TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTATION CONTROL South Terminal C Phase 1 (WS110) Item P-156

Similar documents
Town of Fortville Utility Street Standards

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

SECTION 903 EROSION CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

SECTION EROSION AND SEDIMENTATION CONTROLS

Water Pollution Control for Work in Sensitive Areas

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

Erosion & Sedimentation Control Policy

PART 1 GENERAL REQUIREMENTS

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

CITY OF FARGO SPECIFICATIONS EROSION AND SEDIMENT CONTROL

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)

DOCUMENT SPECIAL PROVISIONS

The Good, The Bad, and The Ugly

Storm Drain Inlet Protection

SECTION UNCLASSIFIED EXCAVATION AND GRADING

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

STANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018

Best Management Practice (BMP) Guidance Manual

EROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: (Rev ) SP1 G180

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Block or Log forms of PAM and PAM blends are manufactured for specific use in drainage waterways to remove suspended particulates from runoff.

SITE DESIGN ENGINEER'S STATEMENT:

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

General Permit No.: OHR Page 53 of 146

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

STANDARD TECHNICAL SPECIFICATIONS

Planning & Building Department. Requirements for Erosion and Sediment Control

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.

PERMEABLE INTERLOCKING PAVERS

AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION

SECTION TRENCHING & BACKFILLING

DIVISION VII SOIL EROSION AND SEDIMENTATION CONTROL

Section 1I-3 - Bioswales

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION EROSION CONTROL PART 1 GENERAL. A. Work covered by this Section includes the control of erosion, siltation and sedimentation.

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

JEFFERSON COUNTY STORM WATER MANAGEMENT

BMP 6.4.4: Infiltration Trench

11 Ways to Avoid Storm Water Fines. No Exceptions!

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

Table of Contents for Guide Specifications

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Builder s enviro guide

SACHSE EROSION CONTROL GUIDELINES

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative

Erosion and Sediment Control Plan for a Timber Harvesting Operation

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION

Module 4 Regulatory requirements for Land Disturbing Activities

CITY OF BUENA PARK EDISON ROW PARKING LOT IMPROVEMENT PROJECT FY PROJECT NO. GP-1775

Curlex II EROSION CONTROL BLANKET SPECIFICATION

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

C. Foundation stabilization for pipe and utility structures.

APPENDIX C DURING CONSTRUCTION BMP TABLES

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

INSPECTION, MAINTENANCE AND HOUSEKEEPING PLAN

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

ITEM 506 Temporary Erosion Control

APPENDIX G Fire BMPs

Tree Protection & Preservation

SECTION 2 DESIGN CRITERIA

DIVISION 31 -SITE CLEARING

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

Diversion Dikes. Fe=0.95

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

Recyclex TRM TURF REINFORCEMENT MAT SPECIFICATION

Richland County Department of Public Works Engineering (Land Development) Division

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018)

Concrete Waste Management

DRAFT TECHNICAL SPECIFICATIONS FOR

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

SPECIFICATION : BORING AND JACKING

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

Construction Inspection Checklists

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5

E. STORMWATER MANAGEMENT

4.8. Subsurface Infiltration

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

KDOT TEMPORARY EROSION - CONTROL MANUAL

Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals

Transcription:

ITEM P-156 EROSION, AND SILTATION CONTROL DESCRIPTION 156-1.1 This item shall consist of temporary control measures as shown on the plans or as ordered by the Engineer OAR during the life of a contract to control water pollution, soil erosion, and siltation through the use of silt fences, berms, dikes, dams, sediment basins, fiber mats, gravel, mulches, grasses, slope drains, and other erosion control devices or methods. The temporary erosion control measures contained herein shall be coordinated with the permanent erosion control measures specified as part of this contract to the extent practical to assure economical, effective, and continuous erosion control throughout the construction period. Temporary control may include work outside the construction limits such as borrow pit operations, equipment and material storage sites, waste areas, and temporary plant sites. Temporary control measures shall be design, installed and maintained to minimize the creation of wildlife attractants that have the potential to attract hazardous wildlife on or near public-use airports. Contractor shall prepare all required documentation, pay all fees and perform all services and work necessary to obtain all permits from appropriate local, state, and federal regulatory agencies for Contractor s staging, stockpile, blending and batch plant areas and operations. In compliance with the National Pollutant Discharge Elimination System (NPDES) permit issued or approved by U.S. Environmental Protection Agency (EPA) pursuant to 40CFR Part 122.6, the contractor shall prepare a project specific erosion control as part of a Stormwater Pollution Prevention Plan. Contractor s Pollution Control Plan. The Contractor s pollution control plan shall address all measures to dispose of, control, or prevent discharge of solid, hazardous and sanitary wastes to the waters of the U.S. The plan shall include procedures to control offsite tracking of soil by vehicles and construction equipment; and procedures for cleanup and reporting of non-stormwater discharges (such as accidental spills). The Contractor shall adhere to the requirements set forth by the Florida Department of Environmental Protection (FDEP) document No. 62-621.300(4)(a), Florida Statute Section 403.0885, and Florida Administrative Code (F.A.C.) 62-62-4.050(4)(d). The pollution plan may be part of the Environmental Resource Permit review and approval process required by South Florida Water Management District (SFWMD). Contractor shall adhere to all requirements set forth in the GOAA Master Water Use Permit No. 48-02319-W and must obtain a letter modification prior to commencement of any dewatering activities. 156-1.2 Coordination and Corrective Requirements. The installation of temporary erosion control features shall be coordinate with the construction of any permanent erosion P-156-1

control features to the extent necessary to assure economical, effective, and continuous control of erosion and water pollution throughout the life of the contract. In cases of repeated failures on the part of the Contractor to control erosion and pollution, right is reserved by the OAR to employ outside assistance to provide such corrective measures and actions deemed appropriate by the OAR to correct the condition(s) and/or to direct the Contractor to perform other work as required by the circumstances. Such measures which may be ordered by the OAR may consist of reconstruction of berms, dikes, dams, drains, sediment basins, ditches, canals, or the use of fiber mats, woven plastic filter cloths, gravel, mulches, quick growing grasses, sod, bituminous spray, and other erosion control devices or methods deemed appropriate under the circumstance(s). Such incurred costs, including related Engineering costs, will be charged to the Contractor and appropriate deductions made from the Contractor s progress payments. 156-1.3 Control of Water Pollution. The Contractor shall take sufficient precautions to prevent pollution of streams, canals, lakes, reservoirs, and other water bodies with fuels, oils, bitumens, calcium chloride, or other harmful materials. Contractor shall also conduct and schedule operations in such a manner as to avoid or otherwise minimize pollution or siltation of such streams, lakes, and other water bodies, and to avoid interference with natural movements of migratory fish. No residue from dust collectors or washers shall be dumped into any water body whatsoever. Contractor shall not cause runoff from water controls to exceed 29 Nephelometric Turbidity Units (NTU) above background values. Contractor shall take all necessary steps to meet this requirement. Except as necessary for construction, excavated materials shall not be deposited in close proximity to waterways and/or water bodies to be washed away by high water and/or runoff. The Contractor shall not disturb lands or waters outside of the limits of construction as staked, except as may be found necessary and authorized by OAR. The location of and method of operation borrow pits, material pits, staging and plant sites and disposal areas for wasted materials from the project (other than commercial operated sources) shall meet the approval of the OAR as being such that erosion during and after completion of the work will not result in the probability of detrimental siltation and/or water pollution. MATERIALS 156-2.1 Grass. Grass that will not compete with the grasses sown later for permanent cover per Item T-901shall be a quick-growing species (such as ryegrass, Italian ryegrass, or cereal grasses) suitable to the area providing a temporary cover. Selected grass species shall not create a wildlife attractant. P-156-2

156-2.2 Mulches. Mulches may be hay, straw, fiber mats, netting, bark, wood chips, or other suitable material reasonably clean and free of noxious weeds and deleterious materials per ItemT-908. Mulches shall not create a wildlife attractant. 156-2.3 Fertilizer. Fertilizer shall be a standard commercial grade and shall conform to all Federal and state regulations and to the standards of the Association of Official Agricultural Chemists. 156-2.4 Slope drains. Slope drains may be constructed of pipe, fiber mats, rubble, Portland cement concrete, bituminous concrete, or other materials that will adequately control erosion. 156-2.5 Silt fence. The silt fence shall consist of polymeric filaments which are formed into a stable network such that filaments retain their relative positions. Synthetic filter fabric shall contain ultraviolet ray inhibitors and stabilizers to provide a minimum of six months of expected usable construction life. Silt fence shall meet the requirements of ASTM D6461. 156-2.6 Other. All other materials shall meet commercial grade standards and shall be approved by the Engineer OAR before being incorporated into the project. Baled Hay or Straw. Baled hay or straw shall meet the requirements of FDOT Standard Specifications Section 104-6.4.9. 156-2.7 Sand Bags. Sand bagging shall consist of furnishing and placing sand bags in configurations and/or piles so as to effectively control erosion and siltation. Turbidity Barriers. Turbidity barriers shall meet the requirements of FDOT Standard Specifications Section 104-6.4.11. 156-2.8 Watering and Dust Control. Watering of the site shall be as required to control blowing dust on open excavations, including subgrade and lime rock surfaces. The Contractor shall apply supplemental water to the areas as directed by the OAR to mitigate blowing dust and debris. This requirement shall be in addition to water required for compaction purposes. The Contractor shall obtain approval from the OAR and make all arrangements to obtain water from suitable sources on the site. Contractor shall also pay all costs for establishing and removing all apparatus required for watering operations. Silt Fence. Silt fence shall meet the requirements of FDOT Standard Specifications Section 104-6.4.10. 156-2.9 Sock Pipe/Horizontal Wells. Sock Pipe/Horizontal Wells shall include the installation of a pumping system or other approved methods of containing perforated plastic pipes, wrapped twice in filter fabric, in a horizontal fashion along the bottom of the excavation pit to dewater as necessary. The Sock Pipe/Horizontal Well shall be used to remove excess surface water if necessary. The excess surface water shall be filtered and discharged into the existing catch basins provided no visible sediment is discharged. If, in the opinion of the OAR, an excess of sediment is being discharged into the existing catch basin, pumping shall be halted until additional filtering methods can be exercised. Pumping of the water into existing stormwater treatment ponds will not be allowed without prior approval of the OAR. P-156-3

156-2.10 Catch Basin Filter Fabric. This item consists of placing approved filter fabric material underneath the grate or covering of existing catch basins, inlets, and manholes, as indicated within the plans. Filter fabric shall be placed in two separate layers, each running perpendicular to each other. The filter fabric layers shall be secured to the bottom of the grate or covering and shall extend at least 12 inches beyond the edge when the grate is placed in its sealed position. The fabric shall be neatly folded over and secured to each other with suitable fasteners. CONSTRUCTION REQUIREMENTS 156-3.1 General. In the event of conflict between these requirements and pollution control laws, rules, or regulations of other Federal, state, or local agencies, the more restrictive laws, rules, or regulations shall apply. The Engineer OAR shall be responsible for assuring compliance to the extent that construction practices, construction operations, and construction work are involved. Acceptance will be on the basis of visual inspection by the OAR. 156-3.2 Schedule. Prior to the start of construction, the Contractor shall submit schedules for accomplishment of temporary and permanent erosion control work for clearing and grubbing; grading; construction; paving; and structures at watercourses. The Contractor shall also submit a proposed method of erosion and dust control on haul roads and borrow pits and a plan for disposal of waste materials. Work shall not be started until the erosion control schedules and methods of operation for the applicable construction have been accepted by the Engineer OAR. The Contractor shall schedule operations such that the area of unprotected erodible earth exposed at any one time is not larger than that of the minimum area necessary for efficient construction operations and the duration of the exposed, uncompleted construction to the elements shall be as short as practicable. The erosion control plan detailed in the plans is provided as a minimum requirement. Contractor is solely responsible for preventing turbidity and for conforming to SFWMD permits. Contractor shall submit his erosion and turbidity control plan to the OAR at the Preconstruction Conference. The Plan shall include a maintenance schedule for rehabilitation of the items contained within the erosion control plan. The submitted plan shall be reviewed by the OAR and the Contractor shall incorporate comments received from the OAR. 156-3.3 Construction details. The Contractor will be required to incorporate all permanent erosion control features into the project at the earliest practicable time as outlined in the accepted schedule. Except where future construction operations will damage slopes, the Contractor shall perform the permanent seeding and mulching and other specified slope protection work in stages, as soon as substantial areas of exposed slopes can be made available. Temporary erosion and pollution control measures will be used to correct conditions that develop during construction that were not foreseen during the design stage; that are needed prior to installation of permanent control features; or that are needed temporarily to control erosion that develops during normal construction practices, but are not associated with permanent control features on the project. P-156-4

Where erosion may be a problem, clearing and grubbing operations should be scheduled and performed so that grading operations and permanent erosion control features can follow immediately if project conditions permit; otherwise, temporary erosion control measures may be required. The Engineer OAR shall limit the area of clearing and grubbing, excavation, borrow, and embankment operations in progress, commensurate with the Contractor s capability and progress in keeping the finish grading, mulching, seeding, and other such permanent control measures current with the accepted schedule. If seasonal limitations make such coordination unrealistic, temporary erosion control measures shall be taken immediately to the extent feasible and justified as directed by the Engineer OAR. The Contractor shall provide immediate permanent or temporary pollution control measures to minimize contamination of adjacent streams or other watercourses, lakes, ponds, or other areas of water impoundment as directed by the Engineer OAR. If temporary erosion and pollution control measures are required due to the Contractor s negligence, carelessness, or failure to install permanent controls as a part of the work as scheduled or directed by the Engineer OAR, the work shall be performed by the Contractor and the cost shall be incidental to this item. The Engineer OAR may increase or decrease the area of erodible earth material that can be exposed at any time based on an analysis of project conditions. The erosion control features installed by the Contractor shall be acceptably maintained by the Contractor during the construction period. Whenever construction equipment must cross watercourses at frequent intervals, temporary structures should be provided. Pollutants such as fuels, lubricants, bitumen, raw sewage, wash water from concrete mixing operations, and other harmful materials shall not be discharged into any waterways, impoundments or into natural or manmade channels. Typical methods of controlling dust and other air pollutants may include exposing the minimum of erodible earth, applying temporary mulch with or without seeding, using water sprinkler trucks, using covered haul trucks, using dust palliatives or pentration asphalt on haul roads, and/or using plastic sheet coverings. 156-3.3.1 Details for Temporary Erosion Control Features. Temporary erosion control features shall consist of, but not limited to: sand bagging, slope draining, sediment basins, sediment checks, artificial coverings and berms per Florida Department of Transportation standards. The OAR may direct use of temporary erosion control features or methods other than those included in the original contract. A. Slope Drains. Slope drains shall consist of constructing slope drains utilizing pipe, fiber mats, rubble, cement concrete, asphaltic concrete sheeting or other acceptable materials as may be approved by the OAR. B. Sediment Basins. Sediment basins shall consist of constructing basins accordance with the details shown on the drawings or as may be approved by the OAR to adequately perform the intended function. Sediment basins shall be cleaned out as directed by the OAR. P-156-5

C. Sediment Checks, Hay Bales, and Silt Fences. Sediment checks shall consist of constructing checks, dams, bales, and/or silt fences as may be approved by the OAR. Prior to the beginning of construction, the area immediately downstream of construction shall be cross-section surveyed to determine existing conditions. Once construction has been completed and just prior to project acceptance, the area shall be cross-section surveyed again. Any silt and washed materials deposited in these areas shall be removed. The upstream side of each installation shall be checked periodically throughout construction for siltation and deposits. Unless otherwise directed by the OAR, any sediment or deposits in excess of six (6) inches shall be removed. Payment for removal of accumulation shall be included in the lump sum payment for this item. The checks shall be maintained by the Contractor for the period of the contract. Just prior to the acceptance of the project, the checks shall be removed by the Contractor unless requested by the OAR that they are to be allowed to remain. D. Artificial Coverings. Artificial Coverings shall consist of furnishing and applying fiber mats, netting, plastic sheeting or other approved covering to the earth surfaces. E. Berms. Berms shall consist of the construction of temporary earth berms to divert the flow of water from an erodible surface. F. Fertilizer. Fertilizer shall be a standard commercial grade material and shall conform to all Federal and State regulations in addition to the standards of the Association of Official Agricultural Chemists. 156-3.4 Installation, maintenance and removal of silt fences. Silt fences shall extend a minimum of 16 inches (41 cm) and a maximum of 34 inches (86 cm) above the ground surface. Posts shall be set no more than 10 feet (3 m) on center. Filter fabric shall be cut from a continuous roll to the length required minimizing joints where possible. When joints are necessary, the fabric shall be spliced at a support post with a minimum 12-inch (300-mm) overlap and securely sealed. A trench shall be excavated approximately 4 inches (100 mm) deep by 4 inches (100 mm) wide on the upslope side of the silt fence. The trench shall be backfilled and the soil compacted over the silt fence fabric. The Contractor shall remove and dispose of silt that accumulates during construction and prior to establishment of permanent erosion control. The fence shall be maintained in good working condition until permanent erosion control is established. Silt fence shall be removed upon approval of the Engineer OAR. 156-3.5 Local Laws, Rules, and Regulations. In the event of differences between these requirements and pollution control laws, rules or regulations of local agencies, the more restrictive laws, rules, and/or regulations shall apply. P-156-6

A. The Contractor shall file a Notice of Intent (NOI) for coverage under the State of Florida Generic Permit for Stormwater Discharge from Large and Small Construction Activities issued under the provisions of the National Pollutant Discharge Elimination System (NPDES). Guidance for and requirements of the NOI, Generic Permit and NPDES are available through the Florida Department of Environmental Regulation website at www.dep.state.fl.us. B. The Contractor shall furnish, as submittals to the OAR and Owner, hardcopy and digital documentation for the NOI, the Contractor s Stormwater Pollution Prevention Plan to be implemented for this project, and the Notice of Termination (NOT) filed upon completion of the project. C. A Construction Stormwater Pollution Prevention Plan Template is in the Florida Stormwater Erosion and Sedimentation Control Inspector s Manual, dated July 2008, or more current edition, available through the Florida Department of Environmental Protection regulation website at www.dep.state.fl.us. 156-3.6 Maintenance of Erosion Control Features A. Routine Maintenance. The Contractor, at his/her expense, shall provide routine maintenance of permanent and temporary erosion control features until the project is completed and accepted. If such erosion control features must be reconstructed due to the Contractor s negligence or carelessness or, in the case of temporary erosion control features, failure by the Contractor to install permanent erosion control features as scheduled, such replacement (labor, tools, equipment, materials, fines, etc.) shall be at the Contractor s expense. Routine Maintenance to control dust and other air pollutants shall include, in addition to other methods mentioned herein, using water sprinkler trucks and covered haul trucks. B. Mowing. The OAR may direct mowing of areas of permanent or temporary grass constructed on the project. The Contractor shall mow these designated areas within seven (7) days of receiving such order. Mowing of slopes which are steeper than four horizontal to one vertical will not be required. C. Suspension of Contractor Operations. In the event that is necessary that the construction operations be suspended for any appreciable length of time, the Contractor shall shape the work in such a manner as to permit runoff of stormwater and shall construct earth berms along the top edges of the embankments to intercept runoff water. Temporary slope drains shall be provided P-156-7

to convey runoff from cuts and embankments which are located in the vicinity of rivers, streams, canals, lakes, ditches, improved water bodies, and/or water bodies. The slope drains shall be located at the intervals of approximately five hundred feet (500-FT) and shall be stabilized by paving or covering with water proof materials. Should such preventative measures fail, the Contractor shall immediately take other action necessary to effectively prevent erosion and siltation. The OAR may direct the Contractor to perform, during such suspensions of time, any other erosion control work deemed necessary. The Contractor shall monitor the project and maintain all erosion control features during any suspension of contract time or work. 156-3.7 Proposed Plan of Operation. At the Pre-Construction Conference, the Contractor shall be prepared to present the proposed plans and schedules for the project in accordance with the requirements of this section. The schedule shall be in written form and approved by the OAR prior to the processing of the first partial pay request. This requirement shall not be waived. This schedule shall specifically indicate the sequence of operations and construction of permanent erosion control features and the proposed uses of temporary erosion control features. It shall also include proposed methods to prevent pollution of the streams, lakes, ditches, canals, tidal waters, reservoirs, and other impoundments as the result of construction operations. The Contractor shall also outline his proposed methods of controlling erosion and preventing pollution on haul roads/routes and in borrow pits, material pits, staging and plant sites, and areas used for disposal of waste materials from the project. No work shall be started until the aforementioned plans and schedules have been accepted by the OAR. The Contractor will be responsible for the accomplishment of the work in accordance with the accepted plans and schedules. The OAR may approve changes made necessary by unforeseen circumstances or conditions which are beyond the control of the Contractor. 156-3.8 Open Surface Area. The OAR shall limit the surface areas of unprotected erodible earth exposed by excavation operations and shall direct the Contractor to provide immediate permanent or temporary erosion/pollution control measures to prevent contamination of any river, stream, lake, tidal water, reservoir, canal or other impoundment or to prevent detrimental effects on property outside of the project limits and damage to the project. The limitation of area in which operations may be under way shall be commensurate with the Contractor s capability and progress in maintaining erosion control measures current in accordance with the approved schedule. 156-3.9 Coordination with Permanent Construction. Any permanent erosion control features shall be incorporated into the project at the earliest practical time. Except where future construction operations will damage slopes, the Contractor shall perform permanent seeding and mulching and other specific slope protection work in stages, as soon as substantial areas of exposed slopes can be made available. Use of temporary erosion control features will be authorized to correct conditions that develop during P-156-8

construction which were not foreseen at the time of design to control erosion prior to the time it is practical to construct permanent control features or to provide immediate temporary control of erosion that develops during the course of normal construction operations but is not associated with permanent erosion control features of the project. Temporary erosion control features may be authorized for use in controlling erosion in areas where stage construction or other conditions not under the control of the Contractor preclude completion of a section of airfield in a continuous manner and in areas where construction operations which must be performed subsequently will cause damage to permanent erosion control features. 156-3.10 Dewatering / Ground Water Control. The Contractor is completely responsible for the site conditions including but not limited to dewater the project site for groundwater and stormwater runoff conditions. A dewatering plan shall be submitted by the contractor to the OAR for review prior to the start of construction. The Contractor shall file for any dewatering permits required, shall pay for all costs associated with dewatering and dewatering permits, and shall implement dewatering in compliance with local water management district, the Airport s SWPPP plan, and any FDEP and/or NPDES requirements simultaneously. Contractor shall adhere to all requirements set forth in the GOAA Master Water Use Permit No. 48-02319-W and must obtain a letter modification prior to commencement of any dewatering activities. The type of methods of site dewatering will be by the Contractor (means and methods), and shall be included in the Contractor s bid. If no specific pay item for dewatering is provided within the bid documentation (plans and specifications), the Contractor shall include enough money in one or more other pay items for dewatering. Dewatering shall be deployed for the entire duration of the project. No additional compensation will be made to the Contractor for dewatering the project. The Contractor s attention is directed to the geotechnical engineering report, the boring logs, the contract documents, and/or the plans for water table information. If no water table information is depicted within the contract documents, it is the Contractor s responsibility to request information during bidding. The Contractor should assume that dewatering will be necessary at all times. The requirements of this section are in addition to the General Provisions and Special Provisions requirements. METHOD OF MEASUREMENT 156-4.1 All aspects of Temporary erosion and pollution control work and dewatering required will be performed as scheduled or directed by the Engineer OAR.. Completed and accepted work will be measured as follows: a. Temporary seeding and mulching will be measured by the square yard (square meter). b. Temporary slope drains will be measured by the linear foot (meter). c. Temporary benches, dikes, dams, and sediment basins will be measured by the cubic yard (cubic meter) of excavation performed, including necessary cleaning of sediment basins, and the cubic yard (cubic meter) of embankment placed as directed by the Engineer. d. All fertilizing will be measured by the ton (kg). P-156-9

e. Installation and removal of silt fence will be measured by the [linear foot (meter)] [Lump sum]. 156-4.1 Temporary erosion and pollution control work required which is not attributed to the contractors negligence, carelessness, or failure to install permanent controls which is performed as scheduled or ordered by the OAR or as required to comply with SFWMD permits shall be measured as a lump sum item. Individual items of work shall not be measured separately but shall be considered subsidiary to the lump sum bid item Erosion and Turbidity Control. 156-4.2 Control work performed for protection of construction areas outside the construction limits, such as borrow and waste areas, haul roads, equipment and material storage sites, and temporary plant sites, will not be measured and paid for directly but shall be considered as a subsidiary obligation of the Contractor. BASIS OF PAYMENT 156-5.1 Accepted quantities of temporary water pollution, soil erosion, and siltation control work ordered by the Engineer and measured as provided in paragraph 156-4.1 will be paid for under: Item P-156-5.1a Item P-156-5.1b Item P-156-5.1c Item P-156-5.1d Temporary seeding and mulching - per square yard (square meter) Temporary slope drains - per linear foot (meter) Temporary benches, dikes, dams and sediment basins - per cubic yard (cubic meter) Fertilizing - per ton (kg) Item P-156-5.1e Installation and removal of silt fence [ per linear feet (meter) ] [ lump sum ] Where other directed work falls within the specifications for a work item that has a contract price, the units of work shall be measured and paid for at the contract unit price bid for the various items. Temporary control features not covered by contract items that are ordered by the Engineer will be paid for in accordance with Section 90-05 Payment for Extra work. 156-5.1 Accepted quantities of temporary water pollution, soil erosion, and siltation control work shall be paid for at the contract lump sum price bid for Erosion and Turbidity Control. Payment will be made under: Item P-156-5.1 Erosion and Turbidity Control per lump sum ASTM D6461 AC 150/5200-33 MATERIAL REQUIREMENTS Standard Specification for Silt Fence Materials Hazardous Wildlife Attractants END OF ITEM P-156 P-156-10