CONSTRUCTION SUMMARY REPORT

Similar documents
Surface Repair Using Form-and- Pour Techniques

Surface Repair Using Form-and-Pour Techniques

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

SECTION SITE CONCRETE

DIVISION 04 MASONRY. Section Title Number MASONRY Maintenance of Masonry Masonry Mortaring Masonry Accessories

SECTION CAST-IN-PLACE CONCRETE

CSI SECTION MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials

By CTS Cement Manufacturing Corp.

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

.1 Formwork for cast-in-place concrete with shoring, bracing, and anchorage.

Construction Specification for Concrete Bus Pad

Tile on Existing. Viewpoint

Heavy Rib. Page 1 of 6. Expanded Mesh & Metal Products. Key Product Features:


Construction. SikaTop 111 Plus. Application Instructions. Sika Corporation

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

CTP STITCH-TIE AGAIN! Quick and easy way to re-anchor existing veneers to back-up structures.

Application Instructions for Dryvit Backstop NT For Use Beneath Claddings Other Than Dryvit EIFS

CONCRETE REPAIR IN ACTION: USING THE MANUAL AS A GUIDE. Christen Longoria, P.E. San Antonio District Project Engineer

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

Bid Opportunity Section CKP File No M May 2009 Page 1 of 9

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:

This specification refers to the following standards, specifications, or publications:

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION

DIVISION 04 MASONRY CAST STONE. A. Design Considerations. 1. Cast stone shall comply with ASTM C1364, Standard Specification for Cast Stone.

***************************************************************************************************************

Con-Spec Industries Ltd.

Author: M Shaw, Sika Limited. Construction. A Guide to the Concrete Repair European Standards BS EN 1504 Series

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

Standard specification for the application of Danosa Two-Layer waterproof roofing membrane to plywood & concrete surfaces.

Madewell Products Corporation December Industrial Court Alpharetta, GA Office: (770) Fax: (770)

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL. 5.1 General Certification Fabrication...

***************************************************************************************************************

SECTION CONCRETE PAVING SLABS SET IN MORTAR

DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340

1.3 Work shall include all reinforcement and accessories necessary to complete installation.

LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap

PRODUCT DATA SHEET Sika Galvashield XP

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

SPECIFICATION FOR REINFORCED SOIL WALL

Construction Standard Specification Section Exposed Aggregate Concrete. Exposed Aggregate Concrete

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

SikaProof Bentonite Plastic DPM overlap - Compacted Backfill Scale 1:5. Detail no: SB01 - Nov 2013

FLUID APPLIED WATERPROOFING

WATERPROOFING CONCRETE TIE HOLES USING XYPEX

3-part thixotropic epoxy patching mortar

A. ASTM C 150 Standard Specification for Portland Cement. B. ASTM C 595 Standard Specification for Blended Hydraulic Cements.

SIKALASTIC-152 EXTERIOR WATERPROOFING MEMBRANE. Product. Scope. Appraisal No. 811 [2013] Appraisal No. 811 (2013) Amended 28 August 2017

Table of Contents. List of Drawings

FIVE STAR PRODUCTS, INC. (800)

PPC Cement TUTORIAL. how to screed a floor

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS)

SECTION REINFORCING STEEL

MOISTURE MANAGEMENT. Providing roofing and waterproofing solutions. Zionsville High School Roof Asset Management Plan

Balconies Information. How to waterproof and reduce efflorescence

TIVOLI CARPARK SITE DEVELOPMENT, LITTLE COLLINS STREET, MELBOURNE BRICK AND BLOCK CONSTRUCTION

CELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES

SECTION COLD APPLIED RUBBER MODIFIED ASPHALT WATERPROOFING

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

Triton DCI Decoupling Mat

SECTION MODIFIED BITUMINOUS SHEET WATERPROOFING

SPECIFICATION GUIDELINE

Control of Random Cracking in Concrete Residential Pavements

SECTION ARCHITECTURAL CAST STONE

SECTION UNIT MASONRY SYSTEM

City of Brandon Division 2 Standard Construction Specifications Section January 2007 (Revision 2) Page 1 of 21 CONCRETE CONSTRUCTION

prospec.com Concrete Repair & Restoration

Product Data Sheet Sikadur -31 CF Normal Product Description Uses ruction Const Characteristics / Advantages

PAVING SLABS ON A CONCRETE BASE

Electronic Machinery Grouting Manual

Construction Specification for Utility Adjustments

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

A.2.a Random Riprap... Table

HILTI HY 150 REBAR DESIGN GUIDE

SECTION 11 - REINFORCED AND PLAIN CONCRETE WORKS CONTENTS

Wall Panels. Structural wall panel. Architectural wall panel. Cladding wall panel. Sandwich wall panel

CONSTRUCTION SPECIAL PROVISION FOR STRUCTURE REHABILITATION - CONCRETE PATCHES, REFACING AND OVERLAYS

PROPORTIONING CONCRETE MIXES

PERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960

System Recommendation SR0618

Tex-450-A, Capping Cylindrical Concrete Specimens

NORTHWESTERN UNIVERSITY PROJECT NAME JOB #

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

High performance shrinkage compensated cementitious grout


INTERNSHIP REPORT GOUTHAM.J

SECTION INTERLOCKING CONCRETE PAVERS

Behaviour of Post-Installed GFRP Adhesive Anchors in Concrete

SECTION CAST-IN-PLACE CONCRETE


DOWEL BAR RETROFIT DO S AND DON TS

SECTION CAST-IN-PLACE CONCRETE

MANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade.

SECTION GYPSUM BOARD ASSEMBLIES

METHOD STATEMENT 001 CONCRETE BALCONY WATERPROOFING FOR DIRECT FIXED TILES

CHOCKFAST INSTALLATION PROCEDURE

SECTION CONCRETE. B. ACI 318 Building Code Requirements for Structural Concrete and Commentary

Transcription:

Edison Engineers Inc. 89 King Street W. Suite 3 Dundas (Hamilton) Ontario Canada L9H 1V1 Info@edisonengineers.ca CONSTRUCTION SUMMARY REPORT To: Halton Condominium Corporation No. 70 c/o Wilson Blanchard Management Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repair Phase 3 From: David Petrina / Jason Truman Project No. 101205 Report: 01 Date: June 24, 2011 Visit Dates: Crew: March 24, 29 April 4, 7, 12, 19, 21, 26 May 3, 5, 10, 13, 24, 25, 26 June 1, 7, 9,13, 14, 15 Tony + 2 to 4 crew Richard + 1 to 2 crew 1.1 Objective.1 The existing masonry balustrades and railings are in very poor condition and their replacement is required. Corrosion of the embedded reinforcing steel at exposed balconies and stairs is causing the concrete to deteriorate and localized repairs are needed..2 The work involves removal of the existing brick balustrades and curbs, extending the balcony edges, removal of masonry columns and installing new steel I- beams, installation of a new waterproof membrane, and supply and installation of new pre-finished aluminum railings. Sections of brick balustrades to remain and adjacent masonry walls will be capped with stone..3 A phase 1 trial repair was carried out at units 1 to 4 at 80 Sarah Lane in 2009. Phase 2 carried out in 2010 included balcony repairs at 80 Sarah Lane, and 2104 and 2110 Marine Drive. Phase 3 is presently being carried out at 2100 and 2120 Marine Drive. 1.2 Work in Progress.1 Balcony and stair concrete repairs and masonry repairs are complete at the 2100 and 2120 blocks. Thin topside repairs and membrane preparations are in progress on both of the blocks. 1.3 Site.1 The contractor is responsible for site safety..2 The contractor used plywood to close and protect balcony doors. The wall mounted light fixtures were wrapped in plastic during the bulk concrete repairs to avoid damaging them..3 Six foot metal fencing is erected at each unit outlining the construction area. The contractor does not lock the fencing during non-work hours to permit residents to access their garages..4 Orange construction fencing surrounds the lower stairs to close balcony access.

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 2 of 8.5 No disposal bins are stored on site. The Contractor removes all debris at the end of each working day..6 A staging area is located in front of 2120-1 Marine Drive. The staging area contains a storage bin that houses material, equipment and construction documents. The staging area is surrounded with metal fencing..7 A portable washroom has been placed next to the visitor parking area north of the 2100 block. The contractor is required to maintain and clean the washroom regularly..8 The contractor is parking on the roadways in front of the 2120, 2110 and 2100 blocks. Efforts are being made to not park near roadway intersections to allow garbage trucks sufficient room to make wide turns. Figure 1: 2120 Block Site Protection Figure 2: 2100 Block Site Protection 1.4 Removals and Reinforcing.1 The existing masonry balustrades and supporting steel channels have been removed as required at all units. Balustrade returns separating unit balconies from one another are not removed. The contractor has salvaged brick units where possible to carry out masonry repairs. The bricks are used to tooth-in units where masonry walls and balustrades are terminated and to infill the new I- beams below the balcony slab edges..2 Edison completed mark-outs of deteriorated concrete on the balconies, stairs and landings with the Contractor. The Contractor used electric chipping hammers for the removals and has confirmed that every effort has been made to distribute the power usage evenly across all phase 3 units..3 All removed bulk concrete and construction waste was disposed and hauled off the site at the end of each working day..4 Extensive concrete repairs were carried out at some heavily deteriorated balconies, landings and stairs. Edison noted the reinforcing steel bars did not extend into the brick walls at some of these particular repairs. Edison advised the contractor to lap new bars over the placed bars and extend into the walls for support. Furthermore Edison advised the contractor to provide a key-in in all masonry walls to provide support to the landings and balcony slabs. The Contractor complied.

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 3 of 8 KEY-INS Figure 3: Landing Reinforcing Steel Figure 4: Key-in to Building Wall.5 Through slab removals were chipped to remove all deteriorated and unsound concrete. Removals were extended as required to encapsulate all heavily corroded bars. The topside patch perimeters were then saw cut to a min. depth of 25mm..6 Edison noted that the Contractor erected formwork at units 2 and 3 on the 2100 block before all the unsound concrete was removed. Edison advised the Contractor to remove the forms, remove remaining unsound concrete and reinstate the formwork. The contractor complied..7 Edison advised the Contractor that no 90 degree outside corners are permitted at repair perimeters. A 90 degree corner will create stress concentrations which may cause the concrete to crack. The contractor removed 90 degree outside corners as advised..8 The existing reinforcing steel was generally sound, and was cleaned and epoxy coated as specified. At extensive removals, where possible, the contractor replaced the existing steel with new epoxy coated bars..9 The cover of the existing steel was found to be typically 25mm or less in some locations. This is considered low. Low concrete cover provides both poor protection to the embedded steel and risks future concrete deterioration should the bars continue to corrode. Where extensive repairs were carried out the cover has been set to 60mm; however achieving a greater cover is difficult at smaller local repairs. Edison advised the Contractor to pry or wedge the existing steel upward to maximize the cover where possible. There is a low risk of further corrosion of the embedded steel since a new waterproofing system will be applied over the balconies and stairs. Also areas of current deterioration are the most prone to deterioration and these areas are being repaired as part of the work..10 Slab extensions are being provided at all balconies. The extensions provide a larger balcony surface and enhance the water shedding characteristics of the balconies. The extensions will help mitigate wetting of the masonry units below the balcony since water is permitted to drain along the front edge of the slab..11 If repairs were not required to the existing slab edge it was roughened with a chipping hammer. The roughened edge will help enhance the bond between the existing slabs and the new slab extensions. New hooked bars are provided at

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 4 of 8 every 100mm to mechanically attach the extension to the existing slabs. The hooks are doweled and epoxied in place. Edison noted that the Contractor had originally not extended the dowel holes to the specified depth. Edison advised that the Contractor recheck all the holes and extend holes to minimum depth of 125mm. The Contractor agreed. Edison noted that all the holes were extended to a 125mm depth where randomly checked..12 At balconies where extensive repairs were carried out hook bars lap over the steel mat. Minimum 300mm laps were provided. Figure 5: Slab Extension Hook Bars Dowelled into Existing Balcony Figure 6: Hooked Bars Lapped Into Steel Mat 1.5 Formwork.1 Formwork was provided at all repair locations. The formwork was lightly coated with an oil to help remove the forms once the concrete had hardened..2 Spray foam was used to fill any voids or open joints in the formwork..3 The existing balcony slabs are 100mm thick, while the designed edge extension thickness is 150mm. Entire balconies were replaced with 150mm thick slabs matching the new edge extensions at units where the deterioration was extensive. A step transition was made between the balcony edge and the existing balcony at units with less extensive repairs. The transition provides a consistent slab edge appearance and provides the specified slab edge thickness at all units. The transition occurs at the backside of the new I-beam and will be concealed by the new metal capping once installed.

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 5 of 8 Figure 7: Erecting Formwork Figure 8: Transition to Thicken Slab Edge 1.6 Concrete Placement.1 The existing concrete substrate was prewetted for a minimum of 24 hours prior to placing the concrete. Prewetting was achieved by appling wet burlap and plastic sheeting over top of the bonding substrate. Pre-wetting improves the bond of the new concrete to the existing concrete..2 Excess water was blown off the formwork prior to concrete placement..3 Plastic chair supports and tie wire were used to help prevent movement of the embedded steel during concrete placement..4 Edison advised the contractor to mix slurry to a 1:1 cement-sand ratio and to a 0.45 water-cement ratio. The contractor complied. The consistency of the slurry generally matched the consistency of the new concrete. The contractor applied the slurry to substrate surfaces to enhance bond between existing and new concrete..5 An independent Concrete Tester measured the slump, air content and temperature of the new concrete prior to its placement. Cylinders were cast for compressive strength testing. The concrete has since achieved all the specified requirements. Figure 9: Slurry Application Figure 10: Pre-Wetting Concrete Substrate

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 6 of 8.6 The concrete was vibrated during placement to help consolidate it. Edison advised the Contractor to drop the vibrator slowly at 1 foot intervals to help remove any entrapped air in the concrete. The contractor complied..7 A front loader transported the concrete from the truck to the repair locations. The concrete was then shoveled into place to minimize any splatter..8 The contractor applied wet burlap over the newly placed concrete for a specified moist cure period of 96 hours minimum. The burlap was covered in plastic to help retain the moisture in the burlap..9 The formwork was not removed until 75% of the concrete s compressive strength was achieved. The strength was verified by testing the cylinders cast during the placement of the concrete. Figure 11: Placing Concrete Figure 12: Freshly Finished Concrete 1.7 Brick Masonry.1 The existing soldier course brick capping along masonry walls dividing adjacent balconies was removed..2 The Contractor provided a mock-up of the new stone cap. The mock-up was approved matching both the phase 2 mock-ups and the project specifications..3 The installation consisted of: providing a smooth layer of mortar to the top surface of the balustrade, applying membrane flashings and upturns, dowelling threaded stainless steel rods to top of the balustrade with epoxy and placing the new stone copings..4 Edison noted that the Contractor had installed membrane flashings incorrectly on top of all the balustrade walls in preparation for the new stone copings. The flashings did not extend to the outside edges of the walls as required. The contractor agreed to reapply the flashings as specified. Edison noted that the flashings were reapplied as agreed..5 The Contractor carried out masonry repairs to remaining balustrades and to the closet walls located beneath the stairs..6 Balustrades and the outside edge of the closet walls are removed as required. Salvaged bricks are used to tooth-in new masonry units creating a clean termination in the masonry.

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 7 of 8.7 New mortar joints have been tooled to match the existing mortar joints. Figure 13: Keyed-in Masonry Figure 14: Doweled Stone Capping Figure 15: Membrane Application Figure 17: New Stone Capping Complete 1.8 Future Visits.1 Edison will continue to visit twice per week on average to review the work while in progress. 1.9 Schedule.1 The Contractor is 3-4 weeks behind the original schedule due to a record rainfall in May. The Contractor maintains that the original finish date can still be attained. 1.10 Materials.1 Ready Mix Concrete 35 MPa C-1 concrete, 6-9% air entrainment, 10mm stone, 150mm slump (±30mm), super plastisizers included. This concrete was used for bulk concrete repairs..2 12.5mm stainless steel threaded rod stone coping anchors.3 Epcon A7 by Redhead epoxy adhesive for coping anchors

Project: 80-100 Sarah Lane & 2098-2120 Marine Drive Balcony Repairs Page 8 of 8.4 PPG Amerlock 400 epoxy coating for embedded reinforcing steel in the balcony slab, stairs or landings..5 SikaTOP 123 plus by Sika for balcony and stair soffit repairs.6 King 1-1-6 Mortar (Type N) for masonry repairs Figure 18: Masonry Mortar Figure 19: Epcon A7 Epoxy