This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

Similar documents
This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

LOWER BOISE RIVER INTERIM FEASIBILITY STUDY

Option 11. Divert Water from Miocene and Hendricks Canal to Supply the Ridge

Indirect Reuse with Multiple Benefits The El Monte Valley Mining, Reclamation, and Groundwater Recharge Project

THE WYOMING FRAMEWORK WATER PLAN

Farmington Dam Repurpose Project

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary

APPENDIX A. Project Scoping

PUBLIC NOTICE Section 404 of the Clean Water Act - Permit Review ENVIRONMENTAL IMPACT STATEMENT U.S. ARMY CORPS OF ENGINEERS REGULATORY BRANCH

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project.

Raw water sources, facilities, and infrastructure

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

STATE OF COLORADO. From: Rod K1.I. harich ewes Director. Date: January 17, 2006 Acting Deputy Director

CONTENTS LIST OF TABLES LIST OF FIGURES

TECHNICAL MEMORANDUM

Hydrology and Flooding

City of Phoenix Tres Rios Wetlands: Water Sustainability & Efficiency. Cynthia Campbell Water Resource Management Advisor City of Phoenix

Alternative: Utilize San Juan-Chama Project Water

Eska Creek Preliminary Feasibility Analysis

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce

Section 5 Packages. 5.1 Package Development Problem Statements A 5-1

BIG CHICO CREEK WATERSHED ALLIANCE

Contribution of Irrigation Seepage to Groundwater-Surface Water Interactions on the Eastern Snake River Plain

COMMUNITY PROFILE PLATTE VALLEY IRRIGATION DISTRICT. Twin Platte Natural Resources District Multi-Jurisdictional Hazard Mitigation Plan Update

Raw Water Supply Master Plan Development

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

City of Phoenix Tres Rios Wetlands: Water Sustainability & Efficiency. Cynthia Campbell Water Resource Management Advisor City of Phoenix

JUNE 20, Collaborative Initiatives: Restoring watersheds and large landscapes across boundaries through State and Federal partnerships

Are Juvenile Chinook Salmon Entrained at Unscreened Diversions in Direct Proportion to the Volume of Water Diverted?

SOUTH FORK AMERICAN RIVER (CHILI BAR), CALIFORNIA

PREPARE60 OVERVIEW 1

NOTICE OF PREPARATION

Over 150 Years of Irrigation Implications for Montana s Water Resources

SLIDES: Status of Southern Nevada Water Authority (SNWA): Third Intake into Lake Mead and Groundwater Project

Madera Irrigation District Water Supply Enhancement Project

MEMORANDUM. The general findings of the assessment are as follows:

UNCLASSIFIED AD NUMBER LIMITATION CHANGES

7.0 SUMMARY AND CONCLUSIONS

Appendix D - Evaluation of Interim Solutions

HYDROGEOLOGY OF THE HUMBOLDT RIVER BASIN, IMPACTS OF OPEN-PIT MINE DEWATERING AND PIT LAKE FORMATION

RED RIVER FLOODWAY OPERATION REPORT SPRING Manitoba Infrastructure

Chapter 8 National Economic Development and Locally Preferred Alternative

Powder/Tongue River Basin Plan Executive Summary

Information Request 37

In the Henry s Fork Watershed, Every Drop Leaves a Ripple. Kisa Koenig

City and County of Broomfield, Colorado CITY COUNCIL AGENDA MEMORANDUM. 11f - Page 1

STORMWATER HARVESTING FOR ALTERNATIVE WATER SUPPLY IN VOLUSIA COUNTY, FLORIDA

OPERATIONS IN THE MONO BASIN*

Pipelines to Nowhere? Structural Responses to Climate Change and Population

SECTION 7.0 PROJECT FEASIBILITY, ENGINEER S RECOMMENDATION AND DESIGN ISSUES NEEDING RESOLUTION

Mike Jastremski, CFM Watershed Conservation Director

Spring Forecast Based Operations, Folsom Dam, California

Kern Water Bank. Kern Water Bank Authority

DES MOINES RIVER RESERVOIRS WATER CONTROL PLAN UPDATES IOWA ASCE WATER RESOURCES DESIGN CONFERENCE

SOUTHERN NEVADA WATER BRIEFING Prepared for the Legislative Commission's Subcommittee to Study Water

V. DRAINAGE IMPROVEMENTS

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE

Informational Meeting- March 31, Boxelder B-2/B-3 Watershed Planning Study

CASE NO. 10CW4 LOWER ARKANSAS VALLEY WATER CONSERVANCY DISTRICT

Forestry Establishment and Wildlife Conservation Programs and Assistance

Informational Meeting- July 21, Boxelder B-2/B-3 Watershed Planning Study

SRCD s Review of Impacts the Proposed Bay Delta Conservation Plan (BDCP) and Companion EIR/EIS on the Suisun Marsh

System Plan Components Inventory

ND Detention Project Development Update

Notice No Closing Date: May 12, 2017

III. INVENTORY OF EXISTING FACILITIES

FEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects

APPLICANT: Board of Water Commissioners for the City and County of Denver (Denver Water)

APPENDIX A NOTICE OF PREPARATION/ NOTICE OF INTENT. Proposed Lower Yuba River Accord June 2007 Draft EIR/EIS

El Dorado Water & Power Authority. El Dorado Water Reliability Project

Chelan County Natural Resource Program. Lake Wenatchee Water Storage Feasibility Study June Executive Summary Why is this study being done?

Start-up of a Secondary Water Supply Company. and First Phase Design of a Regional System

Missouri River Basin Water Management

The Central Utah Project

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

EMERGENCY STORAGE PROJECT

Notice of Intent to Prepare a Draft Environmental Impact Statement for the Intake. Diversion Dam Fish Passage Project, Dawson County, Montana

2.0 Resource Management Goals of Agencies with Jurisdiction Over the Resource to be Studied

Purpose of the Comprehensive Water System Plan

WATERSHED MANAGEMENT INITIATIVE: GOALS & IMPLEMENTATION OBJECTIVES, JULY 26, 1999

Charles W. Binder WATERMASTER SANTA MARGARITA RIVER WATERSHED CIVIL NO. 51-CV-1247-GPC-RBB

Cokato Lake (86-263) Wright County. Hydrologic Investigation

Fort Collins WSDMP Update Additional Supplies and Facilities. Community Working Group Meeting #4 June 22, 2011

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

What Are Environmental (Instream) Flows?

Chehalis Basin Strategy Programmatic SEPA Draft EIS

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC

Executive Summary. ES.1 Project Background

Feasibility of Aquifer Storage and Recovery in the Upper Colorado River Basin

Safe Yield Study January 2004

Information for File # PRH

SCAMA / NOGALES WATER STORAGE STUDY APPRAISAL STUDY

Project Alignment Appendix A

Fargo-Moorhead Metropolitan Area Flood Risk Management Project

Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Ramping May 2015

SCOTT RIVER HYDROLOGY AND INTEGRATED SURFACE WATER / GROUNDWATER MODELING

Constructed Wetland Pond T-8

Chapter 1. Introduction

Transcription:

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact WRDS at wrds@uwyo.edu and include the phrase Digital Documents in your subject heading. To view other documents please visit the WRDS Library online at: http://library.wrds.uwyo.edu Mailing Address: Water Resources Data System University of Wyoming, Dept 3943 1000 E University Avenue Laramie, WY 82071 Physical Address: Wyoming Hall, Room 249 University of Wyoming Laramie, WY 82071 Phone: (307) 766-6651 Fax: (307) 766-3785 Funding for WRDS and the creation of this electronic document was provided by the Wyoming Water Development Commission (http://wwdc.state.wy.us)

VIVA NAUGHTON ENLARGEMENT Level II Study EXECUTIVE SUMMARY Submitted To: Wyoming Water Development Commission Submitted By: 7800 East Dorado Place, Suite 100 Greenwood Village, CO 80111 303.773.3788 www.ecih2o.com In Association With: Sunrise Engineering Dahlgren Consulting Natural Resources Consulting Engineers September 2004

TABLE OF CONTENTS 1.0 INTRODUCTION 2 2.0 BACKGROUND 2 3.0 WATER SHORTAGES 3 4.0 WATER AVAILABILITY 4 5.0 PERMITTING AND ENVIRONMENTAL FACTORS 4 6.0 BENEFITS 5 7.0 EVALUATION AND SELECTION 5 8.0 CONCEPTUAL DESIGNS 7 9.0 ECONOMIC ANALYSIS 8 10.0 CONCLUSIONS 8 11.0 RECOMMENDATIONS 9 LEVEL II STUDY-EXECUTIVE SUMMARY 1

1.0 INTRODUCTION The purpose of the Viva Naughton Enlargement, Level II Study, was to identify a preferred water supply alternative to provide additional water for users in the Hams Fork Valley. These water users are a combination of: Irrigators growing hay for ranching purposes who are represented by a water user association Towns including Kemmerer, Diamondville and Frontier which are represented by a joint power board Small communities including Opal and Granger Industries including, PacifiCorp and Pittsburgh & Midway Coal Company (P&M). PacifiCorp, one of the largest employers in the basin, operates Naughton Power Plant and owns Viva Naughton Reservoir. These users are located within a basin that extends from headwaters in Bridger-Teton National Forest to a terminus at the confluence of the Hams Fork with the Blacks Fork near the town of Granger in southwestern Wyoming. The basin drainage lies mostly within Lincoln County and is approximately 611 square miles. To achieve the objectives of the Viva Naughton Enlargement Study the following steps were undertaken: 1) Water shortages were identified. 2) Potential water supply alternatives were defined. 3) The amount of additional water provided by each alternative was quantified. 4) A comparative analysis of the alternatives was conducted. 5) A set of preferred alternatives was selected. 6) Conceptual designs of the selected alternatives were developed. 7) Opinions of probable cost were prepared for the selected alternatives. 8) An economic analysis with benefits and costs was completed. 9) A set of recommendations was developed. 2.0 BACKGROUND The following three main water users divert most of the Hams Fork flows: Hams Fork Water Users Association (HFWUA) Kemmerer Diamondville Joint Power Board (JPB) PacifiCorp The JPB obtains their share of Hams Fork flows through direct flow rights of 6.45 cubic feet per second (cfs) and storage rights in Kemmerer Reservoir for 1,776.28 acre-feet. The Kemmerer Reservoir storage rights consist of 1,058 acre-feet by permit #5302 Res and 728.28 acre-feet by permit #9776 Res. This total was established by a bathymetric survey completed with the repair work in 1994. JPB also has an agreement with PacifiCorp for 1,000 acre-feet of storage in Viva Naughton Reservoir. The PacifiCorp agreement requires that Kemmerer Reservoir be held full. LEVEL II STUDY-EXECUTIVE SUMMARY 2

PacifiCorp takes Hams Fork flows through storage rights gained by the construction of Viva Naughton Dam. Using storage enlargement permit #7476 Res, PacifiCorp raised the original dam to increase the storage capacity to approximately 45,465 acre-feet. The permit originally allowed the storage volume to be increased to 69,645 acre-feet, however, construction of the dam raise was never completed. In 1974, the SEO approved a second storage enlargement permit for the reservoir (permit #7599 Res). Under this permit, the Viva Naughton dam crest could be raised to elevation 7,272 feet, resulting in a storage volume of 81,895 acre-feet with a water level elevation of 7,262 feet. As of the date of this report, construction of the second enlargement has not begun. PacifiCorp keeps both of the enlargement permits (#7476 Res and #7599 Res) in good standing by performing studies and seeking extensions from the SEO to build the enlarged dam. Kemmerer Dam, which is downstream of Viva Naughton Reservoir, and Viva Naughton Dam are both classified as high hazard structures. HFWUA members control most of the senior direct flow rights in the basin. The members divert most of their water rights to irrigate hay fields. The diversions start above Viva Naughton Reservoir and continue to within a few miles of Granger. PacifiCorp and HFWUA share the storage generated by the first Viva Naughton Enlargement completed under permit #7476. Because the enlargement was started but never completed, the amount of storage HFWUA has in Viva Naughton is not clearly defined. Through mutual agreement, PacifiCorp provides the HFWUA with the top two feet of storage in Viva Naughton Reservoir. The agreement allows PacifiCorp to store direct flows out-of-priority during the spring runoff and in turn provides storage for the HFWUA. This storage however is only available if the reservoir fills and is not a reliable supply. More than anyone else in the basin, HFWUA irrigators are impacted by water shortages. In 2002, the State s Water Commissioner in Cokeville, Jade Henderson, stated that a unique arrangement exists in the Hams Fork Basin where water users discuss and coordinate management of the available stream flows to promote and allow efficient use of water in the basin. This arrangement is demonstrated by irrigators with senior water rights not calling for their water in the spring but instead, cooperating with PacifiCorp to store these flows in Viva Naughton Reservoir for use later in the year. In 2003, this pattern was changed somewhat, when senior direct flow water rights were used to secure two weeks of early spring flows before the reservoir was permitted to fill. By the end of 2003, both PacifiCorp and HFWUA agreed this new arrangement works well to meet both groups needs. 3.0 WATER SHORTAGES Water shortages do exist within the Hams Fork Basin. Past studies have documented these water shortages. This study determined that shortages exist. The river below Kemmerer is frequently limited to stock watering only. Hams Fork is declared futile when the senior water rights of Granger cannot be met. Due to these limited flows, the two larger users at the river s end, Granger and Little America, rely on FMC, a trona mining company in the area, to supply them water from the Green River. LEVEL II STUDY-EXECUTIVE SUMMARY 3

Under current conditions with approximately 8,500 to 9,900 acres being irrigated, the average irrigation demand shortage is 1,470 acre-feet per year. If the total 14,000 acres with valid water rights were irrigated, the average shortage would increase to over 2,500 acre-feet per year. Both of these shortages are based on an agricultural reliability of 80 percent. Neglecting a potential expansion of the Naughton Power Plant, additional storage required to meet the existing irrigation demands 8 out of 10 years, and not cause industrial or municipal shortages, would be 23,000 acre-feet. Under the same conditions 43,000 acre-feet of storage would be needed to meet the additional irrigation demand from 14,000 acres. If PacifiCorp decides to expand the Naughton Power Plant and utilize the permitted storage rights at Viva Naughton Reservoir even more storage would be required. It was estimated that 29,000 acre-feet would be required under this scenario to meet the existing irrigation demand 8 out of 10 years (80 percent reliability). Considering both the power plant expansion and irrigation of the total 14,000 acres would limit the agricultural reliability to 52 percent and require capturing all of the available excess Hams Fork flows. Municipal water shortages are documented in present watering restrictions and the limited amount of water available for future growth. Communications with JPB and the Lincoln Uinta Association of Governments (LUAG) indicate the present supply is not sufficient to attract new businesses to the area. JPB has not been able to divert their 6.45 cfs due to low flows at their diversion points enough times for the JPB to consider a new water supply source. One option they have focused on would be to pump water directly to their water treatment plant from Fontenelle Reservoir on the Green River. 4.0 WATER AVAILABILITY Modeling of existing and future demand scenarios using available stream flow gaging station records determined that there are sufficient Hams Fork flows to meet all but total build out conditions. To meet the demands of total build out conditions, additional storage would be required. Additional water in the Green River can be pumped to Hams Fork from Fontenelle Reservoir about 30 miles away. The limitations for using this supply are capital and operation costs and the need to secure water rights to this stored water. Groundwater as a potential water source has been studied in the past and found limited by quantity and quality. The use of groundwater enhancement alternatives such as aquifer recharge and alluvium flooding is limited by cost and timing issues. 5.0 PERMITTING AND ENVIRONMENTAL FACTORS The single largest regulatory issue for any alternative selected to solve water shortage problems within the Hams Fork Basin would likely involve compliance with the National Environmental Policy Act (NEPA). Compliance would require applications for permits and mitigation of impacts. An enlargement of Viva Naughton Dam or the construction of a new dam would require a 404 Permit from the Corp of Engineers (COE). Any alternatives that would impact the water LEVEL II STUDY-EXECUTIVE SUMMARY 4

rights and operation of Viva Naughton Reservoir would also require agreements negotiated with PacifiCorp. Mitigation measures would be required to offset environmental and cultural impacts identified through the use of National Wetland Inventory (NWI) mapping, Emigrant Historic Trail and Cultural Resource mapping, and information provided by the Wyoming Game and Fish Department (WGF) and Bureau of Land Management. Impacts could be generated by inundation of wetlands, game habitat, and cultural sites. Impacts caused by supply canals crossing sensitive habitats or new reservoir inundation limits that impact power lines or roads would need to be mitigated. Because Hams Fork flows support a good stand of willows, brushes, and other riparian habitat and provide for cottonwoods and other large tree groupings, construction of reservoirs on the main stem results in a greater number of impacts. Storage on ephemeral streams result in fewer wetland impacts but more big game habitat impacts. By all accounts, the largest impact would be approximately 530 acres of classified wetlands covered by the proposed inundation limits of a raised Viva Naughton Reservoir. 6.0 BENEFITS Benefits to offset the impacts and cost of developing a storage alternative include the reduction of water shortages and the improvement of recreational resources in the Hams Fork Basin. It was agreed by reviewers of study draft reports in 2003, that a new reservoir would improve stillwater fisheries. The improvement to stream fisheries from additional storage, though, could not be estimated. The stream below existing Kemmerer and Viva Naughton Reservoirs is already a fishery jewel. According to the WGF, more study would be required before a stream fisheries benefit could be quantified. The benefits associated with a new facility that provides 40,000 acre-feet of additional storage were estimated to be: $780,000 per year in direct and indirect irrigation benefits. $88,000 per year in direct municipal benefits. $345,000 per year in recreational benefits. Hydropower was determined to be a marginal benefit was not considered further in the study. 7.0 EVALUATION AND SELECTION The evaluation process was conducted in steps. The process started with alternative identification. The Green River Ground Water Recharge and Alternative Storage Project dated December 2001 screened 35 alternatives in the Green River Basin and identified the proposed Viva Naughton Enlargement and Dempsey Creek Reservoir as potential storage alternatives. This evaluation study, focusing on the Hams Fork basin, expanded the number of alternatives to 37. In addition to reservoir sites, the comparison also included the study of potential alternatives such as groundwater development. LEVEL II STUDY-EXECUTIVE SUMMARY 5

After discussions with the project sponsors and Wyoming Water Development Commission (WWDC), it was concluded that all the major alternatives could be placed into one of the following categories: Pipelines and tunnels which would bring transbasin water into the Hams Fork Basin for direct use or storage Storage reservoirs on Hams Fork or its tributaries such as the off-the main stem storage site in Dempsey Basin Groundwater supplies developed with the construction of well fields Improved groundwater supplies that would allow pumping on a yearly basis (this would include ASR, recharging the alluvium, and using the existing mines for storage) Potential pipeline alternatives would bring water from Fontenelle Reservoir. Two capacities, 100 cfs and 150 cfs, were evaluated for pipeline alternatives to facilitate the timing of direct irrigation use. Alternatives with 100 cfs capacities would require temporary storage in the basin to meet demand patterns. A pipeline that would bring Fontenelle water directly to JPB s water treatment plant was studied separately. This study determined the alternative would require a 12-inch diameter pipeline, three booster-pumping stations, and would cost $23,157,000 to deliver 5 cfs. Potential reservoir sites studied included the Viva Naughton Enlargement, Dempsey Creek Reservoir, Willow Creek Large Reservoir, Willow Springs Reservoir, Fish Creek Reservoir, West Fork Large Reservoir, Opal Reservoir, Alkali Creek Reservoir, Naughton Power Plant Reservoir, Upstream Watershed combination of smaller reservoirs, Kemmerer Enlargement, Intermediate, Frontier, Upper Willow Creek, and South Fork Fontenelle. General layouts and dam locations for each reservoir alternative was prepared for the initial screening step. Transbasin tunnels and groundwater enhancement alternatives were also configured and developed to a point that quantities could be determined. A first screening followed the identification process and was based on what would and would not work. It also identified what could be permitted. Of those alternatives that were workable and could be permitted, a preliminary Engineer s Opinion of Probable Cost was prepared. The collected data and costs estimates were used as input for a formal matrix screening process. The screening process was used to limit the number of alternatives that conceptual designs would be completed for. The goal was to select a single alternative. The screening process used evaluation criteria and weighting factors. Weighting factors that express the importance of each category to decision-makers were established with the input of stakeholders and the WWDC. The screening process was completed during public meetings in Kemmerer and Diamondville. In those meetings, surface storage reservoirs were ranked high due to the reliability of supply and lower costs. Groundwater alternative were ranked lower than the reservoirs due to the uncertainty of yield per the cost of development. In summary, the majority of sponsors and reviewers supported taking three storage alternatives (Viva Naughton Enlargement, Dempsey Creek, and Willow Creek) into the conceptual design LEVEL II STUDY-EXECUTIVE SUMMARY 6

phase. It was also agreed, at that time, to quantify the actual amount of wetland inundation that would take place if Viva Naughton Reservoir were enlarged. 8.0 CONCEPTUAL DESIGNS Following the Phase I screening meeting, work began on conceptual designs for the three selected alternatives. Design work included configuring, sizing, and quantifying diversion structures, supply canals, dams, spillways, and outlet works as needed for the alternatives. Based on the conceptual designs, an engineer s opinion of probable costs was prepared for each alterative in 2003 dollars. The estimates were based on quantity takeoffs, supplier s information and general cost data and are tabulated in Table ES1. Table ES1: Summary of Opinion of Probable Project Costs in 2003 Dollars Alternative Dempsey Item Viva Naughton Enlargement Creek Dam and Reservoir Willow Creek Dam and Reservoir Embankment $12,748,900 $17,444,500 $7,017,200 Spillway 5,842,600 507,500 680,600 Outlet Works 406,000 1,095,700 1,595,700 Supply Canal - 4,778,800 10,110,300 Inlet and Diversion Structure - 478,800 450,600 Access Road 790,000 382,900 2,331,100 General 2,120,000 2,000,000 4,080,000 Component Cost Sub-Total $21,907,500 $26,688,200 $26,265,500 Engineering Cost $2,190,500 $2,688,200 $2,626,600 Sub-Total $24,098,300 $29,357,000 $28,892,100 Contingency $3,614,700 $4,403,600 $4,993,800 Total Construction Cost $27,713,000 $33,760,600 $33,225,800 Preparation of Final Design $1,939,900 $2,363,200 $2,325,800 Permitting $6,000,000 $675,200 $664,500 Legal Fees $554,300 $675,200 $664,500 Land Purchase and Easements $550,000 $550,000 $550,000 Estimated Project Cost $36,757,200 $38,024,200 $37,430,700 Use $36,800,000 $38,100,000 $37,500,000 LEVEL II STUDY-EXECUTIVE SUMMARY 7

9.0 ECONOMIC ANALYSIS Results of benefits analyses were coupled with a total project cost of $36,800,000 to determine a benefit cost (B/C) ratio and the amount of a rate increase the stakeholders would need to pay for a new storage project. The economic analyses were completed assuming a six percent annual rate of return and a 50-year repayment period. The rate increase was based on distributing the annual cost for a loan to construct a storage facility over approximately: 1,200 existing water taps. 14,000 irrigated acres. B/C ratios were greater than one when project benefits were used to cover the cost of a $9,200,000 loan (25 percent of total project cost). Distributing annual principal and interest (PI) payments for a loan of $9,200,000 over 1,200 taps results in a fee of approximately $486 per tap per year. Distributing annual loan PI payments for a loan of $18,400,000 (50 percent of total project cost) over 1,200 taps results in a fee of approximately $973 per tap per year. Distributing annual PI payments for a loan of $9,200,000 over 14,000 acres results in a fee of approximately $40 per acre per year. Distributing annual loan PI payments for a loan of $18,400,000 over 14,000 acres results in a fee of approximately $80 per acre per year. 10.0 CONCLUSIONS Conclusions from this study include: Water shortages do exist within the Hams Fork Basin. The JPB and HFWUA could solve their drought storage problems by constructing a dam at either the Dempsey Creek or Willow Creek sites, or by enlarging the existing Viva Naughton Dam and Reservoir. The JPB can solve their short-term drought storage problems by negotiating with PacifiCorp to exchange storage in Kemmerer Reservoir for storage in Viva Naughton Reservoir. Such an arrangement would need to be approved by the SEO. Without a power plant expansion the total additional storage required to eliminate the shortages would be 23,000 acre-feet. With a power plant expansion the total additional storage required to eliminate the shortages would be 29,000 acre-feet. LEVEL II STUDY-EXECUTIVE SUMMARY 8

Only by working together have PacifiCorp, JPB, and HFWUA managed available stream flows efficiently. This cooperation will need to be continued. Each of the three potential storage projects identified as possible candidates to solve the shortage problems are estimated to cost around $37,000,000. Considering a 25 percent loan 75 percent grant and a total project cost of $36,800,000, loan repayments would be $583,700 per year. If the project yields 34,000 acre-feet per year, the cost per acre-foot of firm yield would be $17. The cost of new storage would be $920 per acre-feet ($36,800,000 divided by 40,000 acrefeet). 11.0 RECOMMENDATIONS Recommendations based on the results of this study can be separated into three categories. The first category of recommendations are based on moving ahead with a WWDC Level III supported project that would service the entire basin and would have Hams Fork Basin Water Stakeholders: Form a water user district that can generate user fees to guarantee project financing Seek funding for a selected alternative from the WWDC Start the NEPA process on the selected alternative The second category of recommendations can be termed going it alone. The JPB could move ahead and look for a separate water supply like a pipeline from Fontenelle Reservoir or work out an exchange agreement with PacifiCorp. The agreement would attempt to gain extra storage by moving storage water rights that are not presently being used from Kemmerer Reservoir into Viva Naughton Reservoir. The HFWUA could also proceed to move ahead separately and construct a smaller reservoir that solves their additional water supply needs, or work to secure more storage in Viva Naughton Reservoir by seeking an agreement with PacifiCorp. The third category of recommendations would be to perform additional studies to: Determine the mitigation costs and permitting requirements for the enlargement of Viva Naughton Dam and Reservoir. This cost for mitigations has been estimated to be $6,000,000. If this cost could be lowered, the project would be more economically feasible. Determine the geotechnical conditions at the Dempsey Dam site and supply canal. The best structural and economical development option is to form a legal water user district and seek funding from the WWDC to proceed with permitting, design, and construction of the Viva Naughton Enlargement or Dempsey Creek Dam and Reservoir. The funding request should be for at least a 25 75 percent loan and grant mix, if not a 10 90 percent loan and grant mix. LEVEL II STUDY-EXECUTIVE SUMMARY 9