Atlanta BeltLine Corridor Environmental Study. Technical Advisory Committee/Agency Coordination. Kick-Off Meeting

Similar documents
ATLANTA BELTLINE S c o p i n g B o o k l e t

3.0 REVIEW OF PREVIOUS STUDIES

U.S. Department of Transportation Federal Transit Administration and Metropolitan Atlanta Rapid Transit Authority

I-20 East Transit Initiative

AT L A N TA B E LT L I N E C I T Y O F AT L A N TA, F U LTO N C O U N T Y, G A

I-20 East Transit Initiative

Project Steering Committee April 14, 2015

DRAFT Scoping Booklet

12 Evaluation of Alternatives

Preparation of an Environmental Impact Statement for High Capacity Transit

Public Meeting. January 26, 2012 Fulton County North Service Center

Citywide Conversation

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1

Tier 1 EIS Round 2 Local Officials Briefing Fall 2011

BeltLine Corridor Northeast Zone FINAL DECISION DOCUMENT GEORGIA ENVIRONMENTAL POLICY ACT

Business Advisory Committee. July 12, 2016

King of Prussia Rail Project Frequently Asked Questions - Archive Version: Summer 2018

// Rotary Club of Decatur

Durham-Orange Light Rail Transit Project

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX

INTERGOVERNMENTAL AGREEMENT TRANSPORTATION PROJECT FUNDING AGREEMENT

Technical Advisory Committee Meeting #1. December 13, 2011 MARTA Headquarters

Preparation of this Tier 1 DEIS is in accord with the National Environmental Policy Act (NEPA), as amended and implemented by:

GEORGIA 400 CORRIDOR ALTERNATIVES ANALYSIS. Early Scoping Report

National Environmental Policy Act (NEPA) Process and Federal Agency Compliance

National Environmental Policy Act ACECNJ/NJDOT/FHWA 2013 DESIGN SUMMIT

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

Background. Purpose of This Phase of Project Development

Long Bridge Project. Environmental Impact Statement (EIS) Alternatives Development Report. June 19, 2018

SUMMARY S.1 PROJECT DESCRIPTION AND LOCATION S.2 PURPOSE AND NEED

<33 February OMF South Alternatives Evaluation Technical Memorandum

Northern Branch Corridor CLC Meeting. June 30, 2008

EVALUATION OF ALTERNATIVES CARRIED FORWARD

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012

Atlanta BeltLine West Environmental Assessment and Design Engineering Procurements

Executive Summary October 2017

Southwest Corridor Plan Project Update. June 11, 2013

Gold Line Environmental Impact Statement (EIS)

FINAL. Sound Transit Long-Range Plan Update Issue Paper S.6: Potential Tacoma Link Extension - East. Prepared for: Sound Transit

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 945

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

Southern Maryland Transit Corridor Preservation Study Charles County Board of County Commissioners September 22, 2009

Alternatives Analysis Executive Summary

Restoration of Historic Streetcar Service in Downtown Los Angeles

Regional Transportation Studies Regional Council

BUS RAPID TRANSIT CORRIDOR

Evaluation of Alternatives

APPENDIX N East King County Subarea High Capacity Transit (HCT) Analysis: Approach to Assessing System-Level Alternatives

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).

DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL)

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017

SECTION 4. Citizen s Guide to DEIS

I-70 East PACT DRAFT EVALUATION DATA

Chicago Transit Authority Orange Line Alternatives Analysis Study

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

Tacoma Link Stakeholder Group

WELCOME TO THE FEDERAL AVIATION ADMINSTRATION SCOPING MEETING

Reconstruction Project Update

Media Briefing. February 7, 2011

Outer Loop/Rail Bypass Study

A Presentation to: Project Advisory Group Meeting #7

Appendix C Presentation Slides with Script

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT

I-20 East Transit Initiative Scoping Information Packet

Metro Board Action: Motion 22.1

Alternatives Analysis

Alternatives Identification and Evaluation

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

SH 34 Corridor Study & Environmental Assessment:

South Sounder Capital Improvements Program

Gateway Corridor Transitway

West Seattle and Ballard Link Extensions. Stakeholder Advisory Group March 14, 2018

MORE MARTA ATLANTA SUMMARY OF PUBLIC ENGAGEMENT Contents CONTENTS TABLE OF EXHIBITS APPENDIX 2 9/4/18

Final Environmental Impact Statement Addendum: Agreement for the Central Corridor Light Rail Transit Project through the University of Minnesota,

Status Report on the 3 Rail Priorities

TIER 1 & 2 SCREENING RESULTS TECHNICAL MEMORANDUM. Prepared for: Southeastern Pennsylvania Transportation Authority (SEPTA)

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District

11 Joint Development Regulatory Context and Methodology

Phase II Options Feasibility Study. Draft Evaluation Methodology and Options Evaluation Matrix

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting

Progress Report Regional Express & Bus Rapid Transit Program

ATLANTA BELTLINE. U.S. Department of Transportation Federal Transit Administration and Metropolitan Atlanta Rapid Transit Authority

Sunrise Project South I-205 Corridor Improvement Project

Environmental Scoping Information Report

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

S-09: Auburn Station Access Improvements

Environmental Impact Statement for the Baltimore-Washington Superconducting Maglev (SCMAGLEV) Project, between Baltimore, Maryland and Washington, DC

Environmental Impact Statement for the California High-Speed Rail System Burbank to Los Angeles Section, CA

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures

CENTRAL ATLANTA TRANSPORTATION STUDY TABLE OF CONTENTS. Foreword...1. Study Objectives Study Process... 3

.Related Plans and Efforts

Section 7 Environmental Constraints

South Fulton Parkway Transit Feasibility Study Stakeholder Committee Meeting #2

AMENDED RECORD OF DECISION. by the Federal Transit Administration. Dulles Corridor Metrorail Project Fairfax and Loudoun Counties, Virginia

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting.

Identification and Evaluation of Alternatives Tier 1

Transcription:

Atlanta BeltLine Corridor Environmental Study Technical Advisory Committee/Agency Coordination Kick-Off Meeting July 17, 2008

Overview Project Overview Objectives Milestones Why GEPA and NEPA? Environmental Processes NEPA GEPA Northeast Quadrant Existing Conditions Feasibility Assessment

Project Objectives Complete environmental review under GEPA for Northeast Quadrant Identify right-of-way requirements for the Northeast Quadrant Complete Tier 1 EIS under NEPA to serve as the basis for future ROW acquisition in the entire corridor

Project Milestones GEPA Process for Northeast Quadrant Publication of the GEPA EER and beginning of public comment period is anticipated in January 2009; 45-Day public comment period for the GEPA EER is anticipated to end March 2009; Public Hearing for the GEPA EER is anticipated in March 2009; Publication of the GEPA Notice of Decision is anticipated in April 2009; Tier 1 NEPA Process Publication of the Tier 1 DEIS and beginning of public comment period is anticipated in Fall 2009; Public Hearing for the Tier 1 DEIS is anticipated in Fall 2009; Publication of the Tier 1 FEIS is anticipated in Spring 2010; Publication of the Record of Decision is anticipated in Spring 2010.

Why GEPA and NEPA? Need to identify ROW in Northeast Quadrant by December 31, 2008 Avoid violation of NEPA by segmenting the project Allow consideration of cumulative effects of impacts Streamline project management and avoid duplicative costs Efficiently manage work order quality and costs Avoid inefficiencies in schedule, budget and environmental review costs

Environmental Processes Goal of Environmental Process: To determine ROW needs, alignment location, and choose rail technology Atlanta BeltLine is both a federal and state action in terms of potential funding sources NEPA federal environmental process GEPA state environmental process By following both the federal and state processes funding options remain open MARTA is project sponsor, in cooperation with Atlanta BeltLine, Inc (ABI)

NEPA Process, 2-Tiered Approach Federal environmental process for 22-mile corridor, transit and trails

Agency Participation NEPA Lead agency FTA Project sponsor - MARTA Cooperating and Participating agency invitations to be sent shortly Please respond promptly

Technical Advisory Committee (TAC) Comprised of organizations and agencies having specific expertise or interest Responsibilities Input on range of alternatives Input on evaluation methodologies Encourage public participation in NEPA and GEPA processes Future TAC meetings will be scheduled around key project milestones

NEPA Opportunities for Participation Scoping Process Public Hearing on Tier 1 Draft EIS: Fall 2009 FEIS publication: Spring 2010 On-going Public Involvement Plan Technical Advisory Committee (TAC) Stakeholder Advisory Committee Target Audience Briefings Progress Presentations Interface via website, hotline, newsletters, Technical Findings Updates, Public Comment Forms and other media

NEPA Tier 1 EIS Tasks and Schedule

NEPA - Notice of Intent (NOI) Initiates the Tier 1 NEPA EIS Process Invites participation of agencies and public Identifies Scoping Meeting dates and locations Anticipated publication date by FTA in Federal Register: July 22, 2008

NEPA - Scoping Meetings A federally mandated process for identifying issues related to the project Opportunity for Cooperating and Participating agency and public comment on: Purpose and need Range of alternatives Scoping Booklet intended to: Inform agencies and public about the project Provide Scoping and NEPA process schedules Identify opportunities for agency and public input Current schedule Agency Scoping Meetings: August 12 and 22, 2008 Public Scoping Meetings: August 19 and 21, 2008 End of Scoping Process: September 22, 2008 Public and agency involvement continues through NEPA process

GEPA Process in Northeast Quadrant GEPA Lead state agency EPD Project sponsor - ABI Focus on Northeast Quadrant Detailed impact assessment via Environmental Effects Report (EER)

GEPA Process (continued) Schedule Publish EER: January 2009 Public comment period: January 2009 March 2009 Public hearing: March 2009 Notice of Decision: April 2009

Northeast Quadrant Study Area

Existing Conditions Report Preliminary Screening Contents Socio-economic Conditions Natural Environmental Conditions Transportation Conditions Bicycle and Pedestrian Trails Conditions Related Plans and Efforts Summarizes Information to be Used for: Feasibility Assessment Environmental Impact Analysis Conceptual Design of the Project

Existing Conditions Report Socio-economic Conditions Population in study area is 21,500 Employment in study area is 21,200 Environmental Justice Populations 12% are Low Income 33% are Minorities 14% are from Zero car Households Population Density Employment Density Source: Atlanta Regional Commission Source: Atlanta Regional Commission

Existing Conditions Report Socio-economic Conditions 19 Neighborhoods 10 Parks 11 Community Facilities 4 Churches 1 Government Building 3 Fire Stations 2 Police Stations 1 School 8 Archaeological Sites, 7 Historic Resources/Districts, and 5 Historic Buildings 8 Proposed Developments Neighborhoods Land Use Source: City of Atlanta-Bureau of Planning Source: City of Atlanta-Bureau of Planning

Existing Conditions Report Natural Environmental Conditions 3 Wetland Areas Piedmont Park Area Montgomery Ferry Rd Area South of Peachtree Creek 5 Floodplain Areas Peachtree Creek Clear Creek Piedmont Park Area Ansley Mall Area Montgomery Ferry Ten Water Bodies 79 Hazardous Material Sites Water Bodies and Floodplains Sources: City of Atlanta-Bureau of Planning Atlanta Regional Commission Hazardous Material Sites Source: US Environmental Protection Agency

Existing Conditions Report Transportation Conditions 2010 V/C Ratios Bus Routes Roadway System Functional Class 2010 and 2030 Traffic Volumes 2010 and 2030 Volume to Capacity Ratios Transit System Two MARTA Rail Stations 21 MARTA Bus Routes 1 GRTA Express Bus Route Ridership by Route Service Miles and Hours by Route Source: Atlanta Regional Commission Sources: MARTA, GRTA

Existing Conditions Report Pedestrian and Bicycle Conditions On-Street Bicycle Facilities Located Along Many Collector Streets Serve 7 of 12 Station Sites Multi Use Trails Existing Trail Along Freedom Parkway Proposed BeltLine Multi-Use Trail Proposed Feeder Trails Bicycle Routes Multi-Use Trails Source: City of Atlanta-Bureau of Planning Source: City of Atlanta-Bureau of Planning

Feasibility Assessment Purpose: Fatal Flaw Analysis Refine Alignment Options Identify Physical and Environmental Constraints Initiate Conceptual Design Process Focus on Minimum Standards

Feasibility Assessment Refined Alignments Maximize the Efficient Use of Available ROW Minimize Potential for Environmental Impacts Use Existing Transportation Facilities Where Possible Facilitate Intermodal Connections Light Rail/Streetcar Multi-Use Trail Source: DMJM Harris, Inc. Source: DMJM Harris, Inc.

Feasibility Assessment Minimum Typical Cross-sections: Exclusive Right-of-Way At Station with Center Platform- 65 Minimum Rail Transit and Multi-Use Trail Between Stations- 50 Minimum At Station with Side Platforms- 75 Minimum

Feasibility Assessment Minimum Typical Cross-sections: Transit in Mixed Traffic and Trail along Existing Street Rail Transit in Four Lane Street- 68 Minimum Rail Transit in Two Lane Street- 44 Minimum Rail Transit in Three Lane Street- 56 Minimum Trail Along Two Lane Street- 47 Minimum

Feasibility Assessment Right-of-Way Availability Unused Railroad ROW Exceeds 75 North of Freedom Pkwy South of Freedom Pkwy ROW is Only 65 to 75 - may require Center Platform Stations Mixed Traffic on DeKalb Avenue, Armour Dr, Mayson St, Peachtree Hills Ave, Garson Dr., and Lindbergh Source: DMJM Harris, Inc. Dr.

Feasibility Assessment Physical Constraints Narrow Bridges and Underpasses Narrow ROW Potential Property Acquisitions North of I-85 Creek and Stream Crossings Source: DMJM Harris, Inc.

Feasibility Assessment Environmental Concerns Water Resources and Floodplains Hazardous Material Sites Cultural Resources Environmental Justice Source: DMJM Harris, Inc.

Feasibility Assessment Conclusions None of the constraints rise to the level of fatal flaw Mixed Traffic operations likely required for some segments north of I-85 and along DeKalb Ave. New maintenance and storage facility will be necessary and may require property acquisitions and business displacements

Next Steps - Process NEPA Publish NOI and Scoping Booklet Invite Cooperating and Participating agencies Hold Scoping meetings Continue data collection and analysis GEPA Develop EER

Next Steps TAC and Agencies Agencies Please respond to Cooperating and Participating agency invitations for NEPA Agencies and TAC Please provide input/comment to Purpose and Need, and Range of Alternatives TAC Encourage public participation in NEPA Scoping meetings

Existing MARTA System

MARTA + Beltline Lindbergh Station Inman Park Station Ashby Station West End Station Potential Transfer Points

MARTA + Beltline + Clifton Corridor Lindbergh Station Inman Park Station Ashby Station West End Station Potential Transfer Points

MARTA + Beltline + Clifton Corridor + Streetcar Lindbergh Station Peachtree St Howell Mill Rd Marietta St 10 th /Virginia/Monroe Ponce de Leon Ralph McGill Simpson Rd Inman Park Station Ashby Station Auburn Ave Memorial Dr R.D. Abernathy West End Station Metropolitan Pkwy Hank Aaron Dr Potential Transfer Points

MARTA + Beltline + Clifton Corridor + Streetcar + I-20 East Lindbergh Station Peachtree St Howell Mill Rd Marietta St 10 th /Virginia/Monroe Ponce de Leon Ralph McGill Simpson Rd Inman Park Station Ashby Station Auburn Ave Memorial Dr R.D. Abernathy Glen/Memorial Transfer Point West End Station Metropolitan Pkwy Hank Aaron Dr To Stonecrest P&R Potential Transfer Points