Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

Similar documents
The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

Integration issues and simulation challenges of high penetration PV

Grid Interconnection Issues for Wind Generation

Technical Requirements for Distributed Generation Connection

DISTRIBUTION SYSTEM PLANNING TUTORIAL. MN Power Systems Conference November 6, 2014

GRID CODE COMPLIANCE TESTING OF RENEWABLES NEW REQUIREMENTS AND TESTING EXPERIENCES

Slide 1. ABB August 23, 2016

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

EE 741. Load Characteristics

Electrification and its Implications for the California Electricity System

SCE Distributed Energy Resource Interconnection Map (DERiM)

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

2017 NEC Changes for Renewable Energy Systems Session one by Christopher LaForge

Integrated Volt/VAR Control

DEMONSTRATIVE PROJECT ON GRID-INTERCONNECTION INTERCONNECTION OF CLUSTERED PHOTOVOLTAIC POWER GENERATION SYSTEMS

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

Western Wind & Solar Integration Studies

Managing the Distributed Solar Fleet: From Interconnection to Fleet Operations

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

8 th Annual Electric Power Industry Conference

Standard TPL Transmission System Planning Performance Requirements

Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation

Attachment B. [Note: The following new definitions inserted after the definition of Regulations ]

A*STAR Funded IEDS Project - Microgrid Energy Management System. by H B GOOI

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Business Impact of Using the Remote Disconnect Switch October, 2013

Reference: Photovoltaic Systems, p. 229

Active Distribution Networks

Conservation Voltage Reduction: What Are the Savings?

Virtual Power Plant Simulation

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)

International ejournals

Renewables Integration and Smart Grid

Public Utility District Number 1 of Snohomish County

Standard PRC-002-NPCC-01 Disturbance Monitoring

Fringe-of-Grid PV Projects - Normanton Solar Farm

Integrated Capacity Analysis Working Group - Long Term Refinement Topics Scoping Document

MAUI SMART GRID PROJECT

Communication and Control for Microgrid Optimal Energy Efficiency

TRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project

Standard Development Timeline

Southern California Edison

MAY 1, Variable Generation Integration Costs

INTERSTATE TRANSMISSION VISION FOR WIND INTEGRATION

4301 Wilson Blvd. Arlington, VA tel:

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Water & Energy Consulting Lon W. House, Ph.D.

Distribution Information Exchange Code

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

Voltage and reactive power regulation by photovoltaics in distribution systems

What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin?

ENABLING EMBEDDED GENERATION

Circuit of the Future: Interoperability and SCE's DER Program

Inspection Guide for PV Systems in One- and Two- Family Dwellings (For Rooftop Photovoltaic Systems meeting the Standard Plan)

Impacts of the Decentralized Wind Energy Resources on the Grid

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation

A Study on Grid Connected PV system

Information Document Protection System Information ID# R

AORC Technical meeting 2014

2014 Integral Analytics, Inc.

Consumer s Guide to Solar Power

Report on Scenario Development and Analysis

69/12KV SUBSTATION DESIGN

Wind Power Grid Interconnection:

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS

Integrating Building Automation Systems with Microgrid Controls. Mingguo Hong, Associate Professor Case Western Reserve University Cleveland, OH

Facility Interconnection Requirements

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

POTOMAC ELECTRIC POWER COMPANY

Impact study of PV integration in Bornholm power system

The Challenges of Integrating Renewable and Distributed Energy Resources what we can learn from smart grid research and demonstrations

Facilities Study. For. XXXXXXXXXXXX Wind Park Interconnection Switching Station

GRID INTEGRATION OF PV

DISTRIBUTION GRID PLANNING CONSIDERING SMART GRID TECHNOLOGIES

Patrick McHugh. Vice President Con Edison

Microgrid Planning and Design MCAS Miramar, US Air Force Academy, and Fort Carson

The Impact of Grid Connected Photovoltaic Generation System to Voltage Rise in Low Voltage Network

XXXXXXXXXXX Solar (XXX) Generation Interconnection

Proposals and Process 2017 National Electrical Code

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

Distribution Network Planning for Mumbai

Micro Hydroelectricity Installer Skills Assessment

GEOS / ENST Problem set #Grid Due: Tues. May 18

Peak Time Demand Management Using Distributed Solar Inverters

Running the Electric Meter Backwards: Real-Life Experience with a Residential Solar Power System

WWSIS - 3: Western Frequency Response and Transient Stability Study

SUBNET IoT to the PI System: A Bridge to Support Business Use Cases

IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 04, 2016 ISSN (online):

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES

LONG ISLAND LONG ISLAND

DISTRIBUTION CODE OF SRI LANKA. Public Utilities Commission of Sri Lanka

TOWN OF NEWPORT SOLAR PROJECT A 2-MEGAWATT DC NET-METERED PV SYSTEM

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

Top Five Reasons to Implement Distributed Bus Protection

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION

Development of A Comprehensive Software Suite for Stability Monitoring and Analysis Based on Synchrophasor Measurement (DOE-OE )

Transcription:

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile Michael Coddington National Renewable Energy Laboratory Golden, Colorado, U.S.A.

DISCLAIMER ISGAN is an initiative of the Clean Energy Ministerial (CEM). It is formally organized as the Implementing Agreement for a Co-operative Programme on Smart Grids (ISGAN), operating under a framework of the International Energy Agency (IEA). The views, findings and opinions expressed herein do not necessarily state or reflect those of any of ISGAN s participants, any of their sponsoring governments or organizations, the CEM, the IEA Secretariat, or any of the IEA s member countries. No warranty is expressed or implied, no legal liability or responsibility is assumed for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, and no representation is made that its use would not infringe privately-owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring.

Case Study #1 5.2 MVA Located at Colorado State University (Fort Collins, CO, USA) 5.2 MW DC PV System 6.6 miles from substation Installed in 2 phases (2 MW + 3.2 MW) Capacity penetration - 57% (Σ DG / Peak Load)

Case Study #1 5.2 MVA Peak Load on Circuit 9.1 MVA Circuit Voltage 13,200 Volts

Details of PV System and Customer Large Conductors serving Colorado State University West Research Campus Two sets of voltage regulators on circuit and LTC at substation Voltage at campus requested to be ± 1% (per unit) The following steps are to be followed, sequentially, if there are voltage problems (next slide)

Planned Steps if Problems Occured 1. Adjust the voltage regulators to stabilize the voltage levels, and if necessary; 2. The inverters (10 total) will be configured to absorb 100 kvar each to reduce voltage rise, and if necessary; 3. The inverter configurations will be changed so they will absorb 150 kvar each, and if necessary; 4. Request that PV system operator disconnect part or all of the PV system and install a power factor controller or static VAR compensator (SVC)

WHY SMART GRIDS?

Staggered Start for Inverters Required Inverter No. Start-up time Inverter Size 1 230 sec. 500kW 2 260 sec. 500kW 3 290 sec. 500kW 4 320 sec. 500kW 5 350 sec. 500kW 6 380 sec. 500kW 7 410 sec. 500kW 8 440 sec. 500kW 9 470 sec. 500kW 10 500 sec. 500kW

Feeder Load Profile with PV Can you see the Duck Curve shape?

Common PV Penetration Metrics Capacity Penetration* Total PV System MW Peak Load MW Energy Penetration Total DG kwh Total kwh Penetration Screen Fails at 100% MDL or 15% peak load (depending on rules) * This is how Penetration is calculated in Technical Screens

Observations This large PV system behaved well on a typical distribution circuit This distribution feeder circuit is very stiff and has excellent capacity for absorbing DG of this size While this PV system required no system upgrades, most of this size would likely require system modifications

Case Study #2 20 kw Residential PV

Typical Voltage Drop for Utility Loads

Case Study #2 One-Line Diagram

Very High Voltage behind Transformer 131.5 Volts +9.5%

Case Study #2 20 kw Residential PV Voltage rises with minimal local load The ANSI C84.1 (Range A) upper limit is violated at the PV system, and worst violation at the micro-inverters farthest from the service disconnect This facility experienced 127.5 Volts at the utility meter and 131 Volts at the PV array (ANSI Range A upper limit 126 Volts) Local load will affect voltage levels significantly This residential system exports power during the day, which is when most residents are out or using little power. The exported power causes voltage problems locally

Case Study #2 20 kw Residential PV Steady-state voltage can be out of acceptable ANSI C84.1 range A (or B) with even with a small residential PV system This PV system, if only one of a few small PV systems on this feeder, means capacity penetration was <1%, yet there are localized voltage problems. In reality, this system should have failed a review and required mitigation! No other utility customers were negatively impacted by this high voltage example Would you have known there might be a problem with this interconnection application?

Case Study #3 10 MVA Solar PV Carlsbad, New Mexico, US

Case Study #3 10 MVA Solar PV Carlsbad, New Mexico, US Located near Carlsbad, New Mexico 10 MW DC PV System - 3/4 Mile from Substation Capacity Penetration of Approximately 100% based on peak annual load Minimum daytime load on feeder 3.87 MVA (Capacity Penetration ~300%)

Case Study #3 10 MVA Solar PV Carlsbad, New Mexico, US Interconnection with Xcel Energy Distribution voltage 12.47 kv Hopi Substation transformer bank size 16.8 MVA Peak Load on feeder 10 MVA Minimum Daytime Load on feeder 3.87 MVA Circuit conductor ¾ mile 336 ACSR from PV system to substation

Case Study #3 Detailed Impact Studies SynerGEE modeling program utilized for Detailed Impact Studies The following issues were focused on during detailed impact study phase Fault current contribution Protection coordination Voltage profiling studies

Case Study #3 Mitigation Strategies 1. ¾ mile of 336 ACSR feeder conductors installed 2. Additional line protection added to address desensitized relaying 3. Voltage supervised reclosing was added to the substation breakers to address potential problems with PV system size 4. PV owner was required to regulate their output power factor to a fixed value to address possible voltage issues. 5. Additionally the PV owner was required to energize the inverters incrementally in order to avoid large voltage steps.

Case Study #3 Conclusions Detailed Impact Studies were required to interconnect this very large PV system This PV systems exports power to the substation, and back through the substation transformer Load Tap Changer (LTC) Large conductors, short distance to substation were key to the success of this system Mitigation strategies were required The PV system and the utility feeder and substation have operated properly since PV system installation

PV System Size Important Considerations for Siting Locations Distance from Substation (MW-Ω) System Impedance at PV location Distribution Circuit/Substation Design (conductor sizes, regulators, LTCs, etc.) Voltage Regulators & Capacitors Exporting vs. Non-Exporting PV systems Proximity to Other Loads on Circuit Types of Utility Customers on Circuit

Case Study #4 Colorado Convention Center Denver, CO, USA Facility Name: Colorado Convention Center Owner: City and County of Denver Secondary Network Type: Spot PV System Size: 300 kw p DC Type of Interconnection Minimum Facility Load greater than PV System Reverse Power Relay Dynamically Controlled Inverters Utility Company: Xcel Energy (PSCo)

Case Study #4 Colorado Convention Center Denver, CO, USA

Case Study #4 Colorado Convention Center Denver, CO, USA

Network System Integration Approaches Maintain minimum load (MML) Reverse power relays (RPR) Minimum import relays (MIR) Dynamically controlled inverters (DCI)

Maintain Minimum Load Approach Study of historical load data generally supplied by utility (interval recorder data) Evaluate minimum demand during peak PV generation hours (10 AM 2 PM) Interval data estimates demand based on energy usage over 15 minutes (typical) Is an indicator that PV system will be sized smaller than minimum daytime load

Reverse Power Relay Approach Opens circuit breaker tied to PV system if power flows toward utility network Technology is well-known by utility protection engineers Advantages Fairly inexpensive, fast, reliable Disadvantages Manual reset, all-or-nothing

Minimum Import Relay Approach Opens circuit breaker tied to PV system if power into facility drops below threshold (e.g. 25kVA) Similar to reverse power relay utility engineers are familiar with technology Advantages Inexpensive, fast, reliable Better than RPR for network reliability Disadvantages Manual reset, all-or-nothing

Dynamically Controlled Inverter Approach Reduces PV output by % based on actual load of facility (e.g. 25kVA) CTs tie to bus near utility metering Features Very fast response Programmable No resetting of breakers necessary Some loss of energy if activated Inexpensive (~$5k) May not be available on all inverters

DCI (Smart Inverter) Results

Case Study #4 Colorado Convention Center Denver, CO, USA NREL Technical Report NREL/TP-550-45061

Gracias