CHAPTER - 7 RENOVATION AND MODERNISATION AND UPRATING OF HYDRO POWER STATIONS

Similar documents
Why and How: Renovation, Modernization and Uprating of Hydro Power Plants

PANCHET HYDEL STATION TILAIYA HYDEL STATION

Renovation & Modernisation

CHAPTER - 6 BEST PRACTICES IN OPERATION & MAINTENANCE OF HYDRO POWER STATIONS

POWER THROUGH EXPERIENCE

Florentin POP Project Manager Hydro- Engineering Romania

Strojírny Brno WATER TURBINES AND HYDRO-MECHANICAL EQUIPMENT

RenServ RENOVATION, MODERNISATION & UPGRADATION

Hydraulic turbines, storage pumps and pump-turbines Rehabilitation and performance improvement

INTERNATIONAL STANDARD

Justus B.C Mtolera Mtera Hydro plant Manager TANESCO TANZANIA

Main Menu Services Products Finances

List of training courses on electrical power system for Cambodia, Laos, Vietnam and Thailand (CLVT) countries

TURBO GENERATOR SERVICE TO EXTEND YOUR ASSETS LIFETIME

NZQA registered unit standard version 6 Page 1 of 6

Ultra Low Head Hydro Potential

Yale Hydroelectric Project FERC Project No Exhibit C - Construction History

Headquarters. Registered office. Via F.lli Ceirano, Cuneo (Cn) - Italia. Corso Dante, Cuneo (Cn) - Italia.

Steam Turbines-Generators and Auxiliary Systems - Program 65

ErcoleMareliGroup. GreenPowerGenera on HYDROPOWERPLANTTURBINES

ENGINEERING, PROCUREMENT & CONSTRUCTION OF HYDROMECHANICAL WORKS FOR MIDDLE MODI HYDRO POWER PROJECT (15.1 MW) BID DOCUMENT VOLUME 5: PRICE SCHEDULE

Refurbishment of Hydro Power Plants. André BOTTO

Thermodynamic Considerations for Large Steam Turbine Upgrades and Retrofits

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

Alden Turbine Development: Overview of Preliminary Engineering

U J V N Limited (A Govt. of Uttarakhand Enterprise)

Range of utilization. Envelope

Flexible Operation. Integrating thermal power with Renewable Energy & Challenges. Y M Babu Technical Services, Noida

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Electricity from a movable power source

Rock Island Powerhouse 2 Rehabilitation. Board Presentation. November 20, 2017

RENOVATION & MODERNIZATION SERVICES & REFERENCES

Water Power. Modern plant & DAM CONSTRUCTION. New equipment at the Blue Lake Expansion Project. Serving the hydro industry for 67 years

2 FINDING OF THE POTENTIAL SITES

STEAM TURBINE-GENERATOR & AUXILLIARY SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017

Table of Contents. A Operate and monitor Micro Hydel Power Plant (MHP) plant 04

HYDROPOWER INDUSTRY SOLUTIONS

Compact Hydro.

JOURNAL OF ADVANCEMENT IN ENGINEERING AND TECHNOLOGY

Rehabilitation of Kidatu Power Plant Project Presentation

2012 Capital Budgets Phase I: Total Capital Projects Overview Revision 1, October 12 11

Increasing hydro-equipment value with field measurements. P. Weibel, J. Contreras, S. Lais, E. Parkinson. ANDRITZ HYDRO Switzerland

Recent Renovation and Modernization Technologies for Existing Hydro Turbine

HYDRO-QUÉBEC S CONTINUOUS FLOW MEASUREMENT SYSTEM: DEVELOPMENT OF AN INDUSTRIAL PROTOTYPE

Design and Construction of a Mini Hydro Turbine Model

Development of Dalälven Hydropower Scheme in Sweden

Steam Turbines-Generators and Auxiliary Systems - Program 65

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-E Washington, DC Engineering and Design HYDROELECTRIC DESIGN CENTER

CIRED Workshop - Lyon, 7>8 June 2010 Paper 0004 ABSTRACT WHAT IS ISCM? INTRODUCTION WHY ISCM?

Technology Options for Existing Coal Units

Largo & Allegro. Air Compressors. Largo & Allegro

CIP 2019 Project Outline ~ Mechanical Engineering

Innovative Low Head Hydro The StreamDiver in Action. NWHA Small Hydro Workshop 2016, Wenatchee, WA USA

Engineering Design & Power Training Institute

GOVERNMENT OF INDIA MINISTRY OF POWER CENTRAL ELECTRICITY AUTHORITY

MIEL I Hydroelectric Power Plant

Reliability and Availability Evaluation of Sunkoshi Hydro Power Station

Francis Turbine Upgrade for the Lushui Generating Station by Using Computational Fluid Dynamics - A Case Study

Cost Analysis for High Head SHP Projects

DHUKWAN SHEP (24 MW) (UNDER CONSTRUCTION ON RIVER BETWA IN BABINA, DISTT. JHANSI, UP)

Recent approach to refurbishments of small hydro projects based on numerical flow analysis

TCN 02, Dated: WITH REFERENCE TO ABOVE FOLLOWING CHANGES MAY PLEASE BE NOTED AND COMPLIED WHILE SUBMITTING THE OFFER FOR THE SUBJECT JOB:

WindEurope considers that repowered projects could be further provided with a clear path-to-market via:

CONTENTS. PogeNo. Chapter 10: Productivity Approaches. Chapter 11: Human Resources Development in Hydro Sector

DESIGN OF A PELTON WHEEL TURBINE FOR A MICRO HYDRO POWER PLANT

Types of Hydropower Facilities

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Rollair. Air Compressors ROLLAIR 150E AND ROLLAIR 150V-180V-240V

Ingula Pumped Storage Scheme: Project Management Case Study

The Bujagali Hydropower Project. Sept 2011 EAPIC

Technologie - Wasserkraft für den Strommarkt der Zukunft: Von der Komponentenoptimierung zur Systemoptimierung

Swansea Bay tidal powerplant: Bi-directional bulb pump-turbine with variable speed

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT

DPR GUIDELINES FOR ERM OF IRRIGATION PROJECTS

Hydro Capacity Preservation & Expansion

Sharing Experiences of the World s Largest Tidal Power Plant in Lake Sihwa, South Korea

Large Scale Governor System Retrofits U.S. Army Corps of Engineers, North Pacific Region

NUCLEAR TRAINING CENTRE COURSE 134 FOR ONTARIO HYDRO USE ONLY

Mini Voith Global Perspective, Local Solutions

Engineering for SH Operations Voith s new StreamDiver technology. StreamDiver B Murtha, NWHA Sisters Oregon

Course 0101 Combined Cycle Power Plant Fundamentals

Bringing Untapped Hydropower to Reality

Mechanical Overhaul Guide For Hydroelectric Turbine Generators READ ONLINE

Application Note. Case study Predictive maintenance and its contribution to physical asset management at CEMIG

LAW OF THE REPUBLIC OF INDONESIA NUMBER 7 OF 2004 REGARDING WATER RESOURCES

Hydropower retrofitted onto existing water infrastructure assets

Short Term Training Program for year

Current Steam Turbine Technology and its Applicability in the Pulp and Paper Market

Reference List of BOOM Systems Private Limited (Projects / Products / Services)

Bharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA MATERIALS MANAGEMENT

Department of Electrical Engineering. Industrial Visit Report. Sardar Sarovar Narmada Nigam Limited Hydro Electric Power Station

1.1 Name of the Project : 1.2 Proposed Installed Capacity of the Project : MW

HYDRO POWER PROFILE. World-class skills. World-class team. Hydro Power Plant Engineers HYDRO GEOTHERMAL THERMAL WATER INDUSTRIAL

NZQA registered unit standard version 5 Page 1 of 6. Operate hydro-electric generating plant from enterprise control room

OUR FFICIENCY ARTNER

Harnessing the power of water with engineered reliability

Kössler...turns water into power!

Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric

Transcription:

CHAPTER - 7 RENOVATION AND MODERNISATION AND UPRATING OF HYDRO POWER STATIONS Renovation and modernisation (R&M) of hydro power plants is a cost effective way of dealing with the problem of low production levels. It is comparatively easier than constructing new projects and can yield results in about three to four years. The following chapter provides tips on selecting various R&M activities along with residual life assessment studies. 7.1 - Renovation & Modernisation (R&M) of old plants is considered to be the best option to bridge the wide gap between demand and supply of power as R&M programmes are cost effective having much lower gestation period compared to setting up of new plants. - Renovation, modernization and uprating of hydro generating units (RM&U) which have outlived their normative operating life and the relatively new machines with generic problems are recognized to yield considerable additional benefits of energy at minimum cost. RM&U programmes can be expected to yield benefits in about 3 to 4 years as against installation period for new hydro generating capacity of 6 to 7 years. - RM&U programmes may be taken up timely to prevent deterioration in operation of generating units which may lead to their premature retiring. By undertaking timely RM&U & Life extension programme, the generating plant can be made to operate for another extended period of 20 to 25 years with improved reliability and availability. 7.2 NEED FOR RENOVATION, MODERNISATION & UPRATING OF HYDRO POWER PLANTS - The normative operative life of hydro electric power plant is 30 to 35 221

years after which it normally requires Life extension through renovation. - By undertaking activities involving replacement of worn out or damaged components the availability of the generating unit and to some extent its life would be increased but no improvement in output or efficiency can be expected. - The output and efficiency of generating units can be increased by replacing old or damaged components by redesigned components using State of the art materials. Especially in old equipment a significant increase in output and/or efficiency can be achieved by the use of new materials and advanced engineering methods. In addition, the overall life expectancy of the equipment will also be increased. - By undertaking uprating programmes it is possible to uprate the generating capacity of existing units by 10 to 30% based on the water availability, operating margin and technological upgradation. This programme may be involving rewinding of stator from Class B to Class F, restoring stator core, improving air gap, replacing turbine runner with advanced blade profile and material while carrying out uprating of the plant, modernization by replacing conventional excitation system with static excitation system, replacing conventional governing system with micro processor based electro hydraulic governing system, retrofitting existing control and protection system to modern state of the art system etc. may also be undertaken for improvement of reliability in operation of the plant. However, uprating of generating capacity may be taken up after detailed investigations and studies. 7.3 APPROACH FOR SELECTING R&M ACTIVITIES The performance of the generating units should be the guiding factor in selection of R&M activities rather than the period of their operation. The following aspects/requirements to be kept in view whole selecting R&M activities:- 222

- Activities covering main equipment i.e. turbine, generator and C&I equipment and other plant equipment essential for efficient and sustained performance of the units as well as station be identified. - Activities which have direct impact on improvement of generation, efficiency, machine availability etc. be assigned higher priority. - Activities which yield uprating benefits because of rewinding with Class F insulation, runner with improved profile be given priority. - For silt prone hydro power stations, R&D activities on advanced techniques like plasma coating on under water parts of turbine, and development of new materials may be given priority. Adoption of closed circuit cooling system, Cu-Ni tubes for coolers etc. may also be considered. - Activities which include state of the art equipment such as electronic governors, static excitation system, micro processor based controlled high speed static relays, on line monitoring devices and silt content in water. - Activities like argumentation of water conductor system which may increase the discharge/head & hence the peaking capacity & additional generation of the generation station. 7.4 RESIDUAL LIFE ASSESSMENT (RLA) STUDIES RLA studies may be carried out so that a realistic picture is available in regard to the residual life/condition of the entire power station equipments, systems and sub systems. Whole power project is divided into 4 categories for the purpose of RLA studies. These are as under:- Category I : Hydro turbines, generators, valves, governors, excitation system equipments and station auxiliaries. Category II : Main power transformers and switchyard equipments Category III :Hydro mechanical equipments like gates, trash rack, stop logs and gate operating mechanisms Category IV: Civil engineering elements/components namely dams, 223

intake, water conductor system, power house building, foundations etc. i) Besides non-destructive/destructive tests and interpretation of test results, the following should also constitute the RLA study programme:- - Visual examination - On line diagnostics - Review of operational history - Review of plant documents - Discussions with plant authorities and O&M staff on the health of the equipments - Identification of critical components 7.5 STRATEGY OF RM&U & LE PROGRAMME The strategy of RM&U & LE programme is to determine the optimum RM&U & Life extension works, so as to achieve restoration/enhancement of the plant s average performance, reliability, availability, safety of operation, Life extension for another 20-25 years and updation/ upgradation of equipment/system and to determine the potential for uprating the capacity of the units/plant as a whole. 7.6 METHODOLOGY FOR IMPLEMENTATION - Scope of R&M works and life extension programme in respect of generating units having completed more than 30 years of service life should be firmed up based on RLA studies. Uprating, if feasible shall also be taken up along with life extension programme. - RLA studies should be got conducted through competent vendors and the Detailed Project Report for the scheme be prepared based on the findings of RLA studies. - Job of RLA studies and execution of R&M works should be tendered out separately with the later being based on the findings of the first one. - Prior to undertaking uprating works, it is necessary to go for uprating studies. Uprating studies should be got conducted through reputed agencies like CWPRS, CPRI, BHEL, etc. 224

- R&M works as firmed up in the detailed project report should preferably be tendered out on turn-key basis to the reputed manufacturers/vendors. - A high level task force be constituted by the utility for implementation of R&M schemes as per time bound programme. - Completion of activities as well as performance of the equipment after R&M should be guaranteed through stringent penalty clauses. - Addition/deletion of R&M activities from those incorporated in the DPR should not be permitted. Allocation of funds should be activity based and implementation of the scheme should be monitored activity-wise. 225