Storage as a Transmission Asset:

Similar documents
Review TAC Structure Revised Straw Proposal Stakeholder Meeting

Business Practice Manual for The Transmission Planning Process

Generator Interconnection Driven Network Upgrade Cost Recovery. Draft Final Proposal

Day Ahead Market Enhancements: Issue Paper/Straw Proposal

Briefing on 2018 Policy Initiatives Roadmap and Annual Plan

Review Transmission Access Charge Structure. Straw Proposal

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

ISO New England - ISO New England Inc. Transmission, Markets and Services Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

The following members of the Market Surveillance Committee were in attendance: BRIEFING ON REACTIVE POWER REQUIREMENTS AND FINANCIAL COMPENSATION

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

For Bandon Utilities Commission

Generator Interconnection Procedures Overview

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

Load Serving Entity Definition Refinement Draft Final Proposal

Cluster Study Process

Generator Contingency & RAS Modeling

SPP at a Glance. Located in Little Rock. Approximately 600 employees

2017 Stakeholder Initiatives Catalog

Load Shift Working Group.

Electric Price Outlook April 13, 2017

PG&E s General Comments on Demand Response Vision Update. January 11, 2008

Business Practice Manual for the Transmission Planning Process

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Open Access Transmission Tariff ATTACHMENT K

The Expanding Role of Energy Storage in the Regional Power System

Power to Gas: Hydrogen Enabled Storage & Grid Stabilization

Demand Response. Overview. Recommendations

Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting

Congestion and Marginal Losses

2016 Fall Reliability Conference MRO

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Regional Planning Process Task Force Meeting Teleconference - Toll-free call-in number Passcode:

Electric Forward Market Report

APPLICATION INFORMATION: 1. All five sections of the application must be completed.

Update on Supply Chain Risk Management [SCRM] Standard

Tertiary reserve: 15 min 1 h

Temporary Shutdown of Resource Operations. Straw Proposal

COURSE LISTING. Courses Listed. with SAP Ariba SAP Ariba Procurement. 4 February 2018 (03:51 GMT)

State of the Ar t. May Utility Wind Integration Group. American Public Power Association. Edison Electric Institute

Manitoba Hydro - Power Plants and SWOT Analysis, 2011 Update

Value of Energy Storage in Utility Applications. Ben Kaun Sr. Project Engineer SVLG Energy Committee Meeting November 21, 2013

Regional Expansion SB 350 Implementation Timeline Special Study Portfolios

ATTACHMENT K TRANSMISSION PLANNING PROCESS

Service Level Agreement Policy. Table of Contents

Fundamentals of Transmission Operations

Water & Energy Consulting Lon W. House, Ph.D.

DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890

QUICK START GUIDE. SQF Implementation. for.

Final 2014 Flexible Capacity Needs Assessment

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager

Resource Adequacy Availability Incentive Mechanism Modification White Paper

Imperial County Transmission Consultation Current Resource Deliverability Capabilities from Imperial Valley

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

Public Benefit Programs: Energy Efficiency and Renewable Energy in Deregulated Energy Markets

Draft Whitepaper to Platte River Board of Directors

PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016

Modeling the Restructured Illinois Electricity Market as a Complex Adaptive System

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring

Pumped hydro Storage Plants

Review Transmission Access Charge Structure. Issue Paper

Final Flexible Capacity Needs Assessment for 2018

Business Practice Manual for Reliability Requirements. Version 34

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources

1. Introduction Background Purpose Scope of the Tariff Structure Statement... 3

Issue Paper. Direct Participation of Demand Response Resources in CAISO Electricity Markets. December 22, CAISO JEP / BDC/ JDG 12/22/08, page 1

Energy Storage and Distributed Energy Resources Phase 3

The California ISO Transmission Economic Assessment Methodology

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US

ATTACHMENT P. Transmission Planning Process

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

California s Energy Storage Mandate

The New York Independent System Operator s Market Clearing Price Auction Is Too Expensive for New York

Comments of National Grid to the New England States Committee on Electricity on the Coordinated Competitive Renewable Power Procurement Process

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

La regulación del incierto futuro de los sistemas eléctricos

Western New York Public Policy Transmission Planning Report. A Report by the New York Independent System Operator. Final Report

RENEWABLE ENERGY INTEGRATION IN TAMILNADU

X Accept as requested X Change to Existing Practice Accept as modified below Decline

Electrification and its Implications for the California Electricity System

COURSE LISTING. Courses Listed. with SAP ERP. 3 January 2018 (00:08 GMT) SCM600 - Business Processes in Sales and Distribution

Comments of Northern California Power Agency CAISO Load Granularity Refinements Issue Paper. September 20, 2010

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

Cape Town water outlook 2018

Regional Habitat Indicators Project. Workshop #1. Nov 9, 2016

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments

BUSINESS PRACTICE MANUAL CHANGE MANAGEMENT CAISO RESPONSE TO APPEALS

The Virtues of A Virtual RTO

EAGLE MOUNTAIN Hydro Electric Pumped Storage Project

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. Proceeding on Motion of the Commission Regarding a Retail Renewable Portfolio Standard

Transmission Expansion and Interconnection Manual. June 2017

Demand Response Programs. Donnie Clary CoServ President/CEO

89m. 15% Temperature Control revenue 40% Why choose Aggreko?

OVERVIEW OF BC HYDRO S ENERGY PROCUREMENT PRACTICES

Energy Imbalance Market Overview

Emissions Trading in China Progress on the Path towards a Unified National System

Backbone Transportation Service

Transcription:

Storage as a Transmission Asset: Enabling transmission-connected storage assets providing regulated cost-of-service-based transmission service to also access other market revenue streams Issue Paper Karl Meeusen, Ph.D. Stakeholder Call April 6, 2018

Storage as a Transmission Asset Stakeholder Call Agenda 4/6/2018 Time Topic Presenter 9:00 9:10 Introduction James Bishara 9:10 9:25 Background Bill Weaver 9:25 10:00 Scope of policy examination Neil Millar 10:00 11:30 Cost recovery mechanisms and Market participation rules and limitations Karl Meeusen 11:30 11:45 Allocation to high or low voltage Karl Meeusen 11:45 12:00 Next Steps James Bishara

Stakeholder Process POLICY AND PLAN DEVELOPMENT Issue Paper Straw Proposal Draft Final Proposal Board We are here Stakeholder Input Page 3

Stakeholder Engagement Plan Date Mar 30 Apr 6 Apr 20 May 14 May 22 Jun 5 Jun 21 Jul 9 Aug 14 Aug 21 Sep 4 Sep 24 Oct 4 Oct 15 Nov 14-15 Milestone Issue paper Stakeholder call on issue paper Stakeholder comments on issue paper due Straw proposal Hold stakeholder meeting on Straw proposal Stakeholder comments on Straw proposal due Working group meeting Stakeholder comments on working group meeting due Revised straw proposal Hold stakeholder meeting on revised straw proposal Stakeholder comments on revised straw proposal due Draft final proposal Hold stakeholder meeting on draft final proposal Stakeholder comments due Present proposal to ISO Board Page 4

BACKGROUND

The ISO has studied a number of electric storage projects as potential reliability solutions The Transmission Planning Process (TPP) Provides a comprehensive evaluation of the ISO transmission grid to address grid reliability requirements, Identifies upgrades needed to successfully meet California s policy goals, and Explores projects that can bring economic benefits to consumers. The ISO does not approve non-transmission alternatives in its existing TPP; however: The ISO provides opportunities for non-transmission resources, such as storage, to serve as the preferred solution, and Works to support regulatory approvals for those projects if the TPP identifies them as the preferred alternative solution Page 6

The ISO has considered proposals where storage provides cost-of-service based transmission services Over the past several years, the ISO has studied 27 battery storage proposals, and One pumped hydro storage proposal as potential transmission assets. To date, only two proposals have resulted in storage projects moving forward Both in the 2017-2018 Transmission Plan The ISO s experience to date is electric storage has best fit as a market resources providing local capacity resource rather than as a transmission asset Page 7

Storage facilities providing transmission and market services introduce unique challenges that will be addressed in this stakeholder initiative How to treat and manage a hybrid resource, and the ISO s interpretation of previous FERC rulings, dissuaded the ISO from pursuing the concept further Nevada Hydro (2008) Western Grid (2010) ISO will revisit this issue given FERC s Policy Statement regarding the use of electric storage resources for multiple services when receiving cost-based rate recovery Page 8

In its policy statement, FERC clarified several points regarding energy storage providing transmission and market services 1. Providing services at both cost- and market-based rates is permissible as a matter of policy, and 2. FERC provides guidance on some of the details and allows entities to address issues through stakeholder processes and in filings before the Commission FERC states a resource s participation likely would be subject to the following principles: Must be cost competitive with transmission, Must avoid double recovery for providing the same service, Cannot suppress market bids, and Cannot jeopardize ISO/RTO independence Page 9

SCOPE OF POLICY EXAMINATION

If storage is selected for cost-of-service based transmission service, how can that resource also provide market services to reduce costs to end use consumers? Transmission-connected storage only Transmission connected resources are resources that are connected to the ISO controlled grid. This includes connections to both regional (e.g. greater than 200 kv) and local (e.g. lower than 200 kv) ISO controlled grid. Storage resources identified as needed to provide reliability-based transmission services Although a resource may be eligible to access market-based revenue streams, the ISO must determine that the resource is needed to address a reliability need as determined in the ISO s Transmission Planning Process. Page 11

The following issues are outside the scope of this initiative: Storage resources procured or contracted for reasons beyond meeting a reliability need identified by the ISO in the TPP The TPP evaluation methodologies The framework for competitive solicitation and the applicability of the ISO s current competitive solicitation framework Cost allocation of the cost-based revenue requirements for rate-based assets Resource adequacy value as the storage is already part of the determination of local capacity needs Page 12

COST RECOVERY MECHANISM

Transmission asset have traditionally be been fully guaranteed and recovered through the ISO s TAC The lines between a transmission asset and generating asset are clearly defined Page 14

If a cost-of-service based resource providing transmission service is also accessing market revenues, the following need to be addressed: 1. The potential for combined cost-based and market-based rate recovery to result in double recovery of costs by the electric storage resource owner or operator to the detriment of the ratepayer; 2. The potential for cost recovery through cost-based rates to inappropriately suppress competitive prices in the wholesale electric markets to the detriment of other competitors who do not receive such cost-based recovery; and 3. The level of ISO control over the operation of an electric storage resource could jeopardize its independence as the market operator. Page 15

The ISO offers two alternative cost recovery mechanisms for discussion as part of this issue paper The ISO is exploring framework and requirements - and allowable mechanisms - for storage resources to access market revenues Market services must not conflict with the fundamental reliability purpose for which the resource was selected in the TPP Page 16

The ISO offers two alternative cost recovery mechanisms for discussion as part of this issue paper The following alternative mechanisms are set out for discussion purposes: 1. Asset in PTO s TAC rate base, and 2. Contractual provision of cost-based transmission service without becoming a PTO Under both options, the ISO would treat the storage resource like other transmission assets i.e. Resource would be under ISO operational control ISO will need to develop bidding rules that ensure there are no negative consequences to the ISO s markets Page 17

For SATA resources under the PTO model, the ISO is considering two options that rely on maintaining cost recovery through TAC Specifically, the ISO is exploring the following options: Option (a): Wholly in rate base Option (b): Partially in rate base Page 18

Option (a) ensures that a resource s TRR is covered through TAC Any revenue received from market services would be treated as a revenue offset Reduces the revenues otherwise required through TAC Require additional consideration regarding how and when SATA resources are either permitted or required to participate in ISO markets Page 19

Option (b) ensures that a portion resource s TRR is covered through TAC, with the remainder recovered through market revenues Guarantees less of the TRR through TAC ISO market revenues would not be credited against the TAC recovery Project sponsor accepts both upside and downside risk of recovering a portion of its costs (and return) from market services Regulated Transmission Asset Total Cost recovery Generation Resource Total Cost Recovery TAC Energy Market Revenues Guaranteed cost recovery Page 20

Option (b) creates numerous complexities and risks that must be addressed Current transmission planning evaluation method: 1. ISO first approves the storage resource as the preferred solution, 2. Assign the project to an incumbent PTO or award the project through a competitive solicitation process 3. Evaluate projects to determine a) Does the project address the identified need, and b) What is the cost of the project compared to other alternatives Option (b) adds complexities in assessing resources participating in competitive solicitations and assessing financial risks Page 21

The ISO planning decision making process considers inputs, comments, and proposals in making transmission planning decisions If Option (b) becomes viable, the ISO may have to consider the various applicants ability to manage and access market-based revenues ISO planning process currently assumes no market revenue offsetting the reasonable cost of the storage, but other options may need to be considered: a heavily discounted assumption, or some other assumption The final determination regarding the correct assumptions will be addressed in the TPP process Page 22

Other issues also need to be addressed, including: Notification time-lines Schedules specifying when the ISO would notify a resource that it is not needed for reliability and is permitted to participate in other markets; Capability duration needs Specifications regarding how long the resource could participate in the market before it would have to return to a set point required to provide reliability service; and Energy and/or cycle limitations necessary to maintain the resource s life-cycle Ensures market participation does not reduce the useful life cycle of the resources, which would result in additional replacement costs to maintain reliability Page 23

ALLOCATION TO HIGH OR LOW VOLTAGE

The ISO plans to maintain the current practice of allocating costs to high or low voltage TAC based on the point of interconnection Transmission connected resources are resources that are connected to the ISO controlled grid Regional resources greater than 200 kv and Local resources lower than 200 kv Page 25

The ISO plans to maintain the current practice of allocating costs to high or low voltage TAC based on the point of interconnection SATA resource may be connected to the transmission system at a level that differs from the transmission issue it has been identified to resolve For example, the ISO may identify a Regional need, but identify a SATA resource connecting at a Local level as the best solution The ISO plans to allocate to high or low voltage TAC based on point of interconnection Page 26

Next steps Stakeholder written comments due April 20, 2018 Submit to initiativecomments@caiso.com Comments template posted by COB April 6, 2018 Straw proposal posted May 14, 2018 Page 27

THANK YOU Stay connected @California_ISO Download ISO Today mobile app Sign up for the Daily Briefing at www.caiso.com Page 28