Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Similar documents
StormPod Arch Installation Guide

ENGINEERED SOLUTIONS. Precast Bridge Installation Guide

T-WALL Retaining Wall System

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution...

Site Preparation... 2

Reinforced Earth wall Construction Manual

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

CONSTRUCTION MANUAL 2.5 x 5 UNITS

Uwall UNIVERSAL CONSTRUCTION MANUAL

SECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following:

STORMCAPTURE. Installation Manual

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

Strengthened Soil Wall Construction Manual

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting.

Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219.

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

American Concrete Pipe Association. Precast Box Culvert Installation Procedures

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR:

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

Premier Railroad Grade Crossing Installtion Guide PREMIER RAILROAD GRADE CROSSING INSTALLTION GUIDE GUIDE GROUNDED IN STRENGTH

INSTALLATION GUIDELINE POLES USED FOR SUPPORTING ANTENNAS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS

This drawing. is preliminary. and not for. construction or. implementation. purposes. project number 170 END VIEW DESIGN STRENGTHS: PLAN

CONSTRUCTION MANUAL 5-0 x 7-6 UNITS

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

Retaining Wall Systems

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures

Instructions for 12 and 15 IGT systems (12 pictured)

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

ITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.

VOLUME 2 TECHNICAL SPECIFICATIONS BID NO PROJECT MANUAL FOR BONDS RANCH ROAD WIDENING PROJECT BIDS DUE JULY 9, :00 P.M.

SECTION STORM SEWER COLLECTION SYSTEM

Nutrient Separating Baffle Box

SECTION CHAIN LINK FENCES AND GATES (PARK)

Instructions for 12 IGT system

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 9/17/18)

ROOF MOUNT KIT OWNERS MANUAL

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

SECTION 1208 CHAIN LINK FENCING DESCRIPTION

PaveDrain Installation Manual. Table of Contents. Hand-Placement of individual PaveDrain Units. PaveDrain End Cap

TABLE OF CONTENTS. 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers


ROOF MOUNT KIT OWNERS MANUAL

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section

Redi Rock Specification and Installation Manual

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

Design & Detail Installation Manual. LongSpan Bridge and Culvert Construction System

Installation Guidelines for Vault Systems (NSBB, Kraken, Water Polisher, & Other)

DETENTION, RETENTION AND RECHARGE STRUCTURES

Installation Guidelines

LANDSCAPE RETAINING WALLS

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION

SPECIFICATION FOR REINFORCED SOIL WALL

MODULO GEOBENT Installation Guidelines

T-WALL.

SECTION STORM DRAINAGE

StormTech Construction Guide

BEBO CONCRETE ARCHES TECHNICAL GUIDE

ARMTEC.COM. Bridge Materials / Versatile Low Maintenance Rapid Installation

50.20 Drainage Structure Design

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

SECTION CONCRETE FORMWORK

For additional procedures specific to slip base bolt set installation, see separate GESS LTD DOCUMENT NO. GVTG-002

TYPICAL INSTALLATION INSTRUCTIONS

Installation Manual. Foundations. Version 2

Reinforced Soil Slopes (RSS)

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Casino Modular Railing System

1.02 RELATED WORK: Refer to the following sections for related work:

SECTION 1 TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE, AND SYMBOLS 1-3 ABBREVIATIONS Common Usage.

ODOT Design & Construction Requirements for MSE Walls

Section 401. PIPE CULVERTS

STANDARD SPECIFICATIONS SECTION 16 STORM SEWER SYSTEMS

The Aizhai Suspension Bridge is

VERSA-Green TM Plantable Retaining Wall System

Installation and Maintenance Manual for EMH Freestanding Workstation Jib Cranes

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES

Important: Before You Start

Construction Procedures

A. This Section includes subdrainage systems for foundations and underslab areas. A. Product Data: For each type of drainage panel indicated.

SECTION PIPE INSTALLATION

Bordeaux Walling. Product & Technical Information

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS

Multi-Gard PVC Assembly/ Field Cuts

CHAPTER 12 HANDHOLES, PULLING VAULTS, AND JUNCTION BOXES

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

INSTALLATION GUIDE. 4-Post Lift. Model United States. United Arab Emirates. Egypt.

SECTION 10 - TRENCHING AND BACKFILLING

Transcription:

ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

Safety All standard safety precautions and best practices should be followed and be a primary concern. Always check rigging connections, tag lines and rigging devices thoroughly before lifting units. Always start each day with a safety briefing. Tools: Two 60 pry bars 48 spirit level Transit Level Long straight 2 x4 Two 8 foot step ladders One 16 foot extension lader Chalk line or spray paint Large crescent or box end wrenches Foundation and Footings Two come-alongs for use with 2-piece bolt-on headwalls and wingwalls Proper rigging and lifting eyes Materials Checklist: Installation drawings Shims (5 x5 x1/4 and 1/8 masonite shims) Joint wrap material Connection plates, washers, threaded rods and nuts for connections A properly planned and prepared foundation is needed to ensure a successful installation. Following standard construction procedures and safety precautions is an important precondition for a successful ArchCast Bridge installation. Additional steps for setting the foundation include: Grades and elevations must be set according to the approved project drawings. Forms must be constructed in a rigid manner to eliminate movement during placement. Maintain a tolerance of no more than 1/4 every 10 feet. Concrete must have a minimum compressive strength of 75% of the 28-day design strength before placing bridge units. Ensure subgrade preparation is in accordance with project specifications and available geotechnical reports for the project. Deviations in the top surface of footings will make it difficult to set units. For culvert footings constructed on a slope, the same slope shall be carried to the ends of the wingwall footings. Follow proper anchor clearance. The footing top should have a floated surface finish and must not vary more than 1/4 in 10 feet. The horizontal alignment of the keyway is critical to set units properly. If precast wingwalls are utilized, the back of the wingwall footing must be formed with a uniform surface to avoid using sawing and jackhammering. Wingwall footings must be cleared of dirt and large concrete burrs. Make sure the area behind the precast wingwalls are adequately excavated to allow clear placement of the wingwalls and anchors to be placed. In all cases follow project plans regarding dimensions and placement. Mistakes will lead to delayed installation and lost time and money. Site Readiness Verify any local traffic restrictions prior to delivery of units to your site. 2 Ensure your site is ready for a problem-free delivery. Prior to delivery communicate with your County Materials representative and take into consideration delivery accessibility. In advance, make sure the site is accessible, open, dry and compacted. Trucks must be able to pull in and out under their own power. Ensure there is a route and proper access for delivery trucks, including a convenient turn around area to allow trucks to back in. Plan for unloading space next to the crane. Before delivery, verify local restrictions on wide loads or of temporary lane closures that may be necessary. Contractors are responsible for flagmen and traffic control. Expect rutting on non-paved surfaces. Have proper maintenance on hand to repair and level surface between deliveries. Keep in contact with your County Materials representative with any delays and confirm your schedule before delivery. It is not recommended to erect units in the rain.

Crane Selection Be sure the crane you choose is rated to handle the job. Proper crane selection and site preparation are vital the in ArchCast Bridge installation. Several conditions should be prepared before hand: Have a representative from the crane company visit the construction site to determine proper sizing and stabilizing of site. Locate the crane as close to the foundation as possible. ArchCast Bridge unit weights will be provided by County Materials and should be used in considering crane size. Note that the end unit is usually the heaviest and has the longest reach. Before crane operation begins survey the site for tree branches, overhead power lines, underground utilities and other obstacles. De-water the site to a level below the top of the footing to ensure safety and speed installation. Have at least 4 people on site for the installation. Before Installation For maximum safety and efficiency be prepared before delivery. Always follow standard construction safety best practices. Have at least four people on site. More may be required depending on each install. If the crane supplier does not provide a signaler, designate one person to signal. This person is in addition to the four-person minimum. Clean the foundation of any debris, mud or water. Choose a starting point. When the foundations are sloping start at the lowest elevation. Handling Precast Units Tipping bridge units upright with rolling blocks. Units delivered on a truck bed. Units being staged on the ground prior to installation. Bridge Units: Bridge units are typically shipped on their sides and require planning before shipping the units. These units will be lifted off the truck and set onto the ground on their sides. If using a single line crane, lift the unit off of the truck straight up, then place on the ground. Use the top four lift points to rotate the unit upright. It is helpful to rotate the unit to vertical with a pair of rolling blocks or equalizing slings. To prevent spalling of the legs, a bed of soft sand/soil material should be provided in the tipping area. Using a double drum crane will allow for rotating the unit upright without setting the unit down. Units will have four lift inserts in the side and four in the top. Use four cables no less than 20 feet long (for spans under 24 feet) and cables 30 feet long (for unit spans between 28-42 feet). Coordinate cables with the ArchCast and crane suppliers. Units delivered upright may be lifted off the trucks and set directly in place. Precast Wingwalls: Wingwalls are typically delivered lying flat on the truck and set onto the ground lying flat using all four lift points. Rotate wingwall units by using only the top two lift points. Wingwalls are then set in place. Be prepared for units being unbalanced and not hanging in a straight vertical position during installation.* Detached Headwalls: Detached headwalls are delivered with their outside face down. They will be set on the ground using three lift points. Rotate headwalls upright using the top two lift points and lift unit into place. * Since lifting inserts for headwalls and wingwalls cannot be located at the center of gravity, a come-along is recommended to be used in the rigging to plumb and level the units. 3

First unit being set. Shim pads are used to control elevation. Setting ArchCast Bridge Units Follow these guidelines for setting the bridge units Allow for ½ joint between units. Once you have laid out the total length on one footing, starting at one end turn 90 degrees to the opposite footing and lay out the starting point. Follow the same procedure at opposite end of footing and chalk a reference line to the outside of the units. Layout the center line of each joint. Set shims one foot in from the corner of each unit. Use the high point if applicable as the control elevation. Add one inch to this elevation and set all shim pads to this elevation. If installing units on a sloping grade, shoot elevation control points at approximately 50 feet increments and run a sting line between these elevations to set other shims. Projects typically start by setting an end unit with or without an attached headwall. The alignment of this first unit is critical and determines the alignment of all remaining units. At each starting line, secure a 2 x4 to the top of the footing. This will act as a stop for each unit and help with alignment. Stay out from underneath the unit until it is supported on the footing. One person should be ready with a spud bar at each side to help position units as the crane lowers them into place. Leaning the top of units away from the previous set unit before setting in place will create better joints and save time. Spud the unit up against the 2x4 blocks and check for alignment with the chalked line. Then check the vertical alignment. Adjustments can be made with shims to achieve the required front face alignment. Never use hands under a unit to adjust shims. Always use a stick or tool to reach under units. Tip units slightly for easier fit. When setting successive units the joints should be 1/8 to ¾. Place a shim in the tightest area to maintain this opening. Match a rough face with a smooth face. Properly adjust the lifting cable lengths so cables on the far side of the adjacent unit are longer than the near side cables. Units with spans more than 24 feet will be shipped and installed with a horizontal cable tie between the legs, normally located 2 feet above the bottom of the leg. This cable cannot be removed until after grouting has been completed and achieved the required strength. On end units, it is also recommended that the legs be blocked solid to the keyway before setting headwall units. 2 x4 s and chalked line are used for alignment. 4 Second unit is lowered into place. Last unit is set, before setting the headwalls and wingwalls.

Setting the Headwalls Before setting the headwall units, bolt up the tie plates to the top of the arch units. The top and bottom of the headwall must be cleaned before setting into place. Each headwall piece should be marked for a specific location on the bridge to match casting of the headwall units. The front face of the headwall should be placed flush against the front-end bridge unit. A spud bar may be necessary to align the holes over the inserts in the unit s top. After the headwall has been set, place in the first bolt. After all three bolts have been inserted use the double nuts on the bolts to thread in as far as possible. Remove the nuts one at a time before backfilling, and grout the sleeve surrounding the bolts. Replace the nuts and waterproof as explained in the Sealing Joints section. Tie plates installed before setting headwalls Headwall unit is moved into position. Headwall units are bolted into place. The finished headwall. Setting the Wingwalls Clean the footings of any debris and set shims using the same procedure used for the bridge units. Check for proper clearance at the bottom of wingwall anchor. It is important to check the overall clearance behind the wingwall before units are hooked up and ready to install. Wingwall anchors will extend a minimum of 4 feet behind the wall. Before setting the wingwall, loosely fasten the connection plates to the end bridge unit. Then, push the wall back against the bolted plates. A long bolt may be used to help pull the wall back and align the holes. When starting to fasten the plates the wall can still be several inches away from its final position. When the wall is tight against the plates and holes are lined up, use a shorter bolt. Install the drainage pipes before backfilling. Bolted plates are shown attached. 5

Bridge Unit Vibrator Grout Use vibrator to ensure proper grouting. Wingwall Grouting Follow the grout mix outlines from the project specification. Admixtures may be added to make a more flowable fill. Follow these guidelines for each unit: Completely grout underneath bridge unit legs and to the top sides of the keyway. Grout underneath the wall and between the wall anchor and footing. Grout must fill the keyway. For bridge foundation keyway, inspect the inside of the leg to ensure it is filled. Fill grout underneath wingwall and between the wall anchor and footing. Create a temporary keyway by attaching a 2 x4 on both sides of the wall to act as forms. After mounding the grout on the outside of the leg, vibrate the grout until it passes through to the other side. If required, grout or plug the lift insert recesses, then seal with mastic or a piece of joint wrap material. Completely fill the void between the bottom of the wall anchor and the top of the footing. The grout should match the anchor width and depth from the top of the footing. This should be a minimum of 2 ½ feet long and 6 wide. Grout Temporary 2 x4 Grouting the Wingwalls. Grouting the bolts of the headwall. Sealing Joints Butt joints are created in between two adjoining bridge units. Clean the joint surfaces of any debris. These joints should be covered with a 1 x2 piece of butyl rope and a minimum of 9 wide joint wrap. Use a primer compatible with the joint wrap, and apply a minimum of 9 wide on either side of the joint. Continuously cover the joint from the bottom of one bridge section leg across the top of the opposite bridge section leg. Laps of joint wrap should be six minimum with the overlap running down. Joints that form between the end unit and the headwall should also be sealed. If precast wingwalls are used, the joint between the end bridge unit and the wingwall should be sealed with the same type of wrap or as indicated by the engineer. Joint wrap in progress. 6

Backfilling After the grout has achieved design strength begin backfilling and follow all project specifications. Backfilling is a critical component for the overall structure because it provides support and is important for the roadway approach support. For heights of fill more than 12 feet, no backfilling should begin until a compaction testing plan has been completed and approved by an ArchCast representative and the owner. The Critical Backfill Zone is defined as a minimum of 4 feet on either side of the structure, and from the base of the unit to two feet above the crown. When fill heights are less than two feet, the finished grade will be the boundary of the Critical Backfill Zone. For span less than 24 feet, and fill heights less than 12 feet, the backfill material must meet AASHTO classifications: A1, A2, A3, or A4. For fill heights greater than 12 feet, or spans longer than 24 feet, only backfill materials meeting A1 or A3 should be used. Maximum dry density will be determined by AASHTO T-99 or other approved methods. Have project engineer approve all backfill material. Backfill should not be placed against any structural element until approved by the engineer. Drainage pipe must first be installed behind the wingwalls before backfilling. Use only approved compacting equipment for all backfill and embankment up against the side of the structure and on top of the structure to a minimum depth of 1 foot. Lightweight dozers and graders may be operated over units only with a minimum of one foot compacted cover. Heavier equipment (larger than a D-4 dozer weighing more than 12 tons) requires a minimum of 2 feet cover. Any equipment that weighs more than the design load indicated by the manufacturer s drawings and specifications must be pre-approved. Pay close attention to operating compaction equipment too close to the wingwalls or headwalls. A minimum distance of 4 feet is recommended. Use smaller compaction equipment in these areas. In the Critical Backfill Zone place backfill in lifts of 8 or less. Compact backfill in layers to 95% of the maximum dry density. Material outside of the Critical Backfill Zone must be high quality, well compacted embankment or in-situ soil. To prevent unbalanced stresses, place and compact fill less than 2 feet in difference of elevation on both sides. 7

ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Arch Barrel Units Headwalls Wingwalls 8 0730_0117 To order or purchase ArchCast Bridge units, contact via email at: info@countymaterials.com Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com