Eastern Wind Integration and Transmission Study

Similar documents
Eastern Wind Integration and

New England Wind Integration Study Executive Summary

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

Best Practices in Conducting Grid Integration Studies

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

NCSL Transmission Policy Institute Denver, CO

Solar Integration into the PJM Grid

2016 Summer Reliability Assessment

High Voltage Direct Current

Pan-Canadian Wind Integration Study (PCWIS)

State of the Ar t. May Utility Wind Integration Group. American Public Power Association. Edison Electric Institute

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

Integrating High Penetrations of Variable Renewable Generation Lori Bird and Debra Lew, NREL NCSL Webinar March 28, 2012

New Grid Controls to Enable Renewable Generation

Las Vegas, NV Modeling of Clean Energy Policies and Electrification in New York and New England

ANEACIÓN DE SISTEMAS DE ENERGÍA FLEXIBLE.

INTERSTATE TRANSMISSION VISION FOR WIND INTEGRATION

2016 Long-Term Reliability Assessment

Mountain West Transmission Group Frequently Asked Questions Updated through September of 2017

Renewable Electricity Futures Study

MAY 1, Variable Generation Integration Costs

2009 Long-Term Reliability Assessment the reliability of the. October 2009

ISO New England Available Transfer Capability. Implementation Document. Version 1.0

2750 Monroe Blvd Audubon, PA

Accommodating High Levels of Distributed Energy Resources

PJM PROMOD Overview. August 1, PJM

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN

SPP at a Glance. Located in Little Rock. Approximately 600 employees

20 MW Flywheel Energy Storage Plant

PJM Interconnection, L.L.C. ( PJM ) submits hereby submits its responses to the United

New England Electricity Outlook

Congestion Assessment and Resource Integration Studies. A Report by the New York Independent System Operator

Outage Coordination Training MISO Training

WWSIS - 3: Western Frequency Response and Transient Stability Study

MISO Energy Storage Study Phase 1 Report

Electricity Grid of the Future. Program Director: Dr. Sonja Glavaski

New England States Committee on Electricity

2017 Summer Reliability Assessment

PJM Renewable Integration Study


Introduction to the PJM Markets

Integrated Grid Planning Symposium

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

California Grid Operations: Current Conditions and Future Needs

Flexibility in Indian Power System

The Renewable Energy Zones Transmission Planning Process. Nathan Lee National Renewable Energy Laboratory 5 June 2017

MISO s Analysis of EPA s Final Clean Power Plan Study Report

IMM Quarterly Report: Fall 2017

Renewable Integration at ERCOT

Draft Whitepaper to Platte River Board of Directors

MTEP18 Futures. Planning Advisory Committee June 14, 2017

Report on the completion of the Link Foundation Fellowship ( )

Deregulation, Locational Marginal Pricing, and Critical Load Levels with Applications

Summary of 2016 MISO State of the Market Report

Methodology PLG-METH-0002-V1

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

NERC Reliability Functional Model Technical Document Version 5

Evolution of Operating Reserve Determination in Wind Power Integration Studies

Generation Capacity Mechanisms and Resource Adequacy Planning

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

2006 Long-Term Reliability Assessment. The Reliability of the Bulk Power Systems In North America

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments

ICA Demand Curve Development:

PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal

Grid Integration of Wind & Solar

The Virtues of A Virtual RTO

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

Interface Pricing Approach Whitepaper May 2015

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

2015 Summer Reliability Assessment

Dispatch Signal & Locational Marginal Pricing (LMP)

Executive summary OECD/IEA Executive Summary

Energy Markets - The Basics

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY

Solar Impact on Grid Operations - An Initial Assessment

Large Scale Wind Power in New Brunswick

Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration

Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois

The Economics of Capacity Payment Mechanisms in Restructured Electricity Markets

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

2017/2018 Winter Reliability Assessment

Future Electricity Markets. Dr. Daniel Matuszak Clean Coal and Carbon Management Office of Fossil Energy U.S. Department of Energy May 24, 2016

Standard BAL-502-RFC-02

Presentation Overview

Terms of Reference AG 2017/01

Maximizing the Market Value of Flexible Hydro Generation

Modeling Transmission Outages in the CRR Network Model

Sustaining & Enhancing Reliability in NY

PJM Capacity Repricing Market Design Initiatives

U.P. Transmission Business Briefing Planning Update. November 29, 2007 Marquette, MI Flora Flygt, Director of Planning

Table A: NERC Regional Entities

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members:

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE

IRP Advisory Group 2017 IRP Kick Off

Regional Cooperation of US States on Electric Transmission Issues

Transcription:

Eastern Wind Integration and Transmission Study NPCC Governmental/Regulatory Affairs Advisory Group February 23rd, 2010 Dave Corbus National Renewable Energy Lab 1

What is Needed to Integrate 20% Wind in the Eastern Interconnect? Evaluate the power system operating impacts and transmission associated with increasing wind energy to 20% and 30% Impacts include operating with the variability and uncertainty of wind Build upon prior wind integration studies and related technical work; Coordinate with current regional power system study work; Produce meaningful, broadly supported results Technical Review Committee

EWITS Study Organization DOE Sponsor Technical Review Committee NREL Project Manager AWS True wind Wind Modeling Project Team Analysis EnerNex/MISO/Ventyx Stakeholders

Technical Review Committee Includes representation from the following organizations New York Independent System Operator (NYISO) Xcel Energy Southern Company PJM Interconnection Southwest Power Pool(SPP) U.S. Department of Energy Midwest ISO (MISO) Michigan Public Service Commission Area Power Pool (MAPP) American Wind Energy Association (AWEA) Federal Energy Regulatory Commission (FERC) observer status North American Electric Reliability Corporation (NERC) CapX 2020 (Great River Energy) Windlogics National Renewable Energy Lab General Electric (GE) Regulatory Assistance Project University College Dublin Organization of MISO States (Wisconsin Public Service Commission)

EWITS Analysis Provides Detailed Information on Wind generation required to produce 20% and 30% of the projected electric energy demand over the U.S. portion of the Eastern Interconnection in 2024 Transmission concepts for delivering energy economically for each scenario Economic sensitivity simulations of the hourly operation of the power system with wind generation, future market structures and transmission overlay The contribution made by wind generation to resource adequacy and planning capacity margin

Why 20% and 30% Wind?

Key Tasks- Eastern Wind Integration & Transmission Study Wind plant modeling, data development, and Siting Develop high quality wind resource data sets for the wind integration study area Develop wind power plant outputs Identify wind sites and develop siting scenarios Transmission study Develop transmission concepts for different wind scenarios Wind integration study Evaluate operating impacts Evaluate resource adequacy Compare scenario costs

Key Tasks Wind Plant Modeling & Siting Develop high quality wind resource data sets for the wind integration study area Mesoscale modeling 3 years of time series data (2004-2006) 10-minute data at 2 km spatial resolution Develop wind power plant outputs Identify wind sites

Wind Plant Modeling Approach: Re-creating the Weather Wind plant siting Mesoscale model grids

Offshore Wind Great resource Well correlated with load and close to load centers More expensive!

Scenario Development and Siting Reference Case and Four Different Scenarios Three 20% and one 30% wind scenarios Scenario 1 Focus on higher wind speed sites in the Midwest with larger transmission component Scenario 3 Focus on local wind near cities with lower capacity onshore wind and offshore wind Up to 4 GW Canadian hydro and wind scheduled All of the four scenarios require a lot of wind and transmission!

20% Wind Requires Some Regions to Supply More Based on Resource Availability Areas that meet 20% wind energy on a regional basis, by scenario Scenario 1: Midwest ISO, MAPP, SPP Scenario 2: Midwest ISO, MAPP, SPP, New England ISO (ISO-NE), New York ISO (NYISO) Scenario 3: MAPP, SPP, PJM, ISO-NE, NYISO Scenario 4: Midwest ISO, MAPP, SPP, PJM, ISO- NE, NYISO

Scenario 1 20% High Capacity Factor, On shore

Scenario 2-20% Hybrid with Offshore

Scenario 3-20% Local, with Aggressive Offshore April 30, 2009

Scenario 4-30% Aggressive On- and Off-Shore

Wind Capacities by Scenario and Regional Entity

The Power of Aggregation and Geographic Diversity

Geographic Diversity 10-Minute Variability for Five Regions

EWITS Methods & Assumptions 2024 wind scenario development Power system models for 2024 Conventional generation expansion Develop conceptual transmission overlays Evaluate operating impacts Evaluate resource adequacy Estimate annualized costs EWITS Technical Review Committee Webinar October 2, 2009

Key Task - Transmission High levels of new transmission are needed across the 4 scenarios Some transmission elements are common to all overlays Reference case, 20% and 30% wind scenarios all require a significant transmission build out, otherwise they are not feasible Transmission reduces variability and provides capacity benefits in its own right, and enhances the reliability contribution of wind generation The conceptual transmission overlays consist of multiple 800kV HVDC and EHV AC lines EWITS Technical Review Committee Webinar October 2, 2009

Key Tasks- Develop Transmission Plan Reference future and 20% wind and 30% wind scenarios Builds on JCSP work SPP EHV Conceptual Transmission Overlay Regional Generation Outlet Study Scenario T 765kV Conceptual Overlay Analyze different transmission alternatives for different wind scenarios 765 AC and HVDC

Scenario 2 Generation Difference: Copper Sheet Minus Constrained Cases

Scenario 2 Interface Contour: Annual Energy Difference Copper Sheet Minus Constrained Case

Transmission Overlay for Scenario 3

Conceptual Transmission Overlays

Key Task - Wind Integration Study Evaluate operating impacts- Four scenarios plus two sensitivity studies Regulation Load Following Unit Commitment Evaluate reliability impacts (ELCC/LOLP) EWITS is first and foremost a wind integration study What are the integration costs and issues for 20 and 30% wind? How is other generation affected?

Hourly Modeling Objective Chronological simulation of operational planning and power system operation using PROMOD hourly model Mimic Day-ahead unit commitment and scheduling based on load and wind generation forecasts Real-time operation with actual wind and load How do we simulate the Eastern Interconnection in 2024? Period-ahead planning (e.g. day-ahead unit commitment) Real-time operations (at minimum of hourly granularity) Operational structures 11 regions

Assumed operational structure for the Eastern Interconnection in 2024 (white circles represent balancing authorities)

Average Hourly Regulation Requirement (MW) Additional Reserve Requirements 7000 by Region and Scenario 6000 5000 4000 3000 2000 Load Only Reference Case Scenario 1 Scenario 2 Scenario 3 Scenario 4 1000 0 MISO ISO-NE NYISO PJM SERC SPP TVA Operating Region

Integration Cost $/MWH of Wind Energy (2009 USD) Wind Integration Costs $6.00 $5.00 $4.00 $3.00 $2.00 $1.00 Reference Scenario 1 Scenario 2 Scenario 3 Scenario 4 $- 2004 2005 2006 Year

Wind Curtailment (%) Wind Curtailment by Scenario 14.00% 12.00% Reference Scenario 1 Scenario 2 Scenario 3 Scenario 4 10.00% 8.00% 6.00% 4.00% 2.00% 0.00% MISO/MAPP SPP PJM ISONE NYISO SERCNI TVASUB Total Footprint Reference 1.87% 1.80% 1.98% 1.25% 1.48% 1.06% 1.93% 1.73% Scenario 1 4.51% 11.57% 3.07% 0.02% 3.63% 0.07% 8.37% 7.02% Scenario 2 2.69% 12.64% 1.73% 0.56% 10.25% 7.84% 4.34% 6.79% Scenario 3 2.41% 2.70% 1.81% 7.67% 9.43% 0.47% 0.32% 3.39% Scenario 4 8.69% 12.46% 8.37% 11.45% 9.56% 6.91% 9.53% 9.77% Region

High Cost Flexibility Supply Curve Study needed to determine shape of Flexibility Supply Curve and Quantify Costs Low Cost Sources of Flexibility

Objective LOLP and ELCC Analysis Determine contribution of wind generation to Eastern Interconnection resource adequacy Assess resource adequacy value of transmission only Issues Transmission overlay could have significant impact on existing LOLE zones Transmission will serve as capacity resources for some zones; Predecessor tasks Requires PROMOD to determine new area import limits GE MARS model developed from PowerBase Resource constraints may necessitate staging

GE MARS Resource Adequacy Analysis Monte-Carlo based chronological reliability simulation Now in use at MISO Objectives Calculate ELCC for wind generation based on comparative LOLE cases Zone-by-zone basis Input data Network, resource, and load data input developed from PowerBase Wind as load modifier

An Energy Resource in an Capacity World Percentage 40 35 32.8 30 25 20 27.7 27.3 25.4 24.1 20.2 19.9 18.8 28.0 27.0 28.3 28.1 26.4 24.2 23.8 22.7 30.5 26.6 20.4 24.8 20.6 29.8 24.6 Overlay Existing 15 16.0 10 5 0 Scenario 1 Scenario 2 Scenario 3 Scenario 4 2004 Profile 2005 Profile 2006 Profile LOLE/ELCC results for high penetration scenarios, with and without transmission overlays

Annualized Scenario Cost (2009 USD M$) Total Annualized Scenario Costs 200,000 180,000 160,000 140,000 120,000 100,000 80,000 60,000 40,000 Wind Capital Cost New Generation Capital Cost Transmission Cost Integration Cost Wind Operational Cost Production cost 20,000 - Reference Scenario 1 Scenario 2 Scenario 3 Scenario 4

Sensitivity Studies Carbon Price sensitivity using PROMOD Run EGEAS generation expansion model to determine carbon price sensitivities Re-run PROMOD for scenario 2

Carbon Sensitivity Case Change in Energy Generation by Fuel Type

The results of this study pose some interesting policy and technology development questions Could the levels of transmission, including the Reference Case, be permitted and built and what is a realistic time frame? Could the level of offshore wind energy infrastructure be ramped up fast enough to meet the aggressive offshore wind assumption in scenario 3 Would a different renewable profile or transmission overlay arise from a bottom-up planning process? How can states and the federal government best work together on regional transmission expansion and the massive development of onshore and offshore wind infrastructure? What is the best way for regional entities to collaborate to make sure wind is integrated into the bulk electrical grid optimally and reliably? What is the difference between applying a carbon price versus mandating and giving incentives for additional wind and renewables

EWITS Not an End All Catch All but a Link in the Chain The scenarios developed do not constitute a plan but an initial perspective on a top-down, high-level view of four different 2024 futures. The study assumptions were developed in close coordination with the TRC Changes in the assumptions, such as the cost of various fuels, the impact of regulation and policy would have a major influence A complete evaluation of any of the scenarios would require additional technical analysis including An AC analysis that includes power flows that look at voltage and reactive compensation issues, dynamic and transient stability, and HVDC terminal control.

EWITS Conclusions 20 and 30% wind penetrations are technically feasible with significant expansion of the transmission infrastructure. New transmission will be required for all the future wind scenarios in the Eastern Interconnection, Without transmission enhancements, substantial curtailment of wind generation will occur Interconnection-wide costs for integrating large amounts of wind generation are manageable with large regional operating pools, where benefits of load and wind diversity can be exploited and large numbers of supply resources are efficiently committed and dispatched.

EWITS Conclusions Transmission helps reduce the impacts of the variability of the wind and. Reduces wind integration costs Increases reliability of the electrical grid Helps make more efficient use of the available generation resources Costs for aggressive expansions of the existing grid are significant, but they make up a relatively small piece of the total annualized costs in any of the scenarios studied Wind generation displaces carbon-based fuels, directly reducing carbon dioxide (CO 2 ) emissions

and the conclusion is There are no fundamental technical barriers to the integration of 20% and 30% wind energy into the electrical system, but There needs to be a continuing evolution of transmission planning and system operation policy and market development for this to be achieved

Future Work Further analysis of regional results Demand response and smart grid load sensitivities Fuel sensitivity, unit commitment/optimization Plug in electric vehicle charging Sequencing of transmission Include more detailed representation from Canada Curtailment under transmission constrained scenarios and storage analysis

EWITS Schedule & Contacts http://www.nrel.gov/ewits Development of Phase II of EWITS in first quarter 2010 Roll out January 20 th, Washington DC. Contact: Dave Corbus at David.Corbus@nrel.gov