SECTOR ASSESSMENT (SUMMARY): ENERGY

Similar documents
SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Performance, Problems, and Opportunities

ECONOMIC ANALYSIS. B. Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY

AZERBAIJAN ECONOMY AND POWER SECTOR: CHALLENGES AND OPPORTUNITIES

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT: BIHAR POWER SECTOR

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

Asian Development Bank Perspective for Rural Energy Access. Pushkar Manandhar Asian Development Bank Nepal Resident Mission

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY

SUMMARY SECTOR ASSESSMENT: ENERGY 1

Content Introduction Institutional Arrangement Energy Policy Documents Energy Statistics Legal and Policy Efforts for Hydropower Development Problems

SECTOR ASSESSMENT (SUMMARY): POWER

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR)

SECTOR ASSESSMENT (SUMMARY): ENERGY

Gender Mainstreaming in ADB s Energy Projects in Nepal. Pushkar Manandhar 2 October 2017

Report and Recommendation of the President to the Board of Directors

Mr. Gokarna Raj Pantha Senior Divisional Engineer Ministry of Energy, Nepal

Terms of Reference. Conflict Management and Mitigation for Energy Projects in Nepal

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): IRRIGATION. 1. Sector Performance, Problems, and Opportunities

INTRODUCTION. Latitude ' N ' N Longitude ' E ' E Area 147,181 km 2

HYDROPOWER DEVELOPMENT AND REGIONAL INTEGRATION FOR NEPAL

SECTOR ASSESSMENT (SUMMARY): ENERGY (ELECTRICITY TRANSMISSION AND DISTRIBUTION)

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Performance, Problems, and Opportunities

Reliable, affordable, and sustainable energy services for agriculture,

SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

ASIAN DEVELOPMENT BANK

Report and Recommendation of the President to the Board of Directors

SECTOR ASSESSMENT (SUMMARY): TRANSPORT AND INFORMATION AND COMMUNICATION TECHNOLOGY. 1. Sector Performance, Problems, and Opportunities

ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS

SECTOR ASSESSMENT (SUMMARY): TRANSPORT AND INFORMATION AND COMMUNICATION TECHNOLOGY 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (RAIL TRANSPORT [NONURBAN])

SECTOR ASSESSMENT (SUMMARY): ENERGY

ECONOMIC ANALYSIS. A. Background and Approach

SECTOR ASSESSMENT (SUMMARY): POWER Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Background, Performance, Problems, and Opportunities

Report and Recommendation of the President to the Board of Directors. Proposed Grant Nepal: Project Preparatory Facility for Energy

Report and Recommendation of the President to the Board of Directors

SECTOR OVERVIEW. Government of Indonesia, State Electricity Corporation (PLN). Electricity Power Supply Business Plan (RUPTL ). Jakarta.

Ex-Ante Evaluation (for Japanese ODA Loan)

SCALING-UP RENEWABLE ENERGY PROGRAM (SREP) COUNTRY INVESTMENT PLAN KENYA

Results Framework. Quick Guide

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT, AND INFORMATION AND COMMUNICATION TECHNOLOGY

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA982. Project Name. Region. Country

Member State Perspectives

Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector

SUSTAINABLE ENERGY FOR ALL. Suman Basnet Sustainable Energy Coordinator (NPC/UNDP)

SECTOR ASSESSMENT: WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES

SECTOR ASSESSMENT (SUMMARY): AGRICULTURE AND NATURAL RESOURCES 1

IND: Energy Efficiency Enhancement Project in Assam

RAJENDRA KISHORE KSHATRI FOURTH SOUTH ASIA JUDICIAL ROUNTABLE ON ENVIRONMENTAL JUSTICE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

SCALING UP RENEWABLE ENERGY PROGRAME IN TANZANIA

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

General Information AREA: Population: 143 thousand. km2 (93% of the territory is covered by mountains) 8,7 mln. people Capital: Dushanbe city Independ

KNOWLEDGE MANAGEMENT PLAN Nepal Country Partnership Strategy, I. INTRODUCTION

ADB and Renewable Energy

SECTOR ASSESSMENT (SUMMARY): AGRICULTURE, NATURAL RESOURCES, AND RURAL DEVELOPMENT 1

GREEN POWER DEVELOPMENT PROJECT Bringing Benefits to Bhutan and Beyond

SECTOR ASSESSMENT: WATER AND SANITATION. 1. Sector Performance, Problems, and Opportunities

Ex-Ante Evaluation (for Japanese ODA Loan)

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

ECONOMIC ANALYSIS. A. Methodology and Major Assumptions

SREP MALI - INVESTMENT PLAN Scaling Up Renewable Energy. Scaling Up Renewable Energy in Low Income Countries (SREP)

Nepal. Challenges and Measures to Meet the Challenges. Goal 7: Ensure access to affordable, reliable, sustainable and modern energy for all

SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES (WATER AND WASTEWATER)

DEVELOPMENT COORDINATION MATRIX. Rehabilitation of existing hydropower plants (Toktogul HPP, Kambarata-2 HPP)

SECTOR ASSESSMENT (SUMMARY): ENERGY

Energy in Kenya. Energy Scenarios Workshop July 24, 2013 Stanley Hotel

Content Sri Lanka At a Glance Energy reserves Current Energy Policy and Measures Past Energy Demand and Supply Outlook of energy Demand and Supply Ene

Summary of the Chair. Conclusions and Recommendations of the Parliamentarian Forum on Energy Legislation and Sustainable Development

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

International Atomic Energy Agency

ADDRESS BY MINISTER FOR ENERGY, DR. JOE OTENG-ADJEI

EMERGING AND PERSISTENT ISSUES

South Asia Energy Security : Challenges And Opportunities

15 TH ANNUAL EAST AFRICAN POWER INDUSTRY CONVENTION

SE4ALL INITIATIVES IN BHUTAN

SECTOR ASSESSMENT (SUMMARY): WATER SUPPLY AND OTHER MUNICIPAL INFRASTRUCTURE AND SERVICES

Dr. Jyoti Parikh Executive Director Integrated Research and Action for Development (IRADe)

DESIGN DOCUMENT FOR THE PROGRAM ON SCALING-UP RENEWABLE ENERGY IN LOW INCOME COUNTRIES (SREP), A TARGETED PROGRAM UNDER THE STRATEGIC CLIMATE FUND

Brief Overview of Renewable Energy Regulation in Tanzania

Role of Renewable Energy in Combating Climate Change by

SECTOR ASSESSMENT (SUMMARY): 1 WATER AND OTHER URBAN INFRASTRUCTURE AND SERVICES

SECTOR ASSESSMENT (SUMMARY): AGRICULTURE AND NATURAL RESOURCES (ENDANGERED RESERVOIRS) 1

Session 2 Gender and Social Inclusion Energy Linkages: Policies, strategies and practices

Grid Resilience in Developing Countries

Electricity is crucial to

Road to 2030 Consultation Paper: Considerations for ADB s New Strategy

Transcription:

SECTOR ASSESSMENT (SUMMARY): ENERGY Country Partnership Strategy: Nepal, 2013-2017 A. Overview 1. Nepal has long recognized the development of its large hydropower potential as an important cornerstone of its poverty reduction and economic growth strategy. It has viewed this renewable resource as a means to (i) provide clean energy that enhances economic activities in rural and urban areas, and (ii) generate revenue from exporting energy. Despite being engaged in this sector for decades, however, these goals have yet to materialize. This is due in particular to inadequate planning and investment in generation, transmission, and distribution; and delays in project development that have resulted from the lack of an adequate legal and regulatory framework. As a result, Nepal now suffers from a severe power shortage and frequent power cuts. Country diagnostic studies identify this as a major binding constraint on Nepal's inclusive economic growth. 1 2. Generation. The peak load of Nepal s power system reached 1,026 megawatts in 2012, but by 2013 Nepal had only enough installed capacity to generate 705 megawatt (MW) of hydroelectricity. To reduce the country s power shortfall, the previous Three Year Plan had envisaged the completion of 281 MW in new generation and 1,743 MW in initiated generation construction. This target could not be reached due to inadequate infrastructure, including a lack of roads and transmission capacity; failure to restructure the tariff rates; and implementation issues at the local level. 2 The country s new Three Year Plan for FY2014 FY2016 targets the commissioning of 668 MW of new generation capacity and the start of construction for an additional 584 MW. Another reason for Nepal s acute power deficits, particularly during its dry winters, is the dominance of run-of-river and daily storage hydropower plants in Nepal s power system. Only 14% of the total installed capacity is in the form of dam storage-type hydropower installations that can store water for long periods and use it to continue full generation during the dry season when run-of-river must reduce output due to lower river flows. This results in the significant power shortages during winters. Nepal has no alternative sources capable of meeting meet these shortages. Its small capacity thermal power plants (53.4 MW) have a poor record of operation, and it has not diversified into the use of solar and wind power. This leaves Nepal, a potential energy exporter, with no alternative but to increasingly import power from India. These imports reached 18% of the total national grid supply in 2012. 3 3. Transmission. The lack of infrastructure to deliver energy from generation sites to load centers has been a crucial bottleneck. The previous Three Year Plan aimed to add 700 kilometers (km) of transmission lines by FY2013 to the 1,916 km existing in FY2009, but the network had been expanded by only 64 km by the end of FY2011. The absence of a clear plan for developing the country s electrical transmission system is a significant obstacle to greater investment in new hydropower development by Independent Power Producers (IPP), i.e., the private sector companies permitted under current laws to generate electricity in Nepal. Nepal also lacks sufficient cross-border transmission infrastructure. This makes it difficult to develop hydropower on a large scale for export. Except for certain border areas, transmission connectivity with India is limited to about 150 MW. The government initiated efforts in 2010 to construct a major 400 kilovolt (kv) cross-border transmission link to enable better power 1 ADB, Department for International Development, and International Labour Organization. 2009. Nepal: Critical Development Constraints. Country Diagnostics Studies. Manila. 2 Government of Nepal. 2010. Three Year Plan Approach Paper (2010/11 2012/13). Kathmandu. 3 Nepal Electricity Authority. 2012. A Year in Review Fiscal Year 2011/2012. Kathmandu.

2 exchange with India 4. Timely completion of this undertaking will be critical to rapidly developing Nepal s hydropower sector, but delays in the acquisition of land have proven a major obstacle. 4. Distribution. The Nepal Electricity Authority (NEA), which serves more than 2.32 million customers nationwide, has a de facto monopoly over the distribution of electricity. In FY2012, domestic consumers accounted for 94.9% of its customer base, but only contributed to 41.5% of the total sale; industrial and other commercial consumers on the other hand accounted for only 2.3% of the consumer base, but contributed to 47.7% of total sales. 5 Power losses from the NEA systems have declined from an audited 28.6% in FY2011 to a provisional 26.4% in FY2012 due to measures it has taken to control non-technical losses. These steps have included close monitoring of distribution networks, establishment of loss reduction committees, and penal action against errant users. 5. As a government corporation, the NEA has dominated Nepal's power sector since it was established in 1985. It is in poor financial health, however, and had accumulated losses at the end of FY2011 of NRs27 billion. This has been attributed to the absence of a tariff increase during 2001 2012, the rising cost of energy purchases and operations, and high system losses. In response to its deteriorating condition, the Ministry of Energy authorized the financial restructuring of the NEA in December 2011. The restructuring, among other things, (i) increased the NEA s capital share to NRs50 billion, (ii) wrote off its accumulated losses, and (iii) converted interest due by the NEA to the government to equity. The Electricity Tariff Fixation Commission also approved an average retail tariff hike of 20%, which allowed the NEA to revisit its power purchase agreements with the IPPs. These initiatives should contribute to making NEA financially healthier and capable of investing to meet the rising demand for electricity. 6. The government has stated that it is committed to attracting private investment in the generation of hydropower in Nepal. Since they began operations in 1992, IPPs have increased to 25. They now generate a total of 187 MW of electricity for the national grid, or 31.3% of the total electricity supply. The 16 major IPP projects now under construction will add 537 MW of generation capacity by 2017. The government has also allowed the private sector to become involved in distribution. Butwal Power Company is supplying electricity to about 36,000 consumers and about 73,000 households have been electrified through 94 community group arrangements. However, the private sector has to deal with several constraints while investing in Nepal s hydropower. These include, among others, inconsistency in inconsistent policies, lack of comprehensive planning, financial limitations, the NEA s credit and offtake risks, and difficulty in land acquisition and right-of-way issues. B. Government s Strategy 7. The government s policy initiatives in the energy sector include the Electricity Act of 1992, which was adopted to develop and manage the hydropower regime in Nepal and to standardize and safeguard electricity services. It dealt with such issues as licensing, royalties, duties and taxes, tariff fixation, and land acquisition. This was followed by the Hydropower Development Policy 2001, which listed objectives and laid down governing rules for the hydropower sector. It specified the generation, transmission, and distribution functions for the creation of an independent power systems operator. In the absence of corresponding legislation, this policy 4 5 The first among them, the 400 kv Dhalkebar Muzaffarpur transmission line, was scheduled to be completed by 2010. However, due to procedural delays, it is expected to be commissioned only in July 2014. Nepal Electricity Authority. 2012. A Year in Review Fiscal Year 2011/2012. Kathmandu.

document continues to provide the basic framework for private sector participation. The Nepal Electricity Act and the Nepal Electricity Regulatory Commission Act have been approved by the cabinet and submitted to parliament, but remains stalled at the legislature due to the absence of the parliament since May 2012. The former act is to restructure the NEA through unbundling of its operations. The second act is to set up an independent regulatory regime for the power sector, long needed to attract investments in the sector. 8. The National Water Resource Strategy 2002 calls for the NEA to become commercially viable through corporatization, improved management, and separation of its rural electrification operations. It also calls for generation to become the responsibility of a separate corporation. The country s 3-year plans have dealt with such issues as (i) introducing effective regulation of generation, transmission, and distribution of electricity; (ii) adopting a one-window approach to encourage investments in hydropower development; (iii) making consistent efforts to expand electricity generation and transmission. 9. In 2008, the government approved the National Electricity Crisis Resolution Action Plan to provide immediate and long-term strategies for dealing with a worsening power situation. These included increasing power imports from India, construction of thermal power plants, expanding transmission capacity, and controlling the theft of electricity. In December 2008, the government also formed a task force to prepare a road map for developing an additional 10,000 MW of hydropower generation capacity in 10 years. The task force recommended that the production of hydropower to meet domestic demand be given priority over production for export. 10. Other government initiatives to mitigate the power crisis include the Rural Energy Policy of 2006, which targeted the installation of improved biomass technologies, off-grid micro hydro systems for rural electrification (capable of being connected to the national grid when it is extended), and white light-emitting-diode and photovoltaic-based solar lights to replace kerosene lamps. The policy provided for special programs to enhance the benefits of rural energy for women and other marginalized groups, and increase their representation in the formation of community-based organizations through social mobilization. 11. The government has major financing responsibilities in numerous other sectors and is aware that it will be unable to make sufficient investments on its own to fully develop Nepal s hydropower potential. To leverage the investments it can make, share the risks, and make use of efficiencies and innovations of private enterprise, it is considering public private partnerships (PPP) as a preferred model for hydropower expansion. It is engaged in setting up a facility to implement large-scale PPP hydropower projects and to provide related transaction advisory services. PPP already exists in power distribution through the community electrification initiatives of the NEA. The Asian Development Bank (ADB) will continue to strengthen these initiatives. 6 C. ADB Sector Experience and Assistance Program 12. The main development partners in Nepal s power sector are ADB, the Government of Denmark, the European Commission, the European Investment Bank, the Japan International Cooperation Agency (JICA), Kreditanstalt für Wiederaufbau (KfW), the Government of Norway, the Netherlands Development Organization, the United Nations Development Program, and the World Bank. Of these, ADB, JICA, KfW, Norway, and the World Bank have been the most active in the on-grid subsector. Nepal s other development partners are more involved in off-grid 3 6 ADB. 2013. Report and Recommendation of the President to the Board of Directors: Proposed Loans and Administration of Technical Assistance Grant for Project Preparatory Facility for Energy. Manila

4 development. The country s development partners regularly coordinate sector investments and support for establishing an enabling institutional framework. 13. ADB has been the leading partner in Nepal s power sector development. It has focused in particular on on-grid support for the NEA s expansion of generation, transmission, and distribution capacity. To increase generation, ADB and JICA cofinanced the Kali Gandaki A Hydroelectric Project a 144 MW power plant commissioned in 2002. 7 ADB s support in transmission has been through assistance projects in 2009 and 2011, cofinanced by Norway, to strengthen transmission infrastructure from the western border to the central region of Nepal and for the evacuation of electricity from generation sites to the load center in Kathmandu. In distribution, ADB assistance has focused on increased access, rehabilitation of small hydropower plants, and other clean energy interventions, such as solar street lighting and energy-efficient lighting. ADB has also supported several rural electrification projects with participation from local communities. 14. ADB approved the 140 MW Tanahu Hydropower Project in 2013 to address the issue of limited generation of electricity from storage-type hydropower plants in Nepal. 8 The project was cofinanced by JICA, the European Investment Bank, and Abu Dhabi Fund for Development. The project includes pilot programs to expand access by women and other marginalized groups to energy resources and energy-based livelihoods, in partnership with the NEA, the Alternate Energy Promotion Center, and non-governmental organizations. 15. ADB s main focus in the new country partnership strategy will be to make Nepal s energy sector a key driver of inclusive economic growth. This will be achieved through investments in both on-grid and off-grid subsectors. ADB s on-grid investments will include support for development of large-scale hydropower projects and related transmission infrastructure. ADB will provide transaction advisory services to the government to explore suitable PPP modalities and catalyze private sector investment in large-scale hydropower development. ADB s investments in transmission will include support for strengthening the in-country network to evacuate electricity from generation sites to domestic load centers as well as for cross-border lines to exchange power with India. 16. To improve access to modern energy resources in remote areas, ADB will help the government develop off-grid power through the use of renewable energy sources. ADB will also support initiatives that increase energy efficiency. ADB s intervention in the energy sector will comply with stringent social and environmental safeguard requirements and will further enhance inclusive economic and environmentally sustainable growth. ADB will support the development of the institutional capacity of sector agencies to address such concerns as the need to enhance inclusiveness in access to energy. ADB will conduct a policy dialogue with the government to (i) improve the governance and efficiency of the energy sector; (ii) create an independent regulatory authority for energy and water; and (iii) introduce appropriate structural reforms, including the enactment of the relevant legislation, full implementation of the NEA s financial restructuring plan, and regular tariff revisions. Support for sector planning frameworks, such as a regional transmission master plan and basin-level planning, will also be considered, in coordination with other development partners. 7 ADB. 1996. Report and Recommendation of the President to the Board of Directors: Proposed Loan and Technical Assistance Grants for Kali Gandaki A Hydroelectric Project. Manila 8 ADB. 2013. Report and Recommendation of the President to the Board of Directors: Proposed Loans and Administration of Technical Assistance Grant for Tanahu Hydropower Project. Manila

Problem Tree for Energy Sector Constrained economic growth Loss of potential revenue from electricity export Inadequate and unreliable power supply Inadequate power system infrastructure Inadequate hydropower generation Weak transmission & distribution systems with high losses Low off-grid power system development (microhydro, wind, solar) Inadequate financing Inefficient power systems Weak institutional capacity Lack of sector planning, policy, and regulations Limited government resources Lack of Foreign Direct Investment Inadequate domestic private financing Inadequate financing from International Financial Institutions High technical losses Poor operations & maintenance Aging assets underperforming Weak financial position of Nepal Electricity Authority Limited corporate governance structure Limited human resources & management experience Limited function of the regulator Lack of coordination Underdeveloped legal & regulatory framework Lack of tariff rationalization Inefficient cost-recovery mechanisms 5

Outcomes with ADB Contribution Increased use of commercial energy by households Increased cross-border energy trade Sector Results Framework (Energy, 2013 2017) Country Sector Outcomes Country Sector Outputs ADB Sector Operations Indicators with Targets Outputs with Indicators with Incremental Planned and Ongoing ADB and Baselines ADB Targets Interventions Households using electricity Target (2017): 70% (on-grid) Baseline (2012): 56% (on-grid) Per capita electricity consumption Target (2017): 180 kwh Baseline (2012): 102 kwh Level of power trade Target (2017): 400 MW Baseline (2012): 150 MW Contribution Energy infrastructure and system expanded and improved Regulatory environment in energy sector improved Installed electricity generation capacity Target (2017): 1,590 MW Baseline (2012): 705 MW Installed off-grid renewable energy generation capacity Target (2017): 50 MW Baseline (2012): 35 MW New transmission lines installed Target (2017): 2,000 km Baseline (2012): 0 km New distribution lines installed Target (2017): 1,000 km Baseline (2012): 0 km Cost-reflective electricity tariff Target (2017): Tariff reflects 100% of costs Baseline (2012): 75% (i) Planned key activity areas: Large hydropower (large dams) (62% of funds) Renewable (solar, small hydro, wind) (4% of funds) Electricity transmission and distribution (electrical power transmission) (30% of funds) Energy sector development (policy and regulation, tariffs and pricing, PPP) (4% of funds) (ii) Projects in the Pipeline: Project Preparatory Facility ($21 million) Rural Electrification through Renewable Energy ($19 million) SASEC Power System Expansion ($145 million) Hydropower development through PPP ($110 million) (iii) Ongoing Projects: Tanahu Hydropower ($150 million) Energy Access & Efficiency Improvement ($63.2 million) Electricity Transmission Expansion & Supply Improvement ($75 million) Detailed Engineering Study for Upper Seti Hydropower ($2.5 million) Main Outputs Expected from ADB Interventions (i) Planned key activity areas and projects in the pipeline Hydropower projects with capacity up to 740 MW initiated 5.5 MW renewable energy generation (excluding large hydropower) established 400km transmission line and 200 km distribution line installed (ii) Ongoing Projects: 140 MW hydropower plant constructed 550 km transmission line and 600 km distribution line installed 29,000 households electrified At least 1 distribution center established under PPP modality 1 million energy-efficient lighting and 1,500 solar and solar-wind street lighting set up 4 hydropower plants rehabilitated Poor female-headed and disadvantaged households covered under distribution strengthening and expansion Sectoral GESI framework adopted 6 GESI = gender equality and social inclusion, km = kilometer, kwh = kilowatt hour, MW = megawatt, PPP = public private partnership. Sources: Asian Development Bank and government estimates.