INTEGRAL BRIDGES USING PRECAST SUPER TEE BEAMS A CASE STUDY OF SH1 INTERCHANGE BRIDGE AT HOROTIU

Similar documents
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

Bridge Beams. Product brochure

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

ACCELERATED BRIDGE CONSTRUCTION IN NEW ZEALAND THE DESIGN PROCEDURE

Shelly Beach Overbridge Modification, Auckland

Chapter 2 Notation and Terminology

SH20 Mt Roskill Extension Project

Northern Busway - Bridge Structures Linking Communities, New Zealand

BS EN :2004 EN :2004 (E)

Concrete Bridge Design and Construction series

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch

Modeling and Design of Bridge Super Structure and Sub Structure

The Waterview Connection Great North Road Interchange Bridges

Bridge articulation No. 1.04

MIDAS Training Series

PAN PAC PULPMILL TREATMENT TANK

Accelerated Bridge Construction in USA

Bridges on the Northern Gateway Motorway

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

The bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge.

CityLink Tulla Freeway Widening Project Widening of Existing Moonee Ponds Creek Bridges

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

Bijan Khaleghi, Ph, D. P.E., S.E.

Contents. Foreword 1 Introduction 1

ST7008 PRESTRESSED CONCRETE

Experimental study on the seismic performance of RC moment resisting frames with precast-prestressed floor units.

MATERIAL QUANTITIES FOR BALANCED CANTILEVER BRIDGES. FANI ANTONIOU Egnatia Odos A.E., 6th km Thessaloniki - Thermi, GREECE

Concrete Bridge Design and Construction series

Proposed Modifications to the LRFD Design of U-Beam Bearings

NEWMARKET VIADUCT REPLACEMENT PROJECT END OF AN ERA TED POLLEY *, PETER ELCOCK **

Railway Bridge: Design and Detailing for Construction

Seismic Performance of Hollow-core Flooring: the Significance of Negative Bending Moments

Blaxland's Crossing Bridge, Wallacia NSW Bearing Replacement

UHPC Connection of Precast Bridge Deck

Appendix P. Design Philosophy Bridges

Shell Beams. Product brochure

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia.

RESILIENT INFRASTRUCTURE June 1 4, 2016

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

JULY 2014 LRFD BRIDGE DESIGN 5-1

Continuous for Live Load: A Texas Historical Perspective

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Title Page: Modeling & Load Rating of Two Bridges Designed with AASHTO and Florida I-Beam Girders

Design and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway.

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

Progressive Erection Applied to Box Girder with Strutted Wing Slab

MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS

PHASING CONSIDERATIONS FOR BRIDGES

Basarab Cable Stayed Bridge in Bucharest

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction

The New, Balanced Cantilever, Bridge over Acheloos River in Greece

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

International Journal of Scientific & Engineering Research, Volume 5, Issue 1, January ISSN

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables

BrD Superstructure Tutorial

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

Prestress Superstructure Tutorial

Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System

Interaction between ductile RC perimeter frames and floor slabs containing precast units

EXPERIMENTAL INVESTIGATION ON THE INTERACTION OF REINFORCED CONCRETE FRAMES WITH PRECAST-PRESTRESSED CONCRETE FLOOR SYSTEMS

FINITE ELEMENT ANALYSIS AND PARAMETRIC STUDY OF CURVED CONCRETE BOX GIRDER USING ABAQUS SOFTWARE

SEISMIC DESIGN OF BRIDGES SECTION 6 MECHANICAL ENERGY DISSIPATING DEVICES. R.W.G. Blakeley*, L.G. Cormack**, M.J. Stockwell***

Modelling of RC moment resisting frames with precast-prestressed flooring system

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

This precast prestressed concrete pedestrian

MIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES

THE EUROPE BRIDGE, IN PORTUGAL: THE CONCEPT AND STRUCTURAL DESIGN

THE SEISMIC PERFORMANCE OF FLOORING SYSTEMS EXECUTIVE SUMMARY. Dene Cook 1

SORELL CAUSEWAY CHANNEL BRIDGE, TASMANIA Bruce Gibbens CPEng MIEAust Senior Engineer- Bridges GHD Pty Ltd 380 Lonsdale St Melbourne, 3000 Australia

AREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota

Presented by: Taya Retterer BRG Webinar July 30, 2012

Quasi-static cyclic tests of Emulative Precast Segmental Bridge Piers (E-PSBP)

JULY 2016 LRFD BRIDGE DESIGN 11-1

Use of BS 5400: Part 4: 1990

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length

NOTES FOR DESIGNERS AND USERS OF PRESTRESSED PRECAST CONCRETE FLOOR SYSTEMS AND SHELL BEAMS

The Europe Bridge in Portugal: concept and structural design

Launching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008

Consultant: Client: MINISTRY OF EXTERNAL AFFAIRS NEW DELHI IRCON INFRASTRUCTURE & SERVICES LIMITED DIMENSION DETAILS OF RCC SUPERSTRUCTURE.

AASHTOWare BrD 6.8. BrR and BrD Tutorial. PS7-3 Stem PS Bridge Example

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS

Bridge (East) Street Rail Underbridge Replacement for the Albury Wodonga Hume Freeway Project

THE FORENSIC MEDICAL CENTER

mortarless masonry Design Manual Part 1 (IS 456:2000) Section 1 Page 1 IS 456:2000 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE

Seismic Design and Retrofit. Reginald DesRoches Professor and Associate Chair Georgia Institute of Technology

Computer-aided design and analysis of multiple Tee-beam bridges

In-plane testing of precast concrete wall panels with grouted sleeve

Appendix M 2010 AASHTO Bridge Committee Agenda Item

Design of Steel-Concrete Composite Bridges

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Transcription:

INTEGRAL BRIDGES USING PRECAST SUPER TEE BEAMS A CASE STUDY OF SH1 INTERCHANGE BRIDGE AT HOROTIU PETER ROUTLEDGE, MICHAEL CHAN, PETER WILES Opus International Consultants SUMMARY Integral bridges are recognised for their superior durability and lower long-term maintenance costs. As a result they are becoming increasingly popular throughout the world. The State Highway One Horotiu Interchange Bridge recently constructed as part of the Te Rapa Section of the Waikato Expressway is examined in detail in this case study. The paper outlines the project and development of the preliminary and detailed design. The benefits of integral construction are highlighted and aspects of the bespoke beam design are briefly discussed. It also highlights specific features of the case study solution which provided construction, economic and aesthetic benefits. INTRODUCTION The State Highway One (SH1) Horotiu Interchange Bridge is a road bridge recently constructed as part of the Te Rapa Section of the Waikato Expressway, located north of Hamilton in New Zealand. It is located between the two roundabout intersections which connect to the Te Rapa Section and the future Ngaruawahia Section, and carries four lanes of local road traffic over the Waikato Expressway. The successful tenderer was Te Rapa Alliance, comprising of New Zealand Transport Agency (NZTA), Opus International Consultants and Fulton Hogan. They developed a solution using precast concrete SuperTee bridge beams with fully integral abutments and pier. This solution proved to be cost-effective in terms of both capital and whole of life costs and is also graceful in its appearance. This paper is a case study of the SH1 Horotiu Interchange Bridge. The paper outlines the project and development of the preliminary and detailed design. The benefits of integral construction over simply supported construction are highlighted and aspects of the bespoke design of the beams are briefly discussed. Finally, the paper outlines the construction and highlights the economic and aesthetic benefits of the design. THE TE RAPA SECTION OF THE WAIKATO EXPRESSWAY PROJECT The Te Rapa Section is a spur of the Waikato Expressway, a staged project that will provide a continuous four-laned highway between Auckland and Cambridge, south of Hamilton, New Zealand. The Waikato Expressway is a NZ$1 billion plus project that will reduce congestion and shorten the travel time between Auckland and Cambridge by 20 minutes. The existing State Highway 1 route takes traffic from Horotiu, through the industrial area of Te Rapa`Park, passes the newly developed The Base shopping complex, along Avalon Drive and connects to the recently constructed Avalon Drive Bypass.

Figure 1 Te Rapa Route Map (Courtesy of NZTA)

The proposed 7.3km route of the Te Rapa Section will take traffic away from the industrial/commercial area of Te Rapa Park, and eliminates the need for state highway traffic to travel through roundabout and signalised intersections. The route connects to the local roads via grade separated interchanges at Horotiu, Central Road and Gilchrist Road. The northern end of the route is to be connected to the future Ngaruawahia Section of the Waikato Expressway (see Figure 1). Major bridge structures for the Te Rapa Project include the SH1 Horotiu Interchange Bridge, NIMTR Bridge, Central Interchange Bridge, Gilchrist Road Bridge and two local road underbridges. The NIMTR Bridge and Gilchrist Road Bridge are of steel-concrete composite construction, and other bridges will comprise of precast prestressed concrete beams. This paper will focus on the design and benefits achieved for the SH1 Horotiu Interchange Bridge. The Te Rapa Project has been procured through a competitive alliance process for NZTA, a New Zealand government agency. The Te Rapa Alliance is the successful tenderer for the NZ$210 million project, comprising of NZTA, Opus International Consultants and Fulton Hogan. BENEFITS OF INTEGRAL CONSTRUCTION OVER SIMPLY SUPPORTED Integral bridge construction is becoming increasingly popular around the world as it offers several significant advantages including: - Simply supported construction generally requires the bridge to be supported on bearings which enable the bridge to articulate. Bridge bearings commonly have an design life of 25 years, after which they may need to be replaced. Bearing replacement can be a costly and labour intensive exercise, potentially involving traffic management, hydraulic jacks and sophisticated machinery. Integral bridges eliminate the maintenance liability that bridge bearings impose. This minimises the whole of life cost for the bridge. - The use of bearings implies the need for a bearing shelf which provides a ledge on which debris and water ponding can occur. This creates an environment which can be damaging to the concrete and makes inspection of the bearings and structure in the vicinity difficult. Integral bridges avoid the need for bearing shelves, completely eliminating such issues. - Simply supported construction has traditionally required the use of movement joints although recent moves towards semi-integral construction mean this is not always the case. Nevertheless, the use of movement joints creates a maintenance liability and the need for joint replacement numerous times during the life of a bridge, requiring costly traffic management and disruption. Also, in spite of the best efforts to seal movement joints, there is a high probability of water ingress through them with the consequent adverse impact on the durability of structural components in the immediate vicinity. Integral abutments avoid the need for movement joints which improves the durability at the abutments and reduces whole of life cost. - Simply supported bridges usually require longitudinal linkage bolts between the superstructure and the substructure to reduce the risk of span unseating under seismic events. This is a maintenance liability requiring inspection and potential replacement at some point during the life of the bridge. Integral abutments and piers avoid the need for linkages by tying the superstructure directly to the substructure. They also provide additional robustness during extreme seismic events. - Simply supported bridges usually require shear keys to transfer transverse seismic loads from the superstructure into the abutments and piers. These are an additional element to be constructed which can be avoided through the use of integral construction. - Integral construction provides the opportunity for improved aesthetics through the use of smooth clean lines without additional shear keys, ledges and gaps.

SH1 INTERCHANGE BRIDGE PRELIMINARY DESIGN The specimen design for the SH1 Horotiu Interchange consisted of two 2-laned bridge structures spanning over the Waikato Expressway at a skew angle of 25 degrees and total length of approximately 60m. Six 1200mm deep SuperTee beams were utilised for each of the structures. The final alignment was optimised by the geometric designers, resulting in a single 4-laned bridge spanning over the Waikato Expressway at a minimal skew angle of 4 degrees and total length of 45m. The layout of the bridge was governed by factors such as Principal s Requirement to have spill-through abutments and over-dimension headroom clearance to the Expressway. Several superstructure options were developed for the bridge during the tender phase, including steel ladder-deck structures, precast concrete hollowcore beams and a precast concrete SuperTee solution. In combination with the superstructure options, several options for the substructure were also developed and evaluated. The precast concrete SuperTee superstructure option was selected as it provided the following benefits: - The lowest total capital cost compared to other superstructure options, (see Table 1) - Advantages in the whole of life analysis by adopting integral piers and abutments. - A shorter lead time compared to structural steel, resulting an earlier switch over of SH1, which was the critical path - A shallower structural depth compared to the structural steel ladder deck options, reducing the amount of embankment fill - A lower number of beams compared to the precast concrete hollowcore option, minimising number of lifts and transportation - Enhanced aesthetics and relatively slender appearance in comparison to the hollowcore and structural steel options. Aesthetics are important as this is the connection bridge between the Te Rapa Section and the future Ngaruawahia Section. No. Option Description SH1 Horotiu Rate per m 2 of deck area Total cost 1 900SHC 3 SuperTees 4 Steel Option F1 hollow core 900 deep with pad footings $1,939 $1,785,000 Option F2 super tee 875 deep with pad footings $1,744 $1,605,000 Option F3 1.95m deep steel beam on pads $1,537 $1,414,000* 5 Steel Option F4 1.5m deep steel beam on pads $1,862 $1,714,000* *Note these values do not include the cost of embankment fill, which would make the cost of the two steel options significantly higher Table 1 Cost comparison of different superstructure options for SH1 Horotiu Interchange Bridge. DEVELOPMENT OF THE FINAL BRIDGE SOLUTION Refinement to the bridge solution was carried out by all engineering disciplines during the detailed design phase. One example was a raise in finished road level from the tender design due the safe sight stopping distance requirements. A slightly deeper SuperTee beam was adopted, increasing to 1000mm deep from 800mm from the tender design. This allowed the number of beams to decrease from 11 to 9 beams, hence reducing the number of lifts during construction and simplifying the congested integral connection. The final two-span bridge has a pier supported on three 900mm diameter concrete columns, and founded on nine and five 600mm diameter driven steel shell piles at the pier and abutments respectively.

DETAILED DESIGN OF THE SUPERTEE BEAMS Use of Standard SuperTee Beams The 2008 NZTA Research Report 364: Standard Precast Concrete Bridge Beams provides standard superstructure designs using SuperTee beams for spans between 20m and 30m and for skews up to 15 degrees. These superstructure designs assume simply supported construction and therefore cannot be used directly for fully integral construction. Hence a bespoke design of the beams is required. However, the standard designs provide a useful starting point for the analysis and detailing. Furthermore, CAD drawings of the standard designs are available for easy modification of details to suit the particular circumstances of the project. The following sections briefly highlight some of the issues that need to be considered when undertaking the bespoke design of the SuperTee beams. Partial Prestress Design The standard beams in the above Research Report 364 are designed as cracked (Class C) prestressed (or partially prestressed) sections in accordance with NZS 3101 clause 19.3.2 and so for a bespoke design to be at least as efficient as the standard beam designs then partial prestress design needs to be used. Partial prestressing has less onerous serviceability limit state requirements than that required for Class U (uncracked) or Class T (transitional between cracked and uncracked) sections. It acknowledges that a degree of cracking is not detrimental to durability in a similar way to cracks in non-prestressed reinforced concrete sections. In the case of SH1 Horotiu Interchange Bridge, the site is situated inland so it has a relatively low risk exposure classification (Class A2) and the Principal s Requirements allowed the beams to be designed as cracked. The analysis of partially prestressed sections is more complex than that required for uncracked prestressed sections since the position of the neutral axis changes with the degree of bending moment applied. For serviceability design, the stress range in the prestressing and reinforcement steel after decompression of the concrete needs to be checked against codified limits. Road Research Unit Bulletin No. 69: Partial Prestressing in Concrete Bridges provides guidance on the analysis of partially prestressed beams. The analysis is further complicated in the case of SuperTee beams with a composite deck slab due to the strain discontinuity at the interface with the composite slab. Analysis of Cracked Prestressed Concrete Sections: A Practical Approach by Robert F. Mast provides a useful method of accounting for this in the analysis. Temperature, Creep and Shrinkage Effects Temperature, creep and shrinkage effects are often significant to both the superstructure and substructure of integral bridges. Stresses in all the elements were analysed using guidance on the creep and shrinkage properties of concrete from Road Research Unit Bulletin No. 70: Creep and Shrinkage in Concrete Bridges. Designing for these effects for an integral structure is a complex process compared to designing a simply supported structure and the relevant locked-in stresses are dependent on the final construction sequence adopted for the structure. In particular it was found that creep and shrinkage effects imposed significant flexural demand at the tops of the abutment piles. Seismic Response The structure resists longitudinal seismic forces by horizontal frame action between the superstructure and the piled foundations. This increases the stiffness of the bridge compared to an equivalent simply supported bridge which reduces displacements but increases the seismic loads required to be carried. However, since the piles develop double curvature the resistance of the piles is increased. This also imposes additional flexural demand on the beams which would not occur in simply supported construction and needs to be accounted for in the design of the beams and their connections into the abutments and pier. Prestressing and Longitudinal Reinforcing Integral construction enables reduced midspan bending demand due to continuity at the abutments and piers. In the case of SH1 Horotiu Interchange Bridge, this allowed the 1000mm deep SuperTee beams to require less prestressing strands than the Standard Precast Concrete Beam Detail (see Figure 2).

However, additional longitudinal reinforcing is required in the deck topping at the piers and abutments to resist the integral hogging moments, with the bars terminating with a hook into the abutment diaphragm beams. There may not be direct savings from prestressing strands and reinforcing quantities, but integral construction provides savings in the whole of life cost of the structure as mentioned earlier in this paper. Figure 2 The SuperTee beams for SH1 Horotiu Interchange Bridge (left) have six less strands than the Standard Precast Concrete Bridge Beam details (right). Continuity Detailing Continuity detailing, especially at the piers, had to be carefully considered to ensure reinforcing or strands coming out of the beams fit in the available space. The SH1 Horotiu Interchange Bridge beams had strands extending out of the ends and anchored into the insitu concrete at the piercap. The size of the piercap was governed by the anchorage length of the strands. Strands were selected for the integral connection as it was reasonably flexible to shift on site compared to large diameter reinforcing bars. The strands were locally unwound and splayed to improve the anchorage. Transverse Reid bars were connected into couplers cast into the precast beam, similar to the standard precast concrete bridge beam details. Precast Barriers The use of precast barriers was selected for the bridge, improving safety on site as it eliminated the need to use formwork and casting concrete barriers at the edge of the deck. The geometry of the precast barrier was developed with aesthetics in mind. This included a downstand which was detailed to conceal the joint between the precast SuperTee flange and the insitu deck. This detailing provided a smooth pre-cast finish along the whole length of the bridge viewing from the side and from the Waikato Expressway below (see Figure 3).

Figure 3 Precast barriers were detailed to conceal the insitu deck joints and provide a clean finish along the whole length of the bridge Barrier starters in the insitu deck were set out to avoid clashing with the precast barrier starters. When the precast barriers had been landed and set using shim pads and levelling mortar, a cast insitu stitch was poured connecting the barriers to the deck, providing the strength required for the Test Level 4 (TL-4) barrier loads. A non-structural footpath was then poured on top of a debonding membrane in between the barrier and the structural kerb on the northern side of the bridge. CONSTRUCTION The construction of this bridge was relatively straight forward. The ground was excavated to allow for the driving of the piles and ground improvement works at the abutment slopes. The pile capping beams, columns and crosshead were constructed next. The 18 No. precast 1000mm deep Super Tee beams were cast in Stahlton yard in Auckland. The two bottom rows of prestressing strands were extended and cast into the pier crosshead and abutments to achieve a full integral connection. One of the difficulties on site was avoiding clashes between the substructure reinforcing bars and the extended strands from the beams (see Figure 4). Some reinforcing had to be cut and lapped in order to land the beams to its position. Some of the diaphragm bar couplers also did not line up properly, resulting in a non-contact lap for the transverse bars and additional couplers being used, which was checked by the designer.

Figure 4 Photograph looking at the end of the beams. Resolving clashes between the substructure reinforcing and precast beam strands was one of the difficulties during construction Once all the beams were landed, the in-situ deck was cast. The thickness of the deck was varied to achieve the final level for the road. Barriers starters were also cast into the deck, set out to line up with starters extending from the precast barriers. The precast barriers were then connected to the deck by an insitu stitch, and a non-structural footpath was then cast in between the barrier and the kerb. The construction of the bridge began in November 2010 and was open to public in December 2011. CONCLUSION Integral bridge construction is becoming more common around the world. Many road controlling authorities specify that bridges under a certain length (commonly 60 metres) and skew (commonly 30 o ) should be designed as integral structures. Furthermore, the NZTA Bridge Manual Clause 4.7.1 (c) implies this should be the case for bridges designed in New Zealand. The whole of life and economic benefits of removing known maintenance issues from bridges on State Highway One, New Zealand s major North to South route, are well documented. A relative comparison for the per m 2 rate of the physical bridge construction costs in the Te Rapa Section (see Table 2) is evidence that well-designed integral structures can provide the lowest capital cost solution as well as the optimum whole of life solution.

Bridge Description Cost per m 2 ($/m 2 ) SH1 Horotiu Interchange NIMTR Central Te Kowhai Local Fully integral 45m two-span SuperTee bridge on a 4 o skew Simply supported 150m four-span steel beam and concrete slab structure on a 61 o skew. Simply supported 64m four-span Double Hollow Core on a 33 o skew Simply supported 41.5m three-span Single Hollow Core with composite concrete deck Simply supported 40m three-span Single Hollow Core with composite concrete deck 1,816 2,585 2,615 2,130 2,295 Gilchrist Fully integral 60m two-span steel ladder deck bridge on a 24 o skew. 2,255 Note: Physical bridge construction costs only no allowance for P&G or approach formation included Table 2: Construction Cost Rates for Te Rapa Bridges The SH1 Horotiu Interchange bridge has demonstrated that SuperTee beams can be used effectively in fully integral construction. Due to the significant interaction between the superstructure and the substructure, a standard design is not possible and thus the standard NZTA bridge designs cannot be used directly. For integral bridges a bespoke design is required and such design is complex compared to that required for simply supported construction. However, this paper has highlighted that there are cost and durability benefits in using integral construction despite the additional design effort required. The non-standard design approach also provides the opportunity to economise the design solution whereas the standard NZTA bridge designs economise on the design effort but possibly at the expense of construction economies. In the case of SH1 Horotiu Interchange Bridge, the bespoke design ameliorated the overall beam depth to a site specific solution, hence offering increased economy for the approaches. The final solution for SH1 Horotiu Interchange Bridge is a magnificent example of a welldesigned and constructed integral bridge structure. The structure is robust and simple to construct, with bridge completed on time and on budget. The final result is also an aesthetic bridge that signals the transition to the Te Rapa Section of the Waikato Expressway (see Figures 5 and 6).

Figure 5 and 6 The final bridge solution is cost-effective, relatively simple to construct and robust whilst being aesthetically pleasing.