Final Environmental Impact Assessment Report

Similar documents
Proposed Terms of Reference for EIA studies

Environmental Impact Assessment Report

TABLE OF CONTENTS. 3.1 Project Justification Project Description 21

Appendix A Schedule of Amendments to the EIAR

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

HINDUSTAN ZINC LIMITED Maton Rock Phosphate Mine (Maton Mine), Tehsil: Girwa District: Udaipur (Rajasthan) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES

V: PROJECT SCOPING & METHODOLOGY

PROPOSED TERMS OF REFERENCE (TOR) FOR

DESIGN SHEET Wastewater Treatment Plant. Mauritius. Design Sheet. Wastewater Treatment Plant. Revised 08 October Ministry of Housing and Lands

5. ENVIRONMENTAL IMPACT ASSESSMENT

Greater Amman Municipality

Table of Contents. O Devaney Gardens. Page i. Page Number. Section. 1 Introduction

FINAL. WREP Sectional Replacement Project Environmental and Social Impact Assessment. Georgian Pipeline Company

Executive Summary 1. 1 Project Background 6

1 Introduction 1-1. Project Need and Objectives

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

PROPOSED TERM OF REFERENCE

NEW BUGESERA INTERNATIONAL AIRPORT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT REPORT- CUMULATIVE IMPACT ASSESSMENT

CONCLUSIONS 14 CONTENTS

Terms of Reference (ToR) for EIA BUILDING STONE QUARRY OWNED BY LINEJ T.P

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous

10.0 AIR QUALITY AND CLIMATIC FACTORS

2. PROJECT DESCRIPTION

APPENDIX I PROPOSED TERMS OF REFERENCE

CHAPTER 1 INTRODUCTION

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

2) A copy of the document in support of the fact that the Proponent is the rightful lessee of the mine should be given.

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

Combined Cycle Gas Turbine Power Plant Project at Fort George, Mauritius

Division 15 Earthworks Code (including Lot Filling)

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1

18 Cumulative Impacts and Interaction of Effects

3.0 APPROACH AND METHODOLOGY

LEHIGH PERMANENTE QUARRY RECLAMATION PLAN AMENDMENT

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7

EXECUTIVE SUMMARY of the Environmental Impact Assessment Report

Hind Energy & Coal Beneficiation (India) Ltd.

TERMS OF REFERENCE (TOR) FOR THE PROPOSED RESIDENTIAL APARTMENTS LOCATEDON PLOT L.R NO.

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

CONCLUSIONS AND RECOMMENDATIONS CHAPTER 7

Ex-Ante Evaluation (for Japanese ODA Loan)

19. INTERACTION OF IMPACTS

T a b l e o f C o n t e n t s

Appendix F: Noise Report

NOISE IMPACT ASSESSMENT FOR SITE PLAN APPROVAL 12 HAMILTON AVENUE NORTH OTTAWA, ON.

Environmental Impact Statement. Avoca Tank Project

Terms of Reference. As Required by the Environment Act For Preparation of an Environmental Assessment Report

Draft Environmental Impact Statement Guidelines for the Environmental Assessment of the Sydney Tar Ponds and Coke Ovens Sites Remediation Project

Environmental and Social Considerations in Detailed Planning Survey. (Technical Cooperation for Development Planning)

Los Cerritos Wetlands Oil Consolidation and Restoration Project

Tri-County Aggregates Ltd. 92 Kenhar Drive North York, Ontario, Canada M9L 1N2

Environmental Assessment in Canada

A. TABLE OF CONTENTS ENVIRONMENTAL IMPACT STATEMENT

2 ENVIRONMENTAL IMPACT ASSESSMENT

APPENDIX 'G' Noise Attenuation Analysis

COASTAL PROTECTION, LANDSCAPING AND INFRASTRUCTURAL WORKS IN MAURITIUS CASE NOYALE SITE ENVIRONMENTAL IMPACT ASSESSMENT REPORT CONTENTS

ANNEXURE- II Proposed TOR

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary

Noise Feasibility Study EMGO (North Oakville I) Ltd., Town of Oakville, Ontario

Hind Energy & Coal Beneficiation (India) Ltd.

BRIGADE MIXED USE DEVELOPMENT

Proposed Appropriate Best Management Practices for Quality and Quantity Control of Highway Runoff in Amman

NOISE IMPACT ASSESSMENT FOR SITE PLAN APPROVAL 47 HAVELOCK STREET OTTAWA, ON.

Appendix K. Environmental Noise Assessment

APPENDIX C NOISE STUDY TECHNICAL REPORT

Annex F Scoping Checklist

TABLE OF CONTENTS LIST OF TABLES

ENVIRONMENTAL IMPACT STATEMENT FOR A PROPOSED AVIATION FUEL PIPELINE FROM DUBLIN PORT TO DUBLIN AIRPORT

ENVIRONMENTAL IMPACT STATEMENT FOR A PROPOSED AVIATION FUEL PIPELINE FROM DUBLIN PORT TO DUBLIN AIRPORT

COASTAL PROTECTION, LANDSCAPING AND INFRASTRUCTURAL WORKS IN MAURITIUS BAIE DU TOMBEAU SITE CONTENTS

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

Summary of Environmental and Social Consideration in Development Study (Preparatory Study)

PROPOSED TERMS OF REFERENCE

Outline for. Protected Areas Management Planning

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions.

Environmental and Social Considerations in Detailed Planning Survey (Technical Cooperation for Development Planning)

Chapter 17 Cumulative Impacts

ENVIRONMENTAL NOISE ASSESSMENT

Mining Environmental Impact Assessment Guidelines. May 2018

GIS data classes used within the November 2013 Environmental Statement Environmental Maps

Noise and Vibration Management for the Southern Suburbs Railway Project

A. INTRODUCTION B. NOISE ANALYSIS METHODOLOGY

Policy for the Assessment and Mitigation of Traffic Noise on County Roads

IX: HAZARDOUS WASTE MANAGEMENT

Roads Department of the Ministry of Regional Development and Infrastructure of Georgia GEORGIA FOURTH EAST-WEST HIGHWAY IMPROVEMENT PROJECT

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

EDINBURGH TRAM LINES ONE AND TWO

ENVIRONMENTAL BASELINE STUDIES FOR GEOTHERMAL DEVELOPMENTS

Summary of Preparatory Study

TRAFFIC NOISE ANALYSIS GLENN HIGHWAY RECONSTRUCTION MILEPOST PARKS HIGHWAY TO OLD GLENN HIGHWAY PROJECT NO /NH 0A1 5(24)

Coleorton Parish Council Response to HS2 Draft Environmental Statement

Transcription:

NON-TECHNICAL SUMMARY... I 1 INTRODUCTION... 1 1.1 BACKGROUND... 1 1.2 PROJECT IMPLEMENTATION SCHEDULE... 2 1.3 COST ESTIMATE... 2 1.4 KEY LEGISLATIVE, REGULATORY AND INSTITUTIONAL FRAMEWORK... 2 1.4.1 Introduction... 2 1.4.2 Requirement for undertaking an EIA... 2 1.4.3 Exemption from EIA... 3 1.4.4 Other environmental and other relevant legislation, regulations and guidelines... 3 1.4.5 Occupational Health & Safety... 3 1.5 INSTITUTIONAL RESPONSIBILITIES... 4 2 THE PROJECT... 5 2.1 PROJECT LOCATION... 5 2.2 PROPOSED ALIGNMENT... 5 2.2.1 General... 5 2.2.2 Description of the proposed alignment... 6 2.3 GEOMETRIC DESIGN... 6 2.4 PROPOSED DRAINAGE DESIGN CONCEPT... 7 2.5 MAJOR STRUCTURES... 7 2.6 JUNCTIONS... 9 2.7 TRAFFIC FORECAST... 9 2.8 CONSTRUCTION MATERIALS... 14 2.9 LAND ACQUISITION... 14 2.10 CONSTRUCTION ORGANISATION... 14 3 METHODOLOGY... 30 3.1 STUDY CORRIDOR... 30 3.2 INITIAL SCREENING OF POTENTIAL IMPACTS... 30 3.3 STAKEHOLDER CONSULTATIONS... 30 3.4 BASELINE DATA... 31 3.4.1 Desk Studies... 31 3.4.2 Field surveys... 31 4 ALTERNATIVES... 32 4.1 RDA ALIGNMENT... 32 4.2 ALTERNATIVE ALIGNMENTS AND PREFERRED SOLUTION... 32 4.3 NO-PROJECT ALTERNATIVE... 32 5 ENVIRONMENTAL BASELINE... 33 5.1 PHYSICAL ENVIRONMENT... 33 5.1.1 Topography and Land Use... 33 5.1.2 Geology and Hydrogeology... 34 5.1.3 Soils... 38 5.1.4 Climate and Climate Change... 39 i

P a g e ii 5.1.5 Hydrology, drainage & Surface water resources... 43 5.1.6 Groundwater resources... 45 5.1.7 Ambient Air Quality... 48 5.1.8 Ambient Noise... 48 5.2 BIOLOGICAL ENVIRONMENT... 50 5.2.1 General... 50 5.2.2 Flora... 50 5.2.3 Fauna... 51 5.3 PROTECTED AREAS... 52 5.4 UNPROTECTED SENSITIVE AREAS... 53 6 SOCIO-ECONOMIC BASELINE... 54 6.1 INTRODUCTION... 54 6.2 BENEFICIARIES... 54 6.3 DEMOGRAPHY... 54 6.4 SETTLEMENTS... 54 6.5 SECTORS OF ECONOMIC ACTIVITIES AND OCCUPATION OF THE POPULATION... 58 6.6 LAND USE... 59 6.7 RECREATIONAL VALUES AND CULTURAL ASSETS... 59 6.8 PLANNED DEVELOPMENTS... 60 7 ENVIRONMENTAL IMPACTS AND THEIR MITIGATION... 62 7.1 INTRODUCTION... 62 7.2 DESIGN... 62 7.3 IMPACTS ON CLIMATE AND AMBIENT AIR QUALITY AND THEIR MITIGATION... 62 7.4 IMPACTS ON SOILS AND THEIR MITIGATION... 65 7.5 IMPACTS ON WATER RESOURCES AND THEIR MITIGATION... 66 7.6 IMPACTS ON FLORA AND FAUNA AND THEIR MITIGATION... 67 7.7 IMPACTS ON SENSITIVE AREAS AND THEIR MITIGATION... 67 7.8 NOISE IMPACTS AND THEIR MITIGATION... 68 7.9 VISUAL IMPACTS AND THEIR MITIGATION... 74 7.10 IMPACTS ON ROAD / TRAFFIC SAFETY AND THEIR MITIGATION... 74 7.11 INDUCED IMPACTS... 74 7.12 BENEFICIAL ENVIRONMENTAL IMPACTS... 74 7.13 BENEFICIAL SOCIO-ECONOMIC IMPACTS... 75 7.14 POTENTIAL CUMULATIVE IMPACTS WITH OTHER PROJECTS... 75 7.15 RESIDUAL IMPACTS... 75 8 SOCIO-ECONOMIC IMPACTS AND THEIR MITIGATION... 77 8.1 GENERAL... 77 8.2 ECONOMIC IMPACTS... 77 8.2.1 Beneficial socio-economic impacts... 77 8.2.2 Adverse socio-economic impacts... 77 8.3 SOCIAL IMPACTS... 77 8.4 CONCLUSIONS AND RECOMMENDATIONS... 77 9 ENVIRONMENTAL MANAGEMENT PLAN... 78 9.1 INTRODUCTION... 78 9.2 INSTITUTIONAL ARRANGEMENTS AND REPORTING... 78 9.3 COST ESTIMATE... 81 9.3.1 Cost of Environmental Mitigation Measures during Construction Phase... 81

P a g e iii 9.3.2 Monitoring Cost... 81 9.4 IMPLEMENTATION SCHEDULE... 81 10 REFERENCES... 82 APPENDIX A GEOTECHNICAL INVESTIGATIONS... 83 APPENDIX B BIODIVERSITY REPORT... 124 APPENDIX I ENVIRONMENTAL MANAGEMENT PLAN (EMP)... 152 APPENDIX II ENVIRONMENTAL MONITORING PLAN... 162 ANNEX 1 NOTE OF MEETING AT FORESTRY SERVICE... 165 ANNEX 2 NOTE OF MEETING AT WATER RESOURCES UNIT... 168 ANNEX 3 LIST OF PEOPLE MET... 171

P a g e iv LIST OF FIGURES Figure 1-1: Geographical location of proposed link road... 1 Figure 2-1: Proposed Main axis of road alignment (A1 drawing provided at end of this report)... 15 Figure 2-2: Overall alignment of proposed road (Google Image Sheet 1/5 )... 16 Figure 2-3 : Typical Cross Section of road in FILL & CUT sections... 21 Figure 2-4 : Typical Cross Section of road in CUT sections with RETAINING WALLS... 22 Figure 2-5: Locations of stations for manual traffic counts... 23 Figure 2-6 (a) : Locations of Automatic Count Stations (Figures (b) (d) hereunder)... 24 Figure 2-7 : Locations of stations for O D surveys... 28 Figure 2-8 : Sub-division of road alignment into 6 sections... 29 Figure 5-1 : Office of Médine Sugar Estate (left) and prayer site on Rivière du Rempart (right)... 33 Figure 5-2 : Surficial Geology along project road alignment... 35 Figure 5-3 : Location of trial pits... 37 Figure 5-4 : Map of the Aquifers of Mauritius, extract... 38 Figure 5-5 : Soil Map of Mauritius, extract... 39 Figure 5-6: Isohyetal Map of Mauritius, Period 1971 2000... 41 Figure 5-7 : IDF Curves... 42 Figure 5-8: CWA abstraction points for domestic water supply from streams and rivers... 44 Figure 5-9 : Location of existing DWS boreholes in vicinity of road alignment... 46 Figure 5-10 : Groundwater Protection: Overview of Sensitive Zones and Catchment Boundaries... 47 Figure 5-11 : Aspects of forest belts in the reserves of River Cogliano (a) and Papayes (b)... 52 Figure 5-12 : Monvert Protected Forest... 53 Figure 6-1 : Residential morcellements at Beaux Songes Roundabout... 56 Figure 6-2 : Henrietta Village, Morcellement Pousson, La Marie Village... 57 Figure 6-3 : Cultural Site on Riviere du Rempart at the Beaux Songes Roundabout... 60 Figure 6-4 : Planned morcellement development at Beard... 61 Figure 7-1 : Variation of emission factor with vehicle speed for various air pollutants... 63 Figure 7-2 : Filtering Role of Roadside Vegetation... 65 Figure 7-3 : Decibel Scale of Commonly Encountered Sounds... 68 Figure 7-4 : Effect of Increasing Distance on Road Noise Levels... 69 Figure 7-5 : Logarithmic Decrease of Noise Levels Over Growing Distance from the Source... 70 Figure 7-6 : Effects of Noise Barrier Height on Noise Levels at Receptor... 72 Figure 7-7 : Wall, Berm and Combination Noise Barriers... 73

P a g e v LIST OF TABLES Table 2-1 : Proposed Geometric Standards... 6 Table 2-2 : List of hydraulic structures... 8 Table 2-3 : Description of Project Road Sections... 9 Table 2-4 : ANNUAL Traffic (PCUs) Forecast 2015 2036 Eastbound... 10 Table 2-5: ANNUAL Traffic (PCUs) Forecast 2015 2036 Westbound... 12 Table 5-1 : Annual Rainfall Projections 2020-2050... 40 Table 5-2: Intensity Duration Frequency Values... 42 Table 5-3 : List of boreholes along / in vicinity of proposed road alignment... 45 Table 5-4 : Overview of observed ranges of ambient air pollutants... 48 Table 5-5 : Prescribed levels for neighbourhood noise (Mauritius)... 49 Table 5-6 : Overview of traffic noise measurements along different roads in Mauritius... 49 Table 5-7 : Noise Level Patterns at Increasing Distance from Source... 49 Table 6-1 : Estimated Resident Population as at 1 st July 2011... 54 Table 6-2 : Distance between the proposed alignment and settlements along the said alignment... 55 Table 6-3 : Distribution of the Mauritian labour force per Activity... 58 Table 6-4 : Major occupational group... 59 Table 7-1 : Summary of Observed Ranges of Ambient Air Pollutants at Selected Sites... 64 Table 7-2 : Summary of other socio-economic benefits... 76 Table 9-1 : Responsibilities for implementing the Environmental Management Plan... 79 Table 9-2 : Environmental Mitigation and Monitoring Cost (Construction Phase)... 81 Table 9-3 : Implementation Schedule for Environmental Measures... 81

P a g e vi ACRONYMS ADT Average Daily Traffic am ante meridies (before noon) amsl above mean sea level BoQ Bill of Quantities CH chainage CSO Central Statistics Office, Mauritius CWA Central Water Authority db decibel DoE Department of Environment EIA Environmental Impact Assessment EHS Environment Health and Safety Manager EMP Environmental Management Plan EPA Environmental Protection Act 2002 FS Feasibility Study GHG Greenhouse gas GN Government Notice GoM Government of Mauritius h hour HGV heavy goods vehicle km/h kilometer per hour M Million mg/l milligram per litre MoE Ministry of Environment, Sustainable Development, and Disaster and Beach Management MoHL Ministry of Housing and Lands MMS Mauritius Meteorological Services MRU Mauritian Rupees NA not available N.T.S. not to scale O/D survey origin/destination survey p.a. per annum p.m. post meridies (after noon) PCU Passenger Car Unit RDA Road Development Authority RoW Right of Way SE Supervising Engineer s second TDS Total Dissolved Solids TMRSU Traffic Management Road Safety Unit UNFCCC United Nations Framework Convention on Climate Change VOC vehicle operation cost WHO World Health Organisation WRU Water Resources Unit

P a g e vii This report was prepared by POERSCHMANN Melanie MOWLABUCUS Mohammad Farook LUXCONSULT (Mtius) Ltd., Environment Specialist LUXCONSULT (Mtius) Ltd., Environment Specialist With contributions from The Design Team; & Yousouf Mungroo, Biodiversity Expert