THE YEMEN LNG PROJECT LE PROJET GNL YEMEN

Similar documents
Yemen LNG Operational feedbacks

MLNG DUA DEBOTTLENECKING PROJECT

We deliver gas infrastructure

Brownfield Projects. Equinox Engineering

Alaska South Central LNG (SCLNG) Project

ENGINEERING CONSULTANCY SERVICES

Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL

GLADSTONE LNG leads the way with its first LNG shipment in 2012

LNG Plant Overview. Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen

Appendix A: Project Characteristics

Dominion Cove Point Export Project Platts 16 th Annual Liquefied Natural Gas February 9, 2017

A World of Solutions Visit Product Storage Terminals for Bulk Liquids

Floating LNG Business A breakthrough in offshore gas monetization

DSLNG Project Update. Andy Karamoy PT Donggi Senoro LNG. 4 th LNG Supply, Transport and Storage Indonesia May 2014 Bali, Indonesia

Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013

ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

LNG Experience. Owner & Investor Project Management

Teknologi Pemrosesan Gas (TKK 564) Instructor: Dr. Istadi ( )

MOLECULAR GATE TECHNOLOGY FOR (SMALLER SCALE) LNG PRETREATMENT

Evolution of an LNG Terminal: Senboku Terminal of Osaka Gas

Enabling safe and reliable offshore LNG transfer operations By Vincent Lagarrigue, Marketing & Project Manager within Trelleborg Industrial Solutions

Natural Gas. and the Liquefaction Process

UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT

The Technical & Practical challenges of FLNG

FUGRO GROUP LNG FIELD DEVELOPMENT AND FACILITIES. TACKLING your complex challenges. UNDERSTANDING your operational objectives

Energy East Pipeline. Project Overview. Kevin Maloney Manager, New Build Pipeline AB, NB, JV Irving and Cromer September, 2014

Natural Gas Facilities & Pipelines

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

ENERGY MANAGEMENT INITIATIVE AT PETRONAS LNG COMPLEX

Optimising. the LNG process. The rapidly expanding global LNG industry continues. Projects

Transportation of Natural Gas-LPG Mixtures

Improving Natural Gas Liquefaction Plant Performance with Process Analyzers

DYNAMIC SIMULATION FOR DESIGN IMPROVEMENTS, COST REDUCTION AND OPERATIONAL STABILITY IN LNG PLANT DESIGN

MITIGATION OF SEASONAL PRODUCTION LOSS FOR THREE PARALLEL 4.7MMTPA

BASED ON EXPERIENCE TGE GAS ENGINEERING EVOLUTION OF SAFETY DESIGN FOR CRYOGENIC TANKS REVAMP VS. NEW BUILT

LNG UNIT (ENGINEERING DESIGN GUIDELINE)

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

LIQUEFIED NATURAL GAS LIMITED

REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS)

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION

Technical Summary for TCC0 Global overview of the scope for TCC0 contract

Alaska LNG Concept Information. Alaska LNG. Overview. October

The Pipelines Regulations, 2000

Company Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran

Modular Oil & Gas Equipment Onshore & Offshore

INCREASING THE CAPACITY OF NGL RECOVERY TRAINS. Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas de Mayo de 2004

TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum

TCO Future Growth Project Wellhead Pressure Management Project

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA)

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

LIQUEFACTION STORAGE DISTRIBUTION BUNKERING SMALL-SCALE LNG SOLUTIONS

AKAKUS OIL OPERATIONS- LIBYA Gas Utilization& Flare Emission Reduction Project

17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

Azeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment

ITER Quality Assurance

Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant

GAS CONDITIONING & PROCESSING TRAINING

Review of Project Proposed for CSLF Recognition: Al Reyadah CCUS Project (Phase I: Emirates Steel)

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant

LNG LIQUEFIED NATURAL GAS TECHNOLOGIES

PART 3 TERMINAL INFORMATION

Engineering and technologies Gas processing

Document B252TM 2007

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and

B.C. TOWBOAT INDUSTRY CONFERENCE

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

Oman LNG LLC. Pre-Qualification Questionnaire. QEN EPC to Construct Car Parking Sheds with Solar Photovoltaic Panels


Resolution MEPC.11(18) adopted on 25 March 1983 GUIDELINES FOR SURVEYS UNDER ANNEX I OF THE INTERNATIONAL CONVENTION FOR THE PREVENTION OF POLLUTION

DESIGN AND OPERATING EXPERIENCE FOR ANADARKO S LANCASTER FACILITY

Drive Selection for LNG FPSO

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Transportation and regasification infrastructures

ENERGY. Responding to the Upstream Boom

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

Contract Quality Requirements Manual SLM Issue 3

Qualitative Phase Behavior and Vapor Liquid Equilibrium Core

LARGE STORAGE TANK PROJECT

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES

LNG Houston, February 6-7 th, The case for developing a Floating LNG Receiving Terminal on the US East Coast

California Resources Corporation. Health, Safety & Environmental Management System

Appendix A. Project Description

Magnetically Coupled Submerged Cryogenic Pumps and Expanders for Ammonia Applications

Project phases II. Tendering-constructionoperation

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

Saudi Aramco General Bid Slates (GBS)

By-Law Number 9 Concerning Procurement Contracts for Goods, Services and Construction

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Item Hydrogen Gas Plant

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065

Creating Optimal LNG Storage Solutions. 40 in detail

MEETING TECHNICAL CHALLENGES IN DEVELOPING HIGH CO 2 GAS FIELD OFFSHORE

URGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS

CONVERTING DOMINION COVE POINT LNG INTO BIDIRECTIONAL FACILITY

ENGINEERING SERVICES

Transcription:

THE YEMEN LNG PROJECT LE PROJET GNL YEMEN Jean Paul Azalbert Dr. Khaled Muhsin Frank Kern Yemen LNG Company Republic of Yemen ABSTRACT The Yemen LNG Project is on its way now for two years. The paper focuses on the technical part of the substantial efforts carried out so far by Yemen LNG Company, from Project Definition through the Call for Tenders Documents. RESUME Le projet GNL Yémen est maintenant à l étude depuis deux ans. La présentation est centrée sur la partie technique de l important travail réalisé par la Yémen LNG Company, depuis la définition du projet jusqu aux documents d appel d offre. 4.4 1

THE YEMEN LNG PROJECT 1. BACKGROUND The valorization of the gas reserves of Marib fields in Yemen under the form of LNG has been envisaged now for six years. After several attempts to materialize this project, Yemen sent in 1994 a call for tender to various possible Project. On February 1, 1995, the Yemeni Council of Ministers designated TOTAL as the Lead shareholder of the Yemen LNG Project. Shortly thereafter, in early 1995, negotiations were initiated with the Marib field shareholders, for their affiliates joinder to the Project, i.e., EXXON YEMEN LNG COMPANY Ltd (EYLNG), YEMEN HUNT LNG LLC (YHLNG), and YUKONG LIMITED (YUKONG). In September 1995, the Ministry of Oil and Mineral Resources (MOMR), Yemen Gas Company (YGC) and TOTAL signed a Gas Development Agreement to be further approved by the Parliament of the Republic of Yemen. As a consequence, the YEMEN LNG COMPANY (YLNG) was incorporated in Bermuda, for the purpose of implementing the project; its initial shareholders were YGC and TOTAL YEMEN LNG COMPANY (TYLNG). The YLNG Company has been created to process, to export and to sell LNG for a period of 25 years after commencement of Commercial Production, transporting the feed gas from the Marib fields to the LNG Plant, and delivering feed gas to YGC in the North of Sana a area, through a Spur Line, and to construct all corresponding facilities. A Project Definition study was performed by the Lead Shareholder from July 1995 to March 1996: the design criteria of the facilities were defined and the selection of the LNG Plant site and of the pipeline routes were made. For that purpose, a data acquisition campaign was launched on the different potential sites, with topographical and geo-technical surveys. Out of six potential sites surveyed in June 1995, Bal-Haf was selected on the Gulf of Aden coast, approximately 160 km West of Al-Mukalla, 320 km south east of the gas producing field of Marib and 450 km east of Aden. The pipeline routes between the Marib area and the delivery points in Bal-Haf and near Sana a were also identified. The selections of both the pipeline routes and the Bal-Haf site were endorsed by MOMR. As part of the Project Definition studies, after various feasibility scenarios, a Statement of Requirement was developed with identification and selection of all governing principles of the facilities, the selection of the base processing case with Air Products and Chemicals, Inc. (APCI) and the definition of the scope of the Front End Engineering Design phase which commenced in March 1996. 4.4 2

In January 1997, MOMR, YGC and TOTAL in conjunction with EYLNG, YHLNG, and YUKONG, plus associates of some of these companies, signed 7 Agreements as applicable: The Gas Development Agreement (GDA) The Upstream Facilities and Services Agreement The Subscription & Participation Agreement The Shareholders Agreement The Upstream Operating Agreement The Upstream Joint Venture & Shareholders Agreement The Feed Gas Delivery Agreement Both the Gas Development Agreement and the Upstream Facilities and Services Agreement were ratified by the Parliament of the Republic of Yemen, prior to the issue of a Presidential Decree in March 1997. The final closing between the initial and new shareholders also took place in March 1997. As of year-end 1997, the Front End Engineering Design was complete as was the preparation of the calls for tender packages. The lists of potential tenderers have been approved by the Board and MOMR, based on completed prequalification process. 2. SHAREHOLDERS YLNG current shareholders are: % TOTAL YEMEN LNG COMPANY LTD (lead shareholder) YEMEN GAS COMPANY YEMEN HUNT LNG COMPANY LLC EXXON YEMEN LNG COMPANY LTD YUKONG LIMITED 36 26 15.1 14.5 8.4 3. PROJECT PHASES The project will be implemented in three phases : Phase 1 : The Preliminary Phase, comprising the conceptual design work and the Front End Engineering Design and preparation of the calls for tenders 4.4 3

Phase 2 : Construction Phase This phase extends from the date on which YLNG notifies Ministry of its decision to proceed with Phase 2 until Commencement of Commercial Production and shall include all works related to engineering, procurement and construction. Phase 3 : The Commercial Production Phase That phase extends from the date of Commencement of Commercial Production, i.e., the date at which the first regular export of LNG occurs, and shall last at least 25 years. 4. PROJECT DESCRIPTION 4.1. The Fields / The Upstream Facilities Under a Production Sharing Agreement(PSA) with MOMR, Yemen Exploration and Production Company (YEPC) - the Upstream Operator - is currently operating the fields of Block 18, located in the Marib area, approximately 190 km East of Sana a. The gas is processed for LPG extraction and condensate C5 + recovery, prior to reinjection, at the production units located at Alif Central Processing Unit (CPU) and at Kamil Processing Unit (KPU). Out of the 26 000 bpd of LPG currently produced, 11 000 bpd supply the current local market, and the surplus is re-injected with the treated gas. The field reserves have been certified by the certifying independent agent DeGolyer and MacNaughton, who confirmed that the reserves were ample to support the Project. A gas analysis campaign performed during the 1996 spring has shown a gas of good quality, ideal as liquefaction plant feed: low nitrogen low carbon dioxide no hydrogen sulfide nor sulfur components no mercury A total of about 2 100 MMscfd (stream day) of gas are currently produced from 15 fields in the Marib area, with the great majority (95 %) coming from major fields: Al Raja (condensate gas field), Kamil (oil field), Azal (oil field) and Alif (oil field). Some other smaller gas accumulations, already delineated but not developed yet, will be put on production at a later stage according to a Long Term Gas Delivery Plan which is being performed. 4.4 4

Out of these 2 100 MMscfd, approximately 2 000 MMscfd are re-injected into different dedicated reservoirs, of which: 1600 MMscfd are processed through four Natural Gas Liquids (C3 + ) extraction plants: one lean oil absorption plant and one cryogenic extraction plant at the CPU and two cryogenic extraction plants at the KPU 400 MMscfd are by-passing these NGL plants. All along the project life, upstream facilities will be installed and/or modified to meet the LNG project requirement with respect to the quality and quantity of the feed gas. At the early stage of the project, the required new Upstream Facilities were identified as follows: drying of the NGL Cryogenic plant by-pass (mole sieve unit) in order to avoid any water condensation in the main line, minimization of C5+ in the LNG feed gas by processing all or a portion of currently by-passed gas. letdown stations in order to deliver the feed gas at the delivery point at sufficient pressure to enter the mainline, 2 metering stations for custody transfer, flaring facilities, all necessary ties-in, manifolding and interconnecting piping. The studies / modifications to the upstream facilities are performed by YEPC, but at YLNG costs. Currently, YEPC is performing the studies which are part of the approved YEPC 1997 Work Program. 4.2. The Pipelines The project will include three pipelines that will traverse widely varied topography and elevations: For the 2 liquefaction train LNG Plant, the 320 km long, 36 diameter Main Line will transport feed gas from KPU to Bal-Haf at an initial flow rate of approximately 900 MMscfd. Additional flow rate for a potential third liquefaction train at Bal-Haf can be obtained with the installation of an intermediate booster compression station located near Mikrab, 40 km North East from Ataq. Associated with the Main Line, the 26 km long, 20 diameter Transfer Line transports gas between CPU and KPU through a flat desert area of sand dunes at a flow rate corresponding to the requirements of the two train LNG plant. The 200 km long, 14 diameter Spur Line will transport, for MOMR use, gas from CPU to a delivery point North of Sana a at an initial flow rate of 100 MMscfd and with an ultimate potential flow rate of 250 MMscfd by installing future intermediate compressor stations. 4.4 5

These three pipelines will be: operated dry, free of any liquid hydrocarbons and water, designed according to ASME B 31.8 code requirements, including sectionalization block valves, buried, of grade API 5L, X 70 steel, and externally protected with a polyethylene coating. The pipeline parameters and block valves will be controlled by a System Control And Data Acquisition (SCADA system); a fiber optic cable installed parallel to the pipeline will provide communication links. The electrical power needed for emergency shut down valves, SCADA system, and permanent cathodic protection by impressed current, will be supplied, for the extremity sections, respectively from CPU, KPU and the Bal-Haf plant. For each intermediate block valve station, thermo electric generator units will be installed. 4.3. The LNG Plant The LNG Plant will be constructed on a 120 hectare site at Bal-Haf. It will be fully self supporting, independent of any local infrastructure and will include administrative buildings, process facilities, utilities, offsites and a marine terminal. Admin Zone The administrative zone includes a group of buildings, among which are: administrative building canteen medical center training center and other infrastructure needed to support plant operations. Process Area The plant will be designed for minimum capital cost within the limits set by efficiency, reliability, safety and environmental impact. Based on 335 stream days per year, two liquefaction plants in parallel will be installed to achieve an annual guaranteed production of 5.3 million metric tonnes per year, FOB. The two train LNG Plant will have the following major process / product handling facilities, as listed here below: Feed gas reception facilities Acid gas (CO 2 ) removal 4.4 6

Dehydration Liquefaction system LPG Fractionation for refrigerant make-up and C5+ removal. Prior to liquefaction, the carbon dioxide content of the natural gas will be reduced to 50 ppmv in an amine type acid gas removal unit. Water content will be reduced to 1 ppmv in a molecular sieve unit to prevent any freeze out in the cryogenic sections of the plant. A mercury guard bed will be installed to ensure removal of any trace amounts of mercury, although none has been detected in the feed to date. The liquefaction process is based on Air Products and Chemicals, Inc. (APCI) Propane / Multi Component Refrigerant (MCR) process, which requires a propane refrigerant cycle multistage centrifugal compressor driven by a Frame 7 - size gas turbine and a centrifugal / axial compressor for the mixed refrigerant liquefaction cycle, also driven by a Frame 7 - size gas turbine. The overall refrigerant power required for a train of 2.65 Mtpa is approximately 115 MW, of which 66 MW are required for the liquefaction cycle. As a component of their license, APCI are also supplying the spool wound Main Cryogenic Heat Exchanger (MCHE) for gas liquefaction. Utilities Area To support the operation of the LNG Trains, the following common facilities are required: Flare systems Electrical power generation - main and emergency Cooling media Heating media Fuel systems Nitrogen generation Compressed air Fire protection systems Fresh water Telecommunications Surface drainage Direct sea water cooling will be used, with a sea water flow of 60 000 m 3 per hour, for the two trains. Low pressure steam will be used as heating medium. Three Frame 6 power generation sets will be installed to supply the power required for plant operations. The fuel gas required will be supplied from the LNG trains and by the boil off gas from the storage area. Fuel gas demand represents 10 to 12 % of the total gas feed to the plant. 4.4 7

Storage LNG produced will run down to two storage tanks at a temperature of - 162 degree Celsius, with a higher heating value (HHV) in the 1 050 / 1 110 Btu/scf range. The LNG net storage capacity, based on transportation studies, is 250 000 m3. Two 125 000 m3 tanks will be installed. For safety reasons, we have selected above ground full containment tanks with either a concrete outer shell and a free standing 9% Nickel alloy inner tank, or a stainless steel membrane in a concrete outer shell. Marine Facilities All the components of a self sufficient LNG marine terminal will be installed, including a turning basin, a service vessel / tug berth and a marine base. A single berth will be installed to accommodate LNG carriers in the 45 000 / 140 000 m3 range. The location, orientation and design of the berth have been considered with due attention to weather, sea and meteorological conditions, mooring breasting, tug assistance, access and departure in case of emergency. Marine Off-loading facilities (M.O.F.) will also be installed for unloading of equipment for the LNG plant during the construction period. Off Plot Facilities In addition to the above, an air strip for Dash 7 type planes, available take-off 950x45 m, for normal day light shift rotation, will be installed at a short distance, North West of the Plant. An access road will link the main Al Mukala / Aden road to the LNG Plant and to the Permanent Camp Pre investment for a Third Train In view of a potential 50% increase in the capacity of the liquefaction plant, the possibility of installing a third process train and a third LNG storage tank, with associated utilities and plant layout is taken into account in the current design. Permanent Camp Its location is on the Bal Haf North Rock situated to the West of the access road to the LNG Plant, at the crossing with the main AL Mukalla / Aden road, close to the Construction Camp area of the LNG Plant. The Operating Organization is not yet finalized, but for current design purposes, it is assumed that approximately 700 persons will be accommodated in the Permanent Camp, with 23 000 m 2 floor space on a 58 hectare area. 4.4 8

The personnel to be accommodated in this Camp is YLNG Payroll personnel for normal operation, routine maintenance and support services. 5. CONTRACTING/IMPLEMENTATION One of YLNG objective is to finance the Project through non recourse, Project financing credits and Export Credit Agencies (ECA s). 5.1. General During the preparation of the call for tender for the Front End Engineering Design (F.E.E.D.) of the whole facilities (pipelines and liquefaction plant), the following contracting strategy was envisaged for the construction phase of the works: construction contracts will be lump sum, contracts will be awarded by installations, and not by disciplines, number of contracts will be kept to a minimum, some Early Contracts (LNG storage, refrigeration compressors, Main Cryogenic Heat Exchangers, ) will be prepared during the F.E.E.D. period, and ultimately assigned to the selected Main contractor, constraints of non recourse financing will have to be considered, monitoring and control will be made by the Project Task Force. YLNG Contracting Strategy aims to fulfill 3 objectives: to select EPC contractors who will provide their specific LNG experience to design, procure, supply, erect and commission fit-for-purpose facilities, to obtain cost effective implementation through competitive bidding, to maximize non recourse financing by providing to the banking community the comfort of a frozen project cost guaranteed by sound and capable contractors. In order to reach these objectives, the following actions have been / will be implemented: launching a pre-qualification exercise to ensure that the most experienced construction contractors are selected (done), providing calls for tender dossiers with an adequate level of engineering and data acquisition details to allow for all inclusive lump sum quotes. defining a minimum number of bid packages to limit to a bare minimum the potential claims and corresponding increase in investment costs, by reducing interfaces between contractors and between YLNG and the construction contractors (done). The contracting strategy was endorsed by the Board of Directors. 4.4 9

5.2. Action plan Pipeline A pre-qualification questionnaire was issued, answers analyzed, recommendation endorsed by YLNG Board and approved by MOMR. In order to obtain, from the various potential EPC pipeline laying contractors, comprehensive quotes without any qualifications relating to soil conditions and to route changes, an aerial survey of the routes has been performed and precise mapping of all areas has been completed. In addition, a geo-technical survey of the entire pipeline routes has been made. This will allow the incorporation of all pertinent data into the pipeline alignment sheets. The call for tender dossier for the installation of the pipeline consists in the base case of a single package with the Main Line + Transfer Line as one sub package (to be installed first), with the Spur Line as a second sub-package to be sequentially installed. As an option, independent quotes will be solicited for the Main Line + the Transfer Line on one side, and the Spur Line on the other side. Taking into account the importance of the supply of the line pipe, a pre-qualification exercise has been implemented to identify potential steel mills. The line pipe supply could be considered as a Long Lead / Critical Item to be assigned to the EPC contractor(s), or, as the supply of the line pipe is not on the critical path of the Project, could be directly incorporated into the scope of supply of the EPC contractor(s), depending upon the best interest of the Project. LNG Plant A pre-qualification questionnaire was issued, answers assessed, recommendation endorsed by YLNG Board and approved by MOMR. Long Lead / Critical Items A few parts of the facilities have a major impact on cost, schedule and / or on the technical content of the Project; accordingly, Long Lead / critical Items have been identified. The calls for tender, evaluation and pre-award, and possibly award, will be directly performed by YLNG prior to the award of the main construction contract. LNG storage: pre-qualification questionnaire was issued, answers analyzed, recommendation endorsed, MOMR approval obtained. The issue of this call for tender will be coordinated with the issue of the LNG Plant call for tender. refrigeration compressor manufacturers have already been pre-qualified and the call for tender is in preparation; the issue of this call for tender will be coordinated with the issue of the LNG Plant call for tender. It is envisaged that separate quotes will be requested from the turbine manufacturer and from the compressor suppliers, but with a complete guarantee of the whole package from the compressor supplier. 4.4 10

the call for tender for the supply of the Main Cryogenic Heat Exchanger (APCI) is under preparation. The issue of this call for tender will be coordinated with the issue of the LNG Plant call for tender. a questionnaire has also been sent to line pipe manufacturers, before issuing the corresponding call for tender. In order to minimize the interfaces between YLNG and contractors, these early contracts will be assigned to the corresponding main EPC contractor. Permanent Camp Due to the characteristics of an urban type development, the design and construction of the Permanent Camp will be done independently of the lump sum EPC contract for the LNG Plant. This will allow for taking full benefit of the existence of local resources, with an evolutive contractual strategy, depending upon the findings of the local contractor surveys still to be performed, and upon the results of the different calls for tender. Contracts will be awarded per trade or through a Main Construction Contractor. This will be assessed during the Detailed engineering / Tender period. A step like approach will be implemented for the Permanent Camp development: first, a Project Definition period for finalizing YLNG Statement of Requirements then a Building Permit Dossier / Tender Period with detailed construction engineering and subsequent calls for tender / clarifications / negotiations. and last, the construction period. These different periods will be managed and controlled by the Project Task Force, with the help of ad-hoc consultants, i.e., 2 Architects / Urban Planners and their specialized engineering associates. There will be one consultant for Design and Detailed Engineering, and another, drawing on Yemeni cultural resources, for providing architectural support, cultural and local inputs, and for assisting YLNG in construction supervision. LNG Carriers Options are being considered by the Marketing Committee for sale of LNG, F.O.B, C.I.F. and ex ship basis (refer to corresponding definitions in the narrative to be developed by the shipping group). For the C.I.F sales, it will be the responsibility of the Shipping committee to develop the corresponding implementation strategy and determine the organization, resources, schedule and budget required. E.P.C. Contract Implementation and Oversight In addition to their normal EPC activities, contractors will have to implement all the actions detailed in the Procedures which will be part of the E.P.C. contracts, in particular 4.4 11

those related to Quality Assurance (QA), Health, Safety and Environment (HSE) and Project Control. Although it is contractors responsibility to guarantee and to demonstrate that the installations they design and construct meet the specified specifications and standards, the Project Task Force will monitor all their activities through detailed engineering, construction, pre-commissioning and commissioning. In addition, and according to the Inspections and Quality Assurance Plans, the Project Task Force will perform audits relative to such activities. All commissioning activities will be performed by systems, with a specific hand-over mechanism whereby such systems, and relevant documentation, are handed over by the contractor to the Project Task Force, with YLNG Operation team as a witness. The whole facilities will be transferred to YLNG (Operations) care and custody when the last handover certificate is signed. 6. QUALITY ASSURANCE Quality Assurance (QA) addresses the implementation of a disciplined approach toward all activities affecting quality, including verification, where appropriate. It ensures that each task has been satisfactorily completed, that there is documentary evidence that the required quality has been achieved and that this level of quality has not been inadvertently undermined by subsequent change(s). The concept of quality is normally associated with fitness for purpose, as evidenced by demonstrable compliance with an approved specification. Since QA involves all activities affecting quality, very few activities are exclusive to QA personnel. But the primary responsibility for quality rests with the party responsible for the work. To avoid duplication of QA functions within the Project Task Force and with contractor organizations, and to encourage contractors to exercise fully their contractual obligations in respect of QA, the Project QA function and its degree of intervention in the main contractors QA business will be reduced to the minimum consistent with establishing and maintaining effective quality systems and effective Company auditing activities. This requires that only contractors with strong, independent and suitably staffed QA functions will be considered for the Project. All major contractors will be required to submit quality plans showing their proposed QA system, the procedures to be used, the responsibilities and authorities inherent in them and the quality activities and resources to be allocated. This includes QA/QC of all design activities and change control. Such plans must include the contractor s own schedule of internal reviews and audits, which will be monitored by the Project QA for both performance and effect. 4.4 12

7. SAFETY AND ENVIRONMENTAL IMPACT It is the objective of the Project Team to execute the work in a safe manner, in accordance with the relevant Policies on Health-and-Safety-at-Work and Environmental Conservation. Relevant policy on both these subjects is not only to comply with safety (loss prevention), health and environmental impact measures required by law, but to act positively to prevent injury, ill health, damage, loss and pollution arising from its operations. At all stages of the Project, all operations, whether performed by, or on behalf of YLNG, will conform to the requirements of the relevant statutory regulations and established Company Practices and Policies on Safety and Environmental Impact. In order to ensure that the above policy is effectively implemented, the Project Task Force will develop and maintain a Safety and Environmental Impact Plan. This plan will cover all phases of the Project through design development, detailed design, construction and pre-commissioning, commissioning, start-up and hand-over to Operations; the Project Task Force will be responsible for safety until inerting and handover to Operations. The following subjects will be addressed in the Plan: safety objectives environmental quality objectives acceptance criteria legislative requirements statutory / non-statutory requirements risk assessment environmental impact assessments safety requirements management of changes The Project Team has already completed, with the help of various survey contractors and consultants (both for the Pipelines and for the LNG Plant) the Environmental Base Line Surveys and the Environmental Impact Assessments. Mitigation measures have been identified and incorporated into the design. 8. PROJECT COST & SCHEDULE Studies based on past experience, current trends and Shareholder data bases lead to an estimation of overall cost of the Project for Phase 1 and Phase 2 close to 2.5 billion US dollars (1997) A period of 40 months is planned between the launching of Phase 2 and the first shipment. 4.4 13

9. CURRENT ORGANIZATION Incorporated in Bermuda in 1995, YLNG opened Company Offices in Sana a in 1997 where staffing will be greatly expanded for management of activities relating to Phase 2 (the Construction Phase) and for Phase 3. During Phase 1, certain services are being provided for YLNG through the lead shareholder with a team consisting of secondees from the various shareholders under the direction of a General Manager. 10. YEMENISATION PLAN All the policies and procedures related to the operation of the Company in Phase 2 and Phase 3 are being currently finalized. Among these, the Yemenization plan occupies a significant place. From the very beginning, Yemeni senior and junior staff have been involved within the Paris team, holding responsibility positions. This is to be further extended at quite a significant scale for the years to come. 4.4 14

4.4 15

4.4 16