(See paragraph 6) FORM - 1

Similar documents
Annex F Scoping Checklist

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

Form -1. [Vide Notification dated 1 st December 2009] FOR PROPOSED. COSTAL ROAD AT DRONAGIRI, NAVI MUMBAI Precast RCC Bridges On Holding Ponds-

FORM-1. Sr. No 1 Name of the Project Harbour Heights 2 S. No. in the Schedule 8(b) Townships and Area Development projects.

FORM I I. BASIC INFORMATION S. No. Proposed Mixed Use Development Project SPR Binny 2 S. no. in the schedule 8 (b) 1 Name of the project

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

Revised FORM - I & PRE-FEASIBILITY REPORT

A 'N 'E B 'N 'E C 'N 'E D 'N 'E

FORM I GROUP HOUSING PROJECT GH-03C, SECTOR-144 NOIDA, UP. For. M/s GULSHAN HOMES AND INFRASTRUCTURE PVT.LTD ENVIRONMENT CONSULTANT

Centrade At Plot No. 1, Sector 140, NOIDA Noida, U.P FORM- I

Sector D 1,Kanpur Road Yojna

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

Sandipbhai Shankarbhai Patel

FORM- I. Behrampur Gurgaon. Gurgaon, Haryana

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

Jayendrasinh Bharatsinh Jadeja

Proposed Group Housing Project ATS Rhapsody At Plot No. GH 12/1, Sector -01, Greater Noida (U.P.) APPENDX (See paragr FORM 1

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

Prepared by. Regd. Office: January, 2013

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17.

Submitted to. Expert Appraisal Committee (EAC), Mumbai Maharashtra. May 2017

APPENDIX I (See Paragraph 6) FORM 1

APPLICATION FOR ENVIRONMENTAL CLEARANCE

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

Details of the proposed project as presented before the committee are tabulated below:

SCHEDULE. FORM A (Rule 3(1)) THE CERTIFICATE OF ENVIRONMENTAL CLEARANCE RULES 2001 APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL CLEARANCE

"RAMA WORLD desh. PHASE # 2" ZODIAC DEALER PRIVATE LIMITED

Proposed Office Building at Plot no: 11 & 12 Sector 127, Noida, U.P.

3 SCOPING 3.1 DEVELOPMENT OF SCOPING PROCESS Need for Scoping

FORM 1 & 1 A. Proposed Residential Project. Sr. No. 25/2/2A Kondhwa Bk. Tal. Haveli Dist. Pune. M/s. ANISHKA DEVELOPERS PVT. LTD.

M/s Aura Buildwell Pvt. Ltd. 1

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

FORM -1 CAPITAL CITY COMMERCIAL PROJECT. Plot No. 2B, Sector 94, Noida, District: Gautam Budh Nagar, Uttar Pradesh

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

Max. building height (m)

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

Environment Clearance for Proposed Inland Water Transport along East Coast of Mumbai.

Prepared by: Vardan Environet, Gurgaon

M/s. SREE BALAJI NIRMAN & ESTATES

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Assessment Matrix

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Environmental Impact Assessment

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Bangalore Development Authority T. Chowdaiah Road Kumara Park West Bangalore

Summary of Preparatory Study

EIA Notification of LESSEE TANT

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

Wetland Permit Application

Environmental Information Worksheet

ADDITIONAL ATTACHMENTS TO FORM-1 M/S. SDB DIAMOND BOURSE

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009

FORM-I CORPORATE OFFICE FILM CITY PROJECT FC 24C, SECTOR-16A, FILM CITY, NOIDA, UTTAR PRADESH FOR. M/s WINDSOR CORPORATE TOWERS PVT LTD PREPARED BY

Project Proponent: M/S FAITH BUILDTECH PVT. LTD. EIA Consultant:

Form-I for Amendment of Environmental Clearance for Meja TPP (2x660MW) Meja Urja Nigam Pvt. Limited

Guidance on use of Disposal and Recovery Codes (Waste Management Act, 1996 as amended)

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

PRE-FEASIBILITY REPORT

Florida Department of Environmental Protection. Bureau of Mining and Minerals Regulation. Regulation of Mines. Howard J. Hayes, Program Administrator

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS

Environmental Management Plan (EMP)

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695]

Details of Project. Underground source

9.3.9 Industry uses code

Construction Waste Measurement Guide

City of Tacoma Surface Water Management Manual

Proposed New 18 CFR Part Hydraulic Fracturing in Shale and Other Formations:

Application For Prior Environmental Clearance of Proposed IKEA Store

Base Metal and Iron Ore Mining

SECTION A1 EXCAVATION AND BACKFILL GENERAL

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS

PROJECT FEASIBILITY REPORT

Empyrean by M/s Hallmark Housing Infra SURVEY NOS. 212 & 239, PUPPALAGUDA, RAJENDRANAGAR MANDAL, RANGA REDDY DISTRICT 1. FORM I 2.

Greater Dublin Drainage Project

WE EEN Wizard of the Environment: the Enterprise Europe Network. Eurosportello del Veneto Via delle Industrie 19/C Venezia

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

OrbitTowers. M/s. Plerum Infra Projects Private Limited PLOT NO. 30/C, SURVEY NO. 83/1, RAIDURG PANMAKHTA, SERILINGAMAPALLY, RANGA REDDY DISTRICT

Baltic Marine Environment Protection Commission

Application for Gas Exploration and Production

Construction of Dariali HEPP. Reinstatement Plan

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

RAJASTHAN REFINERY TOWNSHIP PROJECT, RAJASTHAN

MATERIALS AND RESOURCES

(Consolidated Version) 1 of COUNCIL DIRECTIVE ON WASTE

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

New York Community Solar Facility Decommissioning Plan

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

Application For Waste Regulation (Check all that apply)

Environmental Impact Assessment of Hydroelectric Power Plant LEEZA MALIK (2013CEP2080) TUSHAR SINGLA (2011MT50623)

Transcription:

(See paragraph 6) (I) Basic Information FORM - 1 Sr. Item Details. 1 Name of the Project Mohan Willows proposed housing complex on property bearing S.. 64, S.. 65, H.. 1, S.. 66 and S.. 67, H.. 1A & 1B of village Shirgaon, Tal- Ambernath, Dist-Thane 2 S.. in the Schedule 8 (a) 3 Proposed capacity/area /length/tonnage to be handled/command area/lease area/ number of wells to be drilled Plot Area. (m 2 ) FSI Area (m 2 ) n-fsi Area (m 2 ) Total Construction Area (m 2 ) 30050.00 sq.m 42973.24 sq.m. 24529.70 sq.m. 67502.94 sq.m. 4 New/Expansion/Modernization New Project 5 Existing Capacity/Area etc. NA 6 Category of Project i.e. A or B B 7 Does it attract the general condition? If t Applicable, Please specify 8 Does it attract the specific condition? If t Applicable yes, Please specify 9 Location Plot/Survey/Khasra. S.. 64, S.. 65, H.. 1, S.. 66 and S.. 67, H.. 1A & 1B Village village Shirgaon Tehsil Ambernath District Thane State Maharashtra. 10 Nearest railway station/airport along with distance in kms. Badlapur Railway Station. (Road Distance :2.8 Km) Chhatrapati Shivaji International Airport, Mumbai. (Road Distance : 59.8 Km) Nearest Town: Badlapur (2.8 km) 11 Nearest Town, City, District Headquarters along with distance in km. 12 Village Panchayats, Zilla Parishad, Kulgoan Badlapur Municipal Corporation Municipal Corporation, Local body Veer Savarkar Flyover, Katrap, Badlapur, Maharashtra (complete postal addresses with telephone 421503 nos. to be given) 13 Name of the applicant M/S Mohan Lifespaces LLP 14 Registered Address G1, Mohan Plaza, Khadakpada, Next to Mohan Pride, Wayle,Nagar,Kalyan (W) - 421 301, India. 15 Address for correspondence: As above Name Mr. Manohar Manchandya Designation(Owner/Partner/CEO) Designated partner 1

Address G1, Mohan Plaza, Khadakpada, Next to Mohan Pride, Wayle,Nagar,Kalyan (W) - 421 301, India. Pin Code 421 301 E-mail mohanwillows.ec@gmail.com Telephone. 0251-2305999/98/97 Fax. - 16 Details of Alternative Sites examined, If ne any. Location of these sites should be shown on a topo sheet 17 Interlinked Projects 18 Whether separate application of t Applicable interlinked project has been submitted? 19 If yes, date of submission t Applicable 20 If no, reason t Applicable 21 Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. The Forest (Conservation) Act, 1980? The Wildlife (Protection) Act, 1972? The C.R.Z. tification, 1991? 22 Whether there is any Government Order/Policy relevant/relating to the site? 23 Forest land involved (hectares) Nil 24 Whether there is any litigation pending. against the project and/or land in which the project is propose to be set up? Name of the Court Case. Orders/directions of the Court, if any and its Relevance with the proposed project. Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for 23 mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.,) (II) Activity 1. Construction, operation or decommissioning of the project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies etc.) 2

SR. NO. Information/ Checklist confirmation 1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) 1.2 Clearance of existing land, vegetation and buildings? / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data Current land use is Residential as per the development plan. 1.3 Creation of new land uses? The proposed project is redevelopment of existing society. 1.4 Pre-construction investigations e.g. bore Geo-Technical investigations have been houses, soil testing? carried out. 1.5 Construction works? Construction of 12 Residential/commercial wings is proposed. Out of 12 wings 7 wings are constructed. Total constructed area as of now = 29906.71 sq.m. Wings Configuration Status Wing ST+12 Floors Constructed A Wing ST+10 Floors Constructed B Wing ST+12 Floors Constructed C Wing ST+10 Floors Constructed D Wing E ST+12 Floors t constructed Wing F G+2 Floors(shops + Club House) Wing ST+24 Floors G Wing ST+24 Floors H Wing I ST+24 Floors Wing J Grd Flr(Shops) Wing ST+12 Floors Constructed A2 Wing B2 ST+12 Floors Constructed 1.6 Demolition works? Existing structure of 160.00 sq.m. is to be demolished. Will be disposed as per the local norms of concern authority. 1.7 Temporary sites used for construction During the construction phase, housing works or housing of construction facilities are not proposed as most of the workers? skilled/unskilled manpower required will be hired on contract basis. The site has temporary store rooms and site office during construction phase, which will be later demolished. NA 3

1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations The above ground structures will comprise 12 residential commercial wings Wings Configuration Wing A ST+12 Floors Wing B ST+10 Floors Wing C ST+12 Floors Wing D ST+10 Floors Wing E ST+12 Floors Wing F G+2 Floors(shops + Club House) Wing G ST+24 Floors Wing H ST+24 Floors Wing I ST+24 Floors Wing J Grd Flr(Shops) Wing A2 ST+12 Floors Wing B2 ST+12 Floors 1.9 Underground works including mining or tunnelling? 1.10 Reclamation works? t Applicable 1.11 Dredging? t Applicable 1.12 Offshore structures? t Applicable Excavation for foundation and laying of cables and pipelines is involved. The excavated material is used for backfilling/leveling within the plot and remaining material had disposed by covered trucks to the authorized site as per the local norms. underground works including mining/tunneling is required except minor activities like excavation of earth for foundation, lay down of pipes, underground storage tank, electric cables etc. 1.13 Production and manufacturing Processes? 1.14 Facilities for storage of goods or materials? 1.15 Facilities for treatment or disposal of solid waste or liquid effluents? t Applicable Separate raw material storage is made which will be temporary. Construction Phase: Cement is stored. Sand is stacked under tarpaulin cover. Bricks and steel are laid in open. Operation Phase: Storage area of manure and sludge is provided. Construction Phase Construction workers have provided with separate toilet blocks. Collection bins are provided separately for bio-degradable and non-biodegradable waste at several locations. Operation Phase 4

1.16 Facilities for long term housing of operational workers? 1.17 New road, rail or sea traffic during construction or operation? 1.18 New road, rail, air waterborne or other transport infrastructure including new or Altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission lines or pipelines? 1.21 Impoundment, damming, realignment or other changes to the hydrology of watercourses or aquifers? Dry Waste (Kg/day): 1017 Wet Waste (Kg/day): 1496 Total solid waste (Kg/Day): 2513 Dry waste: To be managed through authorized recyclers. Wet Waste: To be processed in the Organic Waste Converter and manure so obtained will be used for landscaping. Wastewater generated (608 KLD) from domestic uses will be treated in STP of capacity 630KLD. Sewage sludge of 30 Kg will be used as manure for gardening. Treated water will be utilized for flushing & gardening (239 KLD). Balance water (308 KLD) will be released in the municipal sewer drains long-term housing facilities proposed as most of the skilled/unskilled manpower required for the operation activities will be hired from the nearby areas. The project site is adjacent to 15 m wide DP Road which is utilized during construction and operational phase. New road and rail track is not required. In the post construction phase, there will be increase in the traffic load due to the proposed project will be 1256 nos. of 2W (scooters & cycles) & 50 4W including the traffic load contributed by visitors. Provided parking no. 2W = 1256 s. 4W= 50 s. new road, rail or any other transport infrastructure is required. The entire essential infrastructure is already available. Existing roads will not be affected by upcoming construction. There will be no diversion of electrical transmission line or pipelines. However, the project involves construction of new internal pipelines for fresh water, recycled water, rain water harvesting, and sewer lines within the project. t required 1.22 Stream crossings? There is no stream passing through the site. 5

1.23 Abstraction or transfers of water from ground or surface waters? 1.24 Changes in water bodies or the land surface affecting drainage or run-off? 1.25 Transport of personnel or materials for construction, operation or decommissioning? 1.26 Long-term dismantling or decommissioning or restoration works? 1.27 Ongoing activity during decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either temporarily or permanently? - There will be no change in drainage pattern. The project will not materially affect the drainage or runoff in the area. It will be improved by well planned development. The existing road (15.0m wide DP Road) abutting to the site with 12.00 m wide DP Rd within the plot will be utilized for the transportation of material. Workers required will be fulfilled from nearby area. Transport of construction material to site during construction phase will take place. Transport planning schedule made for such transport planning schedule will be made for such transport to take place during non-peak hours & day time only. NA Construction Phase Temporary influx of construction workers to the site. Operation Phase On completion of the project, additional residents along with existing tenants will occupy their flats. Total population is expected to be 5130 s on permanent basis. 1.29 Introduction of alien species? Indigenous or Natural species will be planted. 1.30 Loss of native species or genetic NA diversity? 1.31 Any other actions? t applicable NA 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply) SR. NO. Information/ Checklist confirmation 2.1 Land especially undeveloped or agricultural land (ha) 2.2 Water (expected source & competing users) unit: KLD / - Details thereof (with approximate quantities/ rates, wherever possible) with source of information data Construction Phase It is expected to work about 50 to 70 labours at site. (Depending upon construction activity). The water demand is met by water tankers. Operation Phase Total water demand of the project is expected to be 693KLD approximately 6

2.3 Minerals (MT) t Applicable 2.4 Construction material stone, aggregates, sand / soil (expected source MT) local dealer. Fresh water (KLD): 448KLD Recycled water (KLD):239KLD Swimming Pool make up : 6 cum The water requirement will be met by the KBMC/Recycled water from STP. The construction materials, which are to be used in the project site, will be procured from S r. N o. Name Unit s 1 Cement bags 2 White Cement 3 Steel Metal Quant ity 29532 5 Appr ox Total Weig ht of each item in tons 1 bags 3164 2 tonn es 4 Metal cuft 6767 3 11389 79 5 Sand cuft 80398 5 5 6 Bricks/sipore 16918 no. x 346 6 7 Binding wire kg. 67503 7 8 Tiles Granite/Marb sq.ft 21095 8 le 9 Paint lts 23204 9 1 Plaster/ sq.m 0 Concrete trs 73831 10 1 1 Wood kg. 18985 11 1 52736 Aluminium kg. 2 7 12 2.5 Forests and timber (source MT) Certified Timber to be purchased from nearby markets. 2.6 Energy including electricity and fuels Operation Phase (source, competing users) Unit: fuel (MT), energy (MW) Particulars Details Connected Load 10913.95 KW 4 Maximum Demand 4614.97 KW The power requirement will be met from MAHAVITARAN. 7

2.7 Any other natural resources (use appropriate standard units) of DG Sets: 1 X 220 KVA and 1 X125KVA of D.G. sets will be provided for emergency backup. 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health SR. NO. Information/ Checklist confirmation 3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by changing living conditions? / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data DG sets will only be used as back up energy during power failures. Drums of HSD will be stored as per MSIHC rules. Other hazardous materials like paints, thinners will be stored as per MSIHC rules in a separate area away from construction area and Temporary Housing Facility provided for the onsite workers. The storage area will be paved and spillages, if any shall be treated as per Operation Control Procedures. During the entire construction phase adequate precaution is to be taken to avoid stagnation of water giving rise to mosquito breeding. Regular fumigation will be carried out. Adequate housekeeping practices to be followed to reduce insect menace on site. The living condition of the public of the nearby areas is not affected due to upcoming of the project. The solid waste will be suitably treated, while the liquid effluent will be treated in the sewage treatment plant of adequate capacity. 3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc., Nearest hospitals, residential area is at 5-6 km. Temporary increment in the pollution load with respect to air and noise during construction phase shall be there. 3.5 Any other causes other causes identified. 4. Production of solid wastes during construction or operation or decommissioning (MT/ month) SR. Information/ Checklist NO. confirmation 4.1 Spoil, overburden or mine wastes / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data Generation of overburden and mine waste is not applicable, however, spoil is generated during site preparation and other activities involving cutting/excavation. The excavated material to be used on the site. 8

4.2 Municipal waste (domestic and or commercial wastes) Dry Waste (Kg/day): 1017 Wet Waste (Kg/day): 1496 4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Mode of Disposal of Waste: Dry waste: To be managed through authorized recyclers. Wet Waste: To be processed in the Organic Waste Converter and manure so obtained will be used for landscaping. Sludge Quantity: 30 kg. Dry sludge will be used as manure for gardening. Used oil from DG set will be stored carefully at separate location duly marked and will be sold to CPCB authorized recyclers. 4.4 Other industrial process wastes t Applicable 4.5 Surplus product t Applicable 4.6 Sewage sludge or other sludge from effluent treatment Dewatered / dried sludge from STP will be used as manure for gardening. 4.7 Construction or demolition wastes Demolition waste to be generated during demolition of existing buildings/structures. The waste generated will be used for backfilling within the plot. Construction phase waste includes empty cement bags, paint containers; scrap metal, wood, broken tiles etc. the wastes with its management is shown in the below table:- Sr no Particulars Quantity Units Management 1 Steel 109 Tonnes To be sold for recycling 2 Cement 5446 Kg Cement waste to be used for bunding purpose, temporary plaster concrete works. 3 Sand 45 Cum Waste sand to be used for bedding for flooring purpose. It will also be used as filler material for toilets water proofing 4 Aggregates 2456 Cum It is to be used as a layer for internal roads and building 9

boundary wall. 4.8 Redundant machinery or equipment 4.9 Contaminated soils or other materials 5 Wood 231 Sqmt To be sold for recycling 6 Tiles 6142 Sqmt Waste tiles to be used as china mosaic water proofing for terraces.. Also it will be used for skirting purpose. 7 Paint cans (20 lit per can) 1914 Paint Cans To be sold for reuse All machinery used for the project will be quality products and there will not be any redundant machinery. Any damaged machinery will be scraped with the authorized operators. During painting, spillage of oil, diesel, leakage from STP etc. Every precaution is to be taken to avoid soil contamination. 4.10 Agricultural wastes t Applicable 4.11 Other solid wastes Only municipal solid waste will be generated. 5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/ hr) SR. Information/ Checklist NO. confirmation 5.1 Emissions from combustion of fossil fuels from stationary or mobile sources 5.2 Emissions from production processes 5.3 Emissions from materials handling including storage or transport 5.4 Emissions from construction activities including plant and equipment / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data Emissions from DG set only in case of emergency. Stacks as per CPCB guidelines shall be provided. Small amounts of emissions will be there from Construction machinery and vehicles during construction phase. During Operations phase, there will be minor emissions from vehicles used by occupants and visitors. There are no production processes involved. Emissions is to be generated, while handling and transportation of materials like cement, sand etc. to site, however, it is temporary in nature. Regular water sprinkling & tarpaulin covers are to be provided to control & arrest dust emissions. The project may cause rise in dust levels during construction phase. Precautions will be taken to reduce dust generation during construction phase. 10

5.5 Dust or odours from handling of materials including construction materials, sewage and waste 5.6 Emissions from incineration of waste 5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources RMC use minimize the handling of cement, sand and concrete thereby reducing dust generation at site. Tarpaulins are used to cover trucks carrying debris. Water sprinkling is to be done at regular intervals to arrest dust pollution. Construction Phase Dust emissions are generated due to movement of vehicles and material handling. Use of RMC reduces the dust emission from material handling. Operation Phase During Operation Phase, emissions will be generated from Operation of DG sets. Minimal emissions will be generated from movement of vehicles as the roads will be paved. Odour will be generated from STP and handling of organic wastes during Operations Phase. t Applicable such practices shall be adopted on site. t Applicable 6. Generation of ise and vibration and Emissions of Light and Heat SR. Information/ Checklist NO. confirmation 6.1 From operation of equipment e.g. engines, ventilation plant, crushers 6.2 From industrial or similar processes. 6.3 From construction or demolition / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data ise generation from construction equipments used for drilling, cutting operations. During Operation Phase, ise will be generated due to operation of DG sets. This will be about 90-105 db (A). All DG sets will be encapsulated as per rules, will be mounted on anti vibration mounts and will confirm to noise standards. The noise generating activities will be restricted to day times and during working days only. The activities will be staggered to reduce cumulative impacts. t Applicable. Average decibles at source during Construction is in the range of 75-90db. The average noise levels during peak construction activities at distance of 200 mts will be 60-70 db. 6.4 From blasting or piling t Applicable 6.5 From construction or The noise levels will be in the range of 75-90 db operational traffic 6.6 From lighting or cooling ise and vibrations may exceed during malfunction of systems Air conditioners during Operations Phase. 6.7 From any other sources t Applicable 11

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea SR. Information/ Checklist NO. confirmation 7.1 From handling, storage, use or spillage of hazardous materials. 7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) 7.3 By deposition of pollutants emitted to air into the land or into water / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data t Applicable 608 KLD sewage generated from the project will be treated in STP of capacity 630 KLD and reused for flushing and gardening. Excess treated water will be sent to existing municipal drain. Dust emissions during construction activities. Treated sewage water will be recycled and reused; whereas the surplus 308 KLD will be discharged in Municipal Sewer line. 7.4 From any other sources t Applicable 7.5 Is there a risk of long term build up of pollutants in the D.G sets will be used as a backup source only. environment from these sources? 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment SR. Information/ Checklist NO. confirmation 8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances. / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data Good housekeeping and safety procedures will ensure that chances of accidents will be minimal. Adequate procedures are laid down for each of the hazard involving activities to prevent mishaps. 8.2 From any other causes t Applicable 8.3 Could the project be affected by natural disasters causing environmental damage (e.g. It comes under Seismic Zone III. The construction will be as per ISI893 (Part-II): 2002. Onsite emergency prepared plan will be created and displayed. Floods, earthquakes, landslides, cloudburst etc)? 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality SR. Information/ Checklist NO. confirmation 9.1 Lead to development of supporting utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: / Details thereof (with approximate quantities/ rates, wherever possible) with source of information data Proposed project is in urbanized area & not a path setting project in the area. Infrastructures like roads, power supply are already established in the area. STP, Rain Water Harvesting, solar energy harvesting system. 12

Supporting infrastructure (roads, power supply, waste or waste water treatment, 31 etc.) housing development extractive industries supply industries other 9.2 Lead to after-use of the site, which could have an impact on the environment. 9.3 Set a precedent for later developments 9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects (III) Environmental Sensitivity t Applicable This project is not a trend setting project in the region. -- SR. Areas Name/ Aerial Distance (within 15 km.) NO. Identity Proposed project location boundary 1. Areas protected under international - NA conventions, national or local legislation for their ecological, landscape, cultural or other related value. 2. Areas which are important or sensitive - NA for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests. 3. Areas used by protected, important or - - sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration. 4. Inland, coastal, marine or underground - - waters 5. State, National boundaries. - The project is located within municipal limits. 6. Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas. - t Applicable 7. Defence installations. - defense installation in the neighborhood. 8. Densely populated or built-up area. - Residential area all around the site. 9. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) - Schools: Schools, hospitals and small temples are observed in 10 km radius. Heaven Bell Convent (0.850km, west side) 13

School College: Bharat College of Arts & Commerce Hospital : Matrix Multispecialty Hospital (4.2 km, East side) 10. Areas containing important, high quality or scarce resources (groundwater resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) (2.1km, East side - NA - t in immediate vicinity of the area. - This area is generally plain & come under seismic zone III. 14