Energy Storage and Distributed Energy Resources Phase 3 ( ESDER 3 ) Issue Paper

Similar documents
Energy Storage and Distributed Energy Resources Phase 3

Expanded Metering and Telemetry Options Phase 2. Distributed Energy Resource Provider (DERP) Draft Final Proposal

Business Requirements Specification

Energy Storage and Distributed Energy Resources Phase 2

CCE3 Workshop Issues Matrix and Next Steps

Stakeholder Comments Template

Commitment Cost Enhancements Phase 3 Action Plan

2016 Fall Reliability Conference MRO

Business Practice Manual for Market Operations

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

Issue Paper. Direct Participation of Demand Response Resources in CAISO Electricity Markets. December 22, CAISO JEP / BDC/ JDG 12/22/08, page 1

Reliability Demand Response Product

SAN DIEGO GAS & ELECTRIC COMPANY

BPM Change Management Meeting

Distributed Energy Resources Integration

ISO Smart Grid Use Case

Metering Rules Enhancements Revised Straw Proposal

Business Practice Manual for Reliability Requirements. Version 34

SPP at a Glance. Located in Little Rock. Approximately 600 employees

Release User Group Agenda

Bid cost recovery and variable energy resource settlement Straw proposal

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Final Flexible Capacity Needs Assessment for 2018

Day Ahead Market Enhancements: Issue Paper/Straw Proposal

Load Shift Working Group.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Proposed Framework for Multiple Use Applications for Electric Storage Resources

EIM Winter Reliability notes and processes for EIM entities. Craig Williams Training and Readiness

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

ISO Course Outline. Market Transactions Class

Commitment Cost Default Energy Bids Enhancements (CCDEBE) Business Rules

5.1.1 Day-Ahead Economic Bids for Supply

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

PG&E s General Comments on Demand Response Vision Update. January 11, 2008

FERC Order 764 Settlements

Benefits from Generation and Storage on the Distribution System

Introduction to the Energy Imbalance Market (EIM Module 1)

Flexible Resource Adequacy Criteria and Must-Offer Obligation

California Independent System Operator Corporation Fifth Replacement Tariff

Load Serving Entity Definition Refinement Draft Final Proposal

Local Market Power Mitigation Enhancements

Stakeholder Process: Commitment Cost Bidding Improvements. Summary of Submitted Comments

3. Overview of Market Instruments

2. Market Operations Overview

Comments of Northern California Power Agency CAISO Load Granularity Refinements Issue Paper. September 20, 2010

Imbalance Conformance Enhancements. Issue Paper & Straw Proposal

Business Practice Manual for Market Operations

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Revised Straw Proposal Short Term Solutions

Distributed Energy Resources Market Design Concept Proposal

Final 2014 Flexible Capacity Needs Assessment

Business Practice Manual for Metering. Version 56

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144

Demand Response Auction Mechanism ( DRAM 3 ) Pre Bid (Bidders) Web Conference

StorageVET Applications and Demonstration Energy Storage Valuation Workshop

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect

Energy Imbalance Market Overview

Load Granularity Refinements. Pricing Study Description and Implementation Costs Information Request

6.1.9 IFM Initial Conditions

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

Load Granularity Refinements Issue Paper

2017 Stakeholder Initiatives Catalog

Operating Procedure PURPOSE... 1

ATTACHMENT M-2 (PECO) Determination of Capacity Peak Load Contributions, Network Service Peak Load and Hourly Load Obligations PURPOSE

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US

Local Market Power Mitigation Options Under Convergence Bidding

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation

Business Practice Manual for Managing Full Network Model. Version 1011

X Accept as requested X Change to Existing Practice Accept as modified below Decline

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments

Electrification and its Implications for the California Electricity System

Dynamic Price, Product and Messaging Specification

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units

California Independent System Operator Corporation Fifth Replacement Electronic Tariff. Appendix A. Master Definition Supplement

Generator Contingency & RAS Modeling

California Independent System Operator Demand Response Barriers Study (per FERC Order 719) April 28, 2009

Clean Energy for all Europeans

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Revised Flexible Capacity Framework

Spring 2014 Release Training

Use-Limit Resource Guide Book Standard Version #8 Effective Date 2/2/2017

Flexible Ramping Product Cost Allocation Straw Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

CAISO TARIFF APPENDIX A Master Definitions Supplement

COMMENTS OF THE PJM INDUSTRIAL CUSTOMER COALITION ON PJM'S CAPACITY PERFORMANCE PROPOSAL. September 17, 2014

Standards for Imports of Regulation

Demand Response and Scarcity Pricing

Briefing on 2018 Policy Initiatives Roadmap and Annual Plan

Energy Marketplace. Nicolé K. Grottoli. Market Overview Course. Senior Market Trainer, Market Training, NYISO. March 8, 2018 Rensselaer, NY 12144

Capacity Market Topics Resource Targets, Qualifications, Performance Standards, Must Offer. Jacqueline DeRosa, Senior Market and Product Economist

Locational Based Marginal Pricing

Third Generation California Electricity Market Design

Capacity Resource Performance in NYISO Markets

Digital for Power & Utility Bottom Line Success. Solutions for Traders, Fuel and Portfolio Managers

ATTACHMENT M-2 (BGE) Determination of Capacity Peak Load Contributions, Network Service Peak Load and Hourly Load Obligations PURPOSE

Powerex Comments on CAISO October 31, 2013 Revised Draft Order No. 764 Tariff Changes. Submitted By Company Date Submitted Gifford Jung

CCA Terms Glossary. Valley Clean Energy Alliance. i CCA Terms Glossary

Two Settlement PJM /06/2016

New Architectures for Interacting with Demand Side Resources in Ancillary Services Markets

Load Granularity Refinements Pricing Analysis Study

Transcription:

Energy Storage and Distributed Energy Resources Phase 3 ( ESDER 3 ) Issue Paper Stakeholder Conference Call October 12, 2017 3:00 p.m. 5:00 p.m. (Pacific Time)

Agenda Time Item Speaker 3:00-3:10 Stakeholder Process and Schedule Kristina Osborne 3:10-3:15 Introductions 3:15-3:30 Background and Scope 3:30-4:00 Potential Scope for Demand Response 4:00-4:20 Potential Scope for Multiple-Use Applications 4:20-4:50 Potential Scope for Non-Generator Resource Eric Kim 4:50-5:00 Next Steps Kristina Osborne Page 2

STAKEHOLDER PROCESS Page 3

ISO Policy Initiative Stakeholder Process POLICY AND PLAN DEVELOPMENT Issue Paper Straw Proposal Draft Final Proposal Board Stakeholder Input We are here Page 4

Background/Scope Page 6

ESDER s goal is to lower barriers and enhance the ability of storage and DER to participate in the ISO market ESDER Phase 1 was completed in 2016 Introduced a new baseline methodology for meter generator output and developed statistical sampling Improved accuracy of SOC for day-ahead optimization and allowed an option for SOC self-management ESDER Phase 2 was approved by ISO Board in July 2017 Planned implementation for spring 2017 New baseline methodologies, changes to net benefits test, and tariff clarification of station power definition Page 6

Below are the potential scope items that were proposed in the Issue Paper Demand Response 1. Demand response modeling limitations 2. Weather-sensitive demand response 3. Resource design constraints 4. Demand response aggregation rules 5. RDRR economic buy-back of day-ahead awards 6. Recognition of behind the meter EVSE load curtailment 7. Load consumption and regulation 8. Load shift product Multiple-Use Application 1. 24x7 CAISO participation requirement for DERs 2. Wholesale market participation model for a micro-grid Non-Generator Resource 1. Reflecting costs and NGR use limitations 2. Managing SOC and throughput limitations for MUA Page 7

POTENTIAL SCOPE FOR DEMAND RESPONSE Page 9

1. Demand response modeling limitations Commitment costs and the impact of a 0 MW Pmin DR resource operators have identified the inability to set use limitations and appropriately define commitment costs DR resources are being committed in the RUC and are susceptible to infeasible real time 5-minute dispatches Minimum and maximum run-time constraints The existing minimum run-time constraint may not effectively utilize PDR/RDRR operational characteristics when its Pmin is equal to 0 MW Stakeholders have requested the utilization of a maximum run-time constraint Page 9

2. Weather-sensitive demand response Weather-sensitive PDR/RDRR cannot deliver a fixed resource adequacy qualifying capacity amount since its capability depends on weather conditions The ISO believes that this issue requires vetting at the CPUC/LRA because the resource adequacy qualifying capacity rules are established by the LRA. Page 10

3. Resource design constraints Currently, PDR/RDRR design requires that aggregations must be located under a single load serving entity (LSE), represented by one demand response provider (DRP), and within a single sub-lap Stakeholders have expressed difficulty in meeting or maintaining the 100 kw minimum participation requirement ISO and stakeholders can discuss removal of the default load adjustment to address this concern Page 11

4. Demand response aggregation rules The current Default Load Adjustment (DLA) settlement mechanism influences the requirement for PDR/RDRR aggregations to be under a single LSE. The ISO is willing to explore modifying or removing the DLA rule to allow for multiple LSEs to exist for one PDR. Page 12

5. RDRR economic buy-back of day-ahead awards Stakeholders have suggested the possibility of RDRR to buy-back their day-ahead awards in the real time market RDRR was designed to ensure that all reliability-triggered MWs that qualify for RA would be available to the CAISO in real-time The CAISO does not plan to consider this item for ESDER 3. Page 13

6. Recognition of behind the meter Electric Vehicle Supply Equipment load curtailment ESDER 1 implementation included the meter generator output (MGO) performance measurement Recognized a sub-metered storage devise s contribution to a facility s overall load curtailment during a CAISO dispatch event Stakeholders have expressed the need to extend the MGO concept to the sub-metered EVSE Would provide an option for EVSE market participation independent of its host customer Page 14

7. Load consumption and regulation The concept of load consumption was introduced in the ESDER 2 initiative. A stakeholder led working group had a general consensus on load consumption capability during periods of oversupply. The CAISO stated in ESDER 2 that more work was needed to develop a load consumption product. Page 15

The ISO will consider the load shift product as inscope for ESDER 3. The load shift product will enhance the PDR model to allow for broad participation by DR resources to provide grid services during oversupply conditions. The focus of the load shift product will be to capture excess supply and consume that energy for productive purposes at a later time. Enable the provision of both load curtailment and shift services yet maintain prohibition on injections into the grid Page 16

POTENTIAL SCOPE FOR MULTIPLE-USE APPLICATIONS Page 9

Multiple-use applications are when DER provide services and receive compensation from more than one entity. Since early 2016, the ISO has collaborated with the CPUC staff in its Energy Storage Proceeding Track 2. A report was released on May 18, 2017 and a workshop was held on June 2, 2017. The following MUA topics are issues that have emerged during the collaborative effort and will be considered for ESDER 3. Page 18

Non-24x7 ISO participation requirements for DERs Currently, DERs utilizing the NGR model are settled 24x7 as a wholesale market resource NGRs are subject to financial settlement for its consumption or production in each interval Regardless of market award or a dispatch Stakeholders desire the ability to opt out of ISO settlements in some intervals in order to provide services to other entities. Page 19

Wholesale market participation model for a micro-grid Stakeholders have asked how micro-grids could participate for energy and ancillary services. Several sub-issues were aligned in the issue paper Can a micro-grid aggregate internal facilities and participate under NGR? Can the entire micro-grid participate as an NGR? If the NGR model does not work what other models? How to distinguish between wholesale consumption for ISO grid services versus retail consumption for internal load? The ISO will consider exploring these paths for microgrids. Page 20

POTENTIAL SCOPE FOR NON- GENERATOR RESOURCES Page 9

Reflecting costs and non-generator resource use limitations Current modeling and bidding practices allow resources to be represented in a way that meets the resource s physical limitations Which also include using the ISO Outage Management System for physical outages Stakeholders have expressed the need to have new tools to manage throughput limitations and SOC Page 22

The ISO does not support establishing MWh throughput limitations based on economic factors, including warranties. The ISO is open to discussing ways to define explicit energy storage costs. Some stakeholders suggested something similar to Material Maintenance Adders or Variable O & M charges. The ISO is open to considering a use-limited status for NGRs. As long as the use-limitation is consistent with those of other generation resources and complies with the definition set by the Commitment Cost Enhancements initiative. Page 23

Market mechanisms for managing SOC and throughput limitations for MUA In the possible scenario that an NGR is given the ability to provide services outside of the ISO market, stakeholders want better tools for the visibility and control of the resource s SOC at the end of an ISO dispatch. Stakeholders have suggested three potential solutions to improve SOC management. Page 24

Suggested SOC management proposals 1. Real-time optimization and dispatch based on SOC Stakeholders want a high degree of certainty on its resource between the bid and market dispatch 2. Multi-segment ancillary service bids Stakeholders want to submit multi-segment A/S bids to manage their real-time SOC 3. Regulation bidding for SOC management Evaluate compensation of fast ramping resource utilization Page 25

NEXT STEPS Page 42

Next Steps Milestone Date Post issue paper September 29, 2017 Stakeholder call October 12, 2017 Stakeholder comments due October 18, 2017 Stakeholder workshop - Issue Paper November 6, 2017 Stakeholder comments due Nov 6 workshop discussion and presentations November 13, 2017 Written stakeholder comments on the issue paper are due by COB October 18 to InitiativeComments@caiso.com. Materials related to the ESDER Phase 3 initiative are available on the ISO website at http://www.caiso.com/informed/pages/stakeholderprocesses/energystora ge_distributedenergyresources.aspx Slide 27

Acronyms Page 42

Acronyms 1. DER Distributed Energy Resource 2. PDR Proxy Demand Resource 3. RDRR Reliability Demand Response Resource 4. DRP Demand Response Provider 5. EVSE Electric Vehicle Supply Equipment 6. NGR Non-Generator Resource 7. SOC State of Charge 8. MUA Multiple-Use Application 9. MGO Meter Generator Output 10. RUC Residual Unit Commitment 11. LRA Local Regulatory Authority 12. LSE Load Serving Entity 13. DLA Default Load Adjustment 14. A/S Ancillary Service Page 29