CASE HISTORY: CONDUCTIVITY & COST COMPARISON FOR VERTICAL AND HORIZONTAL CLOSED LOOP GROUND HEAT EXCHANGERS

Similar documents
Applying Geothermal Technology for Large Scale Projects

IGSHPA Tech. Conference & Expo

Ground Loop Design. Thermal Conductivity Report - 2/15/2012. Calculation Results

IGSHPA Certified GeoExchange Design (CGD) Course

Other Names for Ground Loop Systems

The Implementation of Low Temperature District Energy Systems using GeoExchange Technology

Overview of Geothermal Technologies

Q. How does a ground source heat pump function to heat and cool?

Mechanical Redesign. Existing System: The following schematic was devised below.

Ground Source Heat Pump System Design and Case Studies

Design of Commercial Ground Source Heat Pumps

Geothermal Alliance of IL ComEd trade ally event January 9 and 11, 2018

THE GEOTHERMAL ADVANTAGE

GEOTHERMAL HEAT PUMPS CONFIGURATIONS/INSTALLATION

Ground Source Heat Pump System Design and Permitting AWWA Pacific Northwest Section Conference, May 6-8, 2009 Salem, Oregon

geoexchange as an alternative energy source DESIGN APPROACHES

Geothermal Heating & Cooling in Health Care Applications

In-Depth Exploration of Ground Source Heat Pump Technologies

Glen Burnie High School Glen Burnie, MD. Wade Myers Mechanical Option

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2

Pitfalls of Rules of Thumb in Geothermal Heat Pump Design

Horizontal Borehole Study

Research on Ground Source Heat Pump Design

Highlights of the California GeoExchange Project

GEOTHERMAL OVERVIEW. Presented by John Cole East Coast Account Rep. for RENEWABLE ENERGY. Construction Automotive Industry

Optimal Design for a Hybrid Ground-Source Heat Pump

ASHRAE. Wxá zç Performance Innovation Experience. Why Geothermal HVAC Systems Fill The Bill. Kirk Mescher, PE P PE. Education.

CHAPTER 39 REQUIREMENTS FOR PROPERLY PLUGGING ABANDONED WELLS

GHP Data Collection and Monitoring System at the SRRL

Presented by: David G. Lamothe, P.E.

Geothermal Heating and Cooling A New Way to Realize the Benefits. October Christopher A. Cavanagh, PE

DOE Webinar Residential Geothermal Heat Pump Retrofits

Portland International Jetport s

Renewable Heat for Renewable Cities: Geoexchange Heating and Cooling: Introduction and Case Study of St Peters College Sports Centre

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Adapting Geothermal Flow to Heat Pump s Requirement When efficiency and flow meet

Geothermal Heat Pump Systems Metropolitan Washington Council of Governments Built Environment and Energy Advisory Committee May 19, 2016

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

GEO-HEAT CENTER EXECUTIVE SUMMARY

Assisting Energy Savings While Protecting 2009 REVISIONS TO GUIDELINES FOR THE CONSTRUCTION OF VERTICAL BOREHOLES

Figure 4-8. horizontal trench loops single-pipe, single-trench loops

BETTER BUILDINGS BY DESIGN Sheraton Conference Center Burlington, Vermont. February 8, 2012

CLOSED-LOOP HEAT EXCHANGER FOR GROUND COUPLED HEAT PUMPS

Delta School District #37 Geothermal Project A new direction for provincial Facilities

Summary of Responses to Surveys on Experience with GHP Installations in Federal Facilities and Minimum Qualifications of GHP-related Professionals

2016 International Petroleum Environmental Conference HORIZONTAL DIRECTIONAL DRILLING AND WELL INSTALLATION AT SMALL SITES

GEO-HEAT CENTER EXECUTIVE SUMMARY

A New Type of Hybrid Groundwater Energy System

Alaska Geothermal LLC Geothermal Heat Pumps. Alternatives for Heating, Cooling & Domestic Hot Water Production

Go Green Go Geothermal

Mechanical Depth. Redesign and Analysis

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

Making GeoExchange mainstream. Ed Lohrenz, B.E.S., CGD. III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide 1

The Hybrid Geoexchange Primer. August 2015

FLOWING ARTESIAN WELLS

Contrary to popular belief an engineer doesn t have to be the enemy. T hey can be a valuable team member.

GHEX Borehole Proposed Rulemaking

ABSTRACT & POWERPOINT PRESENTATION

Zero Net Energy Retrofits at UC Davis

An Analysis on Cost Reduction Potential of Vertical Bore Ground Heat Exchangers Used for Ground Source Heat Pump Systems

Underground Thermal Energy Storage (UTES) Opportunities in FL Utilizing Boreholes & Aquifers

Sustainable Utilities using GeoExchange Technology

GEOEXCHANGE: THE ROAD TO THIRTY PERCENT

An Evaluation of the Fort Polk Energy Savings Performance Contract. Patrick J. Hughes John A. Shonder Oak Ridge National Laboratory

A. This Section includes exterior piping for vertical, direct-buried, ground-loop, heat-pump systems that operate between 23 and 104 deg F.

THE SCIENCE OF REFRIGERANT-BASED GEOTHERMAL. Gregor Vialette

III. Economics. A. General Page III-2 B. Initial Capital Costs Page III-3 C. Life Cycle Costs Page III-4

Geothermal Heat Pump Systems Being Green by using the Ground

LARGE DIAMETER HDPE SLIPLINING WHERE EXPERIENCE MATTERS

04/04/2012. Inc. By: Skanska. Image. New. Castle, DEE

Geoexchange for BC Public Sector Organizations

White Paper. Geothermal Heating and Cooling

APPLICATION MANUAL. Improving Geothermal Heat Pump Air Conditioning Efficiency with Wintertime Cooling using Seasonal Thermal Energy Storage (STES)

REHAU MONTANA ECOSMART HOUSE PROJECT Bozeman, MT RMEH 01 Test Report. Geothermal Performance of Helix vs. Vertical Borehole

Implementing the California Ocean Plan - Desalination Amendments - Analysis of Subsurface Intake Feasibility

AB 2339 WORKING GROUP DRAFT DOCUMENT. Draft Energy Commission Policy for Ground Source Heat Pumps April 19, 2013

Evaluation of Vertical and Horizontal Geoexchange Systems

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

LEED Platinum Showcase: 5/14/2013

SECTION GRAVITY WASTEWATER LINES

Ground Source Heat Pumps

The American Council for an Energy-Efficient Economy Emerging Technologies Report. Residential Ground-Source Heat Pumps July, 2007

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

Jack DiEnna Executive Director The Geothermal National & International Initiative

DOE Task 99-4 Extension of Design and Simulation Models 3/24/00 EXTENSION OF EXISTING DESIGN AND SIMULATION MODELS

Geotechnical Investigations Water Main Construction

Section IV : Some Technical Specifications of Geothermal Systems

Closed-Loop/Geothermal Heat Pump Systems

SECTION BORING AND/OR JACKING PIPE

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14

INCORPORATION OF GROUNDWATER FLOW INTO NUMERICAL MODELS AND DESIGN MODELS

Consolidating Systems for a Greener Future:

Geothermal Systems: Harnessing Earth s Energy

The basic elements of the system include: Buried loops of piping (the ground loop); A biodegradable liquid antifreeze;

Energy Efficiency, GeoExchange Systems and Renewable Energy MiAPPA Winter 2010

Introduction to Geothermal Comfort Systems in INDIA

Sustainability Utilization of FAA VALE Grants for Geothermal Projects

Bioreactor Landfill Design

Transcription:

CASE HISTORY: CONDUCTIVITY & COST COMPARISON FOR VERTICAL AND HORIZONTAL CLOSED LOOP GROUND HEAT EXCHANGERS John D. Geyer, CGD John Geyer & Associates, Inc. Vancouver WA October 2014 IGSHPA Baltimore MD

Traditional Horizontal mat Vertical Loops are common design practice for buildings >50,000 Sq. Ft. Vertical bores may be incompatible with artesian flow conditions or groundwater protection closures October, 2014 John Geyer & Associates, Inc. 2

San Francisco Bay Similar 350-ton horizontal systems at two sites, 12 miles apart and in the same year October, 2014 John Geyer & Associates, Inc. 3

Community College Campus (new 140,00 SF Main Building) October, 2014 John Geyer & Associates, Inc. 4

Proposed 440 Borehole Vertical Field hit Artesian Flow with Upward Leakage past Grout October, 2014 John Geyer & Associates, Inc. 5

Vertical field construction was partially done when multiple artesian leaks jeopardized drilling permits October, 2014 John Geyer & Associates, Inc. 6

ARTESIAN LEAKAGE required Plug & Abandon cementing of vertical loops and design change to horizontal bores October, 2014 John Geyer & Associates, Inc. 7

Project Re-design Due to concerns of leakage and pressure from permitting authorities, vertical installation was halted Horizontal options were considered excavated pit loop and horizontal borehole installation No area available for excavated GHX, leaving only a horizontal borehole option Loads and heat pump schedule were integrated into horizontal borehole simulations Preliminary field scope defined by simulations considering available area, site restrictions and asset capabilities TC test parameters defined by simulations October, 2014 John Geyer & Associates, Inc. 8

Heat with >15 Watts/ Foot for 48 Hours (Soil Temperature, Thermal Capacity and Dissipation Rate) October, 2014 John Geyer & Associates, Inc. 9

Alternative Horizontal Loop Configuration Plane View (Top) - 15 End View - 30 10 1.25 HDPE Loops 650 to 1,000 feet long; no grout. U-Bend Assembly length is twice loop length. Bores start and end at -3 feet. U-Bends are -10 Feet. Header at drilling end. October, 2014 John Geyer & Associates, Inc. 10

Vertical Loop Field changed to horizontal across four Baseball Fields (800 Ft) Horizontal re-design required Thermal Conductivity Testing at two loop levels. In-situ Testing at two levels was done with and without bentonite grout. October, 2014 John Geyer & Associates, Inc. 11

Medium-sized horizontal directional drills drilled 800 foot bores in 5 hours 1,600 1.25 HDPE u-bend loop assembly pulled from opposite end of field October, 2014 John Geyer & Associates, Inc. 12

Three drills and a crew of 8 drilled 110 bores in 5 weeks October, 2014 John Geyer & Associates, Inc. 13

For testing purposes, two horizontal loops (-15, -30 ) were grouted and two were not 20% solids bentonite grout used: k = 0.45 October, 2014 John Geyer & Associates, Inc. 14

48 hour In-situ Thermal Conductivity test Testing provided design input for: undisturbed temperature, thermal conductivity, diffusivity, formation lithology and preferred drilling procedures. October, 2014 John Geyer & Associates, Inc. 15

Summary of 6 tests: 2 vertical and 4 horizontal October, 2014 John Geyer & Associates, Inc. 16

Grout or Not to Grout? Four horizontal test bores were installed Two 800 x 15 (nominal depth), one grouted and one not grouted Two 800 x 30 (nominal depth), one grouted and one not grouted Concern was that without grouting voids could be created harming thermal performance We expected this would be a non-issue as the geology is unconsolidated and wet to saturated Testing proved that, at least for these conditions, there was no benefit to grouting Other soil conditions may require grouting project specific October, 2014 John Geyer & Associates, Inc. 17

Table 1 Test Data, School Test Loop Grout TE - Measured TC - Est'd Diffusivity - Undisturbed btuh/ft/ F btuh/ft/ F ft²/day Temp. - F 180 vertical 1.00 0.97 0.63 ~67 400 vertical* 0.88 1.09 0.89 ~68 15' horizontal no grout 0.92 0.60 ~64 30' horizontal no grout 0.97 0.63 N/A 15' horizontal 0.45 1.00 0.65 N/A 30' horizontal 0.45 0.87 0.57 ~64 * by others, from preliminary design effort Horizontal tests confirmed no substantial difference in performance between grouted and ungrouted bores TC values for 180 test similar to 15 and 30 horizontal bores 400 test for perspective only, TC value not substantially greaterfor this location October, 2014 John Geyer & Associates, Inc. 18

1.3 1.2 1.1 1 0.9 0.8 0.7 0.6 0.5 Conductivity k Figure 2 Site 1: School 1 st Order Data from IGSHPA / ASHRAE test procedures 42-48 Hours, > 15w/ft 0.4 180 V1 1.00 15 H1 None 30 H1 None 15 H1 0.45 30 H1 0.45 Label Key: 180 V 1 1.00 180 = Loop length 15 = loop depth V, H = Vertical / Horizontal 1 = Site #1, School 1.00 = grout conductivity, k None = No Grout 0.9 0.85 0.8 0.75 0.7 0.65 0.6 0.55 0.5 0.45 0.4 Diffusivity Ratio 180 V1 1.00 15 H1 None 30 H1 None 15 H1 0.45 30 H1 0.45 October, 2014 John Geyer & Associates, Inc. 19

Final GHX Installation 110 bores installed 55 x 800 x 1.25 DR11 HDPE at 15 nominal 55 x 800 x 1.25 DR11 HDPE at 30 nominal Field simulations based upon hourly load profile horizontal GHX designed to handle 100% of facility cooling and heating A portion of the vertical GHX was retained and is also integrated into the operating system Field and headering infrastructure managed using two HDPE vaults one for the horizontal field and the other for the vertical field October, 2014 John Geyer & Associates, Inc. 20

110 Loop horizontal field covered 75% of 4 baseball fields October, 2014 John Geyer & Associates, Inc. 21

125,000 SF Corporate Building (Green field site, 12 miles away) October, 2014 John Geyer & Associates, Inc. 22

Project Perspective Client determined to have energy efficient mechanical system, needed more energy points (LEED Gold target) Permitting authority would not consider a vertical GHX: Seawater encroachment into bay area aquifers serious concern, fear of aquifer comingling via vertical loops Excavated pit GHX eliminated High water table (very brackish) would make an excavated GHX impractical, also invite more permitting scrutiny Horizontal borehole GHX determined to be feasible through mechanical evaluation only option available Client, Design Team (architect, mechanical engineer) and Contractor assets pro-active key to project s success October, 2014 John Geyer & Associates, Inc. 23

Building Load Total Loop Length Fit to Site 15 Acre site; 8 Acre Loop Field October, 2014 John Geyer & Associates, Inc. 24

Building and Loop field Co-located at Different Depths 18 foot Loop Depth under 12 foot foundation, footings and utilities October, 2014 John Geyer & Associates, Inc. 25

Table 2 Test Data, Corporate (same formation as school, 12 miles to south) Test Loop Grout TE - Measured TC - Est'd Diffusivity - Undisturbed btuh/ft/ F btuh/ft/ F ft²/day Temp. - F 15' horizontal no grout 0.95 0.60 ~71 30' horizontal no grout 0.93 0.59 ~67 Higher ambient temperature at 15 Ft may be due to climate influence Soil conditions wet at test depths October, 2014 John Geyer & Associates, Inc. 26

1.3 1.2 1.1 1 0.9 0.8 0.7 0.6 0.5 Conductivity k 15 H2 None 30 H2 None 0.9 0.85 0.8 0.75 0.7 0.65 0.6 0.55 0.5 0.45 0.4 Figure 3 Site 2: Corporate 1 st Order Data from IGSHPA/ASHRAE test procedures 42-48 Hours, > 15w/ft Diffusivity Ratio 15 H2 None 30 H2 None October, 2014 John Geyer & Associates, Inc. 27

Final GHX Installation 100 bores installed 50 x 650 x 1.25 DR11 HDPE at 15 nominal 50 x 650 x 1.25 DR11 HDPE at 30 nominal Field simulations based upon hourly load profile horizontal GHX designed to handle ~70% to 100% of facility cooling and heating: Intended central chiller plant vendor could not provide sufficient performance tables for data integration into simulation software comparison simulations projected GHX could handle part to all peak loads depending on moving target variables (controls SOO, actual EER of chiller, etc.) No more available area for additional ground loops System is configured to add hybrid cooling device if necessary October, 2014 John Geyer & Associates, Inc. 28

1.2 School Figure 4 Conductivity k 7 tests at 2 sites Corporate 1.1 Vertical Horizontal 800 Ft Horizontal 650 Ft 1.00 Grout No Grout 0.45 Grout No Grout 1 0.9 0.8 0.7 0.6 0.5 180 V1 1.00 15 H1 None 30 H1 None 15 H1 0.45 30 H1 0.45 15 H2 None 30 H2 None October, 2014 John Geyer & Associates, Inc. 29

0.9 Figure 5 Diffusivity Ratios 7 Tests, 2 Sites 0.85 School Corporate 0.8 0.75 0.7 Vertical Horizontal 800 Ft Horizontal 650 Ft 1.00 Grout No Grout 0.45 Grout No Grout 0.65 0.6 0.55 0.5 0.45 0.4 180 V1 1.00 15 H1 None 30 H1 None 15 H1 0.45 30 H1 0.45 15 H2 None 30 H2 None October, 2014 John Geyer & Associates, Inc. 30

Table 3 Similar Buildings / Loads Vertical vs. Horizontal Loops Vertical Horizontal Bores 200 100 Length 350 700 Total Drilling 70,000 feet 70,000 feet Loop field Area ~ 2 acres ~9 acres Headering Area Disturbed ~ 2 acres ~0.8 acres Headering as % of Drilling Cost ~ 25% <15% Headering Time ~ 5 weeks < 3 weeks October, 2014 John Geyer & Associates, Inc. 31

Table 4 Budget (Approximate) Vertical Horizontal Cost per foot $14 - $18 $8 - $13 70,000 ft drilling cost $980k - $1.25M $560k - $910k Headering cost 25% 15% Total headering $245k - $315k $85k - $135k Dirt Management (15%) $150k - $190k $85k - $135k Ancillary Costs (20%, est) $200k -$250k $110k -$180k Site Restoration (10%) $100k - $125k $ 55k - $ 90k All-in Job Cost $1.6 - $2.1M $900 - $1,450k October, 2014 John Geyer & Associates, Inc. 32

Conclusions In non-rocky soils to 40 feet deep, horizontal boring may offer a viable design alternative with multiple advantages over vertical drilling and headering. Observed Conductivity and Diffusivity were similar on all tests regardless of loop orientation or length for these project locations. All tests were performed in dry summer season. Conductivity was essentially the same with and without grout. No voids or subsurface gaps were created. Horizontal construction involved about half the cost, half the time and onethird the surface disturbance as vertical drilling and headering. Co-location of loop field under buildings was accomplished without physical interference or degraded thermal performance. Horizontal construction allows ongoing surface activities and use during 12- month construction season. Cost and operational events have been repeated three times without variance Horizontal areas for horizontal borefields may be up to 4x larger than for a vertical loop field. Schools with parking and athletic fields are superior sitesfor horizontal construction. October, 2014 John Geyer & Associates, Inc. 33

Thank you for your time and attention! JOHN D. GEYER, CGD John Geyer & Associates, Inc. 360 882 5050 jgeyer@jgainc.com October, 2014 John Geyer & Associates, Inc. 34