Diaphragm Walls: A Solution For Deep Excavations In Difficult Soil Conditions With Superficial Water Table

Similar documents
Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Diaphragm wall Construction

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

TECHNOLOGY. Continuous Flight Auger

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

Soil Mechanics Lateral Earth Pressures page Lateral Earth Pressures in case of inclined ground surface or friction at wall-ground interface

Drilled Shaft. Inspection. HQ Construction Office HQ Geotechnical Division

The construction of deep excavation ditch in weak soil in St. Petersburg

Building pit District adjacent to St.Katharinenkirche Hamburg, Germany

Water Well Decommissioning Guidelines

SCOPE OF WORK FOR PILING JOB

Combined Pile Foundation System for a Residential Complex

CONSTRUCTION OF TWO MICROTUNNEL ACCESS SHAFTS USING THE CUTTER SOIL MIX (CSM) METHOD IN THE SAN JOAQUIN DELTA, CALIFORNIA

METHOD STATEMENT for INSTALLATION OF MICROPILE

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

Ground Freezing for Tunnel, Shafts, and Adits

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Aveng Ground Engineering Profile

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

CIVIL BREADTH Exam Specifications

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design

CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

UNDERPINNING A CRANE FOUNDATION

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

Using Thermal Integrity Profiling to Confirm the Structural Integrity of foundation applications

SECTION GRAVEL PACKED WATER WELL

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

Application of Stress-Wave Theory to Piles

Recent Advances in the Selection and Use of Drilled Foundations

Dewatering & Foundations. Water. Low tech

Application of Vibro Techniques for Infrastructure Projects in India

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

Atlaspile. Full soil displacement bored pile, vibration free - low noise economical

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

S.No Description Unit Quantity Rate (Rs) Amount (Rs)

h Installation Manual

Geotechnical Engineering Software GEO5

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

DFI DEEP FOUNDATIONS. Brazil s Megaproject Shipyard Winner of the 2010 Outstanding Project of the Year

Project Address: Name of Person Completing Form:

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Chapter 1. Introduction to Engineering Ground Modification. The Need for Engineered Ground Improvement

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

Temporary Structures. Excavations and Excavation Supports

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN


Overview. O-Pile Attributes

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

DEEP FOUNDATIONS. Rio de Janeiro Subway Line 4: An OPA Finalist. Battered Piles. Sheet Piling. Challenging SOE

Construction Technology B (CON4313)

Case Studies on Soil Nailed Retaining Systems for Deep Excavations

A DSM WALL FOR EXCAVATION SUPPORT

[Kouravand Bardpareh* et al., 5(6): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116

PARSONS BRINCKERHOFF GENERAL GUIDELINES FOR DESIGN AND CONSTRUCTION OF CONCRETE DIAPHRAGM (SLURRY) WALLS. DECEMBER 2008 Revision 0

KIEWIT FOUNDATIONS GROUP

SPECIFICATION FOR REINFORCED SOIL WALL

Estimate FOR THE SEPTIC TANK

SOURCES OF WATER SUPPLY GROUND WATER HYDRAULICS

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR DRILLED SHAFT FOUNDATIONS

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Deep Foundation. Deep Foundation Applications

Ground Improvement Specialists

Steel screw settlement reduction piles for a raft foundation on soft soil

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

Selection of Proprietary Shoring Equipment

Topic: Site Formation

Non-Destructive Testing of Drilled Shafts Current Practice and New Method

Construction Technology B (CON4313)

6 Preliminary Assessment of Construction Method and Constructability Issues

CE 6012 Ground Improvement Techniques Question Bank

SEPTIC TANK CONSTRUCTION GUIDELINES

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

Bonner Bridge Replacement Update:

The Problem. Embankment Dams on Karstic Limestone, Soluble and Erodible Foundations: Challenges and Solutions GEOSYSTEMS, L.P.

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Integrity evaluation of concrete by cross-hole sonic logging in Bangladesh

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS

Bi-Directional Static Load Testing of Driven Piles

Specifications for the Construction of Secant and Tangent Pile Wall Systems using Drilled Shafts

Downloaded from Downloaded from /1

Transcription:

Diaphragm Walls: A Solution For Deep Excavations In Difficult Soil Conditions With Superficial Water Table Paolo Gazzarrini, P.Eng. Sea To Sky Geotech Inc, West Vancouver, BC. ABSTRACT This paper will describe and summarize the definitions, application, construction processes and, briefly, the design methods for Slurry Walls/Diaphragm Walls. This excavation support system has not yet been used in BC or in the Lower Mainland for residential projects even though perfect soil conditions, for this technology, are present. A typical example is Richmond, where deep underground parking is not generally used. Slurry Walls/ Diaphragm Walls can provide economic solutions where temporary and permanent support can be integrated into one retaining structure, or they can provide the only possible solution in extreme soil conditions with the presence of a high water table.. Introduction A Slurry Wall (SW), also called -especially in Europea Diaphragm Wall (DW), is a cast insitu structural underground concrete wall excavated from the surface, with the aid of stabilizing fluids (generally bentonite mud -or polymers- to keep the excavation stable), and constructed in contiguous elements (panels). It is generally reinforced (steel cages) and combines into a single foundation unit, a temporary earth support system, a permanent basement wall, a hydraulic (ground water) cut-off and, usually, a vertical support element. A single element of SW/DW, called a "barrette", can also provide high capacity deep foundation elements as an alternative to piles. "Barrettes" have higher shearing and horizontal bending moment resistance in comparison to piles. It is typically 0.5 to 1.5 meters wide and, if used for excavation support, is typically anchored or braced. Solutions without anchoring or bracing are possible using "T" or "Y" shapes or circular or elliptical plans. Another common, non structural, use of DW/SWs is for water cut-off usually in dams. In this case plastic concrete or self-hardening grout mix is used instead of reinforced concrete. Some definitions, from EN 1538 (European Standard for execution of special geotechnical works- Diaphragm Walls)- Ref (1): carried out using a self-hardening slurry as the supporting fluid. As it is possible to see in Europe there is a very clear distinction between the definition of Slurry and Diaphragm Walls, as is not the case in NA. One should be aware that SW/DWs are totally different from Slurry Trenches, where the excavation is NOT done per panel, but continuously with a backhoe, and where the filling material is NOT engineered. Misleading use of these terms is, unfortunately, still present in our industry. Fig. 1. Diaphragm Wall Cast in situ concrete Diaphragm Wall: wall made of plain concrete or reinforced concrete which is constructed in a trench excavated in the ground. Slurry wall: wall made from a self-hardening slurry. In most cases, the excavation is Historically the first SW/DW was carried out, privately, in Italy by Impresa Costruzioni Opere Specializzate (ICOS) in 1948 and in 1950 the first SW/DW was performed in Fedaia Power Plant. The system was subsequently patented.

Bentonite mud / Polymers The basis of the development of the SW/DW was the study of bentonite mud in excavation. In the early 1920's bentonite was discovered. The first significant advancement to fluid based earth stabilization came from technology developed in East Texas for the drilling of oil and gas. Bentonite, a unique naturally occurring swellable hygroscopic clay with unique electrochemical properties, allows for the control of fluid migration into the formation. Bentonite dispersed in water creates a slurry (mud) with colloidal and tixotropic properties. The bentonite platelets, small brick-like objects in structure with one end of the brick carrying a positive charge and the other end of the brick carrying a negative charge, are transported to the formation interface with the initial migration of water into the formation. However instead of moving into the formation with the water, these clay particles begin to build up on the formation interface. And due to their unique electro-static charge characteristics they start to orient in an organized fashion, end-to-end, or positively charged end to negatively charged end. Within minutes, the bentonite platelets build a wall, or cake, and significantly slow down or stop the flow of the excavation fluid into the adjacent porous formation. Ref (2). See Fig. #2. The hydrostatic pressure of the bentonite slurry in the trench creates a stabilizing action on the internal walls of the excavation preventing its collapse. Sequences, Procedures and Equipment. The typical sequences in the construction of SW/DWs are: 1) Guide Walls Before the construction of SW/DWs, guide walls around the perimeter of the area are constructed. The reasons for the guide walls are: to have a containment of the bentonite slurry that guarantees the presence of a sufficient hydraulic head at the depth in which the slurry start to be necessary, to have a stable starting point of the excavation, assuring the stability of the superficial soil, to easily survey and guarantee the location of the SW/DW and panels, to have a rigid structure to support the rebar cages, to guide the beginning of the excavation tool or equipment chosen for the project. See Fig. #3 with an example of the guide walls. Fig. 3. Guide walls. 2) Excavation. Fig. 2. Bentonite Slurry. Today, more and more frequently, depending on the type of soil to be excavated, and due to potential disposal problems, the bentonite can be substituted by polymers. The excavation can be carried out with the aid of several pieces of equipment, such as (in increasing order of cost): Mechanical clam-shell, Hydraulic clam-shell, Kelly bar Hydromill

Basically any of these excavation tools are mounted on a crane with different characteristics that vary for each tool. See Fig. #4 with the pictures of some equipment. The length of each Primary panel is usually the maximum opening of the clam-shell (or wheels for the hydromill), typically 2.5 to 2.8 meters. In this case the primary panel is done in a single pass 2.5 to 2.8 meters, or so called "single bite". Depending on the type of soil, stability of the excavation, existence of adjacent building, etc, "multiple bites" can be constructed to obtain a bigger Primary panel of a maximum of 6.0 meters. Secondary panels are usually done in a "single bite". See Fig. #5. 2.1) Excavation with mechanical clam-shell, hydraulic clam-shell or Kelly bars. Fig. 4. Typical excavation equipment for SW/DW. The choice of the equipment depends mainly on the characteristics of the soil to be excavated and on the depth to be reached. The excavation is done typically per panel, with, usually, a Primary and Secondary sequence, alternative or successive. In this case the site installation is quite simple. In addition to the bentonite plant (silos or tank for stocking, mixing unit, re-circulation pumps, pipes for distribution to the panels, de-sander and tanks for treatment of the bentonite) and the crane for the excavation, on site it will be necessary to have a service crane that can be used for the installation of the rebar cages, tremie of the concrete and installation and removal of the joints. The simplest tool for excavation is the mechanical clam-shell that is manoeuvred with the free fall cable of the crane. The limitation is in its weight, and to be effective should be quite heavy (6 to 10 tons). An alternate to the mechanical, is the hydraulic clam-shell, more powerful, with the same weight. A Kelly bar mounted clam shell, usually telescopic, has the advantage of being more rigid, providing better control of the verticality in 2 directions (parallel and perpendicular to the SW/DW axis). Fig 5. Sequence of SW/DW construction with multiple bites for the Primary panel.

The bi -axial verticality and tilting of the panel during the excavation is usually measured in real time with bi-axial inclinometers easily installed in the clam-shell. See Fig. #6. Fig. 6 Verticality display in real time and data graphs. Generally the bi-axial verticality and tilting is guaranteed with long hull to assist with the correct balancing of the weight of the tool. Small verticality corrections are possible, adjusting the valves at the bottom of the excavation, or adjusting the number and shape of the teeth. The excavation with clam-shell is carried out with the bentonite slurry "static" and not re-circulating as happens with the hydromill. During the excavation the level of the bentonite slurry is always kept close to the level of the working platform. The clam is used to remove the soil, partially mixed with bentonite slurry, to the surface. Consequently its productivity, with respect to the hydromill, increasingly decreases with the depth. In the case when boulders are found during the excavation, a chisel can be used to break them up. If the boulders are of unusual dimensions, explosives may also be used. In both cases delay in the excavation and over-consumption of concrete can occur. 2.2) Excavation with Hydromill In the case of harder soils, or in the presence of frequent boulders, or soft rock, or when deep excavation with a high degree of verticality is required, a hydromill can be used. Tests of SW/DWs 250 meters deep using a hydromill have been conducted and several case histories of SW/DWs 120 meters deep, mainly in dam cut-offs, are present in the technical literature. See Fig. #7. Fig. 7 Hydromill and typical site installation The site installation is, in this case, much more complicated with respect to the use of a clamshell. The material excavated is brought to the surface through the bentonite slurry (reverse circulation) and the bentonite slurry is always circulating during the excavation. Numerous additional pumps, bigger desanding units and stocking tanks are in this case required. Before the start of the excavation with the hydromill a pre-trench is required, usually done with a conventional mechanical clam-shell, to reach a sufficient depth so that the re-circulation pump (usually installed between the cutters) can start working. Measurement of the verticality is guaranteed with similar bi-axial inclinometers used with the clamshell tools and corrections can be done rotating the wheels of the cutter with different speeds. Verticality can be also corrected using special hulls installed on the body of the hydromill. 3) Concreting Once the final designed depth is reached, after the removal of the clam/hydromill, the steps are as follows: 3.1) If bentonite is used, sand content in the slurry is measured and de-sanding of the panel may be necessary. See table #1, with recommended values of slurry.

Fresh bentonite slurry Bentonite slurry during excavation Bentonite slurry before tremie of the concrete Density (t/m3) < 1.10 <1.25 <1.15 Apparent viscosity (Marshseconds) 32-50 32-60 32-50 Pressure-filtration (ml) <30 <50 - ph 7-11 7-12 - Sand content (%) <3 <6 <4 Table 1. EN 1538 proposal values of sand content for different SW/DW excavation phase. The de-sanding is usually done with air-lifting and/or submersible pumps and/or through the tremie pipes. In cases where hydromill is used the desanding is done directly, keeping the cutter at the bottom of the excavation and pumping fresh bentonite slurry. 3.2) Joints. One of the most delicate points of the final wall, in terms of impermeability, are the joints between Primary and Secondary panels. Several possibilities are available to increase the possible path of the water between the part excavated and the part in contact with the soil, such as installation of sheet or H piles (to be recovered or left in place) with or without a plastic water-stop, or simple pipe, as shown in Fig. #8. Another simple way to protect the joints is not to install any sheet-pile or pipe, but instead to carry out along the join (in the part not to be excavated) small columns of jet grouting. This system is more expensive but allows the penetration of the grout mix inside the joints guarantying their impermeability. Jet grouting outside the joints is also a common way to repair in case of defective execution of the joints. Fig. 8. Joints with simple pipes or sheet piles with or without plastic membrane. 3.3) Rebar cage installation. Once the joints are installed, if required, the rebar cage is installed. The rebar cage is usually constructed in several sections, depending on the depth of the SW/DW, welded, tied or coupled. It has been demonstrated and proven that the bond rebar cage/concrete is not affected by the bentonite slurry. Particular attention should be paid to the design of the rigidity of the rebar cage that will be lifted and installed with the aid of a service crane. Centralizer should be installed to keep the rebar cage at the center of the excavated panel, and to avoid contact with the soil. See Fig #9.

Fig. 9 Lifting and installing a rebar cage. 3.4) Tremie of the concrete. Tremie of the concrete is usually done from the bottom with adequate tremie pipes (25 to 35 cm diameters), with contemporary pumping of the bentonite slurry or polymer from the panel. For a single bite panel one tremie pipe is sufficient, for multiple bites (approx 6 meters long), 2 or more tremie pipes would be required. Concrete to be used for SW/DW shall follow the local standard CSA A23.1 / A23.2 04 (ENV 206 in Europe). The maximum aggregate dimension shall be 32mm or 1/4 of the inter-space between the rebar. Usually the content of cement is between 350 kg/m3 or 400 kg/m3 for maximum aggregate dimension of 32 or 16 mm, respectively. Slump should be (recommended values) between 180 and 210 mm. Depending on the type of soil and the correct tremie procedures the concrete surface may be not perfectly smooth and additional finishing of the face (milling, grinding, sacking or parging) may be required. 3.5) Demolition of the guide walls after the concrete has cured. Fig. #10 shows a completed and excavated SW/DW. Fig. 10 Example of a SW/DW excavated QA/QC Usual QA/QC procedures are used for this kind of work, such as: Design setting out of the position of the wall, guide walls and panels/joints, water, bentonite and concrete, fresh bentonite, excavation (continuous monitoring and recording of the excavation parameters with the hydromill) and verticality, bentonite slurry before installation of rebar cage, installation of sheet-piles or simple pipes for the joints, lowering reinforcement cages, concreting, procedures and samples. While it is not the object of this paper to enter into the details of the DW/SW design, below is a brief summary. The analysis of a flexible diaphragm wall is a classic example of interaction soil-structure. The interaction between the soil and the structure depends on the applied load of the soil and the reaction of the structure. Design of diaphragm walls requires experience and understanding of the principles of both soil mechanics and structural engineering. A proper design must allow for the knowledge of the properties of the soil (geologic profile, groundwater, geotechnical parameters) and for the presence of whatever boundary conditions exist: neighbouring buildings, facilities and surcharge loads.

Other specific problems affecting deep excavations are given by risk of soil flows from the bottom in weak soils, hydraulic piping, and the risk of bottom excavation heave in the presence of an artesian aquifer. Only an experienced foundation specialist, in situations involving these topics, can make reliable estimates about the feasibility and affordability of the excavations. Classic evaluations of earth pressure diagrams are used for the structural design of a SW/DWs, as well as prediction of its displacements. See Fig. #11 and 12.. Fig. #11 Usual diagrams of pressures acting against a vertical wall. Fig. 12 FEM modelling of diaphragm walls

Applications Multiple applications and case histories of SW/DW, around the world, are available both for permanent and temporary utilization, such as: underground basement or parking, subways, underpasses or overpasses, shafts, maritime applications such as piers and wharves, retaining walls, simple foundations (barrettes), impervious positive cut-off wall usually for dam and environmental purposes. Shapes such as square, rectangular, circular or elliptical are possible. See Fig. #13. Facilitating the excavation below groundwater while eliminating dewatering, Providing impervious watertight concrete walls, Eliminating vibro-densification in case of seismic conditions in some cases. Providing structural stiffness which reduces ground movements and adjacent settlements during excavation, Providing load bearing, transferring loads to the underlying layer. (3) In addition Slurry Walls/Diaphragm Walls can: accommodate connection to the structure, be adapted to both anchors or internal bracing, be constructed to a depth up to 120 meters, through virtually all types of soils/rocks, with great control over geometry/continuity and without vibrations. (4) SW/DWs: are installed before the excavation commences, are the basis of top-down, or cut and cover construction. See Fig. #14. Cost Fig. 13 Some application and shapes of SW/DW Advantages and Benefits There are multiple benefits in using SW/DWs for permanent excavation support, such as: The cost of a DW/SW is, usually, in the order of 1,000/1,300 $/m2 and it depends mainly on the thickness, depth and quantity of anchor/bracing necessary for the excavated structure. This cost can not be compared with any conventional British Columbia shoring application such as shotcrete/anchors, jet grouting/anchors or secant piles/anchors as all these systems are applicable in different soil conditions and they are not "permanent" earth retention systems.

Fig. 14 Top down construction. "Milan System". Conclusions Several SW/DWs have already been constructed in the lower mainland mainly for cut-off walls for hydraulic purposes and/or shafts. No deep basements, as for example in Richmond, have been constructed yet, where the perfect conditions are present for this kind of specialty construction methodology: sand/silt/clay and very high water table. Ref. (1) - EN 1538 - Execution of special geotechnical works- Diaphragm Walls (2) - KB International brochures (3) - Diaphragm walls: standard, dimensioning and practical examples. Marco Russo- Lombardi SA, 2005 (4) - Diaphragm walls- Thomas D. Richards Jr. P.E. - Nicholson, 2006