Girth Weld Failure Analysis In Coker BlowdownHeaders

Similar documents
Fast quench problems and how they damage coke drums

Fatigue Life & Reliability Consideration During Field Repair of Coke Drum & Piping

Fast quench problems and how they damage coke drums

Innovative Repairs in Coke Drums. Coking.com Calgary, Alberta Canada

STRESS ANALYSIS USING ACTUAL COKE DRUM BULGE PROFILES A CASE STUDY. Daryl K. Rutt, Richard D. Clark. CIA Inspection Inc.

HIGH ENERGY PIPING INSPECTION PROGRAM

Open Art, Coke Drum Specification

Technical Presentation PVP

HÉZIO Rosa da Silva (PETROBRAS/REGAP)

A Fresh Look at 3 Drum Cokers

Repair and Retrofit of a Coke Drum Skirt Attachment Weld

Repair Weld Simulation of Austenitic Steel Pipe

ASME B31.3 Process Piping. 19. What s Different in B31.1

Bulging Assessment and Long- Term Repair of Coke Drums

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes...

Lecture 1: Introduction to Mechanical design consideration for process equipment

TROUBLE SHOOTING IN DELAYED COKER UNIT- INSPECTION EXPERIENCE

Fatigue Testing of Welded Flat Head Pressure Vessel Joints

Field Modification of DCU Support Skirt-to-Vessel Attachment Weld Geometry

Fatigue Testing and Life Estimates of Welded Flat Head Pressure Vessel Joints. Chris Hinnant Paulin Research Group Houston, TX

Ramifications Of Cracks At The Fillet Welds Of High Temperature Steam Headers

Assessing the structural integrity and remaining life of Coke Drums with Acoustic Emission Testing, Strain Gaging, and Finite Element Analysis

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

SECTION PLUMBING PIPING SYSTEM

Schöck Isokorb Type CV

PIP PNC00001 Pipe Support Criteria for ASME B31.3 Metallic Piping

Sulfur Unit Equipment Problems and Low Silicon Carbon Steel Corrosion Gerald W. Wilks Lemont Refinery CITGO Petroleum

Innovative Solutions for Coke Drum Life Extension. Presented By: Ruben Lah VP/CTO Curtiss Wright Oil and Gas Technology Development Center

Failures of High Alloy Expansion Bellows in Refinery Catalytic Cracking Units

Welcome at our Masterclass. Centre Line Aligned assembly of cans

CHAPTER 1 INTRODUCTION TO PIPING SYSTEM

COMPOSITES - CASE STUDIES OF PIPELINE REPAIR APPLICATIONS. By Andrew J. Patrick, Clock Spring Company, L.P., Huntingdon, UK

CONTENTS. Fittings, Bends, and Intersections

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION

Optimization of FCCU Expansion Joint Application, System Design and Reliability Considerations. Tej Chadda Director, Technology Technical Services

Lessons Learned in Solar Thermal Power Plants

Furmanite s engineered composite repair technology

STATE-OF-THE-ART DELAYED COKING STRUCTURE FOR FRONTIER REFINING

10.1 APPLICATION 1 A. HOT PIPING 1 B. ANTI SWEAT PIPING 1 C. COLD PIPING FINISHES 2

Consolidated Edison Company of New York Water Hammer Predictor Model Update

Reinforced Thermoset Plastic Corrosion-Resistant Equipment

Best Practice On Insulation Of Process Installations

ASME B31.3 CUMULATIVE INDEX INTERPRETATIONS VOLS SUBJECT INDEX. Assembly and Erection Authorized Inspector (see Owner s Inspector)

The planning and design of effective wet duct/stack systems For coal fired utility power plants

Coker Safety and Reliability Lessons Learned

Observations Related to the Master SN Method in the ASME Division 2 Rewrite Project

E APPENDIX. The following problems are intended for solution using finite element. Problems for Computer Solution E.1 CHAPTER 3

Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland, WA, USA

PRESSURE-TEMPERATURE LIMIT CURVES

PROLONG THE INTEGRITY OF HIGH ENERGY PIPING SYSTEMS: UNIT SPECIFIC STRATEGIC PLANNING

ENBRIDGE PIPELINES INC. WELDING PROCEDURE DATA SHEET

Coke Drum Flow Distributions

CYLINDRICAL VESSEL LIMIT LOAD ESTIMATION FOR OBLIQUE NOZZLE BY USING ANSYS AS ANALYSIS TOOL

Reinforced Thermoset Plastic Corrosion-Resistant Equipment

Gas Turbine & Combined Cycle Plants

HYBRID COMPOSITE REPAIR for OFFSHORE RISERS

Stress Evaluation of a Typical Vessel Nozzle Using PVRC 3D Stress Criteria: Guidelines for Application

49 CFR Part 192. Not applicable to welding during manufacture of pipe and components

Marcio I Haraguchi. Mahmod Samman. Ediberto B. Tinoco Fábio C. Marangone Hezio R. Silva Gustavo C. Barcelos

Industry Response to Recent Thermal Fatigue Operating Experience

Design Considerations for Advanced Combined Cycle Plant Using Fast Start Drum Type HRSGs

Prediction of Residual Stresses after Local Post-Weld Heat Treatment

Drums, Vessels, & Storage Tanks. Design Considerations

Design and Operation of Large Fossil-Fueled Steam Turbines in Cyclic Duty

National Academy of Sciences

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION HVAC PIPES AND TUBES

COMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.

TERASEN PIPELINES (TRANS MOUNTAIN) INC. ENGINEERING STANDARDS AND PRACTICES STATION & TERMINAL PIPING DESIGN

NDE Based Finite Element Modeling & Analysis of Wall Thinning in CANDU Feeders

OIL TECH SERVICES, INC.

Technical Inquiries for API Standard 620, Design & Construction of Large, Welded, Low-Pressure Storage Tanks Last updated February 2014

PLASTIC FITTINGS Avenue Edmonton, AB Canada T6E 5Z7. Toll Free: Phone: (780) Fax: (780)

Schöck Isokorb Type CM

WYATT Orifice flow PrOducTs

OPERATING EXPERIENCE REGARDING THERMAL FATIGUE OF UNISOLABLE PIPING CONNECTED TO PWR REACTOR COOLANT SYSTEMS

Designing wet duct/stack systems for coal-fired plants

ASTM Standards for Pipe & Fittings

ASSESSING THE EFFECTS OF CORROSION ON THE MECHANICAL INTEGRITY OF A PIPELINE SUSPENSION BRIDGE

CONVEYOR PULLEY DESIGN Allan Lill

GLAUNACH THE SILENCER HANDBOOK INSULATION SUPPLEMENTARY ACOUSTIC SHIELDING OF SILENCERS, PIPES & CO GLAUNACH GMBH ALL RIGHTS RESERVED -

Ovality Correction Methods for Pipes

Guidance for Specification and Purchase of Segmentable Induction Bends and Elbows

Note 1.1 Introduction to fatigue design

within Epsilon Twin Cities ANSYS User Meeting August 2012 Weld Analysis

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED

Case Study: Failure Analysis of Sulfuric Acid Supply Line

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

HRSG Inspection Planning Guide

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13

Schöck Isokorb type CV

HIGH TECHNOLOGY PRODUCTS AND SERVICES FOR YOUR MOST DEMANDING CORROSIVE CHEMICAL ENVIRONMENTS

Chapter 2 The Structural Hot-Spot Stress Approach to Fatigue Analysis


(Name and address of Manufacturer) (Name and address of Purchaser) (Name and address)

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

Review of ASME Guidance Articles on Repair Strategies

RESULTS OF FEA ANALYSES AT NOZZLE/SHELL JUNCTIONS SUBJECTED TO EXTERNAL LOADS

Transcription:

1 Girth Weld Failure Analysis In Coker BlowdownHeaders Kia Gharib, P.E. Manager of Engineering

2 Background Our customer recently experienced cracking issues with the blowdown header for their Coker Unit blowdown system. The blowdown header was fabricated from 36 Sch. 40/STD A-672-C70 pipe. The thickness of the pipe varied along the length of the header (3/8 or 3/4 ). At the time of the analysis, the following cracks had been observed by the customer: Two (2) through-wall cracks located at girth welds (The cracks were repaired using temporary pipe clamps). Five (5) internal surface cracks (not penetrated through the thickness). Pro-active maintenance for the cracked locations was performed by installing 6 wide C.S. bands at each of the weld locations. All of the cracks were located at approximately the bottom centerline of the header pipe (6 o clock position). All of the cracks initiated from the inside surface of the header pipe. All of the cracks were located at thickness transition welds between 3/8 and 3/4 sections.

3 Scope of the Analysis In order to determine the root cause of the failures observed in the blowdown header, the following analyses were performed: To determine if there were any issues with the original design in regards to the pipe supports or the overall piping flexibility, the blowdown system was analyzed under the intended operating conditions. The effect of circumferential thermal gradient similar to the gradient observed in the field was analyzed. The effect of continuously heating the lower portion of the blowdown header using hot oil stream was analyzed. The effect of insulating the blowdown header was analyzed. The effect of thickness transition used along the length of the blowdown header was analyzed. The life expectancy of the currently implemented repair bands and clamps were determined. Long-term repair for the blowdown header was determined. Temporary repair to the blowdown line was determined to prolong the life expectancy to the next turnaround.

4 Transition Girth Welds 10 years into service our client had cracking issues with the blowdown header for the coker unit blowdown system. The blowdown line was constructed by welding together several segments of pipes. At major branch connections, thicker pipe sections were used to inherently reinforce the openings. The pipe outside diameter was maintained.

5 Reasons for Cracking Formation of liquid pool at the bottom of the blowdown line due to different inside diameter of pipes exacerbates the circumferential thermal gradient. Poor workmanship may have contributed to some weld failures. Abrupt change in stiffness by using two different pipe thicknesses causes accumulation of induced stresses and the eccentricity between the centerlines of the pipe sections additionally intensifies the bending moment.

6 Reasons for Formation of Liquid Pool Formation of a liquid pool at the bottom of the blowdown line causes a circumferential thermal gradient Steam traveling through the drain lines and relief lines loses heat because the lines are uninsulated. A majority of the steam in the relief lines condenses to water prior to entering the header. Hydrocarbon vapor from the drums condenses in the header. The low slope of the header does not reduce the length of liquid pool in the header pipe.

7 Coker Unit Coke Drum 108 Overhead Vapor Line (Typ.) Coke Drum 109 Coke Drum 110 Relief Valve Line (Typ.) Coke Drum 111 Hot Oil Inlet Line Crude/Quench Inlet Line (Typ.) Drain Line (Typ.) Overhead Vapor Line to Fractionator (Typ.) Blowdown Header North Quench Tower

8 Operating Cycle

9 Analysis of Condensate Fill Height Sensitivity analysis was performed to determine the effect of circumferential temperature gradient. Several different "fill heights" for the liquid at bottom of the header were considered: ~0 Normal Operating Condition ~11.25 half angle ~17 half angle ~22.5 half angle ~30 half angle ~45 half angle ~90 half angle Half Angle Liquid Height

10 Analysis of Condensate Fill Height

11 Analysis of Condensate Fill Height

12 Analysis of Condensate Fill Height Legend: Red: Thermocouple Blue: IR Green: FEA Result

13 Thermal Gradient Due to Pooling

14 Temperature During the Operating Cycle Summary of Header Crack Locations (Looking North)

15 Stresses During the Operating Cycle Summary of Header Crack Locations (Looking North)

16 Analysis of Condensate Fill Height Half Angle Liquid Height

17 Analysis of Fill Height and Residual Stress

18 Effect of Residual Stress on Fatigue Life

19 Effect of Pipe Thickness on Fatigue Life

20 Effect of Stress Concentration 3/8 thk. Using Shell Element Brick Element 3/4 thk. Using Shell Element

21 Pipe Thickness Versus Axial Stress 70000 60000 50000 Max Axial Stress (psi) 40000 30000 20000 Orgiinal Original Thickness (shell) (Shell) Original Thickness with SCF (Brick) 10000 0 6 7 10 11 15 23 25 Weld #

22 Effect of Weld Quality on Fatigue Life 4500 4000 3500 Flaw Size vs Permissible # Cycles Permissible # Cycles 3000 2500 2000 1500 1000 500 0 0 0.005 0.01 0.015 0.02 0.025 0.03 Flaw Size (in)

23 Potential Solutions Before crack formation: The addition of hot oil to the blowdown header o The oil had negligible effect on the metal temperature downstream at the overhead vapor inlets. Insulating the Blowdown Line o Insulation would not appreciably reduce the amount of condensate in the header. o Cost would be prohibitive. After crack formation: Installation of bands and clamps

24 Temporary Repair Band

25 Band Design The band design initially used on the header (6 flat band) resists the deformation of the pipe and causes high stresses in the band-to-header fillet welds. An alternative band design was developed to reduce the stresses in the band and the header by remaining more flexible The increased flexibility helped reduce stresses at many locations and will provide 20 year fatigue life

26 Geometry of the Long Term Band 3 Extension *Typical band geometry utilized where interferences did not exist 6 Sch. 80 Pipe

27 Modified Elliptical Design Long Term Repair 3 Extension 10 Inside (*) 6.3125 Total 1/2 Thick *Dimension chosen to keep the band welds out of the heat affected zone

28 Prevention of Cracking in Blowdown Headers Process Improvement Redirecting the condensate through a different line Minimize the amount of steam Fabrication Quality Use uniform pipe thickness throughout to avoid pipe eccentricities Girth welds to be ground smooth, inside and outside surface, to minimize stress concentration. Weld quality and weld inspection to be in accordance with ASME Section VIII Division 2 Tables 5-11 and 5-12. Increase header slope Proactive Measures Monitoring o Temperature data should be collected (using IR or thermocouples) at critical locations on the header Install bands at critical welds

29 Kia Gharib, P.E. Senior Engineer/Manager of Engineering #1 Country Club View Dr. Edwardsville, IL 62025 (618)656-8600 (618)656-1700