RISK ASSESSMENT AND SAFETY METHOD STATEMENT. for. GROUNDWORK PREPARATION AND LAYING OF YORKSTONE SEGMENTAL CIRCLE (3.6m DIAMETER)

Similar documents
SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

Company s Name: GHI Warehouse Date of Risk Assessment:

A-one+ Supply Chain Standards

METHOD STATEMENT SCREEDING OF FLOOR

ACCIDENT PREVENTION PROGRAM FOR CONTRACT AND CONTRACT-TO-HIRE EMPLOYEES

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES BOSTON SPA VERSION 7 APR09

Trip and slip Hazard policy

Volunteer Health and Safety

Pesticide Safety Program

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES COLINDALE, MICAWBER STREET & WOOLWICH VERSION 9 APR09

Safe Work Procedure for installation of

PROHSP4 SQA Unit Code H8WD 04 Develop and implement effective communication systems for health and safety information

PROGRAM OVERVIEW JOB HAZARD ANALYSIS (JHA) SAFETY PROGRAM REGULATORY STANDARD: 29 CFR

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

Lone Working Policy and Guidance

CONTINENTAL FERRY PORT SITE INDUCTION

FEEDLOT DESIGN AND CONSTRUCTION. 39. Agricultural and veterinary chemical storage. AUTHORS: Orla Keane and Peter Watts

HEALTH & SAFETY POLICY TABLE OF CONTENTS RESPONSIBILITIES

Network Rail Project No: Issue: 002 Date 11/07/2017 Work Package Plan Arena Tunnel LSM773 Prepared by: Start Date: 15/07/17 Finish Date: 23/07/17

Nuclear Power Plant Incidents

Implementing an Effective Personal Protective Equipment (PPE) Programme

Advanced Water Recycling Plant tour. Excursion Management Plan

Policy Work Health and Safety (WHS) RCPA Introduction WHS legislation

HFM Asset Management Contractor Induction Queens Riverside Apartments

CONTRACTOR WHS HAZARD STANDARD TRAFFIC MANAGEMENT EXTERNAL USE ONLY

Personal Protective Equipment (PPE) Safety Program

Level 2 NVQ Certificate in Erection of Precast Concrete (Construction)

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC.

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction)

Safety and Health Office phone , fax GUIDELINES FOR USE OF NUCLEAR MOISTURE/DENSITY GAUGES

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision

Health, Safety & Wellbeing Absolute Rules

Forest School Policy To be reviewed October 2016

EASTLAKE WOODLANDS CONTROLLED ACCESS PATROL POST ORDERS

Guidelines for the safe unloading and storage of Polyolefins in packed form V1 August 2012

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

RISK ASSESSMENT SHEET

Introduction. Module Objective

Health and Safety Toolkit

Safety Program. For Packaging, Manufacturing, Distribution

Pesticide Chemical Safety

Level 2 NVQ Certificate in Wall and Floor Tiling (Construction) Qualification Specification

ERINVALE COUNTRY ESTATE HOME OWNERS' ASSOCIATION

Personal Protective Equipment (PPE)

XYX Company. Safety Program. XYZ Company 100 Main Street Somewhere, NH Implementation Date: August 12, 1901 Revision Date: September 31, 1955

V.2. REFERENCE: G:\Public\OCCUPATIONAL HEALTH & SAFETY\3. INDUCTION\General Site Induction REVIEW DATE: 5/6/2013

SAFETY METHOD STATEMENT

Visitor Risk Assessment Report. Completed: February 2006 Updated: Sept 2007, March 2008, August 2012, June 2013

PROHSP7. Develop, implement and review proactive monitoring systems for health and safety. Overview

Corporate Health and Safety Policy July 2012

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

Unit 9 Reinstatement of modular surfaces and concrete footways

Personal Protective Equipment (PPE) Program

Tender Document and Specifications for Council Property Assorted Painting and Decorating between Parks and Recreation and Contractor.

Lone Working Policy Reference DP113

Environmental, Health and Safety Policy for Contractors

RAUPEX SPEED SYSTEM Installation Guide

Dealing with Routine and Non-Routine Waste

RISK ASSESSMENT. HAZARD POTENTIAL 3 x MAJOR 2 SERIOUS 1 SLIGHT. RISK POTENTIAL 3 x HIGH 2 MEDIUM 1 LOW

Using petrol-driven chainsaws

Eurobitume UK. Site Inspection for Delivery of Bitumen

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

The Horse Rangers Association Health & Safety Policy

BEHAVIOUR ON SAFE SITES

SHE 002 Method Statements and Risk Assessments

219 Make sure your own actions reduce risks to health and safety

Adelaide Airport Limited

Evaluation of Occupational Health & Safety Management System

PRO Traffic Management

Turbocharger / TPL-C Original assembly instructions English

PE45 AMAZON MONKEY BARS OWNER'S MANUAL

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT:

METHOD STATEMENT First Fix Joinery

Does this topic relate to the work the crew is doing? If not, choose another topic.

HEALTH AND SAFETY POLICY

Powered Industrial Truck/Forklift Operations Standards and Procedures. Disaster Cycle Services Standards & Procedures DCS SP DMWT

Kingframe Steel Framing System ("SFS") Infill & Oversail - CDM Design Risk Assessment

HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd

STANDARD OPERATIONAL PROCEDURES

Level 2 NVQ Diploma in Roadbuilding and Maintenance (Construction) Pathway 29: Plant Road Sweeping. Qualification Specification

Field Instruction. All Horizon Power workers who work in and around excavations.

Shell Eastern Petroleum. Pte Ltd.

MODULE 14: Off-site Transport and Storage of Healthcare Waste

SAFE SYSTEM OF WORK PLAN (SSWP)

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

COEN GENERAL TEACHING LAB SAFETY SUPPLEMENT FOR INSTRUCTORS & TAs

PERSONAL PROTECTIVE EQUIPMENT SAFETY PROGRAM

Standards of Performance. Mariane Ewbank Chairperson Standards and Customs WG

Dutchess Community College. Personal Protective Equipment (PPE) Program

COSVR69 - SQA Unit Code DY3K 04 Lay sand and cement screeds

Pre-Construction Meeting Minutes

Rail Safety Management Procedure General Engineering and Operational Systems Railway Track Signals - Detonators

St Edward s Church of England Primary School. Work Experience Policy

Rhineland. Site Requirements.

CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11

Subpart C_Roadway Worker Protection

CHAS Assessment Standards

08/2016. n We undertake to use energy as efficiently as possible in terms of both type and quantity.

Part 7 Managing on-road risk A Fleet Managers Guide

Transcription:

RISK ASSESSMENT AND SAFETY METHOD STATEMENT for GROUNDWORK PREPARATION AND LAYING OF YORKSTONE SEGMENTAL CIRCLE (3.6m DIAMETER) at Bourne Abbey Church of England Primary School Abbey Road Bourne Lincolnshire by Volunteer members of The Rotary Club of Bourne St. Peter Bourne Lincolnshire

SUMMARY OF WORK Levelling of made-up ground adjacent to the recently installed wooden outdoor seating area. Applying and compacting a hardcore base and sand blinding the surface area. Mixing sand and cement to lay over prepared surfaces. Laying Yorkstone segmental circle slabs. Grouting circle slabs at a later date when the concrete has cured. Remove all redundant materials from site. Reposition reflective barrier tape around the new Yorkstone area. IDENTIFIED HAZARDS Unauthorised persons in the active working areas risk of third party injury. Handling construction materials personal injury. Working with mechanical plant training and competence. Damage to nearby services. PROGRAMME OF WORK The work will commence on Saturday 16 th May at 8.30 am until 5.00pm latest. There will be a return to site at a date to be agreed for grouting of the Yorkstone slabs. There will be approximately six Rotarian volunteers undertaking the task. Working Site Supervisor for The Rotary Club of Bourne St. Peter will be:- ALAN KAYE Tel: 01778 560 458, Mobile: 07930 663 074 Bourne Abbey School Caretaker contact is: MICHAEL PATEMEN Michael Pateman who lives locally in Bourne will unlock the entrance gates at 8.30am on Saturday 16 th May. He must be contacted on his mobile to return and lock the gates at the end of the working day. During the day, everyone ensure that the gates are kept closed to deter unauthorised entry. MATERIAL SUPPLIER Branch Bros, Cherry Hold Road, Bourne Tel: 01778 426 677 technical advice and additional materials (replacement broken circle slabs if necessary!!) will be available on Saturday until 4.00pm.

Materials will be delivered to the school on Friday 15 th May to include:- Yorkstone stone circle 5 bags cement 1 tonne hardcore 1 tonne sharp sand RISK ASSESSMENT AND SAFETY METHOD STATEMENT The following risk analysis and safe working arrangements have been assessed for this work:- RISK ANALYSIS SEVERITY OF HARM (A) LOW 1 Minor injury or illness MEDIUM 2 Injury or illness causing short term disability HIGH 3 Fatality or major illness causing long term disability LIKELIHOOD OF HARM (B) LOW 1 Very seldom or never occurs MEDIUM 2 Reasonably likely to occur HIGH 3 Certain or near certain to occur RISK FACTOR = ( A x B ) = 1 3 Control or minimise Risk 4 6 Avoid or strictly manage Risk >6 Avoid and seek alternative Risks Associated with the Activity Isolation of the access route and active working areas unauthorised access, personal injury. Risk Analysis Risk Factor = 2 Methods Used and Actions to be Taken to minimise the risks The school will be closed to pupils during our nominated working times. Staff may visit the main school building during the day and we will ensure they or any other unauthorised persons do not enter our active working areas. As there is a long distance from our working areas to the established routes around the school, there will be no need to Heras fence or display warning notices. Branch Bros were visited by me on Wednesday 13 th May and arrangements agreed for safe delivery of materials and liaison

with Caretaker Michael Pateman on Friday 15 th May, a normal school day. Existing services risk of damage and personal injury Risk Factor = 4 There are no known services in the working area but everyone must be vigilant and ensure that any discovered services are not damaged. Portable hand tools and equipment personal injury. Risk Factor = 4 Apart from normal hand tools, there will be a petrol driven Whacker Plate for compacting the hardcore material. The operative that will undertake the mechanical plant work has the necessary skill and experience. Cement and sand will be mixed on a wooden board positioned adjacent to the working area. Water is available from an outside tap near the second gated entrance to site. A hosepipe and bucket transfer will be required due to the length of run from tap to site. Cement mixes will be carried by bucket to the point of use and the Yorkstone circle slabs will be installed section by section. Manual handling of construction materials strain injury. Risk Factor = 4 Full allowance will be made that some volunteer workers are not used to regularly handling building materials. The weight of materials to be used in this work however are readily handled by one or two operatives, and correct lifting and handling techniques will be encouraged by the Site Supervisor.

Handling soils skin contact, health issues. Personal Protective Equipment Risk Factor = 4 All operatives will wear suitable protective equipment including gloves, goggles (when operating mechanical plant) and safety footwear at all times. High levels of personal hygiene will be followed and hands will be washed before handling food and drinks. As the school buildings will be locked during times of our site work, there will be no toilet facilities on site. Toilet and washing facilities in the nearby Co-operative Rainbow store can be used. It is a mandatory requirement on this project that all operatives wear safety footwear and high visibility clothing at all times. In view of the nature of the work, there will be no mandatory requirement for the use of safety helmets that would only be worn where there is a risk of falling objects or impacts to the head. Safety glasses, goggles and gloves will be worm as required when using mechanical tools and handling construction materials. SITE RULES & ARRANGEMENTS 1. Ensure that no unauthorised persons are allowed onto the site or any part where construction work is carried out. 2. A banksman will be used whenever visibility from moving vehicles is restricted. 3. All contractors vehicles and plant are limited to walking speed (5mph). 4. The established routes around the school property are to be kept clear at all times and unobstructed access will be maintained for emergency vehicles to the site and nearby buildings.

5. Toilet and washing facilities are available for use in the nearby Co-operative Rainbow store. 6. Portable hand tools if required during this work will be either battery or 110volt operated. Should 240 volt power tools be used a residual circuit breaker (RCD) will be fitted and trailing leads kept as short as possible. 7. Safety footwear will be worn at all times. 8. Safety helmets to be worn when there is a risk of falling objects or impacts to the head. 9. Other PPE to be worn as directed by the Site Supervisor who has full authority to enforce these arrangements and take any disciplinary action deemed necessary. 10. All materials, waste material, equipment and plant are to be stored within the designated areas agreed by all parties. 11. All contractors vehicles are to be parked in the designated parking areas. 12. There will be no burning of materials on site. 13. Alcoholic drinks and smoking are prohibited on site. 14. Sound producing equipment such as radios or the like are not permitted on the site. The nearest ACCIDENT AND EMERGENCY HOSPITALS are:- Peterborough District Hospital Thorpe Road Peterborough Tel: 01733 874 000 Stamford & Rutland Hospital (9.00am to 5.00pm Ryhall Road weekdays only) Stamford Tel: 01780 764 151 The Site Supervisor will have a first aid kit available on site. HEALTH AND SAFETY PRINCIPLES/OBJECTIVES FOR THE PROJECT We confirm that it is our intention to:-

Take reasonable steps to ensure co-operation between all parties by complying with the requirements and prohibitions imposed by or under the relevant statutory provisions relating to this project. Ensure as far as reasonably practicable that every employee at work in conjunction with the project complies with all the guidelines contained in this method statement/risk assessment. Take reasonable steps to ensure that only authorised persons are allowed into any areas of the working site. Prominently support the school with any relevant project information in our possession that the school should retain for future reference. Alan Kaye For and on behalf of The Rotary Club of Bourne St. Peter 13 th May 2009 Main entrance to school off Abbey

Road leading into the car park to be used by Rotarians. Gate to be closed after entry. Inner pedestrian entrance from car park to playground and site for construction work. Gate to be closed after entry. Branch Bros will deliver materials to hard standing area on playground. Should dry weather permit, delivery vehicle will traverse the grassed area and leave all materials near to the point of use to reduce handling.

View into new development area from rear playground. Location for the Yorkstone segmental circle. Note: Any damage caused to grassed areas or installations within this development area are to be made good.