GLADSTONE LNG leads the way with its first LNG shipment in 2012

Similar documents
We attach a copy of a presentation to be presented to stockbrokers and investors during the month of April 2009.

Gladstone LNG Project First LNG shipment in 2012

LIQUEFIED NATURAL GAS LIMITED

Gladstone LNG Project Fisherman s Landing. The shared vision of HQC and LNG Limited

ARROW ENERGY ARROW LNG PLANT. May 15 th to 19 th 2012

Gladstone LNG Project Fisherman s Landing

The following sub-systems are provided and the integration of these is described below:

Gladstone LNG Project Fisherman s Landing. A Shared Vision of HQCEC and LNG Limited

Liquefied Natural Gas Limited. ASX RELEASE COMPANY UPDATE 20 May 2013

Disclaimer & Important Notice

GLADSTONE TO JAPAN: EXPORT LNG PROJECT. December 2007

Santos and PETRONAS sign historic partnership for Gladstone LNG

Santos proposes multi-billion dollar Gladstone LNG Project

Gladstone LNG Project - Fisherman's Landing

Optimising. the LNG process. The rapidly expanding global LNG industry continues. Projects

LNG Import Facility Infrastructure Options

ASX/MEDIA RELEASE 1 July 2014 KINDER MORGAN FILES FERC APPLICATION TO TRANSPORT GAS TO MAGNOLIA LNG PROJECT

ASX/MEDIA RELEASE 30 APRIL 2015 MAGNOLIA LNG PROJECT FERC NOTICE OF SCHEDULE FOR ENVIRONMENTAL REVIEW RECEIVED

ASX/MEDIA RELEASE 23 APRIL 2015 MAGNOLIA LNG PROJECT TOLLING AGREEMENT UPDATE WITH MERIDIAN LNG

Realising Project Potential in 2010

Linking Energy Globally

GLNG project sanctioned. Final investment decision on US$16 billion 2-train 7.8 mtpa project

Freeport LNG Liquefaction Project

LNG: Energy of the Future

June GLNG Project update. 28 June 2012

Bowen Gas Project. EIS Community Information Sessions. June Arrow s Moranbah Compression Station Bowen Basin

Delivering the Strategy

Australia Pacific LNG: Final Investment Decision

Santos lifts half-year net profit by 155% to $504 million. Underlying net profit up 12% to $236 million

Transforming through LNG UBS Australian Resources & Energy Conference Sydney, 14 June 2012

17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

For personal use only. Good Oil Conference September 2015

MLNG DUA DEBOTTLENECKING PROJECT

For personal use only. GLNG investor visit May 2013

Economic. Our approach. Energy supply

11. NOISE AND VIBRATION

For personal use only

Alaska South Central LNG (SCLNG) Project

For personal use only

World s first LNG from Queensland, Australia A precursor to US LNG exports

Arrow Energy. Surat operational update. July 2016

Standardized, Modular Liquefaction Equipment and Technology

Arrow Energy Arrow in the Surat

Liquefied Natural Gas Limited

We invite you to find out more at careers.conocophillips.com

14 EIS Marine Facilities Construction Environmental Management Plan

2. Project Justification and Feasible Alternatives

Please find attached a presentation GLNG Investor Tour, being presented by Mark Macfarlane in Roma on Thursday 3 November 2011.

Developing and Implementing Floating <Title of Presentation>

Carbon Energy Low cost, low emission energy has arrived

STRIKE ENERGY Limited Energy Users Association of Australia - 4 June 2014

Introduction. FLNG: Costs and Cost Drivers. What is FLNG (and what isn t) FLNG Project Costs

6. GREENHOUSE GAS EMISSIONS

Liquefied Natural Gas Limited

FACT SHEET. QCLNG pipeline The Narrows crossing. QCLNG and Australia Pacific LNG projects. The Narrows pipeline specifications.

We deliver gas infrastructure

ZeroGen Project Update Commercial Scale IGCC+CCS Demonstration. Managing Risks and Uncertainties

Appendix A: Project Characteristics

LNG Supply, Demand & Pricing

Liquefied Natural Gas Limited COMPANY UPDATE 7 OCTOBER 2013

Powering Asia: The Role of Gas Address to the Melbourne Mining Club David Knox, Chief Executive, Santos. 4 February 2010

ANNUAL GENERAL MEETING 2010 ENERGY TO SUCCEED

The Australia Pacific LNG Project. Volume 4: LNG Facility Chapter 14: Greenhouse Gases

Liquefied Natural Gas Limited

Meeting Australia s Energy Needs. Australian Future Energy Pty Ltd QEC Investment Showcase 14 June 2018

Quarterly Production Report For period ended 30 September 2017

For personal use only

Dominion Cove Point Export Project Platts 16 th Annual Liquefied Natural Gas February 9, 2017

Australia Pacific LNG Project. Volume 5: Attachments Attachment 31: Greenhouse Gas Assessment - LNG Facility

COMPLETING THE LNG VALUE CHAIN

Unlocking the Cooper Basin s resource potential

UBS Australian Resources & Energy Conference. Sydney, 13 June 2013

Our technology and expertise are ready to work toward your LNG future today

Partner Up Greg Hallauer, Yokogawa Corporation of America

Quarterly Production Report For period ended 31 March 2018

Arrow Energy. Surat development update. December 2017

6. PROJECT DESCRIPTION: DREDGING

African Gas Infrastructure: Project Development and Financing

Australia Pacific LNG Project. Volume 4: LNG Facility Chapter 3: Project Description

Importance of NSW s Natural Gas: Time to separate fact from fiction

APA gas transmission assets equipped to adapt and grow Mick McCormack Managing Director and CEO

PERP Program LNG Receiving Terminals New Report Alert

WORLD-CLASS LNG CAPABILITIES DELIVERING CLEAN ENERGY AND PROVEN LNG SOLUTIONS

Making Cents of the Eastern Australian Gas Market

Liquefied Natural Gas Limited

Arrow Update. Arrow Research. Groundwater monitoring and modelling. Demonstrations at Theten. Arrow Update. Domestic gas expansion activities

Alaska LNG Concept Information. Alaska LNG. Overview. October

Environmental and Social Management Plan

PORT OF NEWCASTLE CONTAINER TERMINAL PRESENTATION FEBRUARY 2018

Overview. Economics of the LNG Project Chain

11.0 Energy. Summary Energy snapshot

Macquarie Australia Conference. 1 May 2013

MITIGATION OF SEASONAL PRODUCTION LOSS FOR THREE PARALLEL 4.7MMTPA

O I L S E A R C H L I M I T E D. Oil Search and the PNG Gas Project

Leading the Second Wave of US LNG Exports & Challenging the Traditional LNG World Paradigm. Langtry Meyer Founder & Chief Operating Officer Texas LNG

Comet Ridge s Galilee Basin Extended Production Test Project Galilee Basin Coal & Energy Conference 2013 Tor McCaul, Managing Director 25 November

LNG R E F E R E N C E P R O J E C T S. Phone: +49(0) GOC Engineering GmbH Bachovenstr. 8; Sinzig, Germany

Five Global Pty Ltd ABN (0) (0)

Transcription:

GLADSTONE LNG leads the way with its first LNG shipment in 2012

LNG Business Model Development of mid-scale LNG projects of up to 1.5 million tonne per annum (Mtpa) production capacity per LNG train, based on: Gas Access: gas fields seeking international gas pricing, insufficient local energy demand, too small, far from energy markets and/or reserves insufficient to support traditional largescale LNG plant (require multiple trillion cubic feet of gas) Project Location: target sites that are close to low cost gas source, existing infrastructure, availability of suitable sites with access to deep, protected water, LNG Markets: targeting existing LNG markets in close vicinity to Project location LNG Limited offers a complete LNG package/solution structured for the benefit of all stakeholders

Advantages of Mid-Scale LNG Projects Smaller land access requirement, increases ability to strategically locate LNG plants closer to existing infrastructure and sheltered deepwater access (lower associated infrastructure costs) Proven uncomplicated & highly efficient single mixed refrigerant process with lower equipment count, easier installation, operation & maintenance (including faster shut down and start up) and faster construction Use of membrane tank technology delivering a lower construction cost and faster construction schedule Smaller project size and uncomplicated contracting (potential only 1 LNG buyer) reduces period to complete detailed (bankable) feasibility study and achieve financial close All of the above advantages leads to a faster project delivery schedule, thus lower overheads and financing costs

Project Background 2001: LNG Ltd commenced planning of mid scale LNG projects 2004: LNG Ltd first considered coal seam gas (CSG) for LNG export 2006: Maturity of CSG production in Queensland 2007: LNG Ltd signs HOA with Arrow for gas supply Project site identified with Gladstone Port Corporation EOI provided by Golar LNG and others for LNG offtake 2008: LNG Ltd commences voluntary EIS approvals process Signs with LOR / SKEC as preferred EPC Contractor Signs site Licence Agreement with GPC 2009: LNG Ltd signs HOA with Golar LNG for LNG offtake

Project Scope Arrow Energy Ltd / AGL GLNG PL GPC Licence Agreement for Site signed August 2008 with Gladstone Port Corporation

Source: Arrow AGM Presentation 2008

Gas Supply Entire gas supply (Train 1) is covered under proposed Gas Sale Agreement with Arrow Energy. Material terms / conditions are: Parties: Arrow Energy and Gladstone LNG Ltd Maximum Daily Quantity: 257 TJ / day after initial 24 month ramp-up period Annual Contract Quantity (ACQ) (45PJ yr 1, 75PJ yr 2 and thereafter 90PJ/yr for 12 years Delivery Point: Gladstone LNG s Plant Gas Price: floor with oil price upside agreed

The Coal Seam Gas Challenge Little or No Proven Gas Reserves at Financial Close (all 2P / 3P) The low heating value of Coal Seam Gas Potential multi-user gas pipeline, requires careful plant design Variable gas composition over production term Ramp up of coal seam gas requires 12 to 24 months to reach required contractual volumes LNG Plant shutdown may cause major issues upstream Relative new industry in Australian with limited experience LNG is a very conservative industry

Working with Coal Seam Gas CSG Reserves / Deliverability Largely mitigated by implementing a mid-scale LNG project Quantity of CSG required is realistic and achievable Accommodation of ramp up, as opposed to large scale LNG projects Mid scale trains easily duplicated as reserves and deliverability increase CSG - Quality and Pressure Extensive gas quality testing program requested from Arrow to minimise risk of off-spec gas being delivered LNG plant capable of tolerating gas quality beyond current CSG spec Gladstone LNG / Arrow have agreed minimum delivery pressure Gas Delivery to Gladstone Project Site Pipeline Licence already granted to Arrow / AGL (from Bowen Basin) PL variation underway for 5km lateral from Gladstone Gas Gate to Site Only LNG Project that has pipeline approval to Gladstone (from Bowen) Pipeline Licence under development from Surat Basin

Project Site, Fisherman s Landing Co-ordinates are estimates only and are subject to CQPA approval and final survey

Advantages of Fisherman s Landing Natural deepwater harbour Protected, no need for breakwater infrastructure Under-utilised existing Wharf #5 available for LNG export Existing infrastructure (roads, water, etc) Existing dredging approvals for Targinie Channel Future potential for additional Land (expansion project) Only LNG project in Gladstone that can potentially commence construction next year, and be operational in 2012 Avoidance of Curtis Island type issues

LNG Project Overview Location Fisherman s Landing 25ha site, Port of Gladstone, Qld Gas Supply Arrow Energy (coal seam gas) delivered to Gladstone LNG Offtaker Golar LNG Capacity First Train of 1.5 million tonnes per annum Capital Cost: ~ US$500 * million, including owner s and financing costs Process Optimised Single Mixed Refrigerant Process (OSMR TM ) Storage: 1 x 180,000m 3 Membrane storage tank (net capacity) Contractors SKEC and LOR (preferred) Port Facilities Gladstone Ports Corporation Ownership Shareholding at Financial Close likely to be 40% LNG Ltd, 40% Golar LNG; and 20% Arrow Energy Funding US$250 million equity / US$250 million debt (proposed) Schedule Financial Close end of 2009, LNG Sales 2012 * Based on A$ to US$ exchange rate of 0.80, excludes Arrow and GPC s scope

OSMR TM Process Plant Power Grid Power BFW Pump Process Steam CHP Plant ACC Inlet Air Chiller STG Aux Boiler Once Through Steam Genertor Suction Scrubber (x2) Mixed Refrigerant System MR Cooler (x2) OSMR TM PROCESS MR Make-up Ammonia Refrigeration Plant Gas Turbine Compressor (x2) Ammonia Refrigerant HP Fuel Feedgas Chiller Amine Regen CO 2 H 2 0 Gas Sweatening Plant Marine Flare Dehydration Plant Heater H 2 0 To Cold Box # 2 BOG Compressor (x2) LP Fuel (Aux Boiler) Cold Box (x2) Ship Loading LNG Storage & Ship Loading LNG Tank LNG Pumps (x4) LNG From Cold Box # 2

Membrane LNG Storage Tank 1 x 180,000m 3 Membrane storage tank (net storage) Lower capital cost than conventional LNG tank technology Shorter construction schedule than conventional LNG tank technology Comparative risk assessment report completed, stating that when comparing the membrane tank concept to the full containment tank concept these two tank types are considered to provide some of the highest integrity options for above ground refrigerated liquefied gas storage Quantitative Risk Assessment near completion Historically, membrane tank acceptance hindered by lack of accepted standards. Post 2006, European Standard EN 14620 developed, LNG Ltd believes future LNG projects will consider membrane technology as a serious alternative

29 Membrane Tanks Already Built

FEED / EPC / Technology Working with SKEC/LOR throughout 2008, jointly undertaking FEED to ensure a definitive and seamless EPC contract can be concluded The approach eliminates interface issues caused by separate parties undertaking FEED, EPC and providing technology Propose that SKEC and LNG Technology Pty Ltd jointly provide the process guarantee for the OSMR process. SKEC to wrap into EPC contract Strong relationship built with key equipment vendors SKEC undertaking procurement and takes full responsibility for equipment and plant performance

Summary of Benefits Best solution - All aspects of the plant including gas pre-treatment, liquefaction, storage, utilities, construction techniques etc optimised and integrated. Numerous industry experts engaged to accomplish the best techno-economic solution Liquefaction system - single mixed refrigerant composition, flowrate and pressures optimised to match cooling curve and best fit standard available equipment. Proven SMR process used with numerous reference sites Efficient / Simple Process -Modern high efficiency gas turbines (MR compressors) and CHP plant utilised for utility power. Less equipment items required per train compared to alternative processes, resulting in low capital and low operating / maintenance costs High train availability parallel compressors (MR and ammonia) used compared to compressors in series for alternative processes Government no government assistance being sort, provides early start up benefits, sets the scene for the larger LNG projects in Gladstone LNG storage tank uses membrane tank technology and concrete slip form construction technique to minimise construction time (critical path) and reduce costs Project Viability at the floor price level

Port Infrastructure (GPC Scope) Port Interface being addressed under draft term sheets / agreements, currently being reviewed: Commercial Port Users Agreement Agreement to Lease Licence for Services Agreement Engagement of GHD for Wharf Modification design Ship Simulation Work on-going to determine extent of dredging requirements for Targinie Channel Swing Basin and berth pocket adjacent to Wharf #5

Typical LNG Loading Facility

Required Dredging by GPC Dredging Required of: Berth Pocket No.5 Swing Basin Targinie Channel

LNG Off-take Agreement Entire LNG production (Train 1) covered under proposed LNG Sale and Purchase Agreement with Golar LNG. Material terms / conditions are: Parties: Golar LNG and Gladstone LNG Ltd Annual Contract Quantity: 1.5 mtpa, with 24mth ramp up period Delivery Point: FOB from Gladstone Contract Term: matching GSA Term LNG Price: floor with oil price upside agreed

Golar LNG Limited Golar LNG is LNG Limited s largest single shareholder at 16% Golar LNG, with total assets of ~US$2.5 billion and 15 LNG ships, is one of the world s largest independent owners and operators of LNG carriers with over 30 years experience Golar developed the world s first floating storage and regasification unit (FSRU) projects, based on the conversion of existing LNG carriers and leads the FRSU industry in committed projects Golar LNG s stated objective is to become an integrated midstream participant in the LNG industry Golar LNG is listed on both the Oslo and Nasdaq Stock Exchanges

Milestones for 2009 1 st Half 2009: FEED / EPC / Process Guarantee Project Execution Plan Finalise FEED Process Guarantee Agreement with SKEC EPC Contract (near completed draft) with SKEC/LOR Ship simulation modeling / Preliminary design for wharf upgrade EIS assessment report / Development Approval applications submitted Quantatative risk assessment report complete 2nd Half 2009: Agreements / Financial Close All project approvals grant. Project contracts and financing documentation to be signed and conditions precedent to initial drawing of the debt being satisfied for the overall project (end-to-end from gasfield to port activities to LNG offtake) 2012: First LNG Shipment

Disclaimer & Important Notice The information in this presentation is not an offer or recommendation to purchase or subscribe for securities in Liquefied Natural Gas Limited or to retain any securities currently being held does not take into account the potential and current individual investment objectives or the financial situation of investors was prepared with due care and attention and is current at the date of the presentation. This presentation contains forward looking statements that are subject to risk factors associated with the gas and energy industry. It is believed that the expectations reflected in these statements are reasonable, but they may be affected by a range of variables which could cause actual results or trends to differ materially, including but not limited to: price and currency fluctuations, geotechnical factors, drilling and production results, development progress, operating results, reserve estimates, legislative, fiscal and regulatory developments, economic and financial markets conditions in various countries, approvals and cost estimates. All references to dollars, cents or $ in this document is a reference to US$, unless otherwise stated.