Retrofit Installation Guide

Similar documents
Concrete Masonry Unit Block Fill Installation and Estimating Guide

Technical Bulletin. Open-Cell Spray Polyurethane Foam Equipment Set Up and Processing: (Please Review Technical Data Sheet)

10 Steps to Save Energy in Your House

PREP + INSULATION. DISCLAIMER: These tools are for illustrative purposes only and

Application Specification:

TREAT RISING DAMP AND REDECORATE IN UNDER 24HRS

Work Write Up / Specification of Repairs HUD DIVISION 1. MASONRY HUD DIVISION 2. SIDING. Toll Free

MIKE ASHEY PRODUCTIONS PRESENTS MIKE ASHEY S PHASE-II HOBBY ROOM EXPANSION

The Inspection Process. Waxhaw N.C.

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

CITY OF SELMA, TEXAS Inspection Guidelines: Residential

GigaCrete Specification PlasterMax. PlasterMax : Fire Rated Plaster for Direct Application over Cement Masonry Units (CMU) Interior Walls

Attic Insulation. Student Guide

BEP Blue Barrier Installation and Application Guide

Professionally Sealed with GREAT STUFF PRO Products Seal Out Energy Loss. Seal In Comfort.

Product Information CHEMGLAZE B 9942 A/B. Coating for Casting Pits. Easy Application Chemglaze B 9942 A/B will bond to damp and wet surfaces.

Chapter 2 Understanding The Problem

EXCEL Medical Waste - Equipment Installation Section SECTION GYPSUM BOARD

Container Installation Guide

Important: Before You Start

QCI HEP Pre Exam Quiz

Retrofit Installer / Shell

STORAGE AND TRANSPORTION

1 AND 2 FAMILY DWELLING REQUIREMENTS

WEB BASED APPLICATION SPECIFIC INSTALLATION INSTRUCTIONS

Pella 250 Series. Wood Frame Construction with Vinyl Siding... V250-ID-888 Wood Frame Construction with Brick Veneer...

TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS OFFICE OF COLONIA INITIATIVES TEXAS BOOTSTRAP LOAN PROGRAM. Form 15 Work Write-Up

ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET

Container Installation Guide

Work Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos

Installation Procedures for the Ultra Air Barrier Wall System

Document Title: Doc No: FRM B4-59 Rev No: Page: Of: Thermal Insulation Program Certification Report

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018)

FIVE STAR PRODUCTS, INC. (800)

INSULATION OWENS CORNING INSULATION PRODUCTS IN THIS SECTION:

Section BUILDINGS, SHELTERS, ENCLOSURES

FUNDAMENTALS OF SPF FOR THE INDEPENDENT BUILDING ENVELOPE INSPECTOR CHAPTER 3 JOB SITE QUALITY CONTROL FOR THE BUILDING ENVELOPE

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

BEP Blue Barrier Installation and Application Guide

SECTION REFLECTIVE-FACED, MASONRY CAVITY WALL INSULATION

QuietRock 530 RF Application Notes

Kelly Village Apartments 3118 Green Houston, Texas 77020

Compliance Standards of Coated SPF System: inclusive of Permax 108 or Permax 115 Acrylic Elastomeric Coating ± 100

Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018

Respirable Silica Exposure Control Program

ATT-42/95 SAMPLING, Asphalt

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: TERMAL INSULATION SECTION: AIR BARRIERS REPORT HOLDER:

Rev. 07 8/15 Please Read Disclaimers:

Asbestos Awareness Program

Knauf Makes It Easy to Insulate

Improve Energy Efficiency and Air Sealing in Above-Grade Walls

Installation Guide Wall Panels

Continuous Insulation Systems for Exterior Walls

Understanding new Acceptance Criteria of Alternative Assemblies Thermal and Ignition Barriers over SPF

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES

FLUID APPLIED WATERPROOFING

Presented by The National Association of Certified Home Inspectors Chicago Chapter

Radon Vent Pipe System. Labeling Performance Indicators

Energy Efficiency in New Constructions built by Blake Taylor

Seal Harbor Development 1 Nagog Park Acton, MA 01720

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR DROP LOCK FLOORING

Blue Barrier Flash N Wrap 2400

for New Construction Applications

Structural. Orientation of the Home. Northeast Oklahoma REC s Energy Efficient Tips for Home Builders

Insulation Technologies and Installation Specifications for Better Energy Performance of Commercial Buildings

CertainTeed OPTIMA. Installation Instruction Manual

(Project Location) (your firm's name)


HIGHLANDVIEW CEMETERY CHAPEL

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210)

Thermal Laminate Board.

SECTION OUTLET, PULL, AND JUNCTION BOXES

Technical Service. INSTALLATION INSTRUCTIONS FOR TARAFLEX SPORT PRODUCTS over Gypsum base Products. This document refers to the following products:

MAKE ROOFS LAST LONGER

Margaret Batts Tobin Laboratory

Perimeter Relief and Control Joints in Fire-Rated Gypsum Board

Crawl Space Moisture Control

Feature Zone IECC 2009 IECC

ESR-2072 Reissued September 1, 2013 This report is subject to renewal September 1, 2015.

RAUPANEL DRY SYSTEM HIGH PERFORMANCE PANEL SYSTEM

MID-RISE DESIGN & CONSTRUCTION

6110 Horizontal Sliding Windows

2.18 INTERIOR & EXTERIOR FINISHES VAPOR & AIR BARRIERS


LOOSE FILL ASBESTOS INSULATION

SECTION RESILIENT SHEET FLOORING

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: THERMAL INSULATION REPORT HOLDER: SES FOAM

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE. Annex A - BILL OF QUANTITIES 1/9

INSTALLATION INSTRUCTIONS FOR ELECTRICAL CONTRACTORS

STUCCO FAILURES and REMEDIATION Roger G. Morse AIA

Encapsulated, Sealed & Closed Crawlspace Installation Manual

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com

Reflective Insulation Specification & Application Guide for Post Frame and Metal Building Construction

HPW Protocol Reference Manual

Atlantic Builders Saratoga Woods Included Features Classic Series Single Family Homes Included Features - Bridgewater II, Griffin, Ashland, Chelsey

PS 3000 Installation Manual Step-By-Step Procedures C.9. DOOR AND WINDOW OPENINGS C.9.1 PREPARE IN ADVANCE. C.9.2 VBUCK CONSTRUCTION.

Low-cost Construction for High-energy Savings. Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity

Transcription:

Retrofit Installation Guide EQUIPMENT AND ACCESSORIES Required Equipment Same Proportioner, Hoses and Gun as used for Gaco s Open Cell and Closed Cell Foam. Pour Cap for gun. Hard Tubing recommended size: 1/4 interior diameter & 3/8 exterior diameter; approximately a dozen pieces depending on job size, cut at 4 to 6 length. Required Tools for Prep/Cleanup Zip Tool for vinyl siding removal. (i.e. Malco Products SideSwiper II < $10) Borescope to see inside of cavity and ensure it is empty. ($100-$350) Measuring Device to determine stud width, i.e. metal wire. Cat s Paw for removing nails to get sheeting off if you need to remove old insulation. Circular Saw if you need to cut sheeting out to remove old insulation. Suggested Additional Tools InfraRed Thermal Imaging Camera, i.e. FLIR This shows value of the insulation and provides proof that cavities have been filled. Suggestion: Use thermal imaging camera images to prepare a before and after photo package to present to homeowner with project invoice. It is also a valuable tool during installation to help ensure you are completely filling each cavity. The best images are often obtained from the inside it only takes one to two minutes for the heat signature to show through the sheetrock or plaster and lath. Blower Door - arrange for Blower Door availability to document air sealing of the house. Suggestion: Cultivate relationship with energy auditor and/or www.resnet.us has an app on their website. Prior to Bidding Job Do NOT just measure the house. PRE-INSPECTION Become familiar with the types of housing in your area and inspect entire house to ensure you know what all will be required for a successful installation. WARNING: Do not install GacoProFill in walls with Knob & Tube wiring, it will create a fire hazard. Do not install over other products like fiberglass, vermiculite and other insulation materials besides foam.

GacoProFill Retrofit Installation Guide, Page 2 Jobsite Safety and Set Up GENERAL PROCEDURES Upon jobsite arrival, locating the spray rig can sometimes be a challenge. Avoid parking on concrete driveways or other surfaces where drips, leaks or spills would be damaging. Avoid areas where the generator exhaust or noise will cause problems. Safe egress to the spray rig is very important as is the security of the equipment from persons other than the trained spray crew. Ensure jobsite is unoccupied. Homeowners and other persons and pets must vacate the property prior to installation, and should not return for 24 hours after completion. Create a Protected Work Zone. Install warning signs and isolation tape. Use Lock Out / Tag Out program to ensure HVAC equipment cannot be operated during the spray foam process. For added safety, turn off all power. Jobsite ventilation is required during and for a period after the spray foam process. Keep the house under positive pressure (air needs to be coming IN to the house) to keep fumes out. Suggestion: Open windows and use a Blower Door to bring air IN to the home. Personal Protective Equipment (PPE) is essential. Ensure all workers involved in the installation of GacoProFill are assigned the appropriate PPE and have it available when arriving on jobsite. PPE for Installation from INTERIOR of Home - Applicators and Assistants should wear: A NIOSH-approved full face or hood-type supplied air respirator (SAR) as outlined in your company's Respiratory Protection Program MDI-resistant chemical gloves (e.g., nitrile), or fabric gloves coated in nitrile, neoprene, butyl, or PVC Chemically resistant long-sleeve coveralls or chemically resistant full body suit with hood MDI-resistant fitted boots/booties PPE for Installation from EXTERIOR of Home - Applicators and Assistants should wear: A NIOSH-approved full face-piece Air Purifying Respirator (APR) with organic vapor/particulate (P100) cartridges or a supplied air respirator (SAR). Safety goggles (where respirator does not cover the eyes) MDI-resistant chemical gloves (e.g., nitrile), or fabric gloves coated in nitrile, neoprene, butyl, or PVC Chemically resistant long-sleeve coveralls or chemically resistant full body suit with hood MDI-resistant fitted boots/booties WARNING: When drilling through Asbestos siding, additional safety measures need to be adhered to, including specific PPE. Please visit www.spraypolyurethane.org for additional information.

GacoProFill Retrofit Installation Guide, Page 3 Jobsite Prep Exterior Installation: GENERAL PROCEDURES (Continued) Many types of exterior cladding are able to have holes drilled through the outside to allow for installation of foam and then be satisfactorily repaired. Some types of siding such as Vinyl may be removed and replaced. (Do not attempt to remove/replace Aluminum or Steel siding installation will need to be done from the interior.) Regardless of exterior cladding type, contractor must ensure he/she has sufficient knowledge to perform the necessary repairs to meet high expectations of homeowners. Exterior installation is not suitable for Brick. Installation will need to be done from the interior, taking care to not fill the air gap between the substrate and the exterior brick. Hang plastic below the holes you need to fill. This is to prevent getting foam on the siding remaining on the house. Suggestion: Use a 3M M3000 Hand Masker Dispenser that applies the plastic and tape in one step you can run it right down the house and attach to the top lip of the siding. Interior Installation: Move furnishings away from wall to allow easy access and cover them with plastic; remove carpet, or cover with plastic. Use a ZipWall or ZipDoor system to protect inner areas of the home (www.zipwall.com). Ensure path from spray rig to the home s interior is clear of any obstacles. Protect Areas Where Foam Should Not Go Do not allow foam to enter electrical boxes, recessed lights, drop soffits and open penetrations such as hose bibs, gas lines, telephone and cable lines, etc. Electrical Box Prep*: - Remove all cover plates for electrical switches and outlets. - Remove screws holding the switches and outlets and pull the switches and outlets out of the box (leave the wires attached). - Stuff the electrical box full of newspaper so foam cannot enter the box. - Use can foam or tape around the box and sheetrock. *While it is not necessary to shut off the electricity at the circuit breaker in the main electrical panel, please make arrangements with homeowner to do so if you are uncomfortable completing this step.

GacoProFill Retrofit Installation Guide, Page 4 Penetrations GENERAL PROCEDURES (Continued) Drill holes at 4 intervals in each cavity drill with caution to avoid hitting a duct, etc. For an 8 height wall, drill one hole 4 from the floor, and another at the top of the wall. Holes should be a minimum of 1/2 in diameter; there is no maximum size as long as the hole can be repaired. NOTE: Larger holes will be needed if any existing material needs to be removed from the cavity. Suggestion for Easy Patching and Repair of Penetrations: Use a Hole Saw and save the core for patching hole; replace the core and seal the opening. Grace Vycor Self-Adhered Flashings are ideal for sealing holes in wall sheathing systems. Cavities and Substrate Limitations Ensure wall cavity is empty, or remove anything that is inside prior to installation. Locate Fire Blocking many older homes have 10 or 12 ceilings with fire blocking at different heights. - Locate fire blocking within the walls when drilling the first few holes and adjust additional hole locations within each cavity accordingly. - In buildings w/balloon Framing, inspect entire cavity to determine if there are fire breaks or just a continuous empty cavity. The substrate should be clean, dry and warm. While clean, dry, empty cavities give us the best success for a proper fill, warmer substrates give us better yields. The colder the substrate the lower the yields we can expect. Do not spray if surface temperatures are within 5 degrees of the dew point. Substrate moisture levels should be below 18%. Application Always perform a test spray into a trash bag first to check for mix and rise before installation in walls. NOTE: It will splatter if a trash bag is not used. With pour cap and tube installed on gun, place tube into lowest hole in cavity; ensure it is pointed straight down, not tilted to the side. Pull trigger to engage chemical so it drops to bottom of cavity. Approximate spraying time to fill cavity: 1 second per foot Ensure foam extends past lower hole by at least 1 prior to moving to next higher hole; repeat the process in next higher hole within each cavity to completely fill cavity from bottom to top. 8 wall cavity example: It will take approximately 4 seconds to fill from bottom to first hole located 4 up from the bottom; then approximately 4 seconds to fill from the middle to the top hole. Inspect hole to look for proper rise and fill in the cavity. Use thermal imaging camera to help ensure you are completely filling each cavity. The best images are often obtained from the inside it only takes one to two minutes for the heat signature to show through the sheetrock or plaster and lath. Adjust spraying time as needed for a complete fill. Check interior walls frequently for popped or cracked drywall, and make installation adjustments as needed. Suggestion: Fill every other cavity then go back and do the rest this will avoid putting too much pressure on the drywall on both sides of the framing and decrease the chances of a blow out.

GacoProFill Retrofit Installation Guide, Page 5 Final Inspection To help ensure successful installation, check walls with thermal imaging camera. Clean Up/Job Completion Re-check interior walls for popped or cracked drywall, and make repairs as necessary. Replace cores from holes and/or seal holes with Grace Vycor Self-Adhered Flashings. Replace any siding that was removed, or make proper repairs to exterior cladding; touch up paint as necessary; clean up overall jobsite.

GacoProFill Retrofit Installation Guide, Page 6 APPLICATION PROCEDURES Drum Storage Store GacoProFill Poly drums at 50 F to 100 F (10 C to 38 C) when not in use. Drum Prep Prep GacoProFill Poly drums to 60 F to 80 F (16 C to 27 C). In order for the drum to be ready to use, it must be in a temperature range where the proportioner can take it the rest of the way to spray temperature. Example: If your drum temperature is 80 F and you have an E-20 with a delta T of 50 F, your maximum spray temperature can only be 130 F. With this information it is important to know the delta T of your proportioner and drum temperature to achieve the proper spray temperature. For those of you with Recirc capabilities, you can recirculate GacoProFill Poly to raise the drum temperature, but do not recirculate the product over 100 F. Mixing GacoProFill Poly must be mixed on high speed to achieve a milky solution prior to application or recirculation. It must be continuously mixed during application. If GacoProFill Poly is in the line from the previous spray day, it must be recirculated into the drum and mixed before spraying can take place. Flushing When changing from a closed cell product to GacoProFill, pre-mix the GacoProFill Poly drum prior to flushing. Purge the Poly side of the system with water to get the closed cell product out of the system, then come in behind with pre-mixed GacoProFill Poly to flush out the water. Remember to flush the entire Poly system including recirc lines, proportioner and spray hose. Use water again to flush the GacoProFill Poly out of the system before you go back to the closed cell product. Follow steps 1-5 on Tech Tip 028, Eliminate Cross Contamination by Flushing with Water. For a more detailed step by step flushing procedure refer to Tech Tip 045, 12 Proper Flushing Techniques. Tech Tips can be found on gaco.com. Substrate Limitations Substrates should be clean, dry and warm. While clean and dry offers the best success for adhesion, warmer substrates provide better yields. The colder the substrate the lower the yields we can expect. Do not spray if surface temperatures are within 5 degrees of the dew point. Substrate moisture levels should be below 18%. Use Psychrometer for exact measurement of temperature, humidity and dew point. Spray Pressures 1,000 to 1,200 psi for optimal performance. At 70 F (21 C) ambient temperature: Recommended starting pressure setting is 1,000 psi using an AR-4242 (01) mixing chamber. Recommended starting pressure setting is 1,200 psi using an AR-5252 (02) mixing chamber Spray Temperatures 110 F to 135 F (43 C to 57 C). The lower temperature spectrums are used in warmer climates/seasons and the higher temperature spectrums are used in colder climates/seasons. If the foam is reacting too fast, then it is too warm and temperatures need to be dialed down and possibly the pressure reduced if needed. If the foam is reacting too slowly, then you need to increase temperatures and possibly pressures. At 70 F (21 C) ambient temperature: Recommended starting temperature setting for A, B & Hose Heat is 120 F (48 C). Equipment Settings Pre-Heaters - Iso (A): Pre-Heaters - Poly (B): Hose Heat: Recommended Spray Pressure: 110 F to 135 F (43 C - 57 C) 110 F to 135 F (43 C - 57 C) 110 F to 135 F (43 C - 57 C) 1,000 to 1,200 psi (dynamic) Reactivity Time Cream Time: Tack Free Time: Cure Time: 2-3 seconds 6-10 seconds 4 hours