PILOT SOLAR EVAPORATION PONDS COMMISSIONED AT LAKE WELLS POTASH PROJECT, WA

Similar documents
POND DEVELOPMENT PROGRAM IDENTIFIES SURFACE CLAY LAYER, SUPPORTS ON-LAKE UNLINED EVAPORATION PONDS

For personal use only

AUSTRALIAN POTASH COMPLETES FINAL BRINE TRANSFER

SUCCESSFUL INFILL DRILLING CAMPAIGN COMPLETED

For personal use only

Australian Potash Limited (ASX:APC) 1

SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS.

DISCLAIMER & FORWARD LOOKING STATEMENTS

Pilot Pond Update and Harvest Trials. Large Scale Pilot Harvesting Trials March 2018

Australian Potash Limited (ASX:APC) 1

For personal use only

GROW WITH US INVESTOR PRESENTATION MARCH 2019

Australian Potash Limited (ASX:APC) 1

COMPLETION OF PROCESS TESTWORK STUDIES

ABN: AUGUST

Australian Potash Limited (ASX:APC) 1

Lake Wells Potash Project

Grange Resources Australia s leading magnetite producer

For personal use only

FIRST GOLD ORE DISPATCHED FROM ULYSSES

Potash is the main source of fertiliser in the world. Potash demand is expected to be underpinned by a rapidly growing world population.

MOU signed with steel and alloy product company

For personal use only

Bald Hill Delivers Excellent Metallurgical Test Work Results

Maiden Ore Reserve for Camel Creek JV

Grange Resources. Diggers & Dealers 4 August Russell Clark Managing Director & CEO

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES

DALGARANGA PRE-FEASIBILITY UPDATE

For personal use only

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS

For personal use only

Successful Production of Premium Quality Boric Acid

CHINA MINING Conference Tianjin October 2014

Australia s largest Vanadium in magnetite deposit delivering the highest Vanadium grade in concentrate

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD

Lake Wells Potash Project

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES

DEVELOPING FERTILISER PROJECTS TO MEET THE GROWING DEMAND IN BRAZIL AND THE WORLD

For personal use only

Haoma Mining NL. Dear Sir, ACTIVITIES REPORT FOR THE QUARTER ENDED MARCH 31, 2011 HIGHLIGHTS

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING

Haoma Mining NL A.B.N

Haoma Mining NL A.B.N

Mine Infrastructure Construction begins at Nullagine JV First iron ore shipment by December 2010

For personal use only

QUARTERLY ACTIVITIES REPORT For the period ending June 30, 2009

Focused on delivery of high-value metals critical to energy revolution. Peter Williams, CEO Noosa Mining & Exploration Conference July 2018

Thalanga Operations Ore Reserve and Mineral Resource Statement

For personal use only

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER

For personal use only

PACIFIC BAUXITE ACQUIRES NEW BAUXITE PROJECT IN WESTERN AUSTRALIA

5 th Asian Bauxite & Alumina Conference

For personal use only

ASX ANNOUNCEMENT. Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA. Mt Stuart Joint Venture MAIDEN ORE RESERVE STATEMENT

Mt Thirsty Cobalt-Nickel Joint Venture Infill Drilling Results

Thalanga Project Ore Reserve and Mineral Resource Statement (as at 1 December 2017)

CAPITAL DOWN AT TALA HAMZA

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET

QUARTERLY REPORT March 2011

ASX : BLK. Australian gold producer with exceptional growth opportunity

Great Western Scoping Study Update & Onsite Gold Processing

Valence Industries. Australia s Only Graphite Producer. Asia Pacific I Europe I North America. Manufacturing Our Carbon Future TM.

Wetar Expansion Update September 2015

Arafura Resources Limited

ASX Announcement 25 November 2010 MT BEVAN IRON ORE PROJECT EXPLORATION UPDATE. About Legacy Iron Ore. The Company Announcements Office ASX Limited

Building South Australia s Largest Iron Ore Project

Second drill rig to accelerate major drilling program at Productora

For personal use only

Arafura Resources Limited

For personal use only. Mining the Territory. Korab Resources Limited NT RESOURCES WEEK ASX: KOR. Andrej K. Karpinski Executive Chairman

For personal use only

For personal use only

SARACEN MINERAL HOLDINGS LTD

For personal use only

CEO Presentation Annual General Meeting. November 2016

KOGI REPORTS BARGING STUDY COMPLETED

Nolans Project Global Investor Update. Dr Steve Ward Managing Director & CEO Gavin Lockyer CFO & Company Secretary

Shaw River Completes Acquisition of 75.5% Interest in Namibian Manganese Project

Australia s leading magnetite producer. Southdown Magnetite Project

Nullagine Gold Project Pictorial Update October 2011

For personal use only

Hot Chili and CMP sign Non-Binding Letter of Intent on Second Copper Project

For personal use only

Pelletising tests confirm Hawsons Supergrade a standout material for iron making

For personal use only

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE

For personal use only

CORPORATE PRESENTATION. February 2016

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT

EXCEPTIONAL GROWTH OPPORTUNITY WITH PREMIUM ORGANIC FERTILIZERS AUGUST 2016

WORLD CLASS GROWTH OPPORTUNITY WITH PREMIUM SPECIALTY FERTILIZERS

BBY 2010 Rare Earth Conference. 1 February 2010

ABN: MARCH

Haoma Mining NL. Dear Sir, ACTIVITIES REPORT FOR THE QUARTER ENDED JUNE 30, HIGHLIGHTS

For personal use only

Valence Industries Australia s Only Graphite Producer

Strong progress made on development of Montepuez Graphite Project

MARCH 2011 QUARTERLY. December 2013 QUARTERLY. Key Points. Executive Summary

Transcription:

31 Ord Street, West Perth WA 6005 PO Box 1941, West Perth WA 6872 +61 8 9322 1003 australianpotash.com.au ABN 58 149 390 394 3 October 2017 PILOT SOLAR EVAPORATION PONDS COMMISSIONED AT LAKE WELLS POTASH PROJECT, WA Highlights: Pilot solar evaporation pond system commissioned with first fill of brine from site production bores System comprises a series of four ponds that will pre concentrate brine to remove halite salt impurities and produce approximately 20 tonnes of mixed feeder potash salts Piloting the evaporation system builds on the 12 month Class A Pan Evaporation Trial Mixed potash salts will be provided to MOU offtake partners for confirmation test work Management Update on pond network at www.australianpotash.com.au Australian Potash Limited (ASX: APC) (APC or the Company) is pleased to provide an operational update on the pilot solar evaporation pond program currently underway at its flagship Lake Wells Potash project, located 480km north east of Kalgoorlie in Western Australia. Figure 1. Pilot Solar Evaporation Pond at Lake Wells

Figure 2. First Stage Crystalliser Pond at Lake Wells Figure 3. Fill Level in the Crystalliser Pond The design, construction and commissioning of the pilot solar evaporation pond network is an extension of the Class A evaporation pan trial underway since October 2016 i. The evaporation pan trial will continue to collect data that contributes to the evaporation model under which the commercial

ponds will operate and when combined with the outcomes of the pilot solar evaporation pond network, will lead to refining the design of the commercial scale pond network. The pilot ponds have been constructed off the playa in a similar manner to that proposed for the harvest ponds in the full scale project. At full scale, the initial concentration and halite crystallisation ponds will be developed on the surface of the playa lakes, taking advantage of the existing near surface low permeability clay layer to minimise brine leakage, and save considerable pond construction expenditure associated with lining the bottom of the ponds. Figure 4. Installed Production Bore used to Commission the Pilot Solar Evaporation Pond Network Australian Potash, Executive Chairman, Matt Shackleton commented: The feasibility program we are conducting on the Lake Wells SOP Project is looking closely at the three integral parts of a brine SOP operation: brine abstraction, brine evaporation and processing of the feeder salts into SOP. We have been conducting a Class A Evaporation Pan trial for 12 months and are very pleased to extend the work program around the brine evaporation step into commissioned pilot solar evaporation ponds. These ponds will provide over 20 tonnes of feeder salts, which we will then provide to our Chinese partners and our laboratory for test work. APC s Lake Wells SOP Project is auspiciously located 280kms from a rail terminal, which as WA s experience at opening up the Pilbara demonstrates is an essential piece of infrastructure for bulk projects. We look forward to updating our shareholders on the results of the logistics program of work underway as part of the feasibility program. For further information, please visit the Company s website at www.australianpotash.com.au to view the latest management update video, or contact: Matt Shackleton Executive Chairman m.shackleton@australianpotash.com.au +61 (0)438 319 841 Released through Sam Burns, Six Degrees Investor Relations, +61 400 164 067 Follow Australian Potash on Twitter @OzPotash

About Australian Potash Limited Australian Potash Limited (ASX: APC) is an ASX listed Sulphate of Potash (SOP) developer. The Company holds a 100% interest in the Lake Wells Potash Project located approximately 500kms northeast of Kalgoorlie, in Western Australia s Eastern Goldfields. The Lake Wells Potash Project is a palaeochannel brine hosted sulphate of potash project. Palaeochannel bore fields supply large volumes of brine to many existing mining operations throughout Western Australia, and this technique is a well understood and proven method for extracting brine. APC will use this technically low risk and commonly used brine extraction model to further develop a bore field into the palaeochannel hosting the Lake Wells SOP resource. A Scoping Study on the Lake Wells Potash Project was completed and released on 23 March 2017 ii. The Scoping Study exceeded expectations and confirmed that the Project s economic and technical aspects are all exceptionally strong, and highlights APC s potential to become a significant long life, low capital and high margin sulphate of potash (SOP) producer. Key outcomes from the Scoping Study are as follows: Stage 1 production rate of 150,000tpa of premium priced sulphate of potash (years 1 5) Stage 2 production rate of 300,000tpa of premium priced sulphate of potash (years 6 20) Upgraded JORC 2012 Mineral Resource Estimate comprising 14.7m tonnes of SOP, including 12.7mt in the Indicated category ii Operating expenditure of A$368/US$283 tonne SOP in the first 5 years and A$343 tonne SOP over the life of mine At a SOP price of A$795 per tonne SOP, the Project generates LOM annual operating pre tax cashflow iii of A$118m/US$81m Pre production capital expenditure (Stage 1) of A$175m/US$135m and Stage 2 of A$163m/US$125m Life of Mine (LOM) is 20 years (inc. Stage 1 & Stage 2) upside to LOM through continued exploration Forward looking statements disclaimer This announcement contains forward looking statements that involve a number of risks and uncertainties. These forward looking statements are expressed in good faith and believed to have a reasonable basis. These statements reflect current expectations, intentions or strategies regarding the future and assumptions based on currently available information. Should one or more of the risks or uncertainties materialise, or should underlying assumptions prove incorrect, actual results may vary from the expectations, intentions and strategies described in this announcement. No obligation is assumed to update forward looking statements if these beliefs, opinions and estimates should change or to reflect other future developments. Competent persons statement The information in this announcement that relates to Exploration Targets and Mineral Resources is based on information that was compiled by Mr Jeffery Lennox Jolly. Mr Jolly is a principal hydrogeologist with AQ2, a firm that provides consulting services to the Company. Neither Mr Jolly nor AQ2 own either directly or indirectly any securities in the issued capital of the Company. Mr Jolly has over 30 years of international experience. He is a member of the Australian Institute of Geoscientists (AIG) and the International Association of Hydrogeologists (IAH). Mr Jolly has experience in the assessment and development of palaeochannel groundwater resources, including the development of water supplies in hypersaline palaeochannels in Western Australia. His experience and expertise is such that he qualifies as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Jolly consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.

The Hydrogeological information in this announcement has been prepared by Carsten Kraut, who is a member of the Australasian Institute of Geoscientists (AIG), and International Association of Hydrogeologists (IAH). Mr Kraut is contracted to the Company through Flux Groundwater Pty Ltd. Mr Kraut has experience in the assessment and development of palaeochannel groundwater resources, including the development of water supplies in hypersaline palaeochannels in Western Australia. His experience and expertise is such that he qualifies as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Kraut consents to the inclusion in this report of the matters based on his information in the form and context in which it appears. i Refer to ASX announcement 31 January 2017 Scoping Study on Lake Wells Potash Project set for completion in March Quarter following strong flow rates from test bores, December 2016 Quarterly Activities Report. That announcement contains the relevant statements, data and consents referred to in this announcement. Apart from that which is disclosed in this document, Australian Potash Limited, its directors, officers and agents: 1. Are not aware of any new information that materially affects the information contained in the 31 January 2017 announcement, and 2. State that the material assumptions and technical parameters underpinning the estimates in the 31 January 2017 announcement continue to apply and have not materially changed. ii Refer to ASX announcement 23 March 2017 Scoping Study Confirms Exceptional Economics of APC s 100% Owned Lake Wells Potash Project In WA. That announcement contains the relevant statements, data and consents referred to in this announcement. Apart from that which is disclosed in this document, Australian Potash Limited, its directors, officers and agents: 1. Are not aware of any new information that materially affects the information contained in the 23 March 2017 announcement, and 2. State that the material assumptions and technical parameters underpinning the estimates in the 23 March 2017 announcement continue to apply and have not materially changed. iii Operating cashflows include all revenue and operating expenditure, but exclude capital expenditure.