Smart Metering Implementation Programme

Similar documents
Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting

Smart Metering Implementation Programme. Consultation on New Smart Energy Code Content

Self Service Interface (SSI) Design Specification sections and 1.9.4; and Self Service Interface Code of Connection 1.14

Engage Consulting Briefing Note: Smart Metering Implementation Programme: Prospectus

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public

Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out

DCC OPERATIONS UPDATE

Risk Management Strategy. Version: V3.0

Initial Enrolment Project Feasibility Draft Report Consultation Document

CONSULTATION. SMKI and Repository Testing Approach Document. Consultation opens: 12 th March Consultation closes: 10 th April 2015

Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters

Regulatory Approach to Maintaining Local Security of Supply in Electricity

Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Implementation of 868MHz and Alternative HAN

Smart meters, regulation and market development

CER National Smart Metering Programme Policy Implementation Roadmap

Electric Ireland response to CER/15/272 Proposed Decisions on Empowering & Protecting Customers

Consumer ACCess to smart DAtA

Smart Metering Device Assurance Scheme Operator Services. Request for Proposal 10 th September VERSION: V1.2 Final September 2014

Gas Smart Change of Supply Read Project Report v doc. Gas Smart Change of Supply Read Project. Interim Report. Date: 9 th July 2014

DCC OPERATIONS UPDATE

A Guide to the Non-Domestic Gas and Electricity Retail Markets

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011

CER National Smart Metering Programme Status Update

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION

Connect and Manage Guidance March 2013

System Management Action. Flagging Methodology Statement. Version Date: [05 th November 2009]

CUSC Amendment Proposal Form CAP: 162

DCC Draft Development Priorities to

CP1464 Requiring HH consumption data to be processed to appropriate precision

EAI Response to CER National Smart Metering Programme, Presentation of Energy Usage Information (CSI) and Pay As You Go consultation papers

INTRODUCTION. SSE Airtricity welcomes the opportunity to comment on the CER s paper National Smart Metering Programme - Smart Pay As You Go.

In the matter of Gambling (Gambling Harm Reduction) Amendment Bill

In responding to the consultation, we would like to draw your attention to the following points:

Framework for the Provision of Smart Metering Support

Meter Technical Details for Smart Meters (CP1388) Education Session. Adam Lattimore 20 June 2013

Smart DCC Ltd. Licence Application Business Plan. Version: Final Redacted. Date: Licence Application Business Plan Final Redacted.

BSG response to DCMS/BDUK Urban Broadband Fund. Consultation on Connection Vouchers. July Overview of response

DRAFT FOR COMMENT. Comments should be sent to by * September 2005 PROPOSED AMENDMENT REPORT

DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES. Article 1. Subject matter

Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation

This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching directive.

Level 5 NVQ Diploma in Management and Leadership Complete

P302 Improving the Change of Supplier Meter read process for smart Meters

Review of Analysis of Network Benefits from Smart Meter Message Flows

De-Energisation Code of Practice

Charge controls for Wholesale Line Rental implementation and cost orientation

QSS 0 Products and Services without Bespoke Contracts.

European Commission s proposal for a revised Electricity Directive

Business Principles. For. Invoicing. Xoserve Project Nexus

MARKET OPENING PROGRAMME

UNC 0630R: Review of the consequential changes required in UNC as a result of the Ofgem Switching Programme. UNC Request Workgroup Report

02/03/17 Appendix A Reqts Traceability Matrix v3.0 DCC Public. requirements.

Joint Office of Gas Transporters 0212: Revision of the Rough Storage Connection Agreement

System Management Action Flagging Methodology Statement

Disaster Waste Management Principles

System Management Action Flagging Methodology Statement

Trade Effluent. 19 th October 2017

New TCP Code frequently asked questions

Part 2 Business Transformation and Delivery. Price Control 2017/18 Submission

Management, Development, Selling and Maintenance of SPT Advertising Space

Market studies. Guidance on the OFT approach

IGT103: Inclusion of reference within IGT UNC to UNC TPD Section G paragraph inclusive - Meter Point Portfolio Reconciliation

CER National Smart Metering Programme Rolling out New Services: Time-of-Use Tariffs

Update on the Smart Meter Upgrade

PAB197/07 ATTACHMENT A - SMART RISK EVALUATION

Summary: Intervention and Options

Guide - Alternative Procurement - Unsolicited Proposals

DEFINITIONS Glossary of Terms Section A The Code of Practice SCOPE OF THE CODE In Scope...

UNC 0658 (Urgent): CDSP to identify and develop improvements to LDZ settlement processes. UNC Modification

MCE Decision paper. 13 December A National Minimum Functionality for Smart Meters

Revisions to the internal DCC Business Case for the Switching Programme up to May 2019 Switching Programme - Smart DCC

Response to: CER/15/284 - Review of Connection and Grid Access Policy: Initial Thinking & Proposed Transitional Arrangements

The Procedure for Agreement of Change of Supplier Readings and Resolution of Disputed Change of Supplier Readings

Field/Mobile Working Policy

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

Drinking-water Assistance Programme

Blue Telecom is compliant with the Telecommunications Consumer Protection Code (C628:2012), which applies if you meet one of the criteria below.

Solution Terms for Secure Mobility (formerly known as Secure Mobility from Orange)

COMMISSION STAFF WORKING PAPER

System Management Principles Statement. UK Transmission. Effective from 1 April 2017

Charging Statement for Service Charges. Regulatory Year ending 31 March 2019

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem

Indicative Charging Statement. Regulatory Year ending 31 March 2020

Change Proposal Circular: CPC00707: Impact Assessment of CP1366

Technical Assurance of Performance Assurance Parties

Aconite Smart Solutions

DECC CONSULTATION RESPONSE: RO Grace periods consultation

Stronger Together An Organisational Response to One Swindon

All Network operators and providers involved in the provision of premium rate services (PRS) to consumers.

Gas Engineering Recommendation GER2 Issue A GUIDE FOR INDUSTRY PARTIES REGARDING BUSINESS AS USUAL (BAU) ISSUES RELATING TO SMART METERS

Market-wide Half-Hourly Settlement

Re: Modification Proposals 0116V/0116VD/0116A/0116BV/0116CV: Reform of the NTS Offtake Arrangements

The Information Commissioner s response to the Competition and Market Authority s Energy market investigation: notice of possible remedies paper.

A new broadband Universal Service Obligation: Consultation on Design

BT Response A review of consumer complaints procedures - Ofcom consultation

CER National Smart Metering Programme Steady State Model BGN Response to CER/13/151 Consultation

DEFINITIONS Glossary of Terms SCOPE OF THE CODE In Scope Not in Scope Third Parties...

The rule change proposals and associated descriptions of the proposed rules are attached for your consideration.

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note

Transcription:

Smart Metering Implementation Programme Consultation on Smart Metering Rollout Strategy DCC response 19 th May 2015 DCC PUBLIC Page 1 of 14

1 Executive Summary 1.1 Introduction and background 1. DCC provides the shared smart metering communications infrastructure that will allow energy suppliers, network operators and other authorised users to communicate with smart meters. The smart meter communication service will enable consumers to manage their energy usage with near to real-time information of their energy consumption. Consumers will benefit from energy savings and reduced emissions as a result of more accurate information, bringing an end to estimated billing. 2. Energy suppliers are responsible for rolling out smart meters in line with their rollout obligations, with Government s role being to provide the right framework and milestones against which they can plan. 1.2 Consultation on Smart Metering Rollout Strategy 3. On 24 th March 2015, DECC 1 published a consultation on the Smart Metering Rollout Strategy. It consults on key regulatory proposals to inform investment decisions made by energy suppliers and network operators for the main smart meter installation stage. The document consults on the following areas: Introducing a de minimis SMETS2 meter 2 installation and enrolment obligation on Large Supplier Parties 3 and mandating energy suppliers and network operators to become DCC Users within specified timescales Switching on the New and Replacement Obligation in mid-2018 to ensure all new and replacement meters are smart Setting a SMETS1 meter 4 end date 12 months after DCC Live and seeking views on a cap Install and leave provisions to ensure an efficient rollout and optimise the consumer installation experience. In addition, the strategy also announces the commencement of the Initial Enrolment Project for SMETS1 meters. 1 DECC Department of Energy and Climate Change 2 SMETS2 meter means an energy meter that is compliant with Smart Metering Equipment Technical Specification Version 2. 3 Large Supplier Parties are defined as parties that supply electricity and/or gas to 250,000 or more domestic premises. 4 SMETS1 meter means an energy meter that is compliant with the Smart Metering Equipment Technical Specification Version 1. DCC PUBLIC Page 2 of 14

1.3 DCC Live 4. DCC understands that, in the context of this consultation document, DCC Live means August 2016. DCC s response is based on this assumption. This assumption is based on DECC s statement at the TBDG 5 meeting held on 22 nd April 2015. At this meeting, DECC stated that the term DCC Live used in the Smart Metering Rollout Strategy consultation refers to the planning assumption date of August 2016 and not the April 2015 date in the Joint Industry Plan (JIP). 5. DCC suggests that the definition of DCC Live should be made as clear as possible. In particular, DCC considers that clarity on the obligations on Parties if DCC were to achieve DCC Live on different dates in the different CSP 6 Regions would be helpful to Users. 1.4 DCC s response 6. DCC broadly agrees with the proposals set out in the consultation, subject to specific areas for further consideration which we set out in the main body of this response. 7. If you have any questions regarding any part of this response please contact Ekta Sareen at ekta.sareen@smartdcc.co.uk. 5 TBDG Technical and Business Delivery Group 6 CSP Communications Service Provider DCC PUBLIC Page 3 of 14

2 Driving SMETS2 installations Q1 A1 Do you agree with the minded to position to set a de-minimis obligation for all large suppliers to install, commission and enrol 1,500 SMETS 2 meters or 0.025% of total meter points (whichever is the lower) within six months of DCC Live? Please explain your rationale and provide evidence. DCC broadly agrees with the government proposal to set a de minimis obligation on all Large Supplier Parties to install, commission and enrol SMETS2 meters to enable an effective rollout strategy. DCC would, however, like to make the following observations. DCC will provide an End-to-End Test environment against which Device and User System Tests can be undertaken by energy suppliers, and other persons with a valid requirement to participate in testing. Device Testing can be undertaken in a CSP Test Labs 7 or by establishing a remote testing service and these will be provided in advance of DCC Live. DCC agrees that the consumer benefits of smart metering should be realised as soon as possible and agrees that early rollout of meters would support this objective. DCC is, however, concerned that if DECC were to implement this proposal, there is a high chance that DCC would be required to support a high volume of Device Testing at the same time as providing capacity in the CSP Test Labs for Parties to conduct User Entry Process Tests. This is because DCC considers that there is a high likelihood that meter manufacturers would decide to come forward earlier to test a variety of devices, which would bring forward Device Testing for Large Supplier Parties. This decision may be as a result of energy suppliers amending their rollout strategies in response to this consultation. This may represent an increase in the volume of testing activity against the most recent rollout forecasts. If the capacity of the CSP Test Labs is exceeded, DCC will give priority to Parties conducting User Entry Process Tests. This may constrain the ability of energy suppliers to install smart meters immediately after DCC Live unless a remote test service is obtained from DCC. DCC has considered some options for increasing the capacity of the Testing Service in order to support the Government s proposal. This will require DCC to: Establish additional CSP Test Labs (which will require the leasing of additional premises); Provide additional HP ALM (defect management tool) licences; Increase the size of the issue management capacity with DCC and our 7 Test Lab - means a location used for Testing (which may include testing of Communications Hubs) as further described in paragraph 7 of Part C of Schedule 6.2 of the service provider contracts. DCC PUBLIC Page 4 of 14

External Service Providers; and Increase the size of DCC s industry test service support team. It has not been possible for DCC to estimate the value of this impact since it is unclear as to how many concurrent tests participants there would be. These changes will have a cost impact. In addition, a minimum of six months lead time will be required to establish additional CSP Test Lab capacity and to increase the size of the DCC test support service. A clear indication from DECC to increase the capacity of the service is therefore required no later than the end of June 2015, if the expanded service is required from the start of the End-to-End Test stage. Whilst there is no direct impact on DCC, DCC considers that the market would benefit from clarification on the date upon which an energy supplier is considered to be either a Large or Small Supplier Party 8 for the purposes of this obligation, and the mechanism for notification of an energy supplier s status. 8 Small Supplier Party - means a Supplier Party which, at the time at which it is necessary to assess the status of the Party, supplies electricity and/or gas to fewer than 250,000 (two hundred and fifty thousand) Domestic Premises. DCC PUBLIC Page 5 of 14

3 Mandating parties to become DCC Users Q2 Do you agree that given the importance of consumers continuing to receive smart metering benefits upon change of supplier, all suppliers should be Users at DCC Live plus 12 months? Please provide evidence to support your position. A2 DCC agrees that energy suppliers should become Users as soon as reasonably practical after DCC Live in order to maximise smart metering benefits for consumers and to minimise reliance on the Non-Gateway Interface. However, placing a requirement on all energy suppliers to complete testing within 12 months of DCC Live is likely to: a) increase the volume of concurrent entry process tests that will be conducted during the Interface Testing stage and shortly thereafter; and b) increase the volume of Device and User System testing that is undertaken at the start of the End-to-End Test Stage and shortly after DCC Live. This will increase the level of testing support that is required from DCC and the demand for space within the CSP Test Lab. Section H14.4 of the Smart Energy Code places a requirement on DCC to allow persons that are eligible to undertake tests defined in Section H14.1 (which include User Entry Process Tests, SMKI and Repository Entry Process Tests and Device and User System Tests) to undertake those tests concurrently, or to schedule those tests in a non-discriminatory manner. DCC is mindful of its General Objectives under its Licence 9 to achieve efficient and economical transition, completion of implementation and enduring provision of Mandatory Business Services. DCC is establishing a CSP Test Labs service based on assumptions (consulted upon as part of the Interface Testing Approach Document in October 2014), rather than providing an expensive unlimited capacity testing service. DCC assumed that 5 Small Supplier Parties would be conducting testing concurrently with the Large Supplier Parties. These assumptions will no longer be valid if Small Supplier Parties are required to use the Testing Services (Section H14.1 of the SEC) at the same time as the Large Supplier Parties. DCC may therefore be required to: schedule User Entry Process Tests and SMKI and Repository Entry Process Tests in preference to Device and User System Testing. This could constrain the ability of the SMDA Scheme Operator to undertake Device Testing on behalf of energy suppliers; and/or schedule the User Entry Process Tests that are undertaken by Large 9 Smart Meter Communication Licence, available here: https://www.ofgem.gov.uk/licences-codes-andstandards/licences/licence-conditions DCC PUBLIC Page 6 of 14

Supplier Parties in preference to those of other categories of test participants during the Interface Test Stage (on the basis that only Large Supplier Parties are currently obliged to be ready to commence User Entry Process Tests at the start of the Interface Test Stage, SEC T3.20). Placing a requirement on all energy suppliers to be DCC Users within 12 months of DCC Live may therefore impact the ability of some energy suppliers (or their representatives) to conduct Device and User Systems Tests, which would delay the rollout of smart meters and the realisation of consumer benefits. DCC is aware that some Small Supplier Parties may choose to use a shared service provider, which will reduce the number of direct test participants with whom the DCC is required to interact. However, the costs of the shared service may be prohibitive to some Small Supplier Parties. DCC is concerned that the Government s proposal may commercially disadvantage these organisations if they are unable to mobilise their own resources within the proposed timescales required to meet a mandate and are required to take a shared service. Due to the lead times associated with the establishment of additional capacity within the CSP Test Labs and the increase in DCC resource capability, DCC would need to plan on the basis that energy suppliers would test directly against the DCC, unless they were able to confirm that they had established (or have a firm intention to establish) a commercial arrangement with a shared service provider. DCC would like to highlight that the shared service providers would be required to complete testing against the DCC before they would be able to provide a service to energy suppliers. This testing could not be undertaken until the start of the Interface Testing stage. Furthermore, DCC would be required to determine whether it would be acceptable for those energy suppliers to place reliance on the results of User Entry Process Testing and SMKI and Repository Entry Process Testing (SEC H14.29 and SEC H14.20) that had previously been executed. It is possible that some Small Supplier Parties may still be required to execute some tests, even if they had procured a service from a shared service provider. DCC has discussed the options it has considered to increase capacity of the Testing Service capacity, in the response to question 1 above. Q3 A3 Q4 A4 Do you agree that given the importance of consumers continuing to receive smart metering benefits upon change of supplier, all suppliers should be Users at DCC Live plus 12 months? Please provide evidence to support your position. Please see DCC s response to question 2 above. Do you agree that electricity DNOs should be mandated to be DCC Users from DCC Live? Please provide evidence to support your position. DCC agrees with the principle that DNOs should be Users soon after DCC Live, but not from DCC Live. Clause T3.21 of the SEC enables the Secretary of State to require Network Parties to use reasonable endeavours to commence the User Entry Process Tests as soon as reasonably practicable during the Interface Testing stage. Following such direction, DCC would be unable to complete Interface Testing within a DCC PUBLIC Page 7 of 14

Region until at least two Large Supplier Parties (per fuel type and at least one Network Party in respect of the Electricity Distributor User Role and at least one Network Party in respect of the Gas Transporter role) have completed User Entry Process Testing. DCC requests clarity from DECC on the following questions: Does DECC intend to use its powers under clause T3.21 to mandate the electricity DNOs become Users from DCC Live? If, following that action, would clause T3.27 be invoked in respect of electricity DNOs? The latest DCC Plan (as approved by the Secretary of State on 5 th March 2015) is based on the shared assumption that Network Parties would not be mandated to conduct User Entry Process Testing during the Interface Testing Stage. Changes to this assumption may impact the ability of DCC to complete Interface Testing in accordance with the timescales set out in the latest DCC Plan, with a consequential impact on the DCC Live date. DCC does not consider that electricity DNOs should be required to become DCC Users from DCC Live in order for consumers to realise the benefits of smart metering. However all Network Parties will need to complete the SMKI RAPP prior to DCC Live. As with our response to questions 1 and 2 above, this proposal would also place significant pressure on testing services. DCC has discussed the options it has considered to increase capacity of the Testing Service capacity, in the response to question 1. Q5 A5 Q6 A6 Q7 Would a direction from the Secretary of State, focused on electricity DNOs only, to be ready for Interface Testing provide additional impetus to be ready for DCC Live? Please see DCC s response to question 4 (above). Please provide views on whether idnos should be mandated to become DCC Users from DCC Live plus 12 months. Please provide evidence to support your position. DCC has no strong view on the proposal to mandate idnos to become DCC Users within a defined period from DCC Live. However, if the government proceeds with this proposal, DCC wishes to make the following observations: as discussed in response to questions 1 and 4 above, DCC considers that this obligation may place constraints on DCC resources as result of additional cost and timing implications; and DCC would suggest that the deadline for idnos is not the same as the deadline for Small Supplier Parties (as suggested in the consultation) and that Small Supplier Parties should be prioritised over idnos to avoid unnecessary peaks in activity. Do you agree with the position not to mandate GTs and igts to become Users at the present time? Please provide evidence to support your position. DCC PUBLIC Page 8 of 14

A7 Q8 A8 DCC has no strong view on the proposal not to mandate GTs and igts to become Users. If, however, this was to be mandated, DCC would suggest that: it is clear that an end-date must be provided for using the SMKI Portal via the internet since all Users would have access to a DCC Gateway Connection; and any such obligation should be staggered from the dates provided to other party groups above and that if this was to be mandated before the end of rollout Large Supplier Parties, DNOs, Small Supplier Parties and idnos should be prioritised over GTs and igts to avoid unnecessary peaks in activity. Are there benefits that could be driven by imposing a DCC Mandate for GTs and igts before the end of rollout? Please provide evidence to support your position. DCC considers that prospective Users are best placed to comment on this question. DCC does, however, suggest that any such obligation should be staggered from the dates provided to other party groups above to avoid unnecessary peaks in activity. DCC PUBLIC Page 9 of 14

4 Delivering consumer benefits in an efficient rollout - Install and Leave Q9 A9 Do you agree that Install and Leave should be permitted where expected WAN coverage is not available; but only in cases where HAN is established? Please explain your rationale. DCC agrees with the principle of maximising the consumer experience at installation. However, DCC has concerns about the proposal that Install and Leave should be permitted where expected SM WAN 10 coverage is not available, but only where a HAN 11 is established. DCC considers that, in circumstances where a HAN is not established, it would be beneficial to consumers for energy suppliers to leave a SMETS2 compliant meter and the Communications Hub that is powered on, in the premises. This approach would allow CSPs to take action, remotely, to resolve coverage issues and confirm that SM WAN connectivity has been established ahead of any commissioning. DCC considers that this approach would be beneficial to consumers, as it is more likely to result in successful commissioning as issues can be resolved prior to the visit to the consumer s premises. Whether the HAN is established or not is mainly relevant to the provision of smart benefits such as a working in-home display (IHD). Recognising that it is highly beneficial to have a working IHD, DCC considers that it would be counter-intuitive to require energy suppliers to terminate an installation if they fail to establish a HAN, which would then require de-installation of a SMETS2 compliant meter and re-installation of either the original meter or a non- SMETS2 dumb replacement. The consultation document implies that a functioning HAN is required for an installation to be classed as an Install and Leave. However, the status of attempted or partial installations that do not meet this requirement is less clear. DCC notes that to establish a working HAN, energy suppliers require either SM WAN connectivity at the premises or a hand held terminal that is capable of sending pre-signed Service Requests to update the Communications Hub Device Log. There are likely to be a high number of attempted installations within the Coverage Area where these requirements are not met. It should be noted that, within the DCC Coverage Area, first-time (installation) SM WAN connectivity performance measures committed to by the CSPs are 90% for Central and South Regions and 80% in the North Region. CSPs have a commitment to resolve coverage incidents at installation within a defined period of time (90 days, where installation is within the DCC Coverage Area). 10 SM WAN Smart Metering Wide Area Network 11 HAN Home Area Network DCC PUBLIC Page 10 of 14

Under the proposal, (in relation to the Central and South Regions and where mesh is to be used as the SM WAN technology) DCC would like to highlight that, if an Install and Leave is terminated because the HAN cannot be established, resulting in the Communications Hub not being left in the premises, this would mean that it would not be possible to reliably install boundary mesh. Similarly, if the installation is terminated because the SM WAN is not available, the same would apply. Both of which could put Central and Southern region coverage commitments at risk. Q10 A10 Q11 A11 Do you think there are grounds for the Government enabling proactive Install and Leave and would your organisation use it as part of their rollout strategy? Please explain how you would mitigate the potential challenges to consumer experience. DCC considers that energy suppliers are best placed to respond to this question, however DCC wishes to make the following observations. DCC does not consider that proactive Install and Leave would necessarily damage the consumer experience. Whilst precluding proactive Install and Leave would result in consumers failing to receive the full benefit of smart meters early on, it could actually enhance the consumer experience if energy suppliers effectively manage consumer expectations by fully explaining the reasons for a two stage installation. It is important to consider the interaction of any Install and Leave obligations with SMICOP, and the extent to which this type of installation might achieve the energy supplier targets for 2020. Energy suppliers could conduct proactive installs of smart ready equipment (i.e. a SMETS2 ESME 12 and Communications Hub) without necessarily attempting to establish or commission a working HAN (i.e. replacing a dumb meter with smart meter and Communications Hub operating in dumb mode). This approach could ultimately improve the consumer experience as DCC would be able to confirm SM WAN connectivity prior to any revisit thus greatly improving the chances of subsequently enabling smart meter communications services. In this scenario the possibility of failure to complete commissioning on a revisit due to lack of SM WAN coverage (where SM WAN coverage had been expected) would be reduced from 10-20% to near zero. Do you agree that the Government s minded to position on Install and Leave should apply to both SMETS1 and SMETS2 installations? Please provide views on specific issues you think the Government would need to consider in implementing this provisional policy position; and in particular whether there is a suitable period of time during which we would expect WAN coverage to become available, where this has not been available on installation. DCC considers that energy suppliers are best placed to respond to this question, however DCC wishes to make the following observations. 12 ESME Electricity Smart Metering Equipment DCC PUBLIC Page 11 of 14

DCC considers that Install and Leave should be permitted for SMETS2 installations as DCC (through the CSP contracts) provides contractually committed levels of coverage to the meter point and a commitment to resolve coverage incidents at installation within a defined period of time (90 days, where installation is within the DCC Coverage Area). DCC notes that if SMETS1 communications contracts for SM WAN coverage do not provide similar commitments to those included in the Foundation CSP contracts for installation coverage incident resolution, the effectiveness of an Install and Leave approach would be uncertain. Without a commitment in the relevant contracts, it seems likely that if SM WAN coverage is unavailable for SMETS1 installations, then it is unlikely that the relevant Foundation CSP would resolve this within an acceptable period of time. Q12 A12 Do you agree that the Government does not need to regulate to exclude operation of SMETS meters in PPM mode from the scope of its minded to policy position on Install and Leave? Please explain your company s strategy for handling PPM where the WAN is not available at the point of installation. Energy suppliers are best placed to comment on their strategy for handling PPM where the SM WAN is not available at the point of installation. DCC would, however, like to highlight that where there is no SM WAN, DCC would be unable to support SMETS meters in PPM mode as DCC would be unable to communicate with these meters. Energy suppliers, however, would be able to communicate with them via locally delivered commands. Those commands originate in DCC but are transferred to the meters using hand held terminals. Energy suppliers would need to determine whether to use hand held terminals to communicate with SMETS meters in PPM mode or whether to use a different approach. The hand held terminal approach would be business as usual for DCC. DCC would be keen to understand any conclusions drawn following this consultation. In particular, DCC is keen to understand how viable and practically SMETS meters in PPM mode can be adopted into the wider DCC service. DCC PUBLIC Page 12 of 14

5 The New and Replacement Obligation Q13 A13 Do you agree with the proposal to enact the New and Replacement Obligation in mid-2018? DCC has no comment to make in response to this question, as it considers that prospective users are best placed to comment on the timing of the enactment of the New and Replacement Obligation. DCC PUBLIC Page 13 of 14

6 Managing SMETS1 Installations Q14 A14 Q15 A15 Do you agree with the proposal to set a SMETS1 end date of DCC Live plus 12 months? Please provide evidence for your answer. DCC considers that energy suppliers are best placed to respond to this question. DCC would, however, like to make the following observations: DCC understands that, in the context of this consultation document, DCC Live means August 2016. Our response is based on this assumption DCC suggests that the definition of DCC Live should be made as clear as possible. In particular, DCC considers that clarity on requirements if DCC were to achieve DCC Live on different dates in the different CSP Regions would be helpful to Users DCC recognises that the conclusion to this consultation question may impact the scope of DCC s Initial Enrolment Project Feasibility Report There is a link between this and the timing of DCC s enrolment projects. What are the advantages and disadvantages of a SMETS1 cap on individual suppliers both in combination with an End Date and as the sole means that SMETS1 meter installations are regulated? How could such regulation best be designed? Please provide evidence for your answer. DCC considers that energy suppliers are best placed to respond to this question. DCC does, however, consider that a cap would increase the number of consumers benefitting from SMETS2 meters. DCC recognises that the conclusion to this consultation question will influence the scope of the DCC s Initial Enrolment Project Feasibility Report. DCC PUBLIC Page 14 of 14