TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER

Similar documents
The Austrian Koralm tunnel - Investigation, Design and Construction Process for a large Base Tunnel Project

TBM Selection and Specification

Semmering Base Tunnel Large Caverns in Challenging Conditions

Hardrock Tunnel Boring Machines

2

SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING

TUNNEL WIENERWALD ABSTRACT

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

Excellence in tunnel engineering. Consulting, planning, realisation

Experts in tunneling with Tunnel Boring Machines

RISK MANAGEMENT. Harald Wagner PhD, PE

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Pump storage hydro power plant (PSKW) Reißeck

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

2.1 Backfill - General

FAST-Tunn Future Advanced Steel Technology for Tunnelling

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul

Prof. Eng. Daniele PEILA

HORIZONTAL CONCRETE MIXING PLANTS. Horizontal Concrete Mixing Plants HN 1.5 HN 4.0 H 5 H 6

Pipetron Tunnel Construction Issues

CONCRETE FOR THE WORLD S LONGEST TUNNEL REQUIREMENTS, PRODUCTION AND TRANSPORT OF CONCRETE AND SHOTCRETE FOR THE GOTTHARD BASE TUNNEL.

4th International Engineering and Construction Conference - July 28, 2006

GBR Fundamentals. Past Practices and Lessons Learned. Seminar on Geotechnical Baseline Reports. October 5, 2013

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Construction Technology B (CON4313)

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China

Tunnel Kennedy Santiago de Chile

Performance review of a pipe jacking project in Hong Kong

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

Introduction to Tunnel Construction

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

INTERNATIONAL SEMINAR LONG TUNNELS

INTERNATIONAL DESIGN & CONSTRUCTION

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA

Pipe Jacking. Japan Sewage Works Association

Challenges in the Remediation of the Glatscheras-Railway-Tunnel, Bergün, Switzerland

Optimization of Supports in a Road Tunnel through Conglomerate during Construction

DESIGN AND CONSTRUCTION OF LARGE LAINZER TUNNEL PROJECT. Josef Daller, ic consulenten, Vienna - Austria

2015 UTAH ASPHALT CONFERENCE AGGREGATE PRODUCTION 101. Kilgore Companies and Kimball Equipment

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

From Colonia Jardín to Cuatro Vientos

EINRIP. Specification and Construction Issues

Application of Chemical Grouts to Tunnel Repair Latest Technology

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

Metro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban tunnelling

COVERING THE HIGHWAY E12 IN THE CENTRE OF HÄMEENLINNA INNOVATIVE USE OF FOAMED GLASS AS LIGHT WEIGHT MATERIAL OF APPROACH EMBANKMENT

SAFE WORK METHOD STATEMENT

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling

Anti-wear and Anti-dust Solutions for Hard Rock TBMs

Aggregate Specifications

Pipe Jacking. Progress is built on ideas.

Mitigation of the effects induced by shallow tunneling in urban environment: The use of compensation grouting in the underground Line B1 works in Rome

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

Slab Track Austria. System ÖBB-PORR elastically supported slab

Tender for the Supply of Fine Sand for 33kV Cabling Works in Suva

3 rd Edition of the ITA Tunnelling Awards - the winners 2017!

Transport development between Helsinki-Tallinn twin cities

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project

CHAPTER 1 INTRODUCTION

Partial Factors of Safety

Field trips 7, 14, 15. Brenner Base Tunnel

Diaphragm wall Construction

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION

Conception Design Construction Operation.

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

DEEP FOUNDATIONS. Rio de Janeiro Subway Line 4: An OPA Finalist. Battered Piles. Sheet Piling. Challenging SOE

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS

Membrane for tunnels and underground construction

REPORT STATUS: DATE: Report n :

h Installation Manual

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB)

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

UNDERPINNING A CRANE FOUNDATION

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

engineering innovation

SITE INVESTIGATION Validation and Interpretation of data

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

MANAGEMENT. Construction. Jason Adams, VP of Systems

EUROPEAN AGGREGATES ASSOCIATION. A Sustainable Industry for a Sustainable Europe

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary

FIBRE REINFORCED SHOTCRETE FOR LONG TUNNEL PROJECTS IN SWITZERLAND

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. Current Status of the Nuclear Waste Management Programme in Finland 13441

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

Job Reports WR 240 / WR 240 i. Performing to highest quality standards whatever the job

Tel: Neil: Tony: Website:

Optimized crusher selection for the cement industry

THE GROUNDBREAKING TUNNEL

Oil and gas companies are pushing for improved performance and better efficiency from service providers

Transcription:

TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck Gerhard HARER

2 Project overview Koralm railway Part of the Baltic-Adriatic Core Network Corridor, which is one of the most important transeuropean traffic axes. Client Ref.: baltic-adriatic.eu

3 Project overview Koralm tunnel 32,9 km 2 tubes, 2 ventilation shafts, 1 emergency stop 1/3 NATM, 2/3 TBM Ref.: ÖBB, 2015

4 Project overview Koralm tunnel - Geological framework E KAT1 Tertiary sediments KAT2 Crystalline basement KAT3 W Tertiary sediments 32,9 km Exploratory tunnels Ref.: Harer/ÖBB, 2014

5 Excursus: Selection of the appropriate excavation method The selection of the appropriate excavation method is one of the most crucial decisions for a tunnel project. It is influenced from a plenty of parameter, such as: Geological conditions Excavation lengths and cross section Construction program Logistic demands and accessibility Environmental aspects Dumping demands and the re-use of mucking material...

6 2 TBM lots KAT2 & KAT3 Ref. Infothek.bmvit.gv.at KAT2: TBM-DS 16.2 + 17.2 km KAT3: TBM-S (EPB) 10.5 km

7 Lining concept Single shell lining In general drained Pressure-tight for sediment section KAT3 Option for inner lining Ref.:Harer/ÖBB, 2014

8 High-performance hard-rock TBM KAT2 Technical data*: DN = 9.93 m Cutter dia. 17 20 Spacing 80 mm Driving power 4,900 kw Contact force 20,000kN Torque nom. 7,800 knm Torque max. 30,000 knm *) according to technical offer JV KAT2 Ref.: ÖBB, 2013

9 TBM performance KAT2 Start of TBM excavation 2012/2013 Already excavated 12.4 km (S) + 13.2 km (N) Best daily performance 45.7 m Best weekly performance 210 m Recent weekly average performance 100 m Excavation rate Status: 03/2016 2012/2013 Development of excavation rates (South tube, schematic) 2014 fault zone 2015 Construction time

10 TBM performance KAT2 Geological conditions are not significantly different compared to prognosis The technical performance of the JV is outstanding However, a time lag between planned and actual advance occurred So what is the reason of the loss of time?

11 TBM performance KAT2 Singularities: A collapse within a predicted major fault zone caused severe time loss and required additional measures Crumbling/friable rockmass and insufficient annular bedding required additional injection measures (which negatively affected logistics) to avoid additional load and deformation of the tunnel lining Ref.: Harer/ÖBB, 2014

12 TBM performance KAT2 Decrease in penetration: Penetration decreases locally from 4-6 mm/rev. down to 1 2 mm/rev. Locally increased rock stress is the most probable reason for local decrease of penetration (Büchi, 2014) However, This theory is controversially discussed How to predict realistically abnormal stress conditions?

13 TBM performance KAT2 Cutter disk damages: Outbreaks in heading face cause extraordinary high damage of disc cutters The original cutter wear decreases from roughly 300 400m3 cutting volume/disc down to 100m3 cutting volume/disc

14 TBM performance KAT2 Conveyor belt damages: Locally friable and crumbling conditions cause coarse, swordshaped blocks (passing the primary crusher and cutting the conveyor belt) Increase of primary crushing negatively influences the re-use of mucking material normal mucking material sword-shaped mucking material

15 TBM performance KAT2

16 TBM performance KAT2 TBM defects: TBM possesses unexpected high requirement of maintenance and repair Main bearing and main bearing seal Cutter head welding Motors Fire

17 TBM performance KAT3 South tube excavated by means of NATM TBM excavation started in N-tube in late 2015 Already excavated 2.2 km Ref.: metz-partner.at, 2015

18 Re-use of mucking material (KAT2)

19 Mucking material flow (KAT2) Total excavation 8,6 Mio. to Concrete 1,5 Mio. to Open sections 2,9 Mio. to The re-use of 60 % of the excavated material is part of the project! Dumping 3,0 Mio. to External recycling 1,2 Mio. to (removal by rail)

20 Typical petrology for aggregate production Ref. Posch & Tauer, 2016

21 Typical petrology for aggregate production Ref. Posch & Tauer, 2016

22 Requirement of extensive site logistics (KAT2) Ref. Posch & Tauer, 2016

23 Principal facilities (KAT2) Primary crusher on the TBM Conveyor belts (horiz. & vert.) Pre-screening Secondary screening (option.) Gravel and sand plant Aggregates deposits Rail loading facilities Feeder line Open sections and dumping grounds Ref. Posch & Tauer, 2016

24 Aggregate production (KAT2) Up to now (03/2016) 550,000 t successfully produced Ref. Posch & Tauer, 2016

25 Aggregate production (KAT2) Processing rate: Highly volatile Rate (products : input) at present appears to be slightly lower than predicted However, rate tends to increase (since improvement measures have been successfully established) Ref. Posch & Tauer, 2016

26 Re-use of TBM muck concluding remarks: Material processing must be properly designed in advance However, only a few reliable/coherent data from former projects are available Petrological & geochemical conditions as well as the degree of fracturing are highly influencing the output rate Furthermore cutter head design and TBM operation may influence the grain size distribution of muck It s a specialist s job Best available technology, material and interface management, triage at the face and partnership are required

27 Re-use of TBM muck concluding remarks: No shortages in supply occurred Excellent products were achievable (C35/45 up to C50/60) However, the average output rate in the past appears to be slightly lower than predicted The project was honored with an award from the Federal Ministry of Agriculture, Forestry, Environment and Water Ref.: oewav.at

28 Concluding remarks TBM drives: Investigation and design, which considers specific ground parameter and behavior is essential for TBM-, excavationand support design Competent staff on site, good workmanship and partnership are absolutely necessary (both contractor and consumer) To consider only net penetration rates or daily performance is misleading The occurrence of singularities has to be respected Flexibility is very limited in comparison to NATM/drill&blast, in particular in case of special situations Logistics directly influences the advance rates

29 Concluding remarks TBM drives: We are exactly in time and budget (Harer, Oslo 2014) As per the information of ÖBB this is still valid, since a proper overall risk assessment has been made and risk mitigation measures were planned in advance. However, the system limits might be reached soon. Different perceptions of contractors and owner regarding deviations and spheres will cause contractual claim negotiations.

30 Concluding remarks TBM drives: The selection of the appropriate excavation method (and a suitable TBM system) is one of the most crucial decisions Since the geological risk belongs to the owner it is also his responsibility to define appropriate minimum criteria It is also in the responsibility of the TBM suppliers not to arouse false hopes It seems that properly evaluated ground parameter do not fully flow in the TBM design Further research and improvement is requested Communication across the interfaces customer consultant contractor supplier has to be improved

31 Concluding remarks TBM drives: For the lot KAT2 Continuous investigation in advance of heading is performed (TSWD, if required probe drilling) to reduce uncertainties The complex interplay between logistics and TBM excavation was underestimated A state-of-the-art excavation with NATM/drill&blast would have caused considerable additional works and expenses (addl. ventilation shafts, widening of diameter,.) The average daily advance with TBM (in average 13 m/calendar day) is better compared to NATM/drill&blast and comparable or larger than in comparable projects

32 Concluding remarks TBM drives: The advantages of TBMs in the author s opinion arise esp. in: Uniform tunnel shapes (constant diameter, no niches etc.) Long tunnels (taking into account construction time, logistics, ventilation, environment,.. 10 km?) Smaller diameters Homogenous geological/geotechnical conditions Soft ground tunnels with little overburden

Thank you very much for your attention! harer.gerhard@gmail.com