INSTALLATION OF AIRFIELD LIGHTING UNDERGROUND ELECTRICAL DIRECTIONAL BORE DUCT

Similar documents
SPECIAL SPECIFICATION 6666 Charter Communications System

SECTION LIGHTNING PROTECTION SYSTEM

Rapid Axial Load Testing of Drilled Shafts

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE

SECTION GRAVITY WASTEWATER LINES

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

New Conduit Specification

SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System

SECTION HORIZONTAL DIRECTIONAL DRILLING

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

APPENDIX A MEASUREMENT AND PAYMENT

SECTION 1 GENERAL NOTES

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

7/17/2017 Page 1 of 5

2013 ANNUAL AIRFIELD PAVEMENT REHABILITATION CONTRACT NO ADDENDUM NUMBER TWO. Scope of this Addendum

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers.

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

City of Thomasville Water, Sewer & Natural Gas Specifications

SUPPLEMENTAL TECHNICAL SPECIFICATION

SECTION 02215BP TRENCHING AND BACKFILLING

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

MATERIAL ALLOWANCES AND UNIT PRICES

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

REGIONAL CONSTRUCTION STANDARDS

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.

SPECIAL SPECIFICATION Thermal Integrity Profiler (TIP) Wire Cable Testing of Drilled Shafts

SECTION GRAVEL PACKED WATER WELL

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

East US Route 36 Sewer Extension Addendum #1

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

Specification Lightning Protection Systems

SECTION DRILLED CONCRETE PIERS AND SHAFTS

Special Specification 6357 Windstream Telecommunication System

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

Section 70 Airport Transformer Vault and Vault Equipment (FAA L-109)

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

CONSTRUCTION SPECIFICATIONS FOR ALABAMA STATE PORT AUTHORITY MCDUFFIE TERMINALS CONVEYOR 44 PILING INSTALLATION

DESCRIPTION. S-PAPI-1.3. Contractor shall be present and make adjustments as necessary during the FAA Flight Check. EQUIPMENT AND MATERIALS

DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA SPECIAL PROVISION. Section 550 Storm Drain Pipe, Pipe-Arch Culverts, and Side Drain Pipe

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

DIVISION 33 UTILITIES SPECIFICATION : HORIZONTAL DIRECTIONAL DRILLING

SECTION 8 SEPARATION OF LINES

PUBLIC WORKS DEPARTMENT GENERAL NOTES

SPECIAL SPECIFICATION 7441 Remove Components of Existing Traffic Management System

[ADD / DELETE / MODIFY FOLLOWING ITEMS AS APPROPRIATE TO THE PROJECT:]

SUBSURFACE ROTARY DRILLING INVESTIGATION SPECIFICATIONS

Non-destructive Testing of Installed Soil Nails Using Sonic Echo Test Method

SECTION CONCRETE FORMWORK AND ACCESSORIES

ZG Scope. 2 Applicable Documents. 3 General. 4 Stock Item Numbers. Padvault Single-Phase Residential, 2.1 PacifiCorp Material Specifications

SPECIAL SPECIFICATION 5170 Install Weigh-In-Motion (WIM) Equipment

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SPUN CONCRETE POLE AND DRILLED SHAFT FOUNDATION

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

Stainless Steel Aeration Equipment Specification

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION DUCTILE IRON PILES

Section 2: Underground

Best Management Standards / Specifications. For Concrete Slab Raising. Prepared in conjunction with the Concrete Repair Association

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control

Special Specification 6016 Intelligent Transportation System (ITS) Multi-Duct Conduit

SECTION SUBSTATION BUS ASSEMBLIES ERGLE SUBSTATION

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID:

REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form

SECTION PACKAGE BOOSTER PUMP STATIONS

CITY OF UNION, OREGON TECHNICAL SPECIFICATIONS SECTION 9 UNDERGROUND UTILITIES

CONDUITS AND FITTINGS

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

Lantz-Boggio Architects, P.C LBA Project No

SECTION 552 HELICAL ANCHORS AND HELICAL PILES

SECTION SHEET PILES. A. This section covers the contract item Sheet Piles. This work includes:

Soil Improvement by Compaction Grouting

Sample Specifications for Testing Foundations with the Thermal Integrity Profiler (TIP)

SECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving.

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

SECTION GROUNDING AND BONDING

SECTION MINOR CONCRETE

SECTION SINGLE-PLY ROOFING SYSTEM

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 27 Communication 0528 Pathways. Page 1 of 6

CHAPTER 11 CONDUITS AND FITTINGS

SECTION WASTEWATER FORCE MAINS

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

Specifications for Electrical Underground Distribution Systems from Overhead Transformation, Apartments & Condominiums

Transcription:

UNDERGROUND ELECTRICAL PART 1 GENERAL 1.1 SECTION INCLUDES: A. The work specified in this section consists of furnishing and installing underground utilities using the method of installation commonly referred to as directional boring. This work shall include all supervision, services, equipment, materials, labor, area restoration, environmental protection and incidentals for the complete and functional installation of the directional bore duct as shown in the Contract Documents. A #2 AWG solid copper counterpoise conductor shall be installed with and external to the directional bore duct. Quantity of counterpoise shall be per the details. #2 AWG solid copper counterpoise shall be paid for by the linear foot in accordance with Item L-108. 1.2 RELATED DOCUMENTS AND SECTIONS: A. Item L-110; Airport Underground Electrical Duct Banks and Conduits. B. Section 555; Directional Bore - FDOT Specifications for Road and Bridge Construction. 1.3 SUBMITTALS: A. Work Plan: Prior to beginning work, the Contractor shall submit to the Engineer a general work plan outlining the procedure and schedule to be used to execute the work task. Plan shall document the thoughtful planning required to successfully complete the work. B. Demonstration of compliance with Item L-110 and FDOT Section 555. C. Equipment: Contractor shall submit specifications on directional drilling equipment to be used in the work to ensure that the equipment will be adequate to complete the project. D. Material: Specifications on material to be used shall be submitted to Engineer. Material shall include the pipe, conduit, fittings, splicing/coupling method, means of transition from HDPE to PVC and any other item, which is to be an installed component of the project. L-110S-02310-1

1.4 WARRANTY: A. All equipment and materials furnished and installed under this section shall be guaranteed against defects in materials and workmanship for a period of twelve (12) months from final acceptance by the Owner. The defective materials and/or equipment shall be repaired or replaced, at the Owner's discretion, with no additional cost to the Owner. PART 2 EQUIPMENT REQUIREMENTS 2.1 GENERAL: A. The directional drilling equipment shall consist of a directional drilling rig of sufficient capacity to perform the bore and pullback the pipe, a drilling fluid mixing and delivery system of sufficient capacity to successfully complete the crossing, a guidance system to accurately guide boring operations and trained and competent personnel to operate the system. All equipment shall be in good, safe operating condition with sufficient supplies, materials and spare parts on hand to maintain the system in good working order for the duration of the project. 2.2 GUIDANCE SYSTEM: A. The guidance system shall be of a proven type and shall be setup and operated by personnel trained and experienced with this system. The Operator shall be aware of any magnetic anomalies and shall consider such influences in the operation of the guidance system if using a magnetic system. B. The locating and tracking system must provide information on: 1. Clock and pitch information. 2. Depth. 3. Transmitter temperature. 4. Battery status. 5. Position (X,Y). 6. Azimuth, where direct overhead readings (walkover) are not possible (i.e. subaqueous or limited access transportation facility). 7. Ensure proper calibration of all equipment before commencing directional drilling operation. C. Take and record alignment readings or plot points such that elevations on top of and offset dimensions from the center of the product to a permanent fixed feature are provided. Such permanent fixed feature must have prior approval of the Engineer. Provide elevations and dimensions at all bore alignment corrections (vertical and horizontal) with a maximum distance of 5 feet between points. Provide additional points when requested by the Engineer. Provide a L-110S-02310-2

2.3 CONDUIT/DUCT: sufficient number of elevations and offset distances to accurately plot the vertical and horizontal alignment of the installed product. A. The directional bore conduit/duct shall be Carlon Electrical UL Listed Schedule 80 minimum standard dimensional ratio (SDR) 11, suitable for placement with directional boring under pavement or accepted equivalent. All duct connections shall be made by electrofusion coupling splicing, 8 minimum length Morris Compression coupling, or accepted equivalent. B. Splices and couplings shall be permitted only where connection to conventionally installed ducts or manholes are required. C. The HDPE duct shall be properly reamed prior to assembly. 2.4 CONCRETE: A. Concrete shall be P-610 or FDOT Class II concrete with 1 inch maximum size coarse aggregate (FDOT #57 stone) with a minimum 28 day compressive strength of 3,400 PSI or equivalent. Where reinforced duct banks are specified, reinforcing steel shall conform to ASTM A 615 Grade 60. Concrete and reinforcing steel are incidental to the installation/construction of which they are a component part. B. High early strength P-610 concrete will be required for use with ducts, conduits, base cans and other work as directed by the Engineer, in existing operational areas and within the safety areas of operational pavement to comply with the project phasing and scheduling requirements and where the pavement is required to open to aircraft at the end of the designated work period. The extra cost for the high early strength P-610 concrete shall be considered incidental to the respective installation/construction of which it is a component part. 2.5 COPPER COUNTERPOISE WIRE A. The 2 AWG solid copper counterpoise wire shall comply with Item L-108. The 2 AWG solid copper counterpoise wire shall be installed with and externally to the directionally bored duct. PART 3 EXECUTION 3.1 GENERAL: A. The Engineer shall be notified 48 hours in advance of starting work. The Directional Bore shall not begin until the Engineer is present at the job site and agrees that proper preparations for the operation have been made. The L-110S-02310-3

Engineer s approval for beginning the installation shall in no way relieve the Contractor of the ultimate responsibility for the satisfactory completion of the work as authorized under the Contract. 3.2 BORING PATH REPORT: A. Furnish a bore path report to the Engineer within seven days of the completion of each bore path. Include the following in the report: 1. Location of project and financial project number including the permit number when assigned. 2. Name of person collecting data, including title, position and company name. 3. Investigation site location (Contract plans station number or reference to a permanent structure within the project right-of-way). 4. Identification of the detection method used. 5. Elevations and offset dimensions as required in 02310-2.2. B. Provide as-built plans to the Engineer in accordance with FDOT 555-6. 3.3 SPLICING, COUPLING AND TERMINATION: A. The HDPE duct shall relax for 48 hours after installation prior to splicing, coupling or termination. B. Only Engineer accepted methods shall be used to splice, couple or terminate the HDPE or PVC duct. C. All splicing, coupling and termination of HDPE or PVC ducts shall be performed and completed in strict accordance with the manufacturer s instructions and recommendations. PART 4 METHOD OF MEASUREMENT 4.1 METHOD OF MEASUREMENT: A. The items described in this item are incidental to other items and shall not be measured for payment. L-110S-02310-4

PART 5 BASIS OF PAYMENT 5.1 BASIS OF PAYMENT: A. No direct payment shall be made for the work described in this item. All directional bore costs shall be considered incidental to the respective L-108 or L- 110 specification items. END OF L-110S-02310-5

PAGE INTENTIONALLY LEFT BLANK L-110S-02310-6