White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306

Similar documents
Port Capacity Analysis in Long Beach. Matt Plezia, POLB and Vaibhav Govil, AECOM TRB Irvine, CA June 29, 2010

Container Terminal Planning & Operations Current and Coming Trends

UNMANNED CONTAINER HANDLING MEETING THE FUTURE CHALLENGES

Container terminal planning Experiences & lessons learnt

The Challenges of Container Terminal Development. Ashebir Jacob, PE September 10, 2013

PLANNING, DESIGN, and REALIZATION OF AUTOMATED TERMINALS Ashebir Jacob P.E. Senior Port Engineer / Vice President

USWC Port Congestion & ILWU/PMA Contract Update. Last update: November 12, 2014

Operations Systems of Container Terminals: A Compendious Overview

Berths [Everport] Container Terminal Improvements Project Draft EIS/EIR Public Meeting

Port of Los Angeles. America s Port Harbor Transportation Club June 20, 2013 Kathryn McDermott

MARITIME REPORTER AND ENGINEERING NEWS. Offshore Energy. Arctic Operations Finland Breaks the Ice. Markets Fishing Fleet Americas

Container Terminal Robotization

Figure 1-1 Container Trade Evolution. (Source Drewry/MSI)

Re: Participation of the Vancouver Fraser Port Authority in Orientation Session #2 for the Roberts Bank Terminal 2 Project Environmental Assessment

Increasing Throughput Using Automation. Jon Ranstrom Principal Engineer Navis

Trade Update & Opportunity Outlook. Gene Seroka Executive Director, Port of Los Angeles May 19, 2017

Measures for Congestion at Ports. Doug McDonald U.S. Maritime Administration Office of Policy and Plans

2017 Facilities Engineering Awards: Design and Construction of Marine Structures. Title of Project Mississippi River Intermodal Terminal Improvements

3.6 GROUND TRANSPORTATION

PROFESSIONAL BULK HANDLING WITH MOBILE HARBOUR CRANES (MHC) Study case Tecer / Unilink - Terminal de Múltiplo Uso Pecém (TMUT), Brazil

Container Transfer Logistics at Multimodal Container Terminals

Proceedings of The 1st International Seminar on Management of Technology, MMT-ITS Surabaya, July 30 th, 2016

Port of Los Angeles Presentation to the Los Angeles Investors Conference March 19, 2018

IAPH & Challenges facing World s Ports

Port Machinery Container cranes:

Port of Philadelphia Port Advisory Board

The Effect of Ultra Large Container Vessels on Cranes and Infrastructure

Optimization of Terminal Operations September 23, Navis, LLC. All other trademarks are the property of their respective owners.

Port Saint John Facilities

Scenario-based simulation of revenue loss at seismically damaged seaports

Terminal Information Handbook

The Use of Simulation for Bulk Cargo Terminal Planning and Design

FROM THE INVENTOR OF STRADDLE CARRIERS FOR CONTAINER HANDLING A-STRAD: FOR BROWN, GREEN AND FUTURE FIELDS

Improving Productivity of Yard Trucks in Port Container Terminal Using Computer Simulation

Major Issues and Trends Facing the Port and Marine Transportation Industry

OOCL Symposium. Norman Stark, President &CEO. Toronto, Ontario. GCT Global Container Terminals Inc. Vanterm and Deltaport. British Columbia, Canada

logistica portuale: come ridurre i costi e Ing. Marco Fehmer Contship Italia Group

Is the Semi-Automated or Automated Rail Mounted Gantry Operation a Green Terminal?

Intelligent stacking as way out of congested yards? Part 1

Summary Report - Terminal 2 (T2) Trade-Off Process and Outputs Container Capacity Improvement Program

Although tremendous efforts have been made in worldwide port development following issues are still on the agenda in many (container) ports:

Alabama State Port Authority

Barriers to Global Maritime Trade

House Select Committee on Strategic Transportation and Long Term Funding Solutions. November 6, 2017

PORT OF HAMBURG. SysIng. SysIng GmbH Rothenbaumchaussee Hamburg Germany Phone

Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3

CHAPTER 14. ROADWAYS AND MARINE TRANSPORTATION

Measuring Supply Chain Performance A Government Perspective. APCGI Workshop Toronto June 18, 2010

Port Performance Thoughts to Share Why Measure Performance? How to Measure?

Miami River Freight Improvement Plan Financial Management Number:

CHESSCON Capacity. Capacity planning for container terminals

Effect of ULCVs on Cranes and Infrastructure

Congo (D. R.) Ports description

Simulation Models for Evaluation of Terminal Operations and Traffic Flow on Adjacent Road Network

1.1 Background Project Location and Brief Project Overview. Chapter 1 Introduction

Port Planning Texas City International Terminal. William L. Allen, PE, SE*; Christopher B. Cornell, PE, SE**; and Dr. Joseph Moseley, PE***

HENRIQUE DANTAS DE CARVALHO INFORMATION TECHNOLOGY APPLIED TO CONTAINER TERMINALS AUTOMATION

Port Authority of Guam

APM Terminals Announces Innovative, more Sustainable Terminal Design

VOLTRI TERMINAL EUROPA

USA Trade: Export BAF Notices

CONTENTS. S:\Port Information\MetroPort Document October 2015 Document Controller: Marketing and Customer Support

PORT PERFORMANCE: AN ECONOMICS PERSPECTIVE

Appendix B2. Air Dispersion Modeling

Machinery on Trolley Crane Design Port of Singapore

Investor Presentation February 2018 Slide 1. Investor Presentation February 2018

Best Practices in NAVIS TOS Migration: Exolgan Case Study

Inside the Port of Long Beach: Challenges & Opportunities

LOGISTICS & DISTRIBUTION MANAGEMENT

TEXAS PORTS STRATEGIC MISSION PLAN & PORT CAPITAL PROGRAM. November 16, 2016 November Transportation Commission Workshop November 16, 2016

P11 Handling and Storage E212 - Facilities Planning and Design

Cargo Handling Technologies Final Report

CANADA TRANSPORTATION ACT REVIEW INITIAL SUBMISSION FOCUSED ON THE GRAIN INDUSTRY. Infrastructure, Efficiency, Transparency

Introduction. 1 Executive Summary

Simulation-Based Trucks Configuration for Twin 40 Feet Quay Cranes in Container Terminals

PRINCE RUPERT PORT AUTHORITY

RDEIR/SDEIS Traffic Forecasting Key Assumptions Update

PORT OF LONG BEACH SCREENING ANALYSIS OF CONTAINER TERMINAL OPTIONS

Boat Launch Analysis. 5.1 Introduction Boat Launch Study Overview Boat Launch Site Alternatives. Chapter 5

The PHA s desire to develop an implement an EMS was driver by the following factors: Potential to improve environmental performance

Eric Thomas Benchmark River and Rail Terminals

Port Reform, Privatization, and Regulation

RDEIR/SDEIS Traffic Forecasting Key Assumptions Update

INFORMATION HANDBOOK BRISBANE AUTOSTRAD TERMINAL BERTHS 8-10 FISHERMAN ISLANDS

APM Terminals Lazaro Cardenas. Mexico s new gateway to the Pacific

TRANSNET PORT TERMINALS PRESENTATION. Transport Forum Visit Port Elizabeth

Expectations for Port Customers and Clients. Dan Sheehy -NYK Line AAPA Meeting October 23, 2008

Berth [TraPac] Container Terminal Project Final General Conformity Determination

Port Tariff. updated March 14 th Services to the. Shipping Lines & Agents. Head Office, Dock Road. Tel: /5

Berth [China Shipping] Container Terminal Project - Environmental Review -

CHAPTER SUMMARY. Chapter 4 Socioeconomics

Practical Observations for Rail Mounted Crane Interfaces

Preparing port container terminals for the future: making the most of Intelligent Transport Systems (ITS)

Opportunity for Private Investment Mauritius Island Container Terminal

Select U.S. Ports Prepare For Panama Canal Expansion

Chapter 1 INTRODUCTION AND PROJECT DESCRIPTION

Technical Data Sheet. Stowage Planning. Technical Data Sheet. General Features

84 th International Propeller Club Convention Fundamental Changes to a Traditional Transportation Paradigm. October 7, 2009

2.1 Introduction and Project Overview

Investor Presentation November 2017 Slide 1. Investor Presentation November 2017

Transcription:

Appendix C2 White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306 Berths 302-306 [APL] Container Terminal Project December 2011 ADP# 081203-131 SCH# 2009071021

This page left intentionally blank

Oct 31, 2011 Berths 302 306 [APL] Container Terminal Improvement Project White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306 Background Currently Eagle Marine Services, LTD (EMS) operates the existing 291 acre APL Terminal at Berths 302 to 305, within the Port of Los Angeles (POLA). The APL Terminal includes 261 acres covered by an existing lease (Los Angeles Harbor Department [LAHD] Permit No. 733) and an additional approximately 30 acres of adjacent backlands authorized for use under a month-to-month space assignment (Non-Exclusive Berth Assignment No. 01-31). The proposed Berths 302 to 306 [APL] Container Terminal Improvement Project (the proposed Project) would add a new berth at B306 and make available an additional 56 acres, which would be operated by EMS under an amendment to the existing LAHD Permit No. 733. In addition, EMS would continue to utilize the 30 acres currently authorized for use under the month to month Non- Exclusive Berth Assignment No. 01-31. The term of the amended permit would remain unchanged (1998 to 2027), but the permit would be amended to include the additional 56 acres. APL has developed plans to improve approximately 41 acres of already constructed but unimproved fill as container terminal backland and operate this area as an automated terminal within the larger overall terminal. Areas outside this expansion would continue to operate manually, as they do today, for some time. While these existing terminal areas may eventually be converted to automated operations, discussion of this is beyond the scope of this paper. APL is not 100% certain that they will develop the expansion area as an automated terminal. Their other option is to simply expand their conventional operation into the new area. This generates two fundamental questions with regard to terminal capacity which are addressed by this paper: 1) What is the future capacity of the overall terminal including the expansion area? 2) Is the capacity different if the new portion is operated as a manual vs. automated terminal? AECOM s typical technique for analyzing the capacity of a container terminal is to analyze the berth capacity and the container yard (CY) capacity independently. The smaller of these two values establishes the overall terminal capacity because the overall capacity is constrained by the most restricted component. The future terminal, including the expansion project will consist of 5,250 feet of wharf and 347 total acres of terminal area. Berth Capacity The primary inputs to the P300 berth capacity analysis are: Vessel length and number of effective berths in 5,250 feet of wharf Work hours per day Vessel call size and number of dock cranes assigned Dock crane productivity Seasonal peaking factors Maximum practical berth utilization 1

Of these inputs only the work hours per day and dock crane productivity might be different for the automated vs. manual sections of the terminal. 21 hours per day is the current ILWU maximum. It may be possible to do some work on a 24/7 basis in an automated terminal, but because the dock cranes will still feature human drivers, conemen, and lashers, the daily operating hours are unlikely to change with automation. The relative dock crane productivity of manual vs. automated terminals is the topic of a considerable amount of discussion. In order to understand this issue, a bit of background on the basics of dock crane operation is helpful. Typical specifications of a modern dock crane are shown in Table 1. The specifications in Table 1 are also used as the assumptions for the delay incurred to pick and set containers, and to remove or install inter-box connectors (IBCs). Speeds in Table 1 are shown in feet per minute (fpm). Hoist w container 300 fpm Hoist w/o container 600 fpm Trolley 750 fpm Pick or set container 20 sec Align spreader into belowdeck 15 sec cell guides Install/remove IBCs 30 sec Table 1 Typical Dock Crane AECOM has analyzed dual hoist cranes of this nature as part of other planning and analysis projects and believe that they are capable of approximately 40 moves per hour when they are working on one hatch of a vessel and are perfectly fed, i.e. they never have to wait for an automated guided vehicle (AGV). In practice, it is not possible to always have an AGV under a dock crane when it is needed. The dynamic nature of real-world container terminal operations poses many challenges to decisions about AGV routing, which depend on accurate predictions of the future. Some of the many issues include: Complexity of choosing from amongst a large fleet of AGVs for each task. Note that APL is proposing to use 66 AGVs (perhaps 90% of these may be operating under peak conditions), and any of these machines is eligible to do any required task on the terminal. The terminal s operating system therefore has to choose the best AGV of perhaps 60 options, and it needs to do this hundreds of times per hour in order to support efficient operations. Lag in timing between instructions from the terminal operating system (TOS) and AGVs Delay due to navigation conflict between AGVs at intersections Variable timing for the human dock crane driver from one move to the next The need to move hatch covers on and off the vessel The need for dock cranes to gantry between locations on the vessel The need to load reefer containers with doors facing the opposite direction as the rest of the containers on the ship The need to occasionally handle cargo that is out of gage and may not fit in a standard ASC block The need to intermittently refuel (or recharge) AGVs The need to occasionally remove AGVs from service for preventative or corrective maintenance Time lost due to late labor arrival/early departure 2

For these reasons, real world productivity at existing automated terminals CTA in Hamburg and Euromax in Rotterdam have been closer to 25 moves per dock crane per hour at terminal startup. Moderate improvements over time at these facilities have pushed productivity to approximately 30 moves per hour in a mature operation with an experienced staff. Given the unique nature of APL s design, especially the requirement for AGVs to circulate through the ASC stacks instead of simply parking perpendicular to the stack at the waterside end, AECOM would expect productivity at APL s terminal to start below that of other ASC/AGV terminals. APL has predicted a gross dock crane productivity of 27 moves per hour for their automated system. This is similar to what APL is able to achieve today in a conventional terminal. Although automated terminals in Hamburg and Rotterdam have been able to achieve productivity levels somewhat higher than this, AECOM believes that 27 moves per gross hour is reasonable at Pier 300 due to the following differences between P300 and other automated terminals in Northern Europe: 1) The labor unions in Europe allow flexible shift start times whereas the ILWU adheres to strict shift starts. This means that terminals in LA only get an effective seven hours of work from an eight hour paid shift. In other words, the first move at P300 does not happen at 8:00 or 8:01 but more typically 8:15. Similar time is lost around the lunch hour and shift end. This means that a net productivity of 30 moves per hour as measured from first to last move equates to a gross productivity for the entire paid shift of 26 or 27 moves per hour 2) The concept that APL is proposing is unique and more complicated than existing automated terminals. See Appendix A for more detailed discussion. A technical paper Design, Simulation, and Evaluation of Automated Container Terminals from Liu, Jula, and Ioannou, published in 2002, cites an expected productivity of over 40 moves per dock crane per hour for an automated terminal roughly similar to the concept proposed by APL for Pier 300. The paper assumed that a dock crane is capable of a theoretical maximum of 42 moves per hour. In other words, the paper predicted that ASC+AGV terminal systems will be able to achieve in excess of 95% of the theoretical maximum productivity of a dock crane! The dock cranes at ECT, it should be noted, were then and are today operating at perhaps 60% of their theoretical capacity (i.e. the low-mid 20s of moves per hour per crane) so it is surprising that no reference is made to actual productivity from the only real world ASC+AGV terminal operating at the time the paper was written. AECOM believes the paper has little relevance to current discussions of automated terminals due to its age and omission of many key aspects of real world operating conditions. 3

In the long run, container ships that visit POLA are expected to occupy approximately 1,300 feet each. This means that a 5,250 foot wharf is effectively four berths for the purposes of capacity analysis. Inputs for vessel size, crane assignment, seasonal peaking, and maximum practical berth utilization are the collective opinion of APL and POLA. Table 2 shows the expected berth capacity for a 5,250 foot berth at P300 is equal to 3.2 million TEU per year. a Number of berths 4.00 b Work hrs per day 21.0 c Work days per week 7.0 d Max overall berth occupancy 60% e Effective hours per berth [b*c*d] 88.2 f Mean moves per call - peak week 4,500 g Dock crane moves/hr 27.0 h Mean cranes per ship 4.5 i Mean work time per ship [f/(g*h)] 37.0 j Ship tie-up & untie time (hr) 4.0 k Mean vessel call time (hr) [i+j] 41.0 l Potential ship calls per peak week [a*e/k] 8.6 m Peak week capacity (moves) [f*l] 38,687 n Peak/mean season 110% o Annual berth capacity (moves) [m*52/n] 1,830,000 p TEU per container 1.75 q Annual berth capacity (TEU) [o*p] 3,200,000 Table 2 Berth Capacity at P300 CY Capacity While the overall terminal size is listed at 347 acres, the net area available for container storage is estimated by POLA at 262 acres, for a net/gross ratio of just over 75%. The quarter of the terminal not used for container storage is taken up by the wharf, buildings, parking, gate, and other support areas. Each net acre of container storage typically allows about 100 twenty-foot ground slots (TGS) of storage, which means the overall terminal should have approximately 26,000 TGS of container storage available. 4

Based on our past capacity studies at POLA, AECOM expects that the mean dwell time at P300 is approximately 4.6 days. The stacking height of containers on the terminal is expected to increase over time. Both manual or automated terminals are likely to be based on equipment that can stack 1-over-5 high. The highest mean overall height in this case is approximately 3.5 containers per stack. AECOM examined a range of stack height from 3.0 to 3.6. The resulting CY capacity figures are shown in Table 3. a Total TGS available 26,000 26,000 26,000 26,000 b Mean stacking height 3.0 3.2 3.4 3.6 c Total TEU capacity [a*b] 78,000 83,200 88,400 93,600 d Mean dwell time (days) 4.6 4.6 4.6 4.6 e Turnovers per year w/o peaking [365/d] 78.7 78.7 78.7 78.7 f Peak/mean week throughput 110% 110% 110% 110% g Peak/mean inventory per week 140% 140% 140% 140% h Turnovers w/ peaking [e/f/g] 51.1 51.1 51.1 51.1 i Annual overall CY capacity (TEU) [c*h] 3,980,000 4,250,000 4,520,000 4,780,000 Overall Terminal Capacity and Conclusions Table 3 Container Yard Capacity Even the relatively low stacking height of 3.0 containers, the CY capacity of the terminal will exceed the berth capacity by a considerable margin. Figure 1 shows the comparison of berth capacity and CY capacity at a variety of mean stacking heights. 5,000,000 4,500,000 4,000,000 CY Capacity (TEU per year) 3,500,000 3,000,000 2,500,000 2,000,000 1,500,000 1,000,000 500,000 - Berth Capacity 3.0 3.2 3.4 3.6 Mean Stack Height Figure 1 Berth vs. CY Capacity This evaluation above answers the two fundamental questions with regard to terminal capacity which can be summarized as follows: 1) What is the future capacity of the overall terminal including the expansion area? 5

The terminal s overall capacity is equal to the berth capacity of 3.2 million TEU per year. APL s proposed automated CY area may feature a stacking height that is taller than considered by AECOM in this analysis, however, this will only increase CY capacity and not overall capacity due to the berth capacity limitation. The business rationale for automating a portion of the terminal would be to reduce costs rather than to increase capacity as other improvements would be necessary to increase capacity as discussed. 2) Is the capacity different if the new portion is operated as a manual vs. automated terminal? There is no significant difference in the terminal capacity whether or not APL operates the expansion area as an automated terminal or a manual terminal because none of the factors that influence berth capacity are expected to be significantly different between these two options. 6

Appendix A: APL s Concept vs Other Automated Terminals Figure A.1 shows a plan view of APL s proposed layout on the expansion area. Figure A.1 APL s proposed Automated Operation at P300 APL proposes to use dual hoist dock cranes to transport containers between the ship and the backreach of the dock crane. APL will use robotic automated guided vehicles (AGVs) to transport containers horizontally though the automated portion of the terminal. Figure A.2 shows an AGV. Figure A.2 AGV 7

APL proposes to use unmanned rail mounted gantry cranes (RMGs) also known as automated stacking cranes (ASCs) to stack the containers. AECOM is aware of three other AGV+ASC type automated terminals in the world: 1. ECT Rotterdam what many consider to be the world s first automated terminal which opened in 1993. Due to the limitations of the computer systems at the time, this terminal featured only one ASC over each block of containers. 2. CTA Hamburg the first modern automated terminal with two ASCs per block and direct street truck access to the ASC blocks. This terminal opened in 2002. It features dual hoist dock cranes working to the backreach similar to what APL is proposing for P300. This terminal also has the unique feature of the two ASCs within each storage block operating on different rail gauges so that they can pass each other while working. This feature has yet to be copied outside of Hamburg. 3. Euromax Rotterdam. This terminal opened in 2008 and is very similar to CTA Hamburg except for the fact that both ASCs serving each container storage block run on the same set of rails and do not pass each other. What these three terminals, and effectively every ASC based terminal worldwide, have in common is that the ASC blocks are aligned perpendicular to the wharf. Figure A.3 shows an aerial view of CTA Hamburg. Note the AGVs operating in the space between the wharf and the waterside end of the ASC blocks. Figure A.3 CTA Hamburg s ASC+AGV operation 8

The other feature common to every ASC terminal in the world except for the very first one at ECT, is that street trucks back up to the landside end of the ASC blocks to receive and deliver containers directly from and to the ASC. Figure A.4 shows an example of the truck interface at CTA Hamburg. Figure A.4 CTA Hamburg s Truck Interface APL s proposed system has many features that are found in no other terminal in the world including: ASC rows parallel to the wharf AGVs that drive parallel to the ASCs and access containers from the side of the ASC stacks AGVs are used to extract gate containers and move them to a special RMG/street truck transfer area as opposed to allowing street trucks direct access to the ASCs. The RMGs in this transfer area are called landside transfer cranes (LTC). 9

This page left intentionally blank