Improving Weapon System Investment Decisions A Knowledge-based Approach to Weapon System Acquisitions Could Improve Outcomes

Similar documents
NDIA Life Cycle Affordability Project

Department of Defense Financial Management. Program UID. Presented by: Mr. Paul Ketrick Chief, Strategic Planning & Resourcing 31 March 2005

SUBJECT: Better Buying Power 2.0: Continuing the Pursuit for Greater Efficiency and Productivity in Defense Spending

3Z0Z 0? W7? TOTAL QUALITY MANAGEMENT MASTER PLAN* (S)l\f> v^n. 0 Department of Defense. AUG 2 ego, August O/ A./ \o V* TECHNICAL LIBRARY

Performance Based Life Cycle Product Support

Replacing Risk with Knowledge to Deliver Better Acquisition Outcomes

Concept Exploration. Dr. Norbert Doerry, December 8-9, Approved for Public Release Distribution is Unlimited 11/24/2015

Cost-Effective Readiness

Agile Acquisition. Peter Modigliani 10 Dec 12. Presented to: Mr. Koen Gijsbers. General Manager NATO Communications and Information Agency

THE UNDER SECRETARY OF DEFENSE DEFENSE PENTAGON WASHINGTON, DC

Acquisition professionals know that program schedules should be established via eventdriven. Schedule or Event Driven? How Do I Know?

DoD Business Transformation and Environmental Liabilities Recognition, Valuation and Reporting

Naval Set-Based Design

2009 DoD Weapon System Product Support Assessment

UNCLASSIFIED. FY 2016 Base FY 2016 OCO. Work in this project is performed by the U.S. Army Research Laboratory (ARL), Aberdeen Proving Ground, MD.

objective: to ensure our nation can afford the systems it acquires.

Acquisition Domain: Leading Transformation

Performance Assessments and Root Cause Analyses October 11, 2016

Best practices for highly effective test design; Part 1 Beginners guide to mapping the T&E strategy

DOD MANUAL , VOLUME 12 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: SALES AND OPERATIONS PLANNING

OFFICE OF THE UNDER SECRET ARY OF DEFENSE 3000 DEFENSE PENTAGON WASHINGTON, DC

DoD Template for Application of TLCSM and PBL In the Weapon System Life Cycle

Top 5 Systems Engineering Issues within DOD and Defense Industry

Capital programmes in Aerospace & Defence

CHAPTER 1 Introduction

Cross-Service Collaboration

Need for Affordability Analysis in Systems Engineering

Advancing Organizational Project Management Maturity

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

OSD SUPPLY CHAIN ENTERPRISE METRICS STRATEGY. Evolving DoD Supply Enterprise Metrics The Maintenance Customer Perspective

Report of the Reliability Improvement Working Group Table of Contents

Institutionalization of Reduction of Total Ownership Costs (R-TOC) Principles

DoD Hazmat Business Process Reengineering: Environment, Safety and Occupational Health (ESOH) Transformation

Source: -- Downloaded: T07:47Z Check the source to verify that this is the current version before use.

Department of the Navy Probability of Program Success (PoPS)

SoS Considerations in the Engineering of Systems

TenStep Project Management Process Summary

Application of the Integrated Product Support Elements

Net-Ready Key Performance Parameter (NR-KPP) Implementation Guidebook

Overview. Introduction to Honeywell. Environment. Honeywell s Public-Private Partnerships. Partnership Challenges

KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT. The 7-S for Success Framework

Engineered Resilient Systems

INTRODUCTION THE ASSISTANT SECRETARY OF THE NAVY FINANCIAL MANAGEMENT AND COMPTROLLER WASHINGTON, D.C T T W T

Analysis of Alternatives (AoA) Handbook

DEFENSE CONTRACT MANAGEMENT AGENCY

Performance-Based Logistics: Buying Performance, Not Parts

CHANGE MANAGEMENT IN PROCUREMENT TRANSFORMATION. Bloomberg. Page 1

11th Annual Systems Engineering Conference. Reduction of Total Ownership Costs (R-TOC) and Value Engineering (VE) in the Defense System s Life Cycle

Internal audit strategic planning Making internal audit s vision a reality during a period of rapid transformation

Services Acquisition Update

Department of Navy Audit Update

..._ I Page lof 13 ~ LOG200 Intermediate Acquisition Logistics lesson 2.6- Evaluate Product Support Capabilities- Metrics. Welcome to Metrics

National Defense University. Strategic Plan 2012/2013 to 2017/18 One University Evolution

A Navy Energy Vision for the 21 st Century. RADM Philip H. Cullom Director, Energy and Environmental Readiness Division OPNAV N45

Systems Engineering in Large-scale Agile Software Development

THE BUSINESS LIFE CYCLE: AVOIDING DECLINE

Capabilities-Based Assessment (CBA) Handbook

DEPARTMENT OF DEFENSE HANDBOOK MANUFACTURING AND QUALITY PROGRAM

Catching Fraud During a Recession Through Superior Internal Controls. FICPA s 25 th Annual Accounting Show. J. Stephen Nouss September 29, 2010

Implementing the Materiel Availability KPP in DoD Acquisition Programs Balancing Life Cycle Costs with Warfighter Needs

Business Case Analysis. Mr. Ken East, C.P.L.

2017 AIR FORCE MATERIEL COMMAND STRATEGIC PLAN

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015

Mission-Level Systems Engineering

How the FM Target Environment Will Help Us Sustain Financial Auditability. Presentation to the ASMC National PDI June 3, 2016

Defense Health Agency Education Partnership Outreach

DLA Aviation Overview Mr. Ken Winslette, Deputy Director Strategic Acquisition Mr. Floyd Moore, Deputy Director Supplier Operations

ECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP

Investigation into equipment cannibalisation in the Royal Navy

Latest Reliability Growth Policies, Practices, and Theories for Improved Execution

Agile Development & Systems Engineering: The Odd Couple. December Glenn Tolentino, PhD John Wood, PhD

Delivering End-to-End Supply Chain Excellence

For More Information

2011 Aerospace & Defense Industry Perspective

A PMO Value Model. For Strategic Execution and Value Delivery P M. Robert Frost PMP, PMOC. 4/19/2016 PMO Value Model 2016 Robert Frost 1

2011 Aviation Week Program Excellence Award Submission. Phase 1. P-8A Poseidon Program

Alan F. Estevez. Principal Deputy Assistant Secretary of Defense for Logistics and Materiel Readiness

Department of Defense INSTRUCTION

Contents. DCMA Strategic Plan

Quantifying the FBCF and Energy Key Performance Parameter

a message from... AIR-6.0

The Mothership - UAV swarms inspire research into flying aircraft carriers

Enterprise Mission Assistance DAU Board of Visitors

DEFENSE ACQUISITION UNIVERSITY ISA 101 BASIC INFORMATION SYSTEM ACQUISITION

18887 Environment, Safety, and Occupational Health (ESOH) A Design Consideration with Benefits

Integration Competency Center Deployment

Collaborative Planning Methodology (CPM) Overview

From Dictionary.com. Risk: Exposure to the chance of injury or loss; a hazard or dangerous chance

UNCLASSIFIED. Exhibit R-2, RDT&E Budget Item Justification Date: February 2005 APPROPRIATION/BUDGET ACTIVITY DEFENSE WIDE RDT&E BA 6

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date:

CONCLUSIONS APPLYING LESSONS LEARNED. Chapter Four

Optimize Your Incentive Strategy

SUSTAINABILITY ANALYSIS CAPTURING LIFE CYCLE IMPACTS AND COSTS IN DEFENSE SYSTEMS

Supporting OSD Defense Cost and Resource Center (DCARC)

Office Of Small Business Programs

Test and Evaluation for Agile Information Technologies. Steve Hutchison DISA T&E

Collection of Operating and Support Data from Weapon System Support Contracts

Joint Logistics Strategic Plan

Nine Steps to a Better Statement of Work

LEAN ENTERPRISE TRANSFORMATION

Transcription:

Improving Weapon System Investment Decisions A Knowledge-based Approach to Weapon System Acquisitions Could Improve Outcomes Travis Masters Senior Defense Analyst U.S. Government Accountability Office Wright-Patterson AFB, OH

DOD Framework vs. Knowledge-based Best Practices Model

Major Determinant Of Program Outcomes Is The Level Of Knowledge Attained At Key Junctures Knowledge Point 1: At milestone B, a match is achieved between the user s needs and the developer s resources (indicator: technology readiness level) Knowledge Point 2: At critical design review, the product design demonstrates its ability to meet user needs and is stable (indicator: % of engineering drawings released) Knowledge Point 3: At milestone C, it is demonstrated that the product can be produced within cost, schedule, and quality targets (indicator: % of key processes in statistical control)

Making a Business Case that a Product Can Be Developed Within Resource Constraints At milestone B programs should present a business case that provides evidence that: (1)Warfighter needs are valid and can be met with chosen concept, and (2)The chosen concept can be developed and produced within resources-technologies, funding, design knowledge, and time

Resolving Gaps Between Requirements and Resources Before Program Start Early systems engineering enables a developer to identify and resolve gaps between resources and requirements before product development begins Requirements Analysis Functional Analysis And Allocation Design Synthesis Definition of customer wants including planned use, operating environment, and performance characteristics. Decomposition of the requirements into a set of specific functions that the system must perform. Identification of the technical and design solutions needed to meet the required functions. Product Design Source: GAO.

DOD Programs Continue to Experience Cost and Schedule Problems 50% 40% 30% 20% Months 10% 0% Change in Total Acquisition Costs From First Estimates Change in RDT&E Costs From First Estimates Share of programs with 25 percent cost growth 25 20 15 16 17 21 FY 2000 Portfolio FY 2005 Portfolio FY 2007 Portfolio 10 5 0 Average schedule delay in delivering initial capabilities FY 2000 Portfolio FY 2005 Portfolio FY 2007 Portfolio Source: GAO analysis of DOD data.

GAO Continues to Find That Programs Begin Without Key Knowledge Requirements are not well understood Quantum leaps in capability not incremental changes Technologies are not mature Cost and schedule estimates are overly optimistic Program cycle times are too lengthy

Little Evidence of Widespread Adoption of Knowledge-based Acquisition Process DOD s acquisition practices necessary to ensure effective implementation of knowledge-based process are not always followed despite policies and guidance to the contrary. a Not all programs provided information for each knowledge point or had passed through all three key junctures. b In our assessment of two programs, the Light Utility Helicopter and the Joint Cargo Aircraft, are depicted as meeting all three knowledge points when they began at production start. We excluded these two programs from our analysis because they were based on commercially available products and we did not assess their knowledge attainment with our best practices metrics.

GAO s Review of the Acquisition Decision Support Systems GAO has done a lot of work looking at the DAS Congress directed GAO to initiate a body of work looking at the funding and requirements processes and how they could support better program outcomes Defense Acquisition System Joint Capabilities Integration & Development System (JCIDS) Planning, Programming, Budgeting & Execution Process (PPBE)

Portfolio Management: A Successful Commercial Model Each investment must be viewed from an enterprise level as contributing to the collective whole, rather than independent and unrelated Identify and Prioritize Market Opportunities to Lay the Foundation for Achieving the Right Mix of Products Use a Disciplined Process to Identify New Products and Achieve a Balanced Portfolio Ensure strong governance, committed leadership, empowered decision makers, and effective accountability GAO-07-388

The Portfolio Management Funnel

DOD s Decision Making Processes are Service-centric and Fragmented Services identify needs and budget for solutions FCBs don t have the resources to effectively evaluate the service assessments within the context of the broader portfolio FCBs don t have the authority to allocate resources Service funding appears to be allocated according to historical percentages 40% AF, 20% Army, 30% Navy, and 10% DOD Wide JCIDS, PPBE, and DAS led by different organizations Joint Staff, USD(AT&L), OSD (PA&E and Comptroller)

Fragmented Processes With Adverse Incentives PRESSURE ON DECISION MAKER TO Requirements Process promise high performance Budgeting Process promise low resource demands Acquisition Process Source: GAO. move forward, get knowledge later

DOD Commits to Solutions Early and With Limited Knowledge Review points prior to milestone B are optional and typically by-passed Key processes are not integrated early to provide insight into cost and feasibility ICDs don t address cost or technical feasibility AOAs often make the case for a specific solution vs. identifying the preferred solution Programs don t have sound business cases Undefined requirements Immature technology Optimistic cost and schedule estimates

DOD s Funding Process Contributes to Poor Acquisition Outcomes Assessed cost and funding data for 20 major acquisition programs, and conducted detailed analysis of five of those programs: Global Hawk Joint Strike Fighter (JSF) Future Combat Systems (FCS) Warfighter Information Network Tactical (WIN-T) Multi-mission Maritime Aircraft (MMA) Leveraged work GAO has been doing in cost estimating and earned value best practices (GAO Cost Assessment Guidebook) Leveraged prior best practices work and obtained additional input from several of the companies that contributed to our prior work GAO-08-619

Accurate Cost Estimates Are Needed Before Adequate Funding Can Be Allocated Without accurate estimates it is not realistic to assume that funding will be adequate Cost estimating best practice is to assess risk and uncertainty and present estimate as range of potential costs Conduct sensitivity analysis and identify the range of likely costs Ranges will be broader as knowledge is limited but as knowledge is gained (before development begins) the range should narrow until Ranges allow decision makers to make more informed decisions they can test the estimate s reasonableness and decide on what level of funding risk they want to take)

The Cone of Uncertainty

Built-in Funding Instability DOD programs often initiate development with funding that does not reflect true costs 75% of the programs we reviewed were under-funded in the FYDP when they began development The FYDP doesn t cover the entire development program DOD makes unplanned and inefficient adjustments to compensate for poor planning / projections Creates / perpetuates instability Pushes costs into the future Robs Peter to pay Paul Reduces procurement quantities

Unrealistic Cost Estimates Hinder Accurate Funding Commitments Estimates are often based on limited knowledge about requirements and technologies and optimistic assumptions lack of systems engineering analysis up front Our analysis of 20 programs found that both CAIG and Service estimates tended to be too low Estimates are presented as point estimates representing most likely cost and do not depict risk and uncertainty Program cycle times are longer than the FYDP timeframe

DOD s Failure to Balance Needs with Resources Promotes Unhealthy Competition Relying on unrealistically low estimates, DOD has committed to more programs than its resources can support In a zero-sum game, increases in one program will impact other programs Pressure to make a program stand out from others Pressure to appear affordable (fit within the FYDP) When reality hits and things don t go as planned, instability is the inevitable result

Recommended Steps to Improve Program Funding Balance the current portfolio (to reduce the pressures of unhealthy competition) Require programs to have short, manageable development cycles (5 to 6 years long) Require cost estimates to be presented as a range of likely costs (wider at a milestone A point and more narrow at milestone B)

DOD s Requirements Process (JCIDS) Has Not Been Effective in Prioritizing Joint Capabilities JCIDS is not meeting its objective to prioritize joint warfighting needs Military services, not the joint warfighting community continue to sponsor most JCIDS proposals Almost 70% of initial capability proposals submitted to JCIDS since 2003 were sponsored by a military service Virtually all capability proposals that go through the JCIDS process are validated or approved Of 140 capability proposals since 2003 that completed the process, only 6 were not validated Process is also lengthy and cumbersome, making it difficult to respond to near-term needs DOD is losing opportunities to strengthen joint warfighting capabilities and constrain its portfolio of weapon system programs to match available resources GAO-08-1060

DOD Lacks An Approach and Alignment of Resources to Prioritize and Balance Capability Needs JCIDS largely responds to capability proposals that are submitted by sponsors on a case-by-case basis Lacking a more proactive and analytic approach, JCIDS has been ineffective at integrating and balancing needs The military services continue to drive the determination of capability needs, in part because they retain most of DOD s analytic capacity and resources Without an approach and entity in charge to determine what capabilities are needed, all proposals tend to be treated as priorities within the JCIDS process

Recommended Steps To Improve JCIDS Develop an analytic approach within JCIDS to better prioritize and balance capability needs department-wide, and Determine and allocate appropriate resources for conducting joint capabilities development planning

Related GAO Products Defense Acquisitions: DOD s Requirements Determination Process Has Not Been Effective in Prioritizing Joint Capabilities. GAO-08-1060. September 25, 2008. Defense Acquisitions: A Knowledge-Based Funding Approach Could Improve Major Weapon System Program Outcomes. GAO-08-619. July 2, 2008. Defense Acquisitions: Better Weapon Program Outcomes Require Discipline, Accountability, and Fundamental Changes in the Acquisition Environment. GAO-08-782T. June 3, 2008. Defense Acquisitions: Assessments of Selected Weapon Programs. GAO-08-467SP. March 31, 2008. Cost Assessment Guide: Best Practices for Estimating and Managing Program Costs. GAO-07-1134SP. July 2, 2007. Best Practices: An Integrated Portfolio Management Approach to Weapon System Investments Could Improve DOD s Acquisition Outcomes. GAO-07-388. March 30, 2007.