Introduction to Substation Design TADP 542

Similar documents
PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

EIGHT POINT WIND ENERGY CENTER

Substation Bus Design: Current Methods Compared with Field Results

CUSTOMER SERVICE POLICIES

ELECTRICAL INSPECTION BULLETIN (Effective )

CHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary:

5600. LARGE-SCALE GROUND-MOUNTED SOLAR PHOTOVOLTAIC INSTALLATIONS

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

Information Document Protection System Information ID# R

Review Zone Application for D&R Canal Commission Decision

69/12KV SUBSTATION DESIGN

POTOMAC ELECTRIC POWER COMPANY

SECTION SUBSTATION BUS ASSEMBLIES ERGLE SUBSTATION

Inspection Guide for PV Systems in One- and Two- Family Dwellings (For Rooftop Photovoltaic Systems meeting the Standard Plan)

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

Minimum Transmission Design Standards f or Competitive Upgrades Rev 2

Facility Interconnection Requirements

Public Utility District Number 1 of Snohomish County

Proposals and Process 2017 National Electrical Code

Electrical Networks Principles and Performance

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Ontario ENGINEERING STANDARD SPECIFICATION 1/10 REV. ELECTRICAL DISTRIBUTION HIGH VOLTAGE SUBSTATION GROUNDING AND BONDING. Approved by.

SECTION BASIC ELECTRICAL REQUIREMENTS

ARTICLE XXIII SMALL WIND ENERGY SYSTEMS 85

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Photovoltaic System Inspector Job Task Analysis Guide April 2017

Transmission Interconnection Requirements. Table of Contents

Audit Approach to FAC Transmission Vegetation Management FRCC Webinar

What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin?

Facilities Study. For. XXXXXXXXXXXX Wind Park Interconnection Switching Station

Strength & Loading. Of Wood Utility Poles. Webinar

Position Description

Standard of Practice - Campus Electrical Distribution System

WIND ENERGY CONVERSION SYSTEMS

Work Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement

4. GENERAL REQUIREMENTS

SECTION MEDIUM VOLTAGE TRANSFORMERS

Requirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014

(Condensed from National Electric Code)

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

3. GENERAL INFORMATION AND REQUIREMENTS

Nip / Tuck Method A Solution to Providing Additional Conductor-to-Ground Clearances for Transmission Lines

TEMPORARY METER POLE INSTALLATION

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Clearances and conductor spacings and a safe access for a.c. switchyards

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

ORDINANCE NO. VI-III A WIND ENERGY DEVICE ORDINANCE EMMET COUNTY, IOWA AN ORDINANCE ADDRESSING STANDARDS, CONDITIONS, APPLICATION, REVIEW AND

SECTION GROUNDING AND BONDING

Member Service Electric Wiring Guidelines

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY

TRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING, NETWORK SYSTEMS SECTION

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT

ELECTRICAL BULLETIN

2017 NEC Changes for Renewable Energy Systems Session one by Christopher LaForge

A. This section includes building wire and cable rated 600V and less Full Short Circuit Device, Coordination and Arc Fault Study

Joint Use. Guidelines and Construction Standards

Ordinance Number AN ORDINANCE REPEALING AND REPLACING CHAPTER 172 OF THE NORTH LIBERTY CODE OF ORDINANCES, COMMUNICATION TOWERS AND ANTENNAS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Revisions for the 2011 National Electrical Code - Part 2

Permitting and Inspecting PV Systems. PV Codes and Standards 101. Photovoltaic System Basics

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

Eugene Water & Electric Board

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P.

Temporary Wiring Practices And Guidelines For NECA. National Electrical Contractors Association Omaha, Nebraska

ELECTRICAL SERVICE EXTENSION POLICY

NOVA Chemicals Corporation

V. Design, Application, Maintenance & Operation Technical Requirements

C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6

SPP at a Glance. Located in Little Rock. Approximately 600 employees

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification.

PLANNED UNIT DEVELOPMENT, PLANNING APPROVAL & SUBDIVISION STAFF REPORT Date: June 4, 2015

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES

DISTRIBUTION STORM HARDENING AND RESILIENCY. Matt Shellenberger, P.E. American Electric Power

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet

Microgrids in New England Technical Challenges & Opportunities

Unit Substation Transformer Construction Checklist (under 500 kva)

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

Canadian Electrical Code, Part I Full Impact Assessment

For the 2008 Code, the minimum clear distances were revised to reflect an accurate metric conversion (also known as a soft conversion).

TS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS

ELECTRICAL BULLETIN

XXXXXXXXXXX Solar (XXX) Generation Interconnection

Addition to Section 4 - Special Use Regulations

City of Tacoma Surface Water Management Manual

Panel 7 Proposals For 2005 NEC Articles 320, 322, 324, 326, 328, 330, 332, 334, 336, 338, 340, 382, 394, 396 and 398

Civil Engineering and Architecture Detailed and Performance Objective Outline

LINDSEY EMERGENCY RESTORATION SYSTEM

Hazards. Hazards. Hazards. Effects on the Body. GA Tech Electrical Safety Presentation

A SUBSTATION CONCEPT FOR CHANGEABLE LOAD CONDITIONS

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

ELECTRIC METERING GENERAL

ELECTRICITY at WORK REGULATIONS

ENGINEERING & ECONOMIC PLANNING FOR ELECTRIC POWER GENERATION, TRANSMISSION AND DISTRIBUTION

Power Electronics, Inc. Packaged Equipment Center Standard Construction and Design Features

Transcription:

Introduction to Substation Design TADP 542 Design Principles- General Framework Instructor: Richard Snell Transmission & Distribution Program

Module 2 Outline Presentation 1: General Framework Presentation 2: Defining a Project Presentation 3: Project Authorization Presentation 4: Substation Site Issues Presentation 5: Time Issues

General A substation is an integral part of the overall power system. Its design should minimize adverse impacts to substation equipment, transmission and distribution system, and also to customers. The design should minimize costs while providing the required functionality.

General (cont.) A substation can be a very complex facility as can be seen in this picture of the transmission bus in an existing substation.

General (cont.) A substation is analogous to a large commercial or small industrial facility in complexity. It has several subsystems and can have hundreds or thousands of different parts. A substation is usually operated and maintained while it is in service.

General (cont.) Drawings used to depict site development, equipment and structure placement; physical and/or electrical characteristics of structures and equipment and electrical interconnections between and within equipment. The number of drawings for a substation can range from a few to several hundred.

General (cont.) Substations may be owned by exempt wholesale generators; electric transmission companies; integrated, transmission and/or distribution electric utility companies; large commercial facilities or industrial complexes. A substation design must conform to applicable electrical codes as well as some federal, state and local laws and regulations.

General (cont.) Most substation projects are for additions or modifications to existing substations. The number of new substations constructed nationally each year is less than five percent of the total number of existing substations. In rapidly growing areas, the number of new substations being constructed annually may be greater with respect to the number of existing substations in that area than the national average.

General

Design Personnel A substation project should be designed by one or more professional engineers. This is usually a legal requirement set by the state or province where the project is located for the protection of the public. Those engineers may supervise others in the design of all or portions of the project. However, the professional engineers are legally responsible for the design.

National Electrical Safety Code National Electrical Safety Code-ANSI C2 (NESC) establishes minimum requirements for construction, operation and maintenance of electric and communications facilities. Purpose is the safety of persons during installation, operation, or maintenance of electric supply and communication lines and associated equipment.

National Electrical Safety Code (cont.) NESC developed as a voluntary standard. A majority of states have adopted some form the NESC as either law or regulations. A 2007 IEEE survey shows which edition or parts of the NESC has been adopted by each state. The survey results can be seen at: http://grouper.ieee.org/groups/nesc/pucsurvey2007.pdf

National Electrical Safety Code (cont.) Section 9, Grounding Methods for Electric Supply and Communication Facilities covers substation grounding. Part 1, Rules for the Installation and Maintenance of Electric Supply Stations and Equipment covers generating plant and substations.

National Electrical Safety Code (cont.) Part 2, Safety Rules for the Installation and Maintenance of Overhead Electric Supply and Communication Lines covers overhead lines entering, leaving, and within a substation. Part 3, Safety Rules for the Installation and Maintenance of Underground Electric Supply and Communication Lines addresses underground lines entering, leaving and within a substation.

National Electrical Safety Code (cont.) Part 4 Rules for Operation of Electric Supply and Communications Lines and Equipment is applicable to operation and maintenance of the supply and communications lines within a substation.

National Electric Code The National Electric Code NFPA 70 (NEC), a modified version of it or a similar code has been adopted by states to regulate the installation of electrical systems and equipment in buildings and structures. Many states exempt low voltage wiring in substations from meeting the NEC or equivalent when it is covered by the NESC.

National Electric Code NEC requirements for medium and high voltage installations are those of the NESC which are included by reference to the NESC.

Federal Regulations Environmental Protection Agency (EPA) has implemented regulations for controlling and preventing effluents from flowing into waterways. Primary effluent in a substation is the insulating oil in power transformers and/or other oil-insulated equipment.

Federal Regulations (cont.) Substation will require containment structures or devices if distance to waterway is less than proscribed by regulations and effluent could flow into waterway. Includes oil sumps near or impenetrable berms around oil-filled equipment, fence curbing around a crushed rock surface or other containment methods.

Federal Regulations (continued)

Federal Regulations (cont.) FCC Part 15 regulations requires incidental radio frequency radiators to maintain their radio frequency emissions to levels that do not adversely impact other FCC regulated services. A substation will become an incidental radiator if its design or construction creates a corona discharge on its transmission voltage conductors, connectors or equipment.

Federal Regulations (cont.) Corona occurs when an electric field at a point on the surface of an energized conducting object exceeds the breakdown voltage of the air. Corona is most prevalent at transmission voltages of 230 kv and above. See EPRI AC Transmission Line Reference Book 200 kv and Above for further corona information.

Corona

State Laws and Regulations Some states have regulations for control of storm water runoff both during construction of a substation and after its completion. Catch Basins

State Laws and Regulations (cont.) Many states have implemented audible noise limits for substations. Purchasing power transformers with lower sound levels is one method of reducing substation audible noise. Installation of sound reducing barriers is another method of reducing substation audible noise.

State Laws and Regulations (cont.) State laws may require substations be designed to withstand anticipated seismic forces at their locations.

Local Ordinances and Regulations Local jurisdictions may require building permits for substations and/or substation control houses. Local zoning ordinances or decisions may specify requirements for the substation enclosure and/or the landscaping.

Design Software Currently, there is no commercially available software for designing a complete substation. There are software products available to design portions of a substation.

Design Software (cont.) Most substations designs are created by copying existing substation designs and modifying them as needed. Substation designs are mostly presented graphically using drawings. CAD software is used to create, copy and modify substation drawings.

Design Software (cont.) Many utilities and engineers have developed software and/or spreadsheets to accomplish certain tasks. Word processing software can be used to create specifications and contracts related to the substation design. Materials management software can be used for ordering materials for a substation project.

Image Acknowledgements Transmission Bus 115kV Richard Snell Example Drawing List Public Utility District of Grant County Circuit Breaker Addition One-line Diagram Public Utility District of Grant County Corona Discharge Public Utility District of Grant County Catch Basins Public Utility District of Grant County