well Testing

DETERMINING THE MAXIMUM LNG PRODUCTION RATE BY PROCESS SIMULATION MODELLING OF LOW TEMPERATURE NATURAL GAS SEPARATION UNIT

CONTROL SOLUTIONS DESIGNED TO FIT RIGHT IN. Energy Control Technologies

Title slide. LNG Technology. Compiled by PD.Supriyadi

20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile

ON THE OPTIMIZATION OF REFRIGERATION MACHINERY

Exploring the Design Space with System Simulation to Manage Increasing Thermal Loads on Aircraft Fuel Systems

LNG lifecycle dynamic modeling: From process design verification to support operations

There are many cryogenic

Natural Gas Processing Unit Modules Definitions

Thermodynamics: An Engineering Approach, 6 th Edition Yunus A. Cengel, Michael A. Boles McGraw-Hill, 2008

Modular Oil & Gas Equipment Onshore & Offshore

Chiller plant optimization

AP1000 European 15. Accident Analysis Design Control Document

Path Introductory Module to Fundamentals of 01 Oil & Gas Industry. No. Course Title Duration Dates 01 Introductory Module to Fundamentals

Large University Central Chiller Plant Design Considerations

Optimising. the LNG process. The rapidly expanding global LNG industry continues. Projects

Brazed Aluminum Heat Exchangers (BAHX) for Optimisation of Natural Gas Liquefaction Processes. Gastech 2017

Atlantic LNG Train 4 The World s Largest LNG Train

A Discussion of Natural Gas Pipeline System Efficiency. Gas/Electric Partnership Houston, Texas February 11, 2010

DYNAMIC MODELING OF THE ISAB ENERGY IGCC COMPLEX

P. Heyl, H. Quack, Technische Universität Dresden, Lehrstuhl für Kälte- und Kryotechnik, Dresden 01062, Germany

Carbon Capture Options for LNG Liquefaction

AREN 2110: Thermodynamics Spring 2010 Homework 7: Due Friday, March 12, 6 PM

Precooling strategies for efficient natural gas liquefaction

EBARA INTERNATIONAL CORPORATION Cryodynamics Division. Cryogenic Turbine Expanders. cryodynamics. Cryogenic Expanders for Liquefied Gas

Modelica-Based Heat Pump Model for Transient and Steady-State Simulation Using Low-GWP Refrigerants Paper 2264

APPLICATION OF DYNAMIC SIMULATION FOR DESIGN AND COMMISSIONING OF LNG PLANTS (EXPERIENCE IN MLNG TIGA PROJECT)

DYNAMIC SIMULATION OF A PROTON EXCHANGE MEMBRANE FUEL CELL SYSTEM FOR AUTOMOTIVE APPLICATIONS

Total Midstream Solutions in Gas Processing/Treating and Crude Oil Handling

Qualitative Phase Behavior and Vapor Liquid Equilibrium Core

SIMPACK - MODEL DEVELOPMENT PACKAGE FOR POWER PLANTS

Mitigating Emissions and Maintenance Constraints with Flare Consolidation

Steam balance optimisation strategies

DESIGN AND OPERATING EXPERIENCE FOR ANADARKO S LANCASTER FACILITY

Energy. vecta. Forward Thinking

Effects of flow behavior on the design of transient operation scenarios

LNG PROCESS USES AERODERIVATIVE GAS TURBINES AND TANDEM COMPRESSORS

Fluid Mechanics, Heat Transfer, and Thermodynamics. Design Project. Production of Acetone

ME 215. Mass and Energy Analysis of Control Volumes CH-6 ÇANKAYA UNIVERSITY. Mechanical Engineering Department. Open Systems-Control Volumes (CV)

Yokogawa Corporation of America Receives Analyzer Systems and Shelters Order from Freeport LNG

Modularity Approach of the Modular Pebble Bed Reactor (MPBR)

OMESOL. A Potential Hub To Deliver Dynamic Professionals OCTAGON MANAGEMENT & ENGINEERING SOLUTIONS.

How to Evaluate an Existing NGL Recovery Plant Before Finalizing a Process Retrofit Design

0611C. Valve Group. Intelligent Pressure Relief System Management Solution. Farris Engineering Services

Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel

Full electrical LNG-plant: Highest availability and energy efficiency trough overall system design

How to establish an integrated production management system across the reservoir lifecycle

Best Practice Pump Control

LNG Basics for Petroleum Engineers

An Environmentally Friendly Business

Executive Summary. Engineering Report of the: Adaptation of jetties and LNG transfer facilities for loading of bunker vessels in Fos Tonkin

ChE 455 Fall 2001 Major 1. Ethylene Oxide Production

Chandrashekhar Sonwane, David Hanks, Tony Eastland, Ken Tran, Marinelle Peneda, Jeff Mays, and John Vega. September 9-10, 2014

Source Characterization of Ammonia Accidental Releases for Various Storage and Process Conditions

Hydrate Formation in Chevron Mabee Unit for NGL Recovery and CO 2 Purification for EOR. Abstract

CCS system modelling: enabling technology to help accelerate commercialisation and manage technology risk

Natural Gas STAR Methane Challenge Program: Supplementary Technical Information for ONE Future Commitment Option

2014 GCC Conference - Orlando, FL Sept. 30 Oct. 2, Simulation of a Combined Cycle using Dynsim. Eric Liese Office of Research and Development

Varying Views. Variable-primary flow chilled-water systems are of. on Variable-Primary Flow WHAT IS VARIABLE-PRIMARY FLOW? >>>

Yemen LNG Operational feedbacks

2. TECHNICAL DESCRIPTION OF THE PROJECT

THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES

TEST BENCH FOR COMPARATIVE MEASUREMENT OF ENERGY EFFICIENCY OF VARIABLE AND FIXED SPEED SCROLL COMPRESSOR

R13. (12M) efficiency.

Heat Recovery Systems and Heat Exchangers in LNG Applications. Landon Tessmer LNG Technical Workshop 2014 Vancouver

Chapter 5 MASS AND ENERGY ANALYSIS OF CONTROL VOLUMES

Problems in chapter 9 CB Thermodynamics

HOW TO COMPARE CRYOGENIC PROCESS DESIGN ALTERNATIVES FOR A NEW PROJECT

REFRIGERATION CYCLES

CANDU Safety #14 - Loss of Heat Sink Dr. V.G. Snell Director Safety & Licensing

THE CONCEPT OF INTEGRATED CRYOGENIC ENERGY STORAGE FOR LARGE SCALE ELECTRICITY GRID SERVICES. Finland *corresponding author

Optimal operation of the boil-off gas compression process using a boil-off rate model for LNG storage tanks

Ohio Energy. Workshop G. Best Practices in Energy Efficiency to Help You Reduce Your Energy Spend. Tuesday, February 21, :45 a.m.

Transcription:

DYNAMIC SIMULATION FOR DESIGN IMPROVEMENTS, COST REDUCTION AND OPERATIONAL STABILITY IN LNG PLANT DESIGN SIMULATION DYNAMIQUE POUR L AMELIORATION DU PROCEDE, REDUCTION DES COUT, ET STABILITE DE L OPERATION D UN PROCEDE D UNE INSTALLATION DE GNL Satish L. Gandhi, Ph.D. Director - Process (LNG) Felix F. de la Vega, M.S. Vice President - Petroleum (LNG) Fluor Daniel, Inc. Sugarland, Texas, 77487-514, U.S.A. ABSTRACT This paper discusses some of the dynamic and steady state simulation studies performed for LNG plants utilizing the APCI propane (C3) precooled mixed refrigerant () cycle which have resulted in or indicated the way towards design improvements and reduction in plant costs while ensuring stable operation. The dynamic studies presented include (a) reduction in flare header size and cost by minimizing the potential for release from refrigeration compressors; major failure scenarios considered are total and partial loss of power to C3 compressor s air-cooled exchanger fans, inadvertent closure of block valve at the outlet of C3 compressor, and inadvertent closure of block valve at the outlet of C3 receiver, and (b) elimination of pressure surge dampening equipment in LNG loading lines. The steady state design studies presented include (a) optimization of C3 condenser size for the specified availability of gas turbine power, and (b) sensitivity of LNG production to variations in compressor performance characteristics. RESUME Ce papier présente quelques études de simulation en régime dynamique et permanent du procédé APCI à cycle aux réfrigérants mélangés pré-refroidi résultant en ou menant dans une voie d une amélioration du procédé avec une réduction des coûts de l installation tout en assurant la stabilité de l opération. D.3 1

Les études présentées incluent; (a): une réduction de dimension du collecteur de torche ainsi que le coût en minimisant les fuites potentielles du compresseur de réfrigération, en considérant les scénarios de failles majeurs telles que: perte totale ou partielle de l énergie motrice du ventilateur de l échanger à air du compresseur de propane, fermeture inattentive de la vanne de sectionnement du refoulement du compresseur propane, et fermeture inattentive de la vanne de section de la ligne de soustirage du ballon accumulateur de propane, et (b): l élimination de l équipement d élimination de surpression dans les lignes de chargement de GNL. Les études de calcul en régime permanent présentées incluent, (a): optimization de la dimension du condenseur de propane pendant la disponibilité de l énergie motrice de la turbine à gaz, et (b) l analyse de sensibilité de la réponse du compresseur de réfrigération aux variations des caractéristiques de la performance du compresseur. INTRODUCTION This paper presents several studies performed for LNG plants which have resulted in or indicated the way towards design improvements and reduction in plant costs while at the same time ensuring stable operation. Most of these studies have been carried out utilizing an integrated dynamic process simulation model of the APCI propane precooled cycle in LNG plants. Since it is an integrated model, the effects of interactions between the C3 and refrigeration-compression systems are considered which is essential for addressing LNG plant dynamics and design issues. A schematic drawing of an APCI propane precooled cycle in an LNG plant with air cooling is shown in Figure 1. The dynamic process simulation model is built from a library of customized unit operation models of individual equipment and control systems specifically developed for LNG plant design. The dynamic simulation model converts into a steady state modeling tool by simply setting the time derivatives of state variables to zero. The model allows analysis of a wide range of problems related to the process design of LNG plant, either dynamic (time dependent) or steady state. The design issues addressed in this paper include the following: Flare header sizing and cost reduction Hydraulic surge analysis of the LNG loading system Optimum design of the C3 condenser Sensitivity of LNG production to variations in compressor performance curves FLARE HEADER SIZING AND COST REDUCTION The relief flows associated with major plant upsets are usually derived from steady state analysis. Such analyses ignore the dynamic interactions between various parts of the process. This approach also precludes a way to assess the impact of process or control system modifications that could be implemented for mitigating the maximum relief D.3 2

flows. These limitations lead to designing relief and flare header systems that are significantly oversized and costly. The dynamic process simulation model of the LNG plant developed at Fluor Daniel allows us to evaluate the actual dynamic response of the system to any potential failure or upset scenario within the LNG plant. The model also provides an efficient tool for evaluating design alternatives, such as high integrity instrumentation systems, for mitigating or eliminating the impact of plant failures. Three major plant upset scenarios usually considered for sizing the relief and flare header systems during the process design of an LNG project (assumed to be an air-cooled plant) are discussed below. FIGURE 1 LNG EXPANDER G M FLASH GAS COMPRESSOR TO FUEL GAS MERCURY DEHYDRATION REMOVAL UNIT UNIT HHP HP MP LP G EXPANDER LNG RUNDOWN TO STORAGE MAIN CRYOGENIC HEAT EXCHANGER GT M SYSTEM TO/FROM FRACTIONATION UNIT RECEIVER F LP MP HP HHP PROPANE SYSTEM GT M PROPANE RECEIVER LP MP HP HHP Loss of Power to C3 Compressor s Air-Cooled Exchanger Fans The dynamic response of the relief system to the total loss of power to the C3 compressor s air-cooled exchanger fan motors is shown in Figures 2 and 3. Even with the total loss of power, about 1% of air flow is maintained to account for natural convection. The flow and the back pressure at the relief valve are shown as % of the maximum allowable relief rate and back pressure requirements. The back pressure limitation at the relief valve is based on the lowest set pressure of the critical relief valves in the flare header system. The dynamic response of the relief rate at the flare tip is somewhat damped and delayed as compared to that at the relief valve due to the effect of packing in the flare header piping. The dynamic response shows that the total loss of power to the exchanger air fans would result in maximum relief rate and back pressure at the relief valve about 25% higher than the maximum allowable values. This would require increasing the pipe diameters for both the relief valve outlet header piping as well as the long main flare header piping to the flare stack resulting in a significant increase in the cost of the flare header system. D.3 3

An alternative for reducing the maximum relief flow is providing emergency power to some of the air fan motors in case of total loss of power. A dynamic simulation analysis was performed to evaluate the sensitivity of the relief rate and back pressure to the availability of emergency power. The results for 75% loss of power (or availability of emergency power to 25% of air fan motors) are shown in Figures 4 and 5 and for 5% loss of power (or availability of emergency power to 5% of air fan motors) are shown in Figures 6 and 7. It is seen that the relief flows as well as the back pressures at the relief valves are only about 5% and 25% of the maximum allowable value for the 75% and 5% loss of power, respectively. The analysis confirmed that providing emergency power to 25% of the air fans instead of increasing the size of the flare header piping is a cost effective solution to the total loss of power scenario. flow - % max 1 12 2 Total Loss of Power flare tip relief valve rv back pressure - % max 1 12 2 Total Loss of Power Figure 2 Figure 3 flow - % max 2 75% Loss of Power flare tip relief valve rv back pressure - % max 2 75% Loss of Power Figure 4 Figure 5 D.3 4

flow - % max 2 5% Loss of Power flare tip relief valve rv back pressure - % max 2 5% Loss of Power Figure 6 Figure 7 Inadvertent Closure of Block Valve at the Outlet of C3 Compressor with Bypass Relief Valve Similar to the loss of power scenario discussed earlier, dynamic simulation analysis of the inadvertent closure of the block valve in the discharge line of the C3 compressor showed maximum relief rate and back pressure at the relief valve to be higher than the allowable values. The block valve is located between the C3 desuperheater and the C3 condenser after the recycle line take-off point. A proposed solution for minimizing the potential for release is to provide a modulating relief valve as a bypass around the block valve. The set point for the bypass relief valve is lower than that of the relief valve which releases into the flare header at the discharge of C3 compressor. The dynamic response of the pertinent system variables to the closure of the block valve over a period of 15 seconds in presence of the bypass relief valve is shown in Figures 8 to 12. The response in Figure 8 shows the flow rate through the bypass relief valve as % of the initial flow before the closure of the block valve. The C3 compressor discharge pressure in Figure 9, as % of the initial discharge pressure at time zero, shows that the bypass valve is able to maintain the discharge pressure below the relief valve set pressure causing the relief valve to the flare header to remain closed. The C3 and compression power, as % of their respective initial values at time zero, are shown in Figure 1. In this case the gas turbines had enough spare power to avoid trip during the power peaks observed in the transient response. The dynamic response of the anti-surge system in preventing each of the four stages of the C3 compressor from surge is shown in Figures 11 and 12. The simulation results indicate that the transient response of the system stabilizes after about 1 minutes and the C3 compressor is able to operate through the bypass around the closed block valve, although less efficiently and at a higher discharge pressure and consequently higher temperature levels. Thus, the overall dynamic response of the system validates the proposed design modification of using a modulating relief valve as a bypass around the block valve in eliminating the potential for relief due to the inadvertent D.3 5

closure of the block valve. The dynamic simulation analysis of the system was also used to determine the appropriate size of the bypass relief valve. flow - % initial C3 Compressor Blocked Outlet 12 2 block valve bypass rv Figure 8 C3 discharge P - % initial C3 Compressor Blocked Outlet 13 12 11 9 rv set pressure Figure 9 power - % initial C3 Compressor Blocked Outlet 125 12 115 11 15 95 C3 Figure 1 anti surge valve - % open C3 Compressor Blocked Outlet LP 2 Figure 11 MP D.3 6

anti surge valve - % open C3 Compressor Blocked Outlet HP 2 Figure 12 HHP Inadvertent Closure of Block Valve at the Outlet of C3 Receiver Another major failure scenario with potential for a significant release to the flare header is the inadvertent closure of the block valve at the outlet of the C3 receiver. The release would occur if the C3 receiver and condenser become filled with liquid before depletion of liquid C3 inventory from the propane vaporizers. The dynamic response of the system to such a failure scenario is depicted in Figures 13 to 18. The propane condenser gets completely flooded in less than 4 minutes after the closure of the block valve and causes the release to occur. The maximum relief rate and back pressure at the critical relief valve, shown in Figures 13 and 14 respectively, are essentially the same as the maximum allowable values, i.e., %. The C3 compressor discharge pressure, as % of the initial discharge pressure at time zero, is shown in Figure 15. The C3 and compression power, as % of their respective initial values at time zero, are shown in Figure 16. The dynamic response of the anti-surge system in preventing each of the four stages of the C3 compressor from surge is shown in Figures 17 and 18. The dynamic simulation response confirmed the current design of the relief and flare header system to be adequate in handling the relief load associated with this upset scenario assuming enough spare power is available. If not, the compressor will overload and trip shortly on or after the initial relief. An alternative to avoiding such a trip would be a modulating relief valve bypass around the block valve. D.3 7

flow - % max 12 2 relief valve flare tip rv back pressure - % max 12 2 Figure 13 Figure 14 C3 discharge P - % initial 13 12 rv set pressure 11 9 power - % initial 13 12 11 9 C3 Figure 15 Figure 16 anti surge valve - % open 2 LP MP anti surge valve - % open 2 HP HHP Figure 17 Figure 18 D.3 8

HYDRAULIC SURGE ANALYSIS OF THE LNG LOADING SYSTEM A hydraulic surge analysis of the LNG loading system was conducted to determine the need for pressure surge dampening equipment to maintain the surge pressures below the pipeline design pressure. The system comprised of several LNG storage tanks and loading pumps and dual LNG loading lines from the storage tanks to the LNG loading jetty. The study involved evaluation of several potential failure scenarios. One of the potential worst case scenarios considered activation of an emergency trip due to the closure of the trip valves at the LNG loading jetty with a subsequent trip of all loading pumps except one in each tank failing to trip. The emergency trip initiates a simultaneous closure of the trip valves at the jetty (with a closure time of 5 seconds) and the trip valves at the plant boundary (with a closure time of 15 seconds). The closure profiles of the trip valves and associated surge pressure profiles are shown in Figures 19 and 2. The hydraulic transient response showed formation of vapor cavities at the emergency trip valves located at the jetty and certain high elevations in the loading lines. This results in spikes in pressure profile, such as the one seen around 16 seconds in Figure 2 due to the collapse of the vapor cavity at the jetty trip valves. The hydraulic surge study determined that pressure surge dampening equipment was not required for the LNG loading system. 12 Hydraulic Surge Analysis pressure (% max) valve (% open) 12 Hydraulic Surge Analysis pressure (% max) valve (% open) % value Emergency Trip Valves - Plant % value Emergency Trip Valves - Jetty 2 2 5 1 15 2 25 3 time (sec) Figure 19 1 2 3 time (sec) Figure 2 OPTIMUM DESIGN OF THE C3 CONDENSER SIZE The LNG plant simulation model is an effective tool for optimizing the sizes of the C3 and compressor discharge and inter-stage coolers and C3 vaporizers. Results from an LNG plant study conducted for optimizing the C3 condenser size for a fixed total available power from the C3 and gas turbines and helper motors are shown in Figures 21 and 22. A plot of LNG production capacity versus condenser size is shown in Figure 21. Both the LNG production capacity and the condenser area are shown as % of the base design case values. The LNG production capacity increases and the rate of increase in LNG production capacity represented by the slope of the curve decreases with increasing C3 condenser area. Plots of variations in C3 and compression power, as % of the total fixed available power, are shown in Figure 22. The C3 compression power D.3 9

requirement decreases while the compression power requirement increases with increasing C3 condenser area. Based on the above information, an economic analysis was performed to determine the most cost effective size of the C3 condenser. C3 Condenser Size Optimization 14 C3 Condenser Size Optimization LNG prod - % base design 12 98 power - % total 55 5 45 C3 96 75 125 15 175 2 condenser size - % base design Figure 21 75 125 15 175 2 condenser size - % base design Figure 22 SENSITIVITY OF LNG PRODUCTION TO VARIATIONS IN COMPRESSOR PERFORMANCE CURVES The compressor performance curves available during the initial process design of an LNG project furnished by compressor vendors are based on preliminary information. Since the compressor performance curves affect the LNG production capacity, it is worthwhile to assess the sensitivity of LNG production to variations in head-flow performance curves for each stage of the C3 and compressors. This information is very helpful to compressor vendors in optimizing the compressor performance. The LNG plant simulation model provides an effective tool for conducting a study of this type. Results from an LNG plant study on the sensitivity of LNG production to variations in the head-flow performance curve for the HHP stage of the C3 compressor are provided in Figures 23 and 24. The analysis is based on a fixed total available power from the C3 and gas turbines and helper motors. The effect of (+/-) 1% variations in the head value for the HHP stage on the LNG production capacity, as % of base design case value, is shown in Figure 23. The LNG production capacity decreases with an increase in the HHP stage head. Plots of variations in C3 and power, as % of total fixed available power, are shown in Figure 24. These plots show that the C3 compression power requirement increases while the compression power requirement decreases with an increase in the HHP stage head. Similar information developed for each stage of the C3 and compressors can then be furnished to compressor vendors for use in their own design optimization effort. D.3 1

LNG prod - % base design Sensitivity to Variations in Head- Flow Performance Curve 11 99 98 9 95 15 11 C3 HHP head - % base design Figure 23 power - % total Sensitivity to Variations in Head- Flow Performance Curve 55 5 45 9 95 15 11 C3 HHP head - % base case Figure 24 C3 CONCLUSIONS State-of-the-art modeling tools developed by Fluor Daniel are being used in the performance of dynamic and steady state simulation studies in LNG plant design. These studies are very helpful in addressing a multitude of process design issues during various phases of LNG projects including basic design, detailed engineering, and plant startup and operation. The studies result in improved, cost effective and reliable design of LNG plants. D.3 11