Contractors, Property Owners, Plans Examiners & BSD Managers

Similar documents
Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

SUBSTANTIAL IMPROVEMENT

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

DEVELOPMENT SERVICES PO Box 1110 Tampa, FL Date: May 12, Interested Parties. John L. Barrios, CBO, Building Official

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER

PERMIT APPLICATION REQUIREMENTS INTERIOR RENOVATIONS/BUILD OUTS CODES USED: ADOPTED FLORIDA BUILDING CODE & NEC

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

RESIDENTIAL BUILDING PERMIT PROCEDURES

STATE PREFERENTIAL PROPERTY TAX ASSESSMENT PROGRAM

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

BUILDING PERMIT APPLICATION

APPLICATION FOR CONTRACTOR REGISTRATION AND RENEWAL OF REGISTRATION INSTRUCTIONS AND CHECKLIST

PERMIT APPLICATION REQUIREMENTS NEW COMMERCIAL BUILDING/CONSTRUCTION CODES USED: CURRENT ADOPTED FLORIDA BUILDING CODE AND NEC

Commercial Remodel Permit

BYRON TOWNSHIP BUILDING PERMIT APPLICATION 8085 Byron Center Ave SW., Byron Center, MI /Fax

CITY OF CRANSTON RESIDENTIAL PERMIT PROCEDURE BASEMENT RENOVATION

City of Centerville Building, Zoning & Code Enforcement Department

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

THE CONSTRUCTION SUPERVISOR

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50

Received by:* Date Received:* Zoning Approval:* Date:* PERMIT#:* *ZONING: *SETBACKS: FRONT ft/ SIDE ft/ REAR ft *FLOOD ZONE:

Building Permit Application Instructions INFORMATION REQUIRED FOR ISSUANCE OF A BUILDING PERMIT

REQUEST FOR ARCHITECTURAL REVIEW AND HOA APPROVAL - PHEASANT WALK HOMEOWNERS ASSOCIATION, INC.

Town of Pittstown. Office of the Building Inspector / Code Enforcement Officer

Red Fox Run Property Owner s Association, Inc. P.O. Box 194 Tryon, NC 28782

Marbella Isles Homeowners Association, Inc.

COMMUNITY DEVELOPMENT

BUILDING PERMIT APPLICATION

START RIGHT A G U I D E T O L + I S E R V I C E S

NOTICE TO APPLICANT WARNING TO OWNER AND AFFIDAVIT

Construction Summary

PeachStone Capital, Inc. Atlanta s Hard Money Lender When timing is everything, we close! Hard Money Loan Property Worksheet Checklist

Minimum Requirements For One & Two Family Structures FBC 6 th Edition (2017)

Chapter 6 The Improvements Section

RESIDENTIAL COMPONENT TECHNOLOGY Mobile Manufactured Housing

BUILDING PERMIT APPLICATION PACKAGE

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011

Project Green House. Green Team. Making the world greener one house at a time

TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR DECKS

II. IDENTIFICATION A. OWNER OR LESSEE ADDRESS (number, street, P. O. Box, Apt., etc.)

NARI National 2018 CotY Program Categories Please read category descriptions carefully as some criteria have changed.

HOW TO OBTAIN A BUILDING PERMIT

UNINCORPORATED JACKSON COUNTY BUILDING PERMITS


BUILDING CODES & DESIGN CRITERIA

A Guide to Building Permits for Home Owners / Renovators

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements

RESIDENTIAL CONSTRUCTION PERMIT FEES

2016 Wage Survey of Public and Private Construction Projects Building Construction Trades (Excludes Residential Construction)

HENDRY COUNTY BUILDING, LICENSING & CODE ENFORCEMENT

The following materials and documents are required in order for you to obtain a Building Permit:

New Homes Forestbrook Road. Yes, it s INCLUDED!

Application for Commercial Plan Review and Building Permit. Address:

Building Department. Building Permits A Homeowner s Guide

PROCEDURE FOR REQUESTING A BUILDING PERMIT

Home Building Planner

BUILDING DEPARTMENT GUIDE TO RESIDENTIAL BUILDING PERMITS

CITY of COLDWATER. Requirements for Obtaining Building Permits City of Coldwater, Michigan

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

City of Milford, Connecticut Information Regarding Permits

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

THE STRATA UNIT May 25, 2008

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS **************************************************************************

BUILDING PERMIT APPLICATION GUIDE FOR HOMEOWNERS

Chapter UNIFORM CODES FOR CONSTRUCTION BUILDING CODE

Davis Frame Co., Inc. Construction Budget Considerations

Residential New Home Requirements 200 South Main Blue Ridge, Texas

CLIPPER ESTATES HOMEOWNER S ASSOCIATION DESIGN GUIDELINES

APPLICATION. Application filing fee $10.00

Residential Building Permit & Inspection Procedures

CITY OF GLASGOW BUILDING PERMIT APPLICATION 126 E. Public Square Glasgow, KY Phone: (270) Fax: (270)

Residential Building Inspections

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule "C"

The Road Home Small Rental Property Program Guide to Green Building Standards

RESIDENTIAL BUILDING PERMIT INFORMATION

CERTIFICATE OF INSPECTION

Detached Garages and Building Permits. 1 and 2 Family Dwellings

Feasibility Report. Property Inspection Engineers, Inc. (248) Property Address. 405 Fairgrove Royal Oak, MI.

A homeowners/applicants guide to understanding and making application for a building permit.

CITY OF CRANSTON PLANS MUST BE APPROVED BY THE FIRE DEPARTMENT BEFORE SUBMITTING TO OUR OFFICE FOR REVIEW.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

U.S. Department of Housing and Urban Development Community Planning and Development

Required Information for Permit Issuance

New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric

HATFIELD TOWNSHIP DECK/PATIO PERMIT PROCEDURES

RESIDENTIAL BUILDING PERMIT

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

St. Louis County Department of Public Works Division of Code Enforcement. When is a Building Permit required for Residential Projects?

All new construction, mobile home placement & additions.

Residential Building Permit Application

Application Requirements for obtaining a Building Permit

BUILDING PERMIT APPLICATION

Applying for Permits to build a new house in Linn County

Building/Zoning Permit Fee Structure

Schedule T5. Tender Documents. This tender is for: Tender Documents: The documents issued for this tender include the following: Tender Schedules

INC. VILLAGE OF COVE NECK OFFICE: (516) FAX: (516)

Transcription:

DEVELOPMENT SERVICES PO Box 1110 Tampa, FL 33601-1110 NOTICE DATE: June 7, 2017 TO: Contractors, Property Owners, Plans Examiners & BSD Managers FROM: John Barrios, Division Director Building and Construction Services BOARD OF COUNTY COMMISSIONERS Victor D. Crist Ken Hagan Al Higginbotham Pat Kemp Lesley "Les" Miller, Jr. Sandra L. Murman Stacy R. White COUNTY ADMINISTRATOR Michael S. Merrill COUNTY ATTORNEY Chip Fletcher INTERNAL AUDITOR Peggy Caskey CHIEF DEVELOPMENT & INFRASTRUCTURE SERVICES ADMINISTRATOR Lucia E. Garsys SUBJECT: DEFINITION OF SUBSTANTIAL IMPROVEMENT The Hillsborough County Construction and Land Development Codes make reference to the requirement that all new construction and substantial improvements within the Special Flood Hazard Area to be elevated to meet freeboard and/or the minimum-elevation requirement. As defined by Hillsborough County, substantial improvement is any reconstruction, rehabilitation, addition, new construction, manufactured home replacement or other improvement of a structure or manufactured home during a 12- month period measured from the date of final inspection or certificate of occupancy, the cumulative cost of which equals or exceeds 50 percent of the market value of the structure before the start of construction of the improvement. This term includes structures that have incurred substantial damage, regardless of the actual work performed, or repetitive loss. Replacement cost or value is not an acceptable value for determining substantial improvement and is not a replacement for market value. This term does not, however, include either: a. Any project for improvement of a structure to correct existing violations of state or local health, sanitary, or safety code specifications which have been identified by the local code enforcement official and which are the minimum necessary to assure safe living conditions, or b. Any alteration of a historic structure provided that the alteration would not preclude the structure's continued designation as a historic structure. County codes have established that if the cost of the improvement exceeds 50% of the value of the structure before the improvement, then the improvement will be considered substantial and the entire structure must be elevated to meet freeboard and/or the minimum-elevation requirement. This requirement is consistent with minimum standards associated with the National Flood Insurance Program (Chapter 44, U.S. Federal Code of Regulations). Attached to this memorandum are worksheets that are required to be completed by the permit applicant or applicant s representative. If County codes cause an undue hardship due to the configuration of the property, a variance may be requested through the Hillsborough County Flood Damage Control Board. If you have any questions regarding this information, please contact Ms. Vanessa Hernandez (813) 307-4441 or Mr. Eugene Henry (813) 307-4541. HCFLGOV.NET 1 of 9 REV. 10-19-17

SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here s information YOU need to know about the 50% Rule. If your home or business is below the 100-year flood elevation, Hillsborough County has flood damage control prevention regulations that may affect how you remodel, renovate, or add-on to your building. If your home or business sustained structural and/or interior damage, these regulations may affect how you rebuild. These laws are required in order for the County to participate with the National Flood Insurance Program, which assists in recovery from a future flood event. These laws must be enforced in order for federally-backed flood insurance to be made available to Hillsborough County residents and property owners. Save yourself time, aggravation, and money. Please read the following information: SUBSTANTIAL DAMAGE: Means damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damage condition would equal or exceed 50 percent of the market value of the structure before the damage occurred (NOTE: The cost of the repairs must include all costs necessary to fully repair the structure to its before damage condition). SUBSTANTIAL IMPROVEMENT: Means any reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds 50 percent of the market value of the structure before the start of construction of the improvement. If a building is substantially damaged or substantially improved, it must be brought into compliance with Hillsborough County flood damage control regulations, including elevating the building to six-inches above the 100- year flood elevation. Hillsborough County, following National Flood Insurance Program (FEMA) requirements, has the responsibility to determine substantial damage and substantial improvement and has implemented the following procedures to do so: Hillsborough County will estimate Market Value by using the tax assessment value of your structure (excluding the land). If you disagree with this estimate of Market Value, you may hire a state licensed appraiser and submit a comparable property appraisal in which depreciated value of the structure has been calculated. You must submit to Hillsborough County a detailed and complete cost estimate for the addition, remodeling, reconstruction or repair of all the damages sustained by your home, which has been prepared and signed by a licensed general contractor or design professional. The contractor must sign an affidavit indicating that the cost estimate submitted includes all damages or all improvements to your home. (See copy attached) 2 of 9

Hillsborough County will evaluate the cost of improvements or repairs and determine if they are fair and reasonable and in accordance with the cost of construction with the Tampa Bay area as described within the. For damage repairs, pre-storm prices and rates will be utilized. The cost of improvements or repairs does not include items not considered a permanent part of the structure (i.e., plans, surveys, permits, sidewalks, pools, screens, sheds, gazebos, fences, etc.). (See attached form) If your home is determined to have substantial damage or is proposed to be substantially improved, then an Elevation Certificate must be submitted to Hillsborough County to determine the lowest floor elevation. Garages and carports are not considered to be the lowest floor unless such is to be used for living area. If the lowest floor is below the 100- year flood elevation, the building must be elevated to or above that design flood elevation. Likewise, all electrical and mechanical equipment (heating and cooling, etc.), bathrooms and laundry rooms must be elevated above the design flood elevation. Only parking, building access, and limited, incidental storage is allowed below the design flood level (velocity zones and regulatory floodways have further restrictions). If the lowest floor, electrical and mechanical equipment, laundry and bathrooms are already above the 100- year flood elevation, the building can be repaired and reconstructed without further modifications. Building plans must be prepared to show how the building is to be elevated. If located in a velocity zone or regulatory floodway, or if the building is to be flood proofed, additional requirements and certifications exist. These plans must be prepared and certified by a registered professional engineer or architect. (Certificates for this purpose are available from the Development Services Division). Following a presidential disaster declaration, the Federal Emergency Management Agency or the Small Business Administration may make loans available for both house and businesses for purposes of elevating the structure to or above the 100- year flood elevation. Proof of substantial damage from Hillsborough County is required. 3 of 9

SUBSTANTIAL IMPROVEMENT/DAMAGE ITEMS TO BE INCLUDED IN ESTIMATING COST: All structural elements including but not limited to: Spread or continuous foundation footings and pilings Monolithic or other types of concrete slabs Bearing wall, tie beams and trusses Wood or reinforced concrete decking or roofing Floors and ceilings Attached decks and porches Interior partition walls Exterior wall finishes (e.g. brick, stucco, or siding) including painting and decorative moldings Windows and doors Re-shingling or retiling of roof, and Hardware All interior finish elements, including but not limited to: Tiling, linoleum, stone, or carpet over sub-flooring Bathroom tiling and fixtures Wall finishes, e.g. drywall, painting, stucco, plaster, paneling, marble, or other decorative finishes Kitchen, utility and bathroom cabinets Built-in bookcases, cabinets, and furniture, and Hardware All utility and service equipment, including but not limited to: HVAC equipment and duct work Repair or reconstruction of plumbing and electrical services Light fixtures and ceiling fans Security systems Built-in kitchen appliances Central vacuum systems, and Water filtration, conditioning or recirculation systems Also: Labor and other costs associated with demolishing, removing or altering building components, and Overhead and profit 4 of 9

SUBSTANTIAL IMPROVEMENT/DAMAGE ITEMS TO BE EXCLUDED: Plans and specifications Survey costs, and Permit fees Debris removal (e.g. removal of debris from building or lot, dumpster rental, transport fees to landfill and landfill tipping fees), and Clean-up (e.g., dirt and mud removal, and building dry out) Items not considered real property such as: throw rugs (carpeting over finished floors), furniture, refrigerators, and stoves not built-in, etc. Outside improvements, including: Landscaping Sidewalks Fences Yard lights Swimming pools Screened pool enclosures Sheds Gazebos Detached structures (including garages), and Landscape irrigation systems 5 of 9

ITEMS REQUIRED TO DETERMINE SUBSTANTIAL DAMAGE/IMPROVEMENT Applicant must submit the following (Make sure to have extra copies for your files): 1. Complete the attached application. 2. Detailed Cost of Improvement/Reconstruction. (Estimate and Affidavit, signed by a general contractor or licensed design professional and a copy of the license). 3. Elevation Certificate or Elevation Survey. 4. Current photos, or photos before and after the storm (if available). 5. Floor plan drawing (if available). 6. Owner s affidavit- signed and dated. 7. Contractor s affidavit- signed and dated. GUIDELINES TO COMPLETE THE ATTACHED RECONSTRUCTION/IMPROVEMENT COST ESTIMATE Reconstruction/Repair Ratio Percentage of item that must be repaired or reconstructed. (Example: The home has 2 windows, only 10 were damaged and are being replaced; ratio should equal 50%) ITEMS COST LABOR & MATERIAL RECON/REPAIR RATIO OF WORK OFFICIAL USE Concrete, Form, etc. $4,500.00 40% Carpentry Material $9,004.00 100% Doors/Windows, Shutters $2,046.00 50% 6 of 9

ESTIMATED COST OF RECONSTRUCTION/IMPROVEMENT FOLIO #: ADDRESS: This Cost Estimate of Reconstruction/Improvement must be prepared and signed by a Licensed General Contractor ITEMS Concrete, Form, etc. Carpentry Material (rough) Carpentry Labor (rough) Roofing Insulation & Weather Strip Exterior Finish (stucco) Doors, Windows & Shutters Lumber Finish Carpenter labor (finish) Hardware (finish) Hardware (rough) Cabinets (built-in) Floor covering (tile/rug) Plumbing Shower/Tub/Toilet Electrical Light Fixtures Built-in Appliances HVAC Paint Demolition and Removal Overhead and Profit LABOR COST MATERIALS CONSTRUCTION/REPAIR RATIO OF WORK OFFICIAL USE TOTAL (Please attach any additional information) Contractor s Name: CGB Lic #: Address: Phone #: Signature: Date: 7 of 9

OWNER RECONSTRUCTION/IMPROVEMENT AFFIDAVIT FOLIO #: - - - Contractor s Name: License #: Owner Name: Address: Phone #: I hereby attest to the fact that the repairs/reconstruction and/or remodeling list submitted for the Substantial Damage/Improvement Review by my contractor are ALL OF THE DAMAGES/IMPROVEMENTS sustained by this structure and will be done to the existing building and that all additions, improvements, or repairs on the subject building are included in this estimated construction herewith. No other contractor has made any repairs or reconstruction or additions or remodeling not included in the attached list. I understand that I am subject to enforcement action and/or fines if inspection of the property reveals that I have made repairs or improvements NOT INCLUDED ON THE ATTACHED LIST OF REAPIRS to MY HOME or that I have included non-conforming or illegal structures/additions, to the existing structure without having presented plans for such additions. I understand that any permit issued by Hillsborough County pursuant to this affidavit does not authorize the reconstruction, repair or maintenance of any illegal additions, fences, sheds or non-conforming uses or structures on the subject property. STATE OF COUNTY OF Before me this day personally appeared _, who, being duly sworn deposes and says that he/she has read, understands, and agrees to comply with all the aforementioned conditions. Owner s Signature Co-Owner Sworn to and subscribed before me this day of A.D., Year. Notary Public State of My commission expires: 8 of 9

CONTRACTOR RECONSTRUCTION/IMPROVEMENT AFFIDAVIT FOLIO #: - - - Contractor s Name: Address: License #: Property Address: Phone #: I hereby attest to the fact that I, or a member of my staff, personally inspected the above mentioned property and produced the attached itemized list of repairs, reconstruction, and/or remodeling list that are hereby submitted for a Substantial Damage/Improvement Review. These damages/improvements are ALL OF THE DAMAGES/IMPROVEMENTS sustained by this structure, and that all additions, improvements, or repairs proposed on the subject building are included in this estimate. I understand that I am subject to enforcement and penalties for violation action and/or fines if the inspection of the property reveals that I have made repairs or improvements NOT INCLUDED ON THE ATTACHED LIST OF REAPIRS/IMPROVEMENT to THIS STURCTURE or any non-conforming or illegal structures/addition, or repairs included to the existing structure without having presented plans for such additions. I understand that any permit issued by Hillsborough County pursuant to this affidavit does not authorize the reconstruction, repair or maintenance of any illegal additions, fences, sheds or nonconforming uses or structures on the subject property. Total Labor & Materials $ Overhead & Profit $ Total Cost $ See Attached Itemized List STATE OF COUNTY OF Affidavit Before me this day personally appeared, who, being duly sworn deposes and says that he/she has read, understands, and agrees to comply with all of the aforementioned conditions. Contractor s Signature Date: Sworn to and subscribed before me this day of A.D., Year:. My commission expires: Notary Public State of 9 of 9