NALCOR ENERGY. Comments on Draft Request for Proposals for Clean Energy and Transmission

Similar documents
Lower Churchill Project

Atlantic Link: An Update. June 6, 2017

WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES

Muskrat Falls Opportunities to Reduce Risk and Enhance Benefits

The Lower Churchill Project

CIMFP Exhibit P Page 1 Commission of Inquiry Respecting the Muskrat Falls Project. Muskrat Falls Project Timeline

Regional Electricity Cooperation and Strategic Infrastructure (RECSI) ATLANTIC REGION. Summary AR-SPM FOR POLICY MAKERS

Maine Power Express, LLC Response to Request for Comments December 28, 2016

December 28, Introduction

NOVEMBER 5, International Conference on Ocean Energy

TDI-NE Responses to 83D Questions December 28, b. Type of Organization (Public/Industry/Advocacy/Other)

Questions and Answers Contracts and Procurement Process for the Muskrat Falls Project

Analysis of Benefits of Clean Electricity Imports to Massachusetts Customers. Massachusetts Clean Electricity Partnership

PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1

Analysis of Proposed Development of the Maritime Link and Associated Energy from Muskrat Falls Relative to Alternatives

Investing in Alberta s Clean Energy Future A Framework. The Plan

HYDRO-QUÉBEC ELECTRICITY: CLEAN, RENEWABLE AND RELIABLE. November 2015

Muskrat Falls Project Update. June 23, 2017

REDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY

Green Line Overview. system with transfer capability of 660 MW or more (e.g.,1200 MW) miles submarine cable, 1 foot in diameter)

The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts

New England State and Federal Laws and Regulations and the Electric Power Sector

Independent Supply Decision Review

Mystic Marriott Hotel & Spa Register Now cpesconferences.org

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION

Questions and Answers Electricity Demand and Supply in NL

4 Transmission Planning Criteria, AC Integration Studies, and NERC Standards

Danielle Powers. June 3, 2010

ELECTRICITY TRADE AGREEMENT. An Assessment of the Ontario-Quebec Electricity Trade Agreement

ISO New England Overview and Regional Update

Coordinated Procurement Transmission in the Northeast

The Project. Federal Regulatory Approvals and Involvement

Recognizing the Value of Existing Hydropower June 25, 2009

S92A, Good Faith and Regulatory Proceedings in Quebec

HYDRO-QUÉBEC A N AT U R A L A L LY F O R MA S S AC H U S E T T S E N E R G Y T R A N S I T I O N

New England Governors Renewable Energy Blueprint

Renewable Energy for Newfoundland and Labrador: Policy Formulation and Decision Making

Regulatory Issues and Smart Grid Transmission Solutions

August 31, 2015 PROCUREMENT OF RESOURCES PURSUANT TO PUBLIC ACT NOTICE OF PROCEEDINGS AND OPPORTUNITY FOR PUBLIC COMMENT

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

SETTING THE CONTEXT. Overview: Nova Scotia s Electricity System

2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development

From Restructuring to Decarbonization: Operational and Market-Design Challenges in New England

Upper Churchill: Can we wait until 2041? Department of Natural Resources. Department of Natural Resources. October 2012

Comments of National Grid to the New England States Committee on Electricity on the Coordinated Competitive Renewable Power Procurement Process

The State of Wind Energy in New England

The Commonwealth of Massachusetts

Blueprint for Reliability:

ENERGY AND NATURAL RESOURCES

Commissioner Rob Klee, CT Department of Energy & Environmental Protection Massachusetts Electric Distribution Companies Narragansett Electric Company

the power is in our hands

Emera Investor Presentation. November 2008

All Source Request for Proposals Interim Summary

Hydroelectric Development at Buckhorn Lock #31 & Douro Lock #24

Policy Direction for Alberta s Capacity Market Framework

Carbon Pricing Straw Proposal. A Report Prepared for the Integrating Public Policy Task Force. April 30, 2018 DRAFT FOR DISCUSSION PURPOSES ONLY

Carbon Pricing Straw Proposal. A Report Prepared for the Integrating Public Policy Task Force. April 30, 2018 DRAFT FOR DISCUSSION PURPOSES ONLY

Focusing. Our Energy. Energy Plan Progress Report 2015

OTHER REVENUES REGULATED HYDROELECTRIC

Making Best Use of the Lower Churchill:

Electricity Options for Vermont

83D Q & A Set #8. Answer: Please see response to question 117.

Energy and Climate Report

1. the Infeed Option which is the Muskrat Falls Generating Station and Labrador-Island Link HVdc project; and 2. the Isolated Island Option.

Electricity Review Report. Final Report April

Dispatching Variable Generation Resources

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Emera Utility Services 2 Utility services contractor working in Atlantic Canada and other regions

Can Connecticut Meet Renewable Portfolio Standards and Improve Air Quality, Increase Energy Reliability, and Strengthen the Economy?

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE

Emerging Trends In North American Energy: Focusing On New England s Electricity Market

New England Power Sector Overview

Behind the Meter Net Generation Initiative: Energy Supplier Participation Requirements

NOVA SCOTIA TO NEW YORK AN EMERA PERSPECTIVE

A POWERFUL HYDRO PARTNERSHIP FOR MASSACHUSETTS

Canadian Wind Energy Association Operations and Maintenance Summit

FutureMetrics LLC 8 Airport Road Bethel, ME 04217, USA

Ontario s Changing Energy Landscape

Review of the Newfoundland and Labrador Electricity System

Peter Smith P.Eng and Guy Van Uytven, M. Eng., MBA, P.Eng., FCSSE

Demande R ANNEXE 4

NB Power s 10-Year Plan Fiscal Years 2016 to 2025

HOLYROOD THERMAL GENERATING STATION REQUIREMENTS 2011 TO 2020

Support for Competitive Procurement of Renewables in Mongolia

REQUESTS FOR INFORMATION THE NEWFOUNDLAND AND LABRADOR PUBLIC UTILITIES BOARD. GRK-NLH-1 to GRK-NLH-52

CA NLH NLH General Rate Application Page 1 of 3

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

The Impacts of the Green Communities Act on the Massachusetts Economy:

May 17, The important role that Canadian hydropower plays in the U.S.

Results from Canada s Energy Utilities

Update and Preliminary Guide on Renewable Electricity in Nova Scotia: Renewable Electricity Plan Implementation

Nation-building in the 21st Century: The Case for the Lower Churchill Hydro Development

Overview of the IESO- Administered Markets. IESO Training

Marine Renewable Energy in Canada

New England Electricity Outlook

Response to: Notice of Application Maritime Link Proposal (M05419)

National Energy Board. Reasons for Decision. Hydro-Québec EH November For Exports to Citizens Utilities Company

Open Season Guidelines

Practical Implications of the Mass. Omnibus Energy Bill and Other Energy Market Issues

Transcription:

Comments on Draft Request for Proposals for Clean Energy and Transmission Submitted to the CT DEEP, Mass. DOER, Eversource Energy, National Grid and Unitil March 27, 2015 Nalcor Energy (Nalcor), a provincial crown corporation owned by the Government of Newfoundland and Labrador, has experience in the development of large scale hydroelectric development and is pleased to provide the following comments on the draft RFP for clean energy resources in its capacity as both a developer of new hydroelectric generation and an owner/operator of existing hydroelectric facilities in eastern Canada. Nalcor s comments are presented in three parts. First, we provide background on Nalcor Energy and the context for its interest in clean energy procurement opportunities in New England. Second, we present comments that are specifically relevant to procurement of new large scale hydroelectric generation. Third, we present comments relevant to procurement of clean energy supplies from existing generation facilities or relatively low capital cost clean generation projects. (i) Background - Nalcor Energy The Province of Newfoundland and Labrador has significant hydroelectric resources to serve its relatively small population of about 500,000 residents. As a result of previous developments and a new project currently underway, the Province s own clean energy requirements will be met in the foreseeable future. These circumstances put the Province in a position to expand its export of clean energy into the Northeast region. The company s business activities include the development, generation, transmission and sale of electricity; the exploration, development, production and sale of oil and gas; as well as industrial fabrication and energy marketing. Nalcor currently owns and operates over 7,000 MW of electrical generating capacity that is predominantly comprised of hydroelectric power. Our fleet of hydroelectric generating facilities includes the 5,400 MW facility at Churchill Falls, Labrador which is owned and operated by Churchill Falls Labrador Corp. CF(L)Co., a subsidiary of Nalcor. The Churchill Falls generation facility has been operational since the 1970s. The majority of its production is currently exported to Hydro Quebec under long-term contractual arrangements that end in 2041. However, Newfoundland and Labrador Hydro, a subsidiary of Nalcor, sells some capacity and energy supplied to it by CFL(L)Co. from this facility for use in Labrador and for export. Nalcor s future hydroelectric generation supply is encompassed by developments underway and planned for the lower portion of the Churchill River. The Lower Churchill Project includes two hydroelectric sites (Muskrat Falls and Gull Island) downstream from the Churchill Falls generation 1 P a g e

station. These two facilities, when completed, will have a combined generating capacity in excess of 3,000 MW and on average annually produce 17 terawatt hours (TWh) of electricity. Phase I of the Lower Churchill Project, Muskrat Falls (824 MW), was sanctioned in 2012 and is currently under construction with first power scheduled for 2017. The project will meet growing demand in Newfoundland and Labrador and Nova Scotia, while enabling reduction in carbon emitting generation in both provinces. Surplus energy from this development will meet additional future domestic needs as they arise and /or be exported. This significant development also involves construction of HVDC transmission, including a 1,100 km transmission link from Labrador to the Island of Newfoundland and a 180 km Maritime transmission link from the Island of Newfoundland to Nova Scotia the latter is being financed and constructed by Emera. The combined generation and transmission project configuration will interconnect Newfoundland to the North American grid and produce significant improvements in the operation of the Newfoundland and Labrador and Nova Scotia systems. The development of this project has provided Nalcor with current experience in the negotiation of a regional, large scale generation and transmission project involving multiple governmental jurisdictions, public and private sector organizations, regulatory agencies, aboriginal groups, community consultations, financing agencies and others. Phase II of the Lower Churchill Project is the Gull Island site, with 2,250 MW of generating capacity and an annual average energy of 12 TWh, this is a very significant source of clean power. While construction has not yet commenced, the project has been well studied in terms of engineering and environmental impacts. The generation portion of the project has received environmental release. The output from this facility would substantially exceed the Province s requirements for the foreseeable future and therefore is an ideal long-term clean electricity supply available for export that could be committed under a longterm power contract. In addition to the Lower Churchill project, there are other smaller untapped hydroelectric resources and wind resources in the province that could be developed to optimize utilization of new transmission developments. Interconnection of the Province s electrical system to the North American grid as part of Phase 1 of the Lower Churchill project will mark a significant milestone for the Province and Nalcor Energy in its plans as a clean energy supplier in the region. Phase 2 of the Lower Churchill Project will mark a further and greater expansion as 2,250 MW of Gull Island power will be available to meet clean energy requirements on a long-term basis in the northeast region. It is in this context that Nalcor Energy is interested in clean energy procurement opportunities in the New England market that will enable development of this large scale resource. (ii) Procurement considerations for new large, scale hydroelectric generation The solicitation for comments indicates that the current draft RFP was developed pursuant to the clean energy goals of the states of Connecticut, Rhode Island and Massachusetts. 2 P a g e

While the RFP provides the opportunity for the participating states to act jointly to procure large supplies of electricity that no single state could procure unilaterally, the terms of the draft RFP are not suitable to enable proposals of supply requiring significant capital investment of the magnitude required for new large scale hydro development. The financing requirements and development lead times of these projects have significant implications for the procurement process and terms necessary for project development. However, once these projects are developed they have very long operating lives offering reliable, long-term clean electricity supply at predictable cost. These requirements and benefits distinguish new large scale hydro from other renewable sources. The following comments are proposed considerations for potential future RFPs. While Nalcor understands the limitations on the current draft RFP imposed by current eligibility criteria, we respectfully suggest that these comments be taken into consideration in the development of future RFPs designed to advance the region s clean energy goals. Quantities and Contract Term Lengths The quantity and term of the power purchase contract are two elements that are essential to enabling financing of new project development. They determine the project s future revenue stream. The quantities specified in the draft RFP would not be sufficient relative to the output of new large scale hydro to facilitate project financing or to optimize use of new associated transmission required to deliver incremental hydro imports from these projects. In order to benefit from economies of scale, a maximum transmission capacity of 1200 MW would have the capability to deliver up to 10 TWh/year. Thus a joint procurement for at least 10 TWh/year would enable a commitment of annual production sufficient to support financing, would achieve a lower delivered cost of power and allow for the integration of hydro with intermittent renewables, such as wind generation, to optimize use of transmission. With respect to contract term, large scale hydroelectric facilities have operational lives in excess of 75 years. The significant up front capital investment combined with the low operating costs result in a predictably priced, cost effective supply over a long service life. A longer term supply contract would better reflect the longer debt amortization period necessary and appropriate for these projects. In addition, a longer contract term will reduce the delivered cost of energy and result in stable priced clean power for a longer period. Nalcor suggests that longer term contract proposals should not be disqualified if proponents can demonstrate cost effective benefits to ratepayers. Contract terms up to 30 or 35 years would be more likely to result in new large scale hydro proponents participating in the procurement process. Full Value Proposition The current draft RFP states that there will be no payments or price supports from the EDCs for capacity associated with any Qualified Clean Energy procured under the RFP. The proponent must rely on the New England forward capacity market to realize capacity value. While this may be appropriate for the current solicitation, this market mechanism does not provide sufficient revenue security to enable long- 3 P a g e

term project financing as the pricing is uncertain and there is no long-term firm market commitment as is the case with a power purchase agreement. To secure access to new large scale hydro resources, a long-term revenue commitment that recognizes the full large scale hydro power value proposition that includes energy, capacity, reliability contributions and clean attributes over the term of PPA, i.e. 30 or 35 years, is required. Solicitation Process The proposed schedule for the bidding process under the current draft RFP provides 75 days from the release of the RFP to the submission deadline at which time the proponent is making a firm commitment offer (as per section 3.5, informational updates are permitted however changes to the terms are not permitted). If selected, the schedule provides a further 90 days for negotiation and execution of the contract. These timelines would not be appropriate in the context of negotiation of large scale hydro projects given the magnitude of the capital investment required (multiple billion dollars), and the lead time and complexities of developments of this nature and scale. Nalcor Energy has successfully completed negotiation and sanctioning of an 824 MW hydroelectric generation project and associated transmission in Atlantic Canada. From this experience, a staged process between the submission of a proposal, agreement on a term sheet outlining the principal terms and the ultimate negotiation of the power contract is required. This process, by necessity, provides for an engagement between the bidder and the EDCs to negotiate towards mutual benefit. As greater confidence is gained through the engagement process, all parties gain greater certainty regarding the project proposal and advantages while managing risk and thus will enable a final binding contractual commitment. (iii) Procurement Considerations for clean energy supplies from existing generation facilities or low capital cost clean generation projects Section 2.2.5 - Interconnection Requirements The RFP states that the EDC will not be responsible for any costs associated with Delivery other than the payment of bid prices. Similarly, EDCs will not be responsible for any scheduling associated with delivery. The Eligible Bidder will be responsible for all costs associated with interconnecting its project to the transmission grid and for ensuring that the Qualified Clean Energy is recognized in ISO-NE s settlement system as injected in the ISO-NE energy market at a specified and agreed upon pricing node. The assignment of this responsibility to the bidder is reasonable as long as there are market mechanisms in place to enable the bidder to manage potential congestion risk between the injection point and the agreed upon delivery point over a long term contract. Question: Have the Soliciting Parties and/or ISO New England given consideration to the issue of transmission congestion risk between the point of injection and the delivery point and how it may be mitigated by Eligible Bidders? How might this congestion risk be managed over a long-term contract? 4 P a g e

Conclusion Nalcor recognizes the potential benefits of multi-state RFP s for long-term supply contracts in achieving clean energy goals for Massachusetts, Connecticut and Rhode Island and for developers of clean power projects to supply these markets. Nalcor has recent experience in the development of new large scale hydropower and presents the above comments primarily for consideration in the development of future solicitations to enable broader participation of potential developers of large scale hydro in the clean energy procurement process. In addition, we offer comment so that we may better assess the opportunity for Nalcor to participate in the current draft RFP. 5 P a g e