RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

Similar documents
RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name:

Bridges. Chapter 6: chapter contents

RISK ASSESSMENT SHEET

+/0'-/12!"&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=!

Deck Joints and Bearings

V.2. REFERENCE: G:\Public\OCCUPATIONAL HEALTH & SAFETY\3. INDUCTION\General Site Induction REVIEW DATE: 5/6/2013

TEMPORARY FACILITIES

Temporary Watercourse Crossing: Culverts

Speedlock Pallet Racking

Tower Site Inspection Procedures

"SUPPORTED SCAFFOLDING SAFETY IN CONSTRUCTION ENVIRONMENTS"

CONTRACTOR WHS HAZARD STANDARD TRAFFIC MANAGEMENT EXTERNAL USE ONLY

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

24 Portable Saw Mill OWNER S MANUAL

"WALKING AND WORKING SURFACES IN CONSTRUCTION ENVIRONMENTS"

DTE Energy St. Clair Power Plant

Building 17 Roof Safety Assessment. Not Applicable - No fall restraint system. Within handrailed and marked painted areas NA

EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities

HFM Asset Management Contractor Induction Queens Riverside Apartments

Cause of Loss and Risk Control Techniques

PAY TO PLAY: OSHA ISSUES NEW GUIDANCE ON EMPLOYEE PERSONAL PROTECTIVE EQUIPMENT (PPE) AND EMPLOYER DUTY TO PAY

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

or from the OSHA website, adisp.show_document?p_table=fed ERAL_REGISTER&p_id=20094.

Risk Assessment Form (Qualitative)

Network Rail Project No: Issue: 002 Date 11/07/2017 Work Package Plan Arena Tunnel LSM773 Prepared by: Start Date: 15/07/17 Finish Date: 23/07/17

Company s Name: GHI Warehouse Date of Risk Assessment:

FW66 FORESTRY WINCH FW66. Owner s Manual 19/02/2016

2.1 Backfill - General

DRIVER CODE OF CONDUCT FOR TRUCK AND HEAVY VEHICLE OPERATORS PERFORMING WORK FOR OR ASSOCIATED WITH CDM LOGISTICS

Scaffolding. Safety Guide. STOP! Before you climb

SECTION ROOF PEDESTAL PAVER SYSTEM

Technical Test Theory Industrial Forklift Truck A16

Excavations. OSHA (Revised)

STANDARD OPERATIONAL PROCEDURES


Personal Protective Equipment

WRITTEN SAFE WORK PROCEDURES FALLING

MAINTENANCE PLAN Wing Village Hall, Morcott Road, Wing, Oakham LE15 8SA

Cyclic Meter Reading,

Hazards Outside The Laboratory: Loading Dock Safety

Excavation Safety Program

Document Number: HSE Created: February 21, 2013 SCAFFOLDING. Author: A Holland

Good practice. Deck machinery. It s your ship and equipment look after them and they will look after you GOOD PRACTICE

Safe Work Method Statement

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

ACCIDENT PREVENTION PROGRAM HAZARD ANALYSIS SAFETY HEIRARCHY

10.1 INTRODUCTION 10.1 DRAINAGE

SEPTIC SYSTEM EVALUATION AND CERTIFICATION FORM

PREFABRICATED STEEL TRUSS SPECIFICATIONS

Standards Summary Sheet

DURO-SHIELD ROOF COATING CARE GUIDE TABLE OF CONTENTS

Implementing an Effective Personal Protective Equipment (PPE) Programme

No part of this manual may be reproduced in any form or by any means, without prior written permission of Darrera.

Walking and Working Surfaces in Construction Environments. Leader s Guide and Quiz

ACT Scaffolding Services LTD METHOD STATEMENT Scaffold erection

Pesticide Safety Program

Commercial Roof Cover Maintenance and Repair Risk Engineering Your Business Insurance Specialists

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Ironton Russell Bridge Project

Guidelines for Working in Loading Docks

Personal Protective Equipment

OCCUPATIONAL STANDARD (For use in the development of supply chain related job descriptions, performance evaluations, career development plans, etc.

MICHIGAN DEPARTMENT OF TRANSPORTATION

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

VISE MOUNTED. Model 97359

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

HANDING-OVER CERTIFICATE - SCAFFOLDING

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

Near Miss and Incident Reporting

Conergy SolarFamulus II

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Alberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.

Inspection guidance for bridge expansion joints. Part 2 Inspector s Practical Guide

NACE Coating Inspector Bridge Specialty Written Exam NACE-Bridge-001

POLICY ON PERSONAL PROTECTIVE EQUIPMENT

The Inspection Process. Waxhaw N.C.

TRENCHING AND EXCAVATION

TLILIC2001 Licence to Operate a Forklift Truck

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

Safety on Heights: Our Policy

GAF Scheduled Maintenance Checklist

Ironton Russell Bridge Project

Selection of Proprietary Shoring Equipment

Stainless steel rolling cabinet

Industry guidance for the safe operation of tilt-tray vehicles

Table of Contents. July

SEVERITY OF HAZARD? ASSESSED RISK

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3

PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE

Tour Manager/Guide Health & Safety Induction Booklet

Open-Web Truss Long Span Installation Guidelines

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Level 2 NVQ Certificate in Erection of Precast Concrete (Construction)

Field Instruction. All Horizon Power workers who work in and around excavations.

Pesticide Chemical Safety

Transcription:

RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Bridge Inspection Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE: DATE: / / Projects: BRIDGE INSPECTIONS Critical Steps in this Activity: Potential Hazards: Safety Controls: Preparation for operations Driving to worksite Traffic Control Inadequate planning Drive into other people Road users Plant Drive off embankment Poor drivers Poor drivers Inappropriate traffic control measures Indentify people, PPE, equipment, potential hazards and safety controls prior to commencement of works Team leader to issue traffic management plan to work crew All relevant signs to be placed on vehicle Team leader to arrange extra signs and traffic control if required All MSDs s for Hazardous substances to be placed in vehicle Be in possession of proper Drivers/operators license Being aware whilst driving Travel at a safe speed according road conditions and load Follow traffic management plan from team leader Ensure the traffic control measures are appropriate for all weather conditions Use of appropriate PPE high visibility clothing ETC Stay alert for traffic on worksite Aftercare signage to be left if work has loose surface on carriageway

Road surface for depressions, cracking at approaches Traffic Listen for traffic on dead-end roads. Stay alert. When working on roadway full traffic control will be required Bridge bituminous surfaces for cracking also depressions Traffic Listen for traffic on dead-end roads. Stay alert. When working on roadway full traffic control will be required Footpaths for unevenness Signs and delineation for damage and visibility for road users Barriers for damage post, missing bolts, clamps, corrosion Deck joints missing and damage bolts and other components Bridge Drainage for accumulation of debris, Walking Surface Accidents l Keep a watch for frosted. wet, slippery, uneven or cracked surface Wear proper footwear gloves, goggles, long sleeved shirt & pants etc. Wear sturdy footwear. Do not take unnecessary risks to speed up job. Proceed with caution

Weep holes LOW Road & bridge drainage for scour, especially at outlets to culverts and off deck channels Embankment & Slope for erosion and scour Vegetation around abutments and wing-ways Waterways for accumulation of debris and silt, vegetation growth and scour Climbing steep and muddy banks Carrying equipment Falls Carrying equipment Falls Make sure you have a proper footing when descending or climbing banks. Watch for slippery, muddy or wet banks and holes. Late spring to early summer could be safer than in winter months. Safety harness could help protect employee when descending steep banks Do not overload yourself. Plan ahead. Get help or maybe two trips if necessary. Use proper lifting and carrying techniques Do not take unnecessary risks. Maintain balance when working on steep slopes. Carry a radio in case of a fall. Use fall protection Do not overload yourself. Plan ahead. Get help or maybe two trips if necessary. Use proper lifting and carrying techniques Do not take unnecessary risks. Maintain balance when working on steep slopes. Carry a radio in case of a fall. Use fall protection

Pier, abutments, cross-heads, bearing pedestals and substructure drains for accumulation of dirt and debris Timber members for termite activity, decay, insect attack Timber members for excessive deflections Iron and steel elements for build-up of salt, silt, debris or dirt Using inspection equipment Using inspection equipment Using inspection equipment Caution should be used when probing timber members with sharp pointed tools wear proper safety equipment and protective clothing: hard hats, gloves, goggles, long sleeved shirt & pants etc. Wear sturdy footwear. Do not take unnecessary risks to speed up job. Proceed with caution Caution should be used when probing timber members with sharp pointed tools Caution should be used when probing timber members with sharp pointed tools

Deck, girders, piers, abutments and wing walls for looseness, and major damage Deck, girders, bearings for defects such as spalling, cracking, staining, dampness, corrosion and excessive vibration Wedges in works for tightness Visual damage to bridge bearings Masonry elements to joints between blocks/bricks and cracking in masonry Physical Physical Physical Using inspection equipment Caution should be used when sounding concrete with a hammer

Bridge in general graffiti, damage to installed services and encroaching vegetation and fire hazards LOW All inspection sheets to be handed to team leader for yearly program and kept for future claims

License/Training Drivers License Work Activity Induction Red Card List Plant-Equipment Bridge Truck, Generator, Hand Tools, Harness, Life Jacket List: /Personal Protective Equipment required for this Activity Hi visibility clothing Rubber Boots List Equipment Maintenance Checks required for this Activity Plant Log Sheet Engineering Certificates Type Level 1 Bridge Inspection Training Traffic Management Plans MSDS s Hazardous Substance Type Torch Sunscreen Hand Mirror Safety Boots First Aid Kit Duties & Responsibilities To ensure the safety of co-workers and general public. To report all incidents and near misses to team leader. Ensure equipment is in safe working order. Perform safety checks of equipment

Safe Work Method Statement The personnel listed below have been made aware or and understand the procedure, hazards and control measures outlined in the Safe Work Method Statement. They will abide by the control measures outlined within the Save Work Method Statement. Name Position Signature Any changes. Additions or deletions made to this Safe Work Method Statement are to be covered with the above personnel and The Principal Contractor representative at a Toolbox meeting. (Record date and time of Toolbox meeting below) Date: Time: Comments: Reviewed by: Date: