Informational Meeting- March 31, Boxelder B-2/B-3 Watershed Planning Study

Similar documents
Informational Meeting- July 21, Boxelder B-2/B-3 Watershed Planning Study

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

V. DRAINAGE IMPROVEMENTS

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update

Prepared for Urban Drainage and Flood Control District

Appendix J Hydrology and Hydraulics

III. INVENTORY OF EXISTING FACILITIES

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

Looking at Dam Safety from a Resiliency Perspective. February 23, 2017

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Table of Contents. 5-5 Release Rates Year Allowable Release Rate WQCV Release Rate EURV Release Rate...

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Chapter 12 Storage. Contents. Overview... 1

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

DAM SAFETY PRESENTATION REGULATORY REQUIREMENTS FOR DAM ENGINEERING ASSESSMENTS IN NEW YORK Allan Estivalet, PE

Carbon Creek Channel (OCFCD Facility No. B01) from upstream Intersection of Western/Orange to upstream Beach Boulevard.

Dam Safety & Planning: Examples of Collaboration and Lessons Learned

CHOLLA POWER PLANT BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_Inflowflood_003_

Project Drainage Report

Volume 2, Chapter 10 - Storage

San Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis

Presentation Overview

Developments in the Safety and Security of Mining Industry Dams

CHOLLA POWER PLANT FLY ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_InflowFlood_002_

Fullerton Creek Channel (OCFCD Facility No. A03) from downstream Beach Blvd. including undercrossing to downstream I-5 Freeway.

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

Inflow Design Flood Control System Plan for Louisa Generating Station CCR Impoundment. MidAmerican Energy Company

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

HYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006

DAM AND CANAL SAFETY GUIDELINES

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

New Castle County, DE. Floodplain Regulations

Visual Inspection Checklist

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project.

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Freight Street Development Strategy

Constructed Wetland Pond T-8

TVA Colbert Fossil Facility Ash Disposal Pond 4

CHAPTER 7. San Dieguito River Flooding Adaptation

Stantec Consulting Services Inc Lebanon Road, Cincinnati, OH 45241

Abstract. Introduction. Table 1. Millsite Dam Critical Elevations Feature Dam Crest Spillway Existing Elevation (NAVD88) 6222.

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Chapter 11 Culverts and Bridges

Mountain States Chapter International Erosion Control Association Conference

Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map

Classification and Inflow Design Flood Criteria

Uncertainty in Hydrologic Modelling for PMF Estimation

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

Northland Regional Council. Awanui Flood Scheme Preliminary Design

Does Water Resources Management in the Snake River Basin Matter for the Lower Columbia River? Or Is the Snake River Part of Another Watershed?

Hydrologic Calibration:

Hydrology and Flooding

CCR Certification: Initial Inflow Design Flood Control System Plan for the

Dam Safety Program. Managing Risk to Support the Core Mission. Karen Weghorst, P.E. Manager, Flood Hydrology and Consequences Group

Fargo-Moorhead Metropolitan Area Flood Risk Management Project

Folsom Dam Water Control Manual Update

INFLOW DESIGN FLOOD CONTROL PLAN

Mill Pond Dam Modifications Feasibility Study

Stormwater Local Design Manual For Houston County, Georgia

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

CCR Rule Report: Initial Inflow Design Flood Control System Plan For Ash Basin B At Brayton Point Power Station

ENVIRONMENTAL ENGINEERING LAND SURVEYING

Filter Tube Barriers (Instream)

Water Balance and Regulation Alternative Analysis for Kajakai Reservoir using HEC-ResSim

MODEL Stormwater Local Design Manual. City of Centerville

PAPERWORK REDUCTION ACT A. GENERAL

S.R. 4031, SECTION FVR OVER BEAVER RUN SEGMENT 0170, OFFSET 6093 EAST NANTMEAL TOWNSHIP, CHESTER CO. ENGINEERING DISTRICT 6-0

June 22, Francis E. Borcalli, P.E.

This material was downloaded from the website Please contact the PhillyH2O webmaster for more information about this material.

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds

Urban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology. Presented by:

SUMMARY OF HYDROLOGICAL SPECIALIST STUDY

Storm Water & Drainage Projects 2011 Program Update

Constructed Wetland Channel T-9

Will be modified map from GIS 6/16 EOD

2A Stormwater Regulations and Permitting A. Iowa Drainage Law and Resources 1 B. Regulated Activities 1

PRESENTATION FOR THE POTENTIAL ADDITION OF SPECIAL FLOOD HAZARD AREAS

Appendix VI: Illustrative example

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

STATE OF COLORADO DEPARTMENT OF NATURAL RESOURCES DIVISION OF WATER RESOURCES GUIDELINES FOR DAM BREACH ANALYSIS

Information for File # PRH

Temporary Watercourse Crossing: Culverts

Farmington Dam Repurpose Project

IAFSM 2010 Annual Conference. City of Rockford Keith Creek Greenway Flood Mitigation Project

2 Hydrology Studies. 2.1 Introduction

SECTION 7.0 PROJECT FEASIBILITY, ENGINEER S RECOMMENDATION AND DESIGN ISSUES NEEDING RESOLUTION

Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals

Transcription:

Informational Meeting- March 31, 2016 Boxelder B-2/B-3 Watershed Planning Study

Agenda Introductions Work Completed to Date Phase 1 Evaluations Alternatives Evaluations Economic Evaluations Draft Watershed Plan Development Investigation and Analysis Report Environmental Evaluation (EE) Questions/Discussions

Introductions NPIC Golder NRCS Guests sign-in sheet April 5, 2016 3

Dam Locations and Watershed April 5, 2016 4

Watershed Dam B-2 April 5, 2016 5

Watershed Dam B-3 April 5, 2016 6

FEMA Regulatory Floodplains April 5, 2016 7

Impact of New Hazard Classification The new hazard classification for both B-2 and B-3 has been raised from significant to high based on downstream development Colorado Dam Safety Requirements: Inflow Design Flood (IDF) Significant Hazard: 50% PMP Event High Hazard: 90% PMP Event NRCS Dam Safety Requirements: Inflow Design Flood (IDF) Full PMF Event Current spillways do not meet capacity requirements April 5, 2016 8

Regulatory Floodplain Benefits Dam Drainage Area (sq mi) Storage at Crest (acft) Q 100 without Dam (cfs) Q 100 with Dam (cfs) Sunny Day Breach Discharge (cfs) Residences in Breach Zone B-2 109 12,000 17,500 (20,080) 295 83,900 >1,000 B-3 61 6,410 4,950 (5,850) 175 54,500 >1,000 FEMA FIS: Boxelder Creek Upstream of I-25 near Wellington, Q 100 = 1,170 cfs Coal Creek at Town of Wellington, Q 100 = 830 cfs April 5, 2016 9

Dam Breach Inundation Maps April 5, 2016 10

Purpose & Need Dams were originally constructed to protect agricultural land from flooding Dams now protect developed portions within Larimer County, Wellington, Fort Collins and Timnath Hazard classification has been raised by the Colorado DWR from Significant to High (spillway capacity requirements have changed) Desire to maintain flood control benefits Develop alternatives to meet all current Colorado DWR and NRCS dam safety requirements Minimize environmental, socio-economic and cultural resource impacts and damages April 5, 2016 11

Watershed Planning Study Components Phase 1: Collection and Analysis of Information (May-Aug, 2015) Phase 2: Formulation and Evaluation of Alternatives (Sept-Mar, 2015) Phase 3: Watershed Plan Supplement Preparation (Apr-Jul, 2016) April 5, 2016 12

Work Completed to Date Reviewed Previous Work Developed Purpose and Need Statement Developed Work Plan Developed Public Participation Plan Performed environmental and cultural resources field surveys Completed preliminary hydrologic and Incremental Damage Assessment (IDA) evaluations Completed embankment stability evaluations Completed sediment deposition evaluations Developed alternatives for modifications Commenced economic evaluations Progressed Environmental Evaluation (EE) spreadsheets April 5, 2016 13

Public Participation Informational Meetings Public Meetings (3 scheduled) Web Page: http://npicwater.com April 5, 2016 14

Field Assessments Summary Conducted environmental and cultural resources field surveys Environment/Wildlife: Raptor nests Cultural Resources: Archaelogic sites identified in study area Irrigation turnout may require special consideration Wetlands: Wetlands delineation prior to construction 404 Nationwide permit Compensatory wetlands for disturbed areas No significant findings that would limit construction of modifications April 5, 2016 15

Geotechnical Evaluations Summary Large amount of subsurface data exists for B-2 and B-3 collected as part of original design Embankments and structures appear to be in good condition Geotechnical stability evaluations indicate no issues with embankment stability in their current condition April 5, 2016 16

Condition Assessment Summary Existing facilities are in relatively good condition requiring no major repairs Sediment deposition within the reservoirs has been minimal April 5, 2016 17

Hydrologic Evaluations Summary Incorporated USBR methodology consistent with State of Colorado guidelines Infiltration/soil based on GIS datasets USBR Unit Hydrograph methodology Evaluated General and Local (Thunderstorm) events Areal reduction for Local Storm event PMF reduced by 25-40% (General Storm) and 70-80% (Local Storm) from previous NRCS evaluations General Storm produces highest peak discharges Dams would overtop under the greater than 25% (B-2) and 40% (B-3) PMF events April 5, 2016 18

Determination of Inflow Design Flood (IDF) Based on current hazard classification, dam needs to safely convey 90-100 percent of the Probable Maximum Flood (PMF) event Both NRCS and State of Colorado criteria allow for determining a different design flood based on evaluating incremental damages Differences in peak discharges between no dam and dam breach scenarios used to screen for appropriate design flood Evaluated increase in flood depths and velocities associated with a dam failure versus no dam scenario for various ratios of the PMF event: Incremental depth increases are less than 2 feet The product of the incremental depth and average cross section velocity is less than 7 April 5, 2016 19

Preliminary Incremental Damage Assessment (IDA) Hydrologic model used to estimate ratios of the PMF for cases 1) with dam, 2) without the dam in place, and 3) assuming an overtopping dam failure Boxelder B-2 Boxelder B-3 PMP 90% PMP 75% PMP 50% PMP 40% PMP 30% PMP With Dam (Peak Flow, cfs) (El. Ft AMSL) Overtop Depth (feet) Without Dam (Peak Flow, cfs) (El. Ft AMSL) Dam Breach (Peak Flow, cfs) (El. Ft AMSL) With Dam (Peak Flow, cfs) (El. Ft AMSL) Overtop Depth (feet) Without Dam (Peak Flow, cfs) (El. Ft AMSL) Dam Breach (Peak Flow, cfs) (El. Ft AMSL) 156,545 157,193 231,444 84,910 85,238 136,769 5,577.8 3.4 N/A 5,576.1 5,492.2 3.2 N/A 5,490.5 140,845 141,474 230,219 76,395 76,714 135,059 5,577.5 3.1 N/A 5,576.1 5,491.8 2.8 N/A 5,490.5 117,293 117,895 225,476 63,616 63,929 129,262 5,577.1 2.7 N/A 5,576.2 5,491.3 2.3 N/A 5,490.4 77,926 78,596 206,477 42,176 42,619 113,467 5,576.3 1.9 N/A 5,576.0 5,490.3 1.3 N/A 5,490.1 61,483 62,877 193,600 32,898 34,095 N/A 5,575.9 1.5 N/A 5,575.8 5,489.7 0.7 N/A 5,489.7 41,714 47,158 174,999 22,589 25,571 N/A 5,575.4 1.0 N/A 5,575.4 5,488.4 0.0 N/A 5,488.4 April 5, 2016 20

50% General Storm Hydrographs April 5, 2016 21

75% General Storm Hydrographs April 5, 2016 22

B2 Incremental Damage Assessment April 5, 2016 23

B-3 Incremental Damage Assessment April 5, 2016 24

Incremental Damage Assessment Summary Hydraulic model evaluated for both the no dam and dam breach flood scenarios for various ratios of the PMF event Comparison of increase in depth and increase in depth-velocity product for the no dam and dam breach scenarios Event B-2 B-3 100-year Dam does not overtop Dam does not overtop 30-percent PMF Dam overtops; failure unlikely Dam does not overtop 40-percent PMF Dam overtops; incremental depth greater than 2 ; depth-velocity product greater than 7 50-percent PMF Dam overtops; incremental depth greater than 2 ; depth-velocity product greater than 7 75-percent PMF Dam overtops; incremental depth greater than 2 ; depth-velocity product greater than 7 in some areas Dam overtops; failure unlikely Dam overtops; incremental depth greater than 2 ; depthvelocity product greater than 7 in some areas Dam overtops; incremental depth less than 2 ; depthvelocity product less than 7 90-percent PMF Full PMF Dam overtops; incremental depth less than 2 ; depthvelocity product less than 7 Dam overtops; incremental depth less than 2 ; depthvelocity product less than 7 Dam overtops; incremental depth less than 2 ; depthvelocity product less than 7 Dam overtops; incremental depth less than 2 ; depthvelocity product less than 7 April 5, 2016 25

Recommended Inflow Design Flood B2: Full PMF Event B3: 90-percent PMF Event April 5, 2016 26

Preliminary Alternatives Future Without Project (No Action Alternative) Decommissioning Auxiliary Spillway Modifications Modify crest (ogee, labyrinth) Lower crest; install gates Widening/lowering of existing spillway Embankment Crest Raise Overtopping Protection Roller Compacted Concrete (RCC) Articulated Concrete Blocks (ACB) Geosynthetics/Turf Reinforcement Mats (TRM) Secondary Emergency Spillway New Secondary Spillway Fuseplugs in Embankment April 5, 2016 27

Future Without Project (No Action) Assumes no Federal or outside funding for modifications Breaching of embankment would likely be required by Colorado DWR Embankment and hydraulic structures would remain in place April 5, 2016 28

Decommissioning Design breach to meet all NRCS and State requirements Breach would need to be 200 feet wide with 3H:1V side slopes and armoured Demolition of all hydraulic structures and reclamation Re-establishment of stream channel April 5, 2016 29

Auxilllary Spillway Modifications Widening/lowering of spillway Increased spillway hydraulic efficiency Ogee crest structure Labyrinth crest structure Lowering of spillway and installation of fusegates April 5, 2016 30

Embankment Crest Raise Raise embankment crest to increase freeboard and spillway capacity Abutments and upstream development limit height of embankment crest raise Dam B-2 April 5, 2016 31

Overtopping Protection Roller Compacted Concrete (RCC) overtopping protection Alternative overtopping materials Geotextiles Articulated Concrete Blocks (ACB) April 5, 2016 32

Secondary Emergency Spillway Installation of a new secondary spillway on the abutment Installation of a fuseplug within the embankment April 5, 2016 33

Alternatives Considered in Evaluations No Action (Future Without Project) Decommissioning RCC Overtopping Protection TRM Overtopping Protection ACB Overtopping Protection Existing Auxiliary Spillway Widening/Lowering Auxiliary Fuseplug Spillway in Embankment April 5, 2016 34

No Action (Future Without Project)-B2 April 5, 2016 35

No Action (Future Without Project)-B3 April 5, 2016 36

Breaching vs. Decommissioning Breach Alternative Decommissioning Alternative April 5, 2016 37

Overtopping Alternatives April 5, 2016 38

Existing Spillway Widening-B2 April 5, 2016 39

Existing Spillway Modifications-B3 April 5, 2016 40

Auxiliary Fuseplug Spillway-B2 April 5, 2016 41

Auxiliary Fuseplug Spillway-B3 April 5, 2016 42

Estimated Construction Costs 1,2 Alternative B-2 B-3 Future without Project 3 $3.6M $1.6M Decommissioning 3 $3.8M $1.7M RCC Overtopping Protection $27.6M $11.6M TRM Overtopping Protection $15.2M $7.2M ACB Overtopping Protection $28.1M $12.7M Existing Spillway Modifications $8.6M $2.4M Auxiliary Fuseplug Spillway in Embankment $6.1M $2.4M 1. Costs are for planning purposes only and do not include permitting, legal and land acquisition fees. 2. Costs include 25% contingency. 3. Costs do not include additional costs for floodproofing, buyouts, downstream flood protection. Actual costs for implementation would be much greater. April 5, 2016 43

Recommended Alternatives Dam B-2 Future Without Project (No Action) Auxiliary Fuseplug Spillway in Embankment Dam B-3 Future Without Project (No Action) Existing Emergency Spillway Modifications Auxiliary Fuseplug in Embankment April 5, 2016 44

Impacts of Decommissioning Approximately 2,300 structures in downstream floodplain impacted as a result of decommissioning B2 (majority within Town of Wellington) Approximately 1,800 structures in downstream floodplain impacted as a result of decommissioning B3 (majority within Town of Wellington) Downstream structures constructed by the Boxelder Regional Stormwater Authority would not function as designed Several road crossings (including I-25) impacted Currently performing economic evaluations to estimate benefit-cost of the various alternatives Benefit: Reduction in damages of keeping dams in service Large benefit for events up to 100-year frequency event Minimal benefit for very extreme flooding events April 5, 2016 45

Potential Funding Sources Project Sponsors Federal Agencies NRCS - anticipated to fund up to 65% of the eligible project cost not to exceed 100% of construction costs FEMA Grants Stakeholders April 5, 2016 46

Watershed Plan Schedule Preliminary Watershed Plan for Internal Review (end of April, 2016) Draft Watershed Plan for NRCS Review (mid-may, 2016) Public Meeting No. 3 (mid-june, 2016) Final Watershed Plan (late-july, 2016) April 5, 2016 47

Discussion/Questions/Comments April 5, 2016 48