PRE-FEASIBILITY REPORT

Similar documents
Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha

PRE-FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT

PRE-FEASIBILITY REPORT

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres )

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

PRE-FEASIBILITY REPORT. for

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal

PRE- FEASIBILITY REPORT

PRE FEASIBILITY REPORT (PFR)

Hind Energy & Coal Beneficiation (India) Ltd.

PRE FEASIBILITY REPORT

KL) Proposed capacity of the. No change similar as existing i.e KL (MS KL, HSD KL & SKO KL) Terminal

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

PRE - FEASIBILITY REPORT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

RURAL LIVING AREAS Rural Living Areas Rural Lifestyle and Rural Residential 8.1 Issues, Objectives and Policies

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

Pre-Feasibility Report. for. Proposed Construction project of Santnagari

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

Details of the proposed project as presented before the committee are tabulated below:

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

A 'N 'E B 'N 'E C 'N 'E D 'N 'E

Project Proponent: Shri Kuldeep Pratap Singh Bhati Page - 11

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

Hind Energy & Coal Beneficiation (India) Ltd.

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

CONTENTS CHAPTER : ONE. 1-9 CHAPTER : TWO.10-16

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

Annex F Scoping Checklist

KALYAN DOMBIVLI MUNICIPAL CORPORATION PRE FEASIBILITY REPORT

Table 1 Population in MBMC

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

PRE FEASIBILITY REPORT

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Production of fresh and dry fruits, a district wise analysis in Jammu and Kashmir

WATER AWARENESS PROGRAM (WAP) FOR FARMERS (Moga, Punjab)

Infrastructure Development and Environment

Torpa Small Hydro Power Project

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT

Bio-Based Eco Industrial Clustering in Dambulla Sri Lanka

ANNEX 11 WATER SUPPLY, SANITATION AND SOLID WASTE MANAGEMENT

THE CONCEPT OF ORGANIC FARMING:

PRE FEASIBILITY REPORT. This is a proposal of running mining lease for which CTO has been issued by Regional officer, Jaipur.

PROMOTION OF DRY LAND MANGO CULTIVATION FOR INCOME SECURITY

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002

Agricultural Productivity of the Baramati Tahsil, Pune District (Maharashtra).

Bishunpur Small Hydro Power Project

Fig: Alignment of a ridge or watershed canal (Head reach of a main canal in plains)

Environmental and Social Considerations in Detailed Planning Survey. (Technical Cooperation for Development Planning)

PRE FEASIBILITY REPORT

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

Demand Potential of Indian Spun Pipes

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

APPLICATION OF RAPID IMPACT ASSESSMENT MATRIX (RIAM) METHOD FOR THE FEASIBILITY STUDY OF A MOBILITY HUB IN KOTTAYAM

CONCEPTUAL PLAN. M/s. APOLLO HOSPITALS ENTERPRISE LTD., (Construction of Oncology Block)

STANDARD OPERATING PROCEDURE

- 1 S. NO. PARTICULARS DETAILS

For. Coal Washery. Promoter. : Budbud & Kerajharia. Plot No.29, Transport Nagar, Indira Complex, Korba [C.G.] May 2012

DEVELOPMENT of. LPG Storage & Bottling Plant. Haldia. Project Feasibility Report

Provincial Policy Statement 2014 Training Aid

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Thethaitangar Small Hydro Power Project

SPECIAL CONDITIONS OF CONTRACT

SITE PRIORITIZATION FOR IBFI

Application for Gas Exploration and Production

Unit A: Introduction to Forestry. Lesson 3: Recognizing the Importance of Forests

Hybrid-Annuity based Public Private Partnership (PPP) model for creation of sewage treatment infrastructure

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

MCDR INSPECTION REPORT

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan

Impact of Air-Pollution on ph of soil of Saran, Bihar, India

STATE OF ENVIRONMENT ATLAS OF INDIA-OUTLINE

M/s ARYAN ENERGY (P) LTD.

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

Title Action Plan toward Effective Flood Hazard Mapping in My Country

Proposed Redevelopment of Anand Vihar Railway Station, Anand Vihar, East Delhi CONCEPTUAL PLAN

Research Compendium. Coal Sector in India 2013 A comprehensive data and information update

Bench terraces on loess soil China - 土坎梯田, 梯地

PRE FEASIBILITY REPORT

Research Article. Abdul Rauf 1 *, S. A. Saraf 1, P. A. Khan 2, and Q. J. A. Peer 3

Socio-Environmental Impacts of Mining Social Impact Key Issues

Intended Nationally Determined Contributions

PRESENTATION ON MANGANESE ORE DEPOSITS OF SMIORE FOR THE WORK SHOP ON REVISION OF THRESHOLD VALUES OF MINERALS AT GOA

Using the Online Database

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1

Dying fisheries in a changing environment: A study on livelihood strategies of fishery communities in Mumbai, India.

Galiuro Exploration Drilling Project

The Impact of Rural Water Supply Systems on Property Values

Transcription:

PRE-FEASIBILITY REPORT Consultant-Ascenso Enviro Pvt. Ltd. Page 19 of 32

1.0 EXECUTIVE SUMMARY S.No. Information Details 1. Project name Sand Mining Project on Ganga River at Kallu-GangajalGhat of District - Saran, State-Bihar 2. Mining Lease Area 23 Ha. 3. Location of mine Village District : State : Kallu-Gangajal Ghat, Mauza- Rasulpur Kasmer Block- Sonepur, District- Saran Saran Bihar 4. River/Nalla/Nadi GangaRiver 5. Minerals of mine Sand 6. Proposed Production 831058tonnes/annum. 7. Bulk Density 2.0 7. Method of mining Open Cast manual Method 8. Drilling or Blasting No 9. No of working days 270 days 10. Mining Period 3 Years 11. Water demand Domestic Water :2.4 KLD 12. Man Power 80 Dust Suppression: 1.5KLD Green Belt Development :0.9KLD Total Water Requirement:4.8KLD 13. Nearest railway station Sonepur railway station, approx. 5.5 Km towards East 14. Nearest state highway/national highway NH-19, approx. 3.5 Km towards NE. 15. Nearest air port Jay Prakash Narayan International Airport, Patna, approx. 12.5 Km towards South. Consultant-Ascenso Enviro Pvt. Ltd. Page 20 of 32

2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 Identification of Project and Project Proponent Name of the Project:Sand Mining Project atkallu-gangajal Ghat on Ganga River of District- Saran of State-Bihar. Kallu-Gangajal Ghat, Mauza- Rasulpur Kasmer Block- Sonepur, District- Saran Khasra no- 13,14,15,16,17,18,19,20,21,22,23,24,25,26,27,28,29,30,31,32,33,34,35,36,37,38,103, 104,101,102,105,127,128,129,124,97,98,90,86,87,88,82,83,84,85,89,90,91,92,93,94,95,96,98,99,10 0,106,107,108,109,110,76,77,78,2063,2064,2093,2094,2095,2096,2097,2098,2099,2100,2101,2102, 2103,2104,2105,2106,2107,2108,2109,2092,2065,2070,2071,2072,2079,2077,2078,2080,2081,2082,2088,2089,2090,2091,2040,2039,2136,2135,2134,2133,2137,2138,2145,2146,2147,2144,2087,208 6,2141,2142,2143,2085,2084,2083,2076,2075,2074,2067,2068,2069,2073,1992,1993,1994,1995,19 96,1997,1998,1999,2000,2001,2002,2003,2004,2005,2006,2151,2152,2153,2154,2148,2149,2150,2 007,2008,2009,2010,2011,2012,2013,2014,2015,2016,2017,2018,2019,2020,2021,2022,2023,2024, 2025,2026,2027,2028,2029,2030,2031,2032,2033,2034,2035,2036,2384, Location details of the stretch wise along with co-ordinates are as:- Kallu-Gangajal Ghat: A. 25 42'11.90"N85 6'40.86"E B. 25 42'11.86"N 85 6'50.46"E C. 25 42'45.90"N 85 6'37.50"E D. 25 41'45.68"N 85 6'48.20"E Village- Kallu-Gangajal Ghat, District- Saran 2.2 Brief description of nature of the project The project is open cast mining of minor mineral in the form of Sand. 831058 tonnes/annum. Sand will be excavated by Open cast manual Method. The project has been proposed bym/s. Broad-Son Commodities Pvt. Ltd. The project proponent had obtained mining permission for District- Saran. 2.3 Need for the Project and Its Importance to the Country or Region Consultant-Ascenso Enviro Pvt. Ltd. Page 21 of 32

Sand is used widely in the construction industry. It is mixed with cement and other ingredients to create mortar for building. It is also used in agriculture, as sandy soils are ideal for crops such as watermelons, peaches and peanuts. Sand is also used in Aquaria as it makes a low cost aquarium base material. 2.4 Demands-Supply Gap Creation of huge infrastructure as being envisaged by Government of India particularly in road and housing sector requires basic building raw materials. Thus the demand for Sandis ever growing with the growth of the infrastructure sector in our country. The requirement for the mineral is always high in the nearby cities and towns. Therefore there is always a good demand of the mineral in the domestic market. 2.5 Imports vs. Indigenous Production The demand in the domestic market is high for Sand. Mineral is available in abundant quantity in allotted area and can be excavated indigenously. Vast quantities of sand are available in various river ghats of the respective the river stretches. Therefore import of sand is not required. 2.6 Export Possibility There is no proposal to export the mineral as the minerals excavated, caterto the indigenous demand and the development is a never ending process. 2.7 Domestic/ Export Markets a) DOMESTIC MARKET There is always an ever increasing demand of these minerals in the domestic market. b) EXPORT MARKET The proposed mining activity is for indigenous consumption only for real state, road making etc. So no export will be envisaged. 2.8 Employment Generation (Direct and indirect) due to the project The total direct manpower requirement for the proposed mining operation will be around 80. Significant Indirect employment is also expected due to the associated activities. 3 PROJECT DESCRIPTION 3.1 Type of Project Including Interlinked and Interdependent Projects, If Any. Consultant-Ascenso Enviro Pvt. Ltd. Page 22 of 32

The proposed project for excavationofsandis an independent project in which minerals excavated will be directly sold in the local markets. It does not involve interlinked and interdependent project. 3.2 Location The mining lease area is located at,kallu-gangajal Ghat on Ganga River of District- Saranof State- Bihar Site Coordinates:- A. 25 42'11.90"N85 6'40.86"E B. 25 42'11.86"N 85 6'50.46"E C. 25 42'45.90"N 85 6'37.50"E D. 25 41'45.68"N 85 6'48.20"E 1 Km and 500 m radius google map, 10 km Topographic map attached asannexure IV and Annexure V respectively.the vicinity map of the mine location is given below: Consultant-Ascenso Enviro Pvt. Ltd. Page 23 of 32

Project Site Consultant-Ascenso Enviro Pvt. Ltd. Page 24 of 31

PFR for Proposed Sand Mining Project of Area 23 Ha. at Kallu-Gangajal Ghat on Ganga River of 3.3 Details of alternate sites considered and the basis of selecting the proposed site, Particularly the environment considerations gone into should be highlighted. Mineral location is site specific as well as the lease has been allotted in the particular sand bearing area. Hence no alternative site is examined for mining. The land has been allocated by government for the mining only. As there is potential of Sand in large amount, so the mining will help to use a resource for beneficial purposes. 3.4 Size or magnitude of operation The proposed mine has lease over an area of 23 Ha. The maximum rated capacity of the project wills approx. 831058 tonnes/annum. 3.5 Project description with process details This is an open-cast mining project, confined to excavation of Sand from the proposed site. The mineral- sand will be collected in its existing form. Excavation will be carried out only up to a depth of 2 m (Maximum) below ground level or above water level, whichever comes first. Excavation of Sand material will be done only during the day time and completely stopped during the monsoon season. 3.6 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area of Final Product/s, Mode of Transport of Raw Material and Finished Product No raw material will be required in the proposed project. The operation involves only the excavation of Sandin its existing form and transported to the end users/ market. 3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE Minerals are generally depleting asset once mined; but minerals like Sandwill be replenished naturally. Thus a scientific approach will be taken up for excavation of mineral with systematic method. 3.8 AVAILABILITY OF WATER, ITS SOURCE, ENERGY/ POWER REQUIREMENT AND SOURCE 3.8.1 Water Requirement Activity Water requirement (KLD) Dust suppression 1.5 Domestic 2.4 Green Belt Development 0.9 Total 4.8 Thus total water requirement will be 4.8KLD. This water will be supplied by private tankers. Consultant-Ascenso Enviro Pvt. Ltd. Page 25 of 31

3.8.2 POWER The material will be excavated by open cast manual method and loaded directly into tractors by the workers themselves. The operation will be done only from sun rise to sun set. So there is no power requirement for the mining activity. 3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL 3.9.1Solid Waste Generation& its Disposal No Municipal solid waste will be generated. 3.9.2 Liquid Effluent No liquid effluent will be generated at the mine site due to the mineral excavation. 4 SITE ANALYSIS 4.1 Connectivity The Kallu-Gangajal Ghat is well connected to the nearest Village metalled road (mirapur road.) via an approach road of approx. 250 m towards East.Haul Route Map is attached as Annexure VI. 4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP The proposed activity is to take place in thedry river bed of concerned rivers. The land form is mostly river bed and non-forest land. The entire land is Government land. Moreover there will be no change in land use as the mining will be confined to the river bed, which will get replenished naturally with the continuous flow of water. 4.3 TOPOGRAPHY This district is situated between 25036 and 26013 North latitude and 84024 and 85015 East longitude. The geographical area of the district is2641 km2. It comprises of 3 civil sub-division, 20 community development blocks, and 1783villages. The total population of the district is 4943098 (Rural 3591053 & Urban 352045).The river Ganga constitutes the southern boundary of the district beyond which Patnaand Bhojpur district lies. Siwan and Gopalganj district forms the northern and westernboundaries of the district. The River Gandak forms the boundary in the east beyond whichvaishali and Muzaffarpur districts lies. There are 5 statutory towns in the district. These are Chapra, Revelganj, Sonepur, Dighwara and Marhaura. Chapra is the main town in the district. Source: - http://cgwb.gov.in/district_profile/bihar/saran.pdf Consultant-Ascenso Enviro Pvt. Ltd. Page 26 of 32

4.4 EXISTING LAND USE PATTERN AND SHORTEST DISTANCES FROM FORESTS, WATER BODIES, ECO-SENSITIVE AREAS, ETC. The mine lease area is flat. There is no forest land or agriculture land in the mine lease area. The entire mining lease lies within the inactive channel of the bed of rivers, The existing landuse pattern is dominated by agriculture followed by barren lands. 4.5 EXISTING INFRASTRUCTURE The site has no existing infrastructure, except for connecting road for transportation. 4.6 SOIL CLASSIFICATION The two types of soils dominant in the district are as follows: 1) Younger alluvial soil (sub type of Entisols) is restricted in the North Gangetic plain. It is generally deficient of nitrogen and phosphoric acid but not of lime and potash. The generaltexture of the soil in the area is sandy to loamy sand. High soil moisture and regular flooding are causing water-logging condition in this soil type area. These are most fertile soils and eminently suitable for extensive cultivation of Paddy and Sugarcane. 2) Calcareous alluvial soils (sub type of Inceptisols) occur mostly in the central part of the area. This soil is generally enrich edinpotas hand phosphoric acid. The calcareous material brought by Gandak and its tribute arise is causing this soil type. 4.7 CLIMATIC DATA FROM SECONDARY SOURCES The westerly wind accompanied by dust storms around middle March marks the beginning of the summer season. May is the hottest month of the year when ambient temperature shoots upto 46 C. The summer continues up to June before onset of monsoon. The winter starts towards the middle of October and ambient temperature dips down to about7 C during the month of January, which is the coldest month of the year. The humidity is lowest in April and highest in August. The monsoon is active from June mid to the end of September.The average annual rainfallin the district is 837 mm for year 2004. The monsoon rainfall is about 80 % of the annualrainfall. Source: http://cgwb.gov.in/district_profile/bihar/saran.pdf 4.8 SOCIAL INFRASTRUCTURE AVAILABLE Consultant-Ascenso Enviro Pvt. Ltd. Page 27 of 32

S.No. Items Distance and Direction (Approx.) 1. Nearest School Primary School,MirzapurApprox. 1.5 Km towards North 2. Nearest Hospital Primary health center, Sonpur,Approx. 5.5 Km towards East 3. Nearest Worship Mata mandir, Approx. 1.5 Km towards North 4. Nearest Railway Station Sonepur railway station, approx. 5.5 Km towards East 5. Nearest Airport Jay Prakash Narayan International Airport, Patna, approx. 12.5 Km towards South 6. Nearest Highway NH- 19, Approx. 3.5 Km towards NE. 5 PLANNING BRIEF 5.1 Planning Concept Mining will be done as per the guidelines of Bihar Mineral Policy, and guidelines of Bihar Minor Mineral Concession Rules (amended thereof) This is an open-cast mining project. Excavation of minerals will be carried out only up to a depth of 2 meter. Safety distance of 3 meter or 1/10th of the width of the river whichever is more will be maintained from both the banks of river. Mining will be confined to the dry bed of the river within allotted area. 5.2 Population projection The project will employ most of the workers from nearby villages except for supervisory staff. Thus there will no increase in population due to the project. However, few people from other area may migrate in this area for employment directly and indirectly for business opportunities. 5.3 Land use planning (Break up along with green belt, etc.) Mining will be done in slices starting from the topmost level progressivelyadvancing downwards. The area so excavated will get filled up due to sediment inflow during monsoon. Plantation will be done near the civic amenities or road sides in consultation with the local authorities/government body.it is not feasible to plant trees in the lease area. Native plant / tree species will be planted in consultation with grampanchayat and local forest officials. List of Green Belt Consultant-Ascenso Enviro Pvt. Ltd. Page 28 of 32

S. No. Scientific Name Hindiname 1 Azadirachta indica Nim 2 Tectona grandis Teak 3 Terminalia arjuna Arjun 4 Tuti Tut 5 Syzygium cumini Jamun 6 Ficus religiosaa Pipal 7 The castor Erandi 8 Neolamarckia cadamba Kadamb 9 Dalbergia sissoo Shisham 10 Madhuca longifolia Mahua 5.4 Assessment of Infrastructure Demand (Physical & Social) Infrastructure like evacuation road, site services will only be required. Only local villagers from nearby villages will be employed for the mining activity. Thus no housing facility is proposed. 5.5 Amenities/Facilities The following facilities/amenities will be extended by the mine management: Direct and indirect Employment, most of which most will be from nearby villages depending upon the suitability of persons required for the job. Arrangements for safe and healthy working conditions& temporary rest shelters. Provision of Drinking water. Provision of PPE. Consultant-Ascenso Enviro Pvt. Ltd. Page 29 of 32

First-Aid facilities and Health check-up camps for the workers. Conducting medical camps for workers and nearby villagers at regular interval. Mobile toilets will be provided for sanitation purposes. 6 PROPOSED INFRASTRUCTURE 6.1 Industrial Area (Processing Area) No industrial area is proposed. 6.2 Residential Area (Non Processing Area) As the local people will be given employment, no residential area/ housing are proposed. 6.3 Green Belt It is proposed to plant local trees and bushes along the river banks and along haul road in consultation with the local authority/ Govt. body. Approx. 300 trees will be planted at the river bank and the haul roads.tree plantation programmes are as:- S. No No of Year No of Trees 1 1 st Year 150 2 2 nd Year 150 3 3 rd Year Maintenance 6.4 Social infrastructure Road facility (existing roads will be maintained regularly) Employment opportunity Medical camps Social awareness camps, Donations to schools Secondary employment opportunities Formation of self-help groups for the women in nearby villages 6.5 Connectivity The Kallu-Gangajal Ghat is well connected to the nearest Village metalled road (mirapur road.) via an approach road of approx. 250 m towards East.Haul Route Map is attached as Annexure VI. 6.6 Drinking Water Management Water required for drinkingpurposewill be obtainedthrough tankers/or by private tankers. Consultant-Ascenso Enviro Pvt. Ltd. Page 30 of 32

6.7 Sewerage System No sewerage system is proposed. 6.8 Industrial Waste Management Not applicable 6.9 Solid Waste management No solid waste will be generated from the proposed project. 6.10 Power Requirement & Supply/Source. The mining activity will be done Open Cast Method and the operation will be done only during the day hours from sun rise to sun set. So there is no power requirement for the mining activity. 7.REHABILITATION AND RESETTLEMENT (R&R) PLAN The mine area is inactive channel of river bed, so rehabilitation and resettlement plan is not required. 8 PROJECT SCHEDULE & COST ESTIMATES 8.1 Likely date of start of construction and likely date of completion. The project will commence once Environmental Clearance and other necessary certificates are obtained from the respective departments. 8.2 Estimated project cost along with analysis in terms of economic viability of the project Sr. No. Description Cost in Lakhs(in Rs.) 1 Auction cost 179.2 2 Labour & Equipment s cost 15.0 3 Site facilities 2.0 4 Environnemental Protection cost 12.0 5 Miscellaneous 1.0 TOTAL The total cost of project would be around Rs. 209.2 Lakhs 209.2 Lakhs Consultant-Ascenso Enviro Pvt. Ltd. Page 31 of 32

Environment Management Cost S. No Description Cost Rs.in Lakhs 1 Dust suppression 2.5 2 Haul road maintenance 3.0 3 Green belt & Maintenance 2.5 4 Monitoring cost 4.0 Corporate Social Responsibility Cost:- CSR cost will be 2% of total project cost i.e209.2lakh X 2 % = Approx. Rs.4.1 Lakhs The CSR cost will be used for the welfare of people residing nearby the lease area with consultation with the Local Authority. 9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) The Project will bring economic benefits to the state by the way of Royalty for mineral. Achieving a huge infrastructure as being envisaged by Government of India particularly in road and housing sector requires basic building materials. Sandis one of primary building material required for the purpose. The mining activities as proposed are the backbone of all construction and infrastructure projects as the raw material for construction is available only from such mining. Sandexcavated is in high demand at the local market for real estate industry. This project operation will provide livelihood to the poorest section of the society/economically backward population and tribal in the area. It provides employment to the people residing in vicinity directly or indirectly.the mine management will also help nearby villages by providing aid to school, conducting medical and social awareness camps, helping in formation of self-help groups, etc. Thus the project will bring about socio-economic improvement of the area and will prove beneficial to the area. ********** Consultant-Ascenso Enviro Pvt. Ltd. Page 32 of 32