Ontario ENGINEERING STANDARD SPECIFICATION 1/10 REV. ELECTRICAL DISTRIBUTION HIGH VOLTAGE SUBSTATION GROUNDING AND BONDING. Approved by.

Similar documents
PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

Grounding Principles. The need to ground! Definitions. Introduction. Grounding Codes and Standards. 2 Ph:

CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION

ELECTRICAL INSPECTION BULLETIN (Effective )

A Proper Design of Wind Turbine Grounding Systems under Lightning

Substation Design Volume X

SECTION FACILITY LIGHTNING PROTECTION

The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999

TS 804 CABLES TABLE OF CONTENTS TRAFFIC SIGNAL EQUIPMENT POLE WIRING DIAGRAM LOCATIONS WITH CENTRE MEDIANS

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National

Document No Amendment No Approved By Approval Date Review Date NS222 MAJOR SUBSTATION EARTHING LAYOUT DESIGN

THE OFFICIAL TRADE JOURNAL OF BICSI

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

Parameters Effecting Substation Grounding Grid Resistance. Dwarka Prasad 1, Dr.H.C Sharma 2

SECTION LIGHTNING PROTECTION SYSTEM

Substation Grounding Tutorial

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

Earthing in electrical network purpose, methods and measurement

LIGHTNING PROTECTION. 3.6 National Fire Protection Association (NFPA) NFPA 780, Standard for the Installation of Lightning Protection Systems

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION

EXTERNAL GROUNDING (EARTHING)

CONSTRUCTION SPECIFICATION FOR GROUNDING

Improvement of Substation Earthing

An Overview of Earthing

Wind Power Solutions. Company Registration No: Vat Registration No.:

Transmission Line General Requirements Including Typical Overhead Line Structures. Document Number: 1-03-FR-09

VALE # MSPEC LAST REVISION. Name: Brian Koltun Position: Process Superintendent Department: Power Department, Ontario Operations

Inspection Guide for PV Systems in One- and Two- Family Dwellings (For Rooftop Photovoltaic Systems meeting the Standard Plan)

CHAPTER 02 LITERATURE SURVEY

ELECTRICAL SAFETY Information Bulletin

Ufer grounding. Ufer Ground - Wikipedia, the free encyclopedia

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

Earthing of Utility and Industrial Distribution Systems

STANDARD DRAWINGS. September 2013 UPDATED FEBRUARY 2016

TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. Policy Bulletin No Appendix A SAFETY & INTERCONNECTION REQUIREMENTS FOR ALTERNATE ENERGY PRODUCTION

Facility and Equipment Grounding

Facilities Study. For. XXXXXXXXXXXX Wind Park Interconnection Switching Station

ELECTRICAL SAFETY Information Bulletin

GB Translated English of Chinese Standard: GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

INTEGRATED GROUNDING SYSTEM OF WIND-FARMS FOR LIGHTNING AND FAULT PROTECTION

Level One and Level Two

SECTION GROUNDING AND BONDING

EFFECTIVE DATE: November 1, 2011, unless a later date is cited at the end of a section. [ NMAC - Rp,

Technical Specification TS Issue 5 September 2014 EARTHING

LIGHTNING PROTECTION AND EARTHING

Substation Grounding. Presented by: Bruce Kayser, PE Assisted by Danny Seele

Wind Power Solutions CADDY ERICO HOFFMAN RAYCHEM SCHROFF TRACER

Petroleum Production and Disposal Facility Static and Lightning Mitigation

APPLICATION NOTE 6. Use of Decouplers for AC Voltage Mitigation. PART 2: DESIGN CONSIDERATIONS

SECTION GROUNDING

Walk through the associated design considerations associated with transmission line design

ISO Rules Part 500, Facilities Division 502, Technical Requirements Section Bulk Transmission Technical Requirements

4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING.

NPS/002/001 Technical Specification for Earthing Materials

SECTION GROUNDING AND BONDING

ELECTRICAL BULLETIN

SECTION PART 1 GENERAL

Earthing of Utility and Industrial Distribution Systems

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

Power Systems 2 ELE3015. Lecture 1: Transmission Lines

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Specification Lightning Protection Systems

REVISIONS. App Sud. App PC. App Thom AA 2014/10/28 AA 2014/11/24 AA 2015/06/24

XXXXXXXXXXX Solar (XXX) Generation Interconnection

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.

GROUNDING AND BONDING

GROUNDING SYSTEMS. Design & Application Nov 2018, Dubai Nov 2019, Dubai

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Series 8009A 9-Meter Earth Station Antenna. Site Preparation Manual

Foundation Specifications

a) Line and load compartments must be separated by a stable barrier.

POOLS, SPAS AND HOT TUBS

Conductor Shield A combination of semi-conducting tape and extruded thermosetting semi-conducting material meeting UL 1309, IEEE 1580 and UL1072.

UNDERGROUND SERVICES SECONDARY

Lightning Protection Practice for Large-Extended Photovoltaic Installations

Field Instruction. Any part of a person (body). Any conducting object, tool or equipment being held or carried.

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

7 Project Description

SECTION HEAT TRACING FOR PLUMBING PIPING

Review of Substation Grounding Practices, Safety and Constructability Enhancements. Authors: V. SIMHA, X.WU, M.THAKUR

Standard of Practice - Campus Electrical Distribution System

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

Section 7: Specifications

Foundation Specifications

Bulletin Grounding and bonding of solar photovoltaic systems Rules , , , and

COMPLETE REVISION January Process Industry Practices Electrical. PIP ELIGD000 Grounding Installation Details

Local Government District of Pinawa P.O. Box 100 PH: Pinawa, MB R0E 1L0 FX:

Pre-Qualification Certificate

SECTION HEAT TRACING FOR PLUMBING PIPING

2015 Code Rollout Meeting Q & A

CHAPTER 13 GROUNDING AND BONDING

Requirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014

Objectives and Task Analysis for the Installer of Grid Connect Photovoltaic System

ATTACHMENT A - TECHNICAL SPECIFICATIONS 1.1 GENERAL REQUIREMENTS

2 3 4 Distance from centre of reactor (m)

Section 2: Underground

Foundation Specifications

Chapter ELECTRICAL CODE*

Transcription:

/0 Rev Description Revision by Approved by Issue Date YYYY/MM/DD New Format Replaces 5322-0.0. T.C. 206/02/09 T.C. 206/03/02 206/03/02

2/0.0 PURPOSE This specification describes the minimum requirements for the design, installation and testing of grounding and bonding systems for outdoor 34.5 KV or higher voltage substations. 2.0 REFERENCE DOCUMENTATION The following documents are related to this specification: SPEC-5302 99-999-H-004226 99-999-H-004227 HV Substation - 69 KV 7.5/0/.2 MVA Grounding - Substation Fence HV Substation Grounding & Bonding 3.0 CODES, STANDARDS AND REGULATIONS The following codes and regulations in their latest version shall be applicable: CSA OESC OHSA 854 CAN/CSA-M42 IEEE 80 IEEE 8 IEEE 8.2 IEEE 42 IEEE 367 IEEE 525 IEEE 837 IEEE 998 Canadian Standards Association Electrical Safety Code Occupational Health & Safety Act & Regulations for Mines & Mining Plants Use of Electricity in Mines Guide for Safety in Substation Grounding Guide for Measuring Earth Resistivity, Ground Impedance and Earth Surface Potentials of a Ground Grid Guide for Measurement of Impedance and Safety Characteristics of Large Extended or Interconnected Grounding Systems IEEE Green Book Recommended Practice for Determining the Electrical Power Station Ground Potential Rise and Induced Voltage From a Power Fault Guide for the Design and Installation of Cable Systems in Substations Standard for Qualifying Permanent Connections Used in Substation Grounding Guide for Direct Lightning Stroke Shielding of Substation

3/0 4.0 OBJECTIVES The objectives for substation grounding are:. To maintain step potential and touch potential within safe values at all times for personnel working within and in the immediate vicinity of the substation. 2. To provide a safe means for dissipation of energy to earth in the event of surges and lightning strikes. 3. To ensure flow of sufficient current to earth during ground faults for protection devices to operate. 4. To provide stabilized ground reference potential for the facility electrical power system. These objectives shall be achieved by maintaining a low resistance connection to earth in all seasons and to limit ground potential rise (GPR) under fault conditions, for lightning strikes to the substation or to any conductor entering or leaving the substation and for any surge voltages on the system. The ground grid ground resistance shall be achieved by design and verified by measurement after installation to meet the OESC tolerable step and touch voltage levels. The ground grid resistance shall be achieved without use of building/structure foundation steel, cable sheaths or transmission line tower footings or sky wires. A lower resistance may be required to meet other design criteria. 5.0 GROUND GRID DESIGN CRITERIA The basis for achieving the design objectives will be dependent on the following site-specific information.. Soil resistivity 2. Maximum and minimum ground fault current 3. Fault clearing time 4. Body Weight of 50kg

4/0 5. SOIL RESISTIVITY Once the substation site has been identified, the soil resistivity at the location shall be established by measurement. The Wenner method as described in IEEE 8 shall be used. 5.2 GROUND FAULT CURRENTS This information will be available from Vale Power Department. The fault level at the location of the proposed substation or the fault level at 69 KV at the sending end substation will be made available. In case of the latter the fault levels at the substation being designed will have to be calculated. 5.3 FAULT CLEARING TIMES This information will be available from the protection co-ordination study for the subject substation. If it is not available then 0.5 sec time as per CEC or OESC shall be used. 6.0 GROUND GRID CALCULATIONS Once the soil resistivity readings have been obtained and the fault level calculations completed, the designer must decide on the size (minimum #4/0) and the spacing between grid conductors buried at 8 inches below a top layer of crushed stone as well as number and location of ground rods. Note: Ground rods are to be stainless steel on the Smelter complex property. 6. METHOD OF CALCULATIONS The preferred software package is AutoGrid Pro modeled as a two-layer horizontal soil, soil resistivity and fault current distribution. If any other software program is proposed for running the calculations then equivalence to the preferred software must be demonstrated. On approval from Vale the alternate software may be used. Longhand calculations performed by an experienced professional engineer are also acceptable. 6.2 CALCULATION RESULTS The report for the design calculations shall include the following data:

5/0. Input parameters (resistivity readings, fault levels and fault clearing times) 2. Safe touch and step potentials 3. The maximum step potential 4. The maximum touch potential 5. Temperature rise of grid conductors (this should be lower than maximum permitted for compression type fittings for copper conductors) 6. Touch and step potentials on the outside of the substation fence 7. Minimum number of rods and their locations 8. Graphs for touch and step potential generated by the software (not required in case of hand calculations) 9. The completed design shall be checked by calculation for safe touch and step potentials in winter conditions by incorporating a frozen top layer in the soil model 7.0 FINAL RESISTANCE READING After the completion of the ground grid installation the resistance of the grid shall be measured as per procedures given in IEEE 8. 8.0 OTHER DESIGN CONSIDERATIONS It is understood that there are many other factors that can have an influence on substation grounding; the following issues will be treated on a case-by-case basis as applicable.. Soil treatment & chemical rods 2. Seasonal variations in ground resistance values 3. Fence bonding 4. Corrosive soil 5. Equipment grounding & bonding

6/0 6. Grounding of reinforcing in concrete 7. Power cables and overhead lines in and out of substation 8. Communication/signaling cables in and out of substation 9. Remote ground grid 0. Lightning protection for substation 8. SOIL TREATMENT It may be a consideration to add soil treatment to the substation soil or to consider chemical rods as an alternative to achieve the desired grid resistance value. To consider soil treatment a search of professional literature on the subject shall be conducted to identify the most suitable treatment. Lifetime cost analysis shall be carried out in comparing the proposed treatment against chemical type rods. This procedure shall be carried out after approval by Vale. 8.2 SEASONAL VARIATIONS The design of the ground grid shall take into account the effects of soil freezing in winter season. 8.3 FENCE BONDING All fence bonding shall be as per CEC or OESC Section 36-32 and the reference drawings. The grid shall extend meter beyond the fence. If the gates in substation fence open outward then the grid shall be extended one meter beyond the maximum swing point of the gate at that location. If the control building is located within the substation fence and it has a basement cellar for cabling, mesh potential in the basement shall also be checked for personnel safety. 8.4 CORROSIVE SOIL The soil at the substation location shall be evaluated for corrosive properties. If it is determined to be detrimental to grounding material used then alternate materials shall be

7/0 proposed (i.e stainless steel ground rods) or cathodic protection shall be designed as a part of the grounding grid. 8.5 EQUIPMENT GROUNDING & BONDING All equipment grounding and bonding shall be as per CEC Section 36 and generally as per reference drawings indicated in this guide. 8.6 GROUNDING OF REINFORCING IN CONCRETE Concrete reinforcing steel may be used as a part of the grounding grid when approved by Vale. 8.7 POWER CABLES IN AND OUT OF SUBSTATION Power cables having shielding and armour shall have the shields and the armour grounded at both ends unless special requirements prevent this. For single core cables, if shields are grounded at one end only, it must be ensured that induced shield voltages do not exceed 25 V. See IEEE 525. 8.8 COMMUNICATION/SIGNALLING CABLES IN AND OUT OF SUBSTATION Communication and instrumentation cables are a particular concern. For shielding and grounding of instrumentation and control cables see IEEE Std. 050. In case of cables used for SCADA applications see IEEE Std. C37.-987. In addition the general rules set forth in standards should be tempered by manufacturer s recommendations. In general such cables will have their shields grounded at one point only in order to avoid noise signals due to circulating currents that may result from ground potential rise being different at different grounding points. 8.9 REMOTE GROUND GRID Remote ground grids are to be used only to resolve GPR (ground potential rise) design issues. Remote grids are not to be used to reduce step/touch. The practice of using remote ground grids is highly discouraged and shall only be considered as the last resort action in the event that computations considering all other measures (using foundation reinforcements, grid embedded in concrete or other treated soil, chemical rods etc.) to achieve the desired grid resistance fail.

8/0 When such grids are installed they should be tied together by a minimum of two # 4/0 AWG copper stranded conductors buried at a depth of 36 inches and installed generally as per Standard SPEC-53002. Usage of remote grounds introduces hazards of its own and additional safety measures like warning signs and barrier posts will be required. The route of the buried conductors should be marked with well-placed stakes. The remote grid must be clearly identified with warning signs (DANGER REMOTE GROUND). The location of remote ground and interconnecting conductors must be marked on As Built mark ups. 8.0 INTERFACE WITH LIGHTNING PROTECTION FOR SUBSTATION Lightning protection for substations is covered in a separate standard. Since the two issues are related it may be noted that lightning whips and arrestor leads are to be connected to dedicated ground rods by the shortest possible connection without any sharp bends. These rods shall then be bonded to the substation ground grid. 9.0 OTHER RECOMMENDATIONS 9. ROCK LAYER A layer of ¾ crushed high resistivity rock covering the substation area to a depth of 6 must be installed. The material must extend at least 2 meter beyond perimeter of fence as per Section 36 of the CEC or OESC. 9.2 TRANSFERRED VOLTAGES Transferred voltages are a concern that may be overlooked in many substation installations. A case in point is the connection of the plant security fence to the substation fence. Section 36 of the CEC or OESC clearly indicates that the two fences must be safely isolated. An acceptable solution is a 2.4m wood fence. Transferred voltages are also a problem as it relates to using portable tools fed from energized substation. This problem is to be reviewed for each and every substation.

9/0 0.0 DELIVERABLES Calculation report as per clause 6.2 Grounding Layout Drawings (Specification Drawing 99-999-H-004227 shall be used as a reference guide for preparation of ground grid layout drawing) Final Grid Resistance test value.0 APPENDICES Appendix A: Revision and Transition Notes Appendix B: Keywords

0/0 Appendix A: Revision and Transition Notes (Revisions are listed in reverse chronological order with most recent revision at the top. Revision notes describe: what was changed, why it was changed, and the plan to implement the change, including whether changes are retroactive) Note: The revision notes are a summary of the changes and may not necessarily be a complete list. Revision New format - Previous Standard number was 5322-0.0. Rev 4.