Reclamation Guidelines

Similar documents
How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.

Cold In-Place Recycling

MNDOT PAVEMENT DESIGN MANUAL

Puerto Rico. Pavement Preservation Conference and Technology Implementation. US. Department of Transportation Federal Highway Administration

Full Depth Reclamation

Airport Pavement Rehabilitation 2015 Minnesota Airports Conference

COLD IN-PLACE RECYCLING (CIR) Starting with what is there i.e. in situ materials

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

BASE CONSTRUCTION MATERIALS A Aggregate

What is it? What is Granular Base Stabilization ti (GBS)? Emulsion Full Depth Reclamation Process

MNDOT PAVEMENT DESIGN MANUAL

Renae Kuehl, PE, SRF Consulting Group Dan Wegman, PE, Braun Intertec Corporation November 2, 2017

Project Selection for In-Place Recycling and CRAB. Types of Cold Recycling

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction

Full-Depth Reclamation with Cement

Pavement Maintenance Best Practices. Thomas J. Wood

FULL DEPTH RECLAMATION FOR CITIES AND COUNTIES. OTEC - October 27, 2015

COLD-IN-PLACE RECYCLING

NOTICE TO BIDDERS ADDENDUM NO. 1

Session TH83. Using In-Place Recycling Technologies to address the needs of the Owner Agencies FHWA and ARRA Advances 2014

Recommended Mix Design Guidelines For Cold Recycling Using Foamed (Expanded) Asphalt Recycling Agent CR202

NJDOT STATE REPORT NORTHEAST PAVEMENT PRESERVATION PARTNERSHIP ANNUAL MEETING APRIL 29 MAY 1, 2015 NEWARK, DELAWARE

MnPavement Rehabilitation Best Practices LRRB Inv 808

MIDLAND COUNTY ROAD COMMISSION

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING

ADOT s Use of RAP in Asphaltic Concrete

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

Pavement Design. TTP Orientation Seminar 2017

Nova Scotia 2009 Pavement Preservation. Jim Chisholm Highway Construction Services

Rehabilitation Recommendations for FM 97 in Gonzales County

Cold Foam In-Place Recycling (CIR)

550 Surface Treatments

January 2008 No. 700

Full Depth Pavement Reclamation

The Cardiac Arrest of Hot Mix Asphalt Pavements

Recycling and Reclamation of Airfield Pavements

1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.

Reclaimed Asphalt Pavement

Combining Preservation Treatments

Prepaving Conferences

Performance of Thin Bituminous Treatments for Low-Volume Roads. Greg Johnson Minnesota Department of Transportation June 25, 2003

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

4-07 Asphalt Treated Permeable Base (ATPB)

SHRP2 R21 Composite Pavement Systems Project Overview

PAVEMENT MANAGEMENT REPORT 2011

Pavement Preservation with Thin Lift Concrete Overlays. Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center

The Cardiac Arrest of Hot Mix Asphalt Pavements. Timothy R. Murphy, P.E., M. ASCE President

Asphalt Guidelines. Courtney Rousseau, P.E. Lloyd Consulting Group, LLC

SECTION AGGREGATES

INTELLIGENT PAVING SPEC & PROJECTS

asphalt (PWMA) processes in accordance with these Specifications. PWMA processes include organic 9

An Overview of Low Cost Pavement Alternatives in Canada

Cement Stabilized Aggregate Base

Chip Sealing The Nuts and Bolts. Thomas J. Wood Research Project Supervisor MN/DOT

Materials for Civil and Construction Engineers

SOM August 2009 Alaska

DESIGN OF BITUMINOUS MIXTURES

Re: The Responsible Use of Recycled Materials in Asphalt Mixtures Critical Look

Intelligent Compaction and Pave-IR in Minnesota NCAUPG Technical Conference February 16, 2012 Greg Johnson Mn/DOT Asst. Bituminous Engr.

Student Services & Classroom Addition

Alligator Cracking. Light. Medium. High

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SUPERPAVE HMA MIXTURES. C&T:CJB 1 of 5 C&T:APPR:SJP:DBP: FHWA:APPR:

Binder with a proven track record worldwide. Foamed bitumen

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

ITEM 340 DENSE-GRADED HOT-MIX ASPHALT (METHOD)

ROAD PAVEMENTS GENERAL

5/6/2010. Sustainable Pavement Management practices. Perpetual Pavement

Plantmix Asphalt Industry of Kentucky Winter Meeting February 10, 2011

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

2014 APC/ Dist. 9-0 BITUMINOUS PAVING

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LATEX MODIFIED EMULSION TREATMENT (MICRO-SURFACING)

Ania M. Anthony, M.Sc., P. Eng. Senior Surfacing Engineer Saskatchewan Ministry of Highways and Infrastructure

SACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG):

FAA s Mixture Specifications

SECTION FLEXIBLE PAVING

2016 Local Roads Workshop Selecting the Right Mix for Your Project MICHIGAN RIDES ON US

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

A Case Study of Work done by a HOT IN-PLACE RECYCLING (HIR) Machines

Asphalt Institute. to Univ. of KY A.S.C.E. Student Chapter 10/5/16. Mark Buncher, Ph.D., P.E. Director of Engineering

Using Pavement Management Data to Determine Asphalt Pavement Performance Cycles

610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT

Section 505. CHIP SEALS

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL

Review of Cold In-Place Recycling: Environmental, Economical, and Performance Analysis

Asphalt Materials: Basics of RAP, Usage and Specifications

Tools and Tactics for Roadway Pavement Preservation: An Implementation Guide to Preserving High-Traffic-Volume Roadways

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

OGFC Meets CRM : Where the Rubber meets the Rubber

Successful Implementation of Warm Mix Asphalt in Ontario

Mix Design & Construction -1-

Materials 206: Handling RAP (Advanced) Contractor QC and Specifications

Cement Stabilized Soil (CSS) (Portland cement)

Pavement Design. TTP Orientation Seminar 2011

1985: FT02 Kuala Lumpur - Kuantan (Temerloh) 1988: FT08 Pagar Sasak - Merapoh, Pahang

THIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES

Transcription:

Reclamation Guidelines MAAPT 63 rd Asphalt Conference December 7, 2016 Terry Beaudry MnDOT Grading Base, Recycling, and Aggregate Engineer

Outline 2 Design and Preliminary Work Construction Production and Inspection Common Problems Cold In Place Recycling (CIR) Cold Central Plant Recycling (CCPR) Stabilized Full Depth Reclamation (SFDR) Full Depth Reclamation (FDR) Hot In Place Recycling (HIR)

Preliminary Work - All 3 Assess Roadway Conditions Core every 1000 for depth & Condition of HMA, Base, and Subgrade Assess gradation, depth, FAA crushing percentages of HMA (burn) DCP after core removed, then auger for base sample Perform Ground Penetrating Radar (GPR) to supplement coring Assess whether there are weak spots that you want to repair, preferably with lime/cement stabilization, fabric may also be used Perform assessment and a mix design. Designs for CIR, CCPR, and SFDR are in Grading and Base Manual Assess for what would be best project fix Need to meet design criteria MnPave, GE, SN, or other.

Cores - Note Height and Gradation 4

CIR Design and Preliminary Work 5 Cold In Place Recycling Want at least 1-2 HMA to remain in place. Rule of Thumb want at least 4-5 in situ HMA. Roads that are predominately structurally sound. Paver Laid so close to one lift of hot mix for ride quality. Make sure you do not over-mill, want rock and crushing in final product, or need to add rock, cement and/or lime to mix design Consider as alternative on second or third OL as successive overlays tend not to last as long as first ones Note that you can t fix profile, i.e. no excess material. May be used for BOC, Iowa has had great success with crack suppression Consider where there are no or few areas where additional structure is needed If strength needed in isolated spots, mill off HMA and remove base, then fix by cement treating subgrade then bringing back as CCPR 20 year design life Economically good alternative to 3 4 overlay as reflective cracking is alleviated

CCPR Design and Preliminary Work 6 Cold Central Plant Recycling Both CIR and CCPR produce the same product. One should only choose CCPR where the project dictates that CIR cannot be used because of project constraints. For most central plant cold mix (CCPR) projects the asphalt is milled from the project and stockpiled on site for CCPR. A Cold in place mixing device (may use the same mixer as used for CIR projects), processes the mix and then the mix is hauled back, placed, and compacted.

CCPR (cont.) 7 Cold Central Plant Mix CCPR mix is produced by mixing RAP with an emulsion or foaming bitumen. If cement is required by mix design, place immediately after mixing Since there is extra handling, it is more expensive than CIR

Uses for CCPR I believe that two good uses of CCPR would be the following: Best: Where you have a full depth bituminous section over very little or no base over a weak subgrade. Remove all but 2 of HMA, stabilize with subgrade and lime or cement, and compact. Bring back 4-8 of the CCPR mix (4 maximum lifts), place and compact. So some typical MnDOT Full Depth HMA roads with 10 HMA: Mill 8 Stabilize 6 12 of subgrade (leave 2 HMA for a platform and incorporation into the subgrade) Bring Back 1 to 2 four inch max lifts of CCPR Place new HMA on top Good alternative to white-topping: fixes weak subgrade, therefore longer life is anticipated May be less expensive (perform economic analysis) No grade raise 100% in place recyclable next time road is repaired 8

Uses for CCPR (continued) 9 Good Use: On shoulders where either the width or the Structure underneath the HMA is not adequate to support a CIR train. Mill the shoulder, haul the milling to a central site on the project, process, then bring back CCPR mix, place and compact. Competitive if replacing 1.5 of HMA: i.e. 3 CCPR plus 1.5 HMA is approximately equal to 3 HMA on shoulder.

SFDR Design and Preliminary Work 10 Use SFDR where you need to beef up base over a large portion of project, or HMA is too thin for CIR (less than 4 ), otherwise use CIR or FDR Design so that you only go into base 1 2 use your depth checks, less $ more uniform Make sure you do not over-mill, want rock and crushing in final product, or need to add cement and or lime to mix design Be willing to repair week areas if needed. Again - Consider starting on second or third OL where added strength in the base is needed as successive overlays tend not to last as long as first ones Consider isolated areas where additional structure is not needed If needed in isolated spots, fix by cement treating subgrade then bringing back as Cold Mix 20 year design life Economically good alternative to 3 4 overlay Reflective cracking is alleviated

SFDR Design & Preliminary Work (cont.) 11 SFDR Full Depth Reclamation Blade Laid SFDR two passes pulverize then inject, FDR one pass SFDR higher oil demand than CIR SFDR oil demand depends on amount of base incorporated

CIR versus SFDR versus FDR Perform an economic analysis for CIR, FDR, & SFDR to determine total cost which depends upon how much HMA is needed for each design.

Design for Depth of SFDR or FDR Plan Material Removed after Reclamation 13 Photo used from Ruston Paving Company website

HIR Design and Preliminary Work 14 Hot In Place Recycling Where Used: Raveling of HMA Treats the top 2-3 only Has been used in some for Minnesota counties and cities, but not for State work Do not have a special provision, within the Bituminous Unit

Economics 15 Assumptions: Oil at $45/Barrel PG graded foaming oil at $385/ton (Metro short haul), and adequate rock and crushing in mix design HMA at $60/ton = $3.25/sy inch CIR 2% new oil at 4 = $2 + $1.70 = $3.70/sy = $0.925/sy inch 90/10 HMA/Base 2.25% at 6 = $4.85/sy = $0.80/sy inch 50/50 HMA/Base 3.25% at 6 = $6.15/sy = $$1.025/sy inch Overlay 12 15 year design life CIR/SFDR 20+ year design life (with low initial maintenance)

TCRACKH, count/km Iowa Field Performance 70 Average High Severity Transverse Cracking 10 Year Span (3-4 inches HMA Surface) 60 50 40 30 20 HMA/PCC HMA/HMA HMA/CIP/PCC HMA/CIP/HMA HMA/PCC (MILLED) HMA/HMA (MILLED) 10 0 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 Cumulative Trucks, millions

Production with all Stabilized 17 Have Preconstruction Meeting Review Weather Requirements Review Equipment requirements Review Depth of Reclamation Review Maximum Size Requirements Review QC/QA checks Take in place moisture before stabilizing FDR, want to be close to optimum moisture, the emulsion or foamed asphalt counts as extra moisture Compaction will be tested by DCP unstabilized or Nuke Gauge for stabilized

QC/QA Tests 18 Gradation Maximum Size Requirements Depth Checks Ball Test Foaming Tests Calibration area for density check with nuke gauge Yield Checks Forms and procedures are in the Grading and Manual and website

Measuring Grinding Depth 19 A. General Measuring grinding depth in the field is a method of determining the grindinbg depth of HMA and base for (S)FDR and CIR B. Equipment Tape measure, Straight Edge, and Shovel C. Procedure 1. Always wear the proper safety equipment and never stand close to a reclaimer while it is in motion, wait until it is a safe distance away before measuring. 2. Use a shovel to reach the bottom of the reclaim layer, use the adjacent bituminous pavement as a guide. 3. Place the straight edge on the bituminous pavement and the tape measure on the bottom of the reclamation cut and measure the cut depth the nearest 0.5-inch. Measure the cut depth on both sides. Measure both HMA and Base against a non reclaimed HMA.

Ball Test Test to see if you can form a ball (if not mix may be too lean) If emulsion is used, let it harden for a half hour, foam test right away, break open with fingers: Should/may flex slightly look if uniform no blobs of oil.

Measuring Expansion Ratio & Half-Life of Foamed Asphalt in the Field 21 Figure 28 Measuring Expansion Ratio for Foamed Asphalt NOTE: BAD SAFETY PRACTCE. WEAR GLOVES!

Problems FDR and SFDR: Chunks 22

Problems SFDR & CIR 23 Material Sticking to Tires

Other Problems 24 Incorrect or poor Equipment to reclaim or Compact Teeth Too Dull Reclaiming too fast - chunks Milling too Deep No Rock left in reclaim Material Check Cores and GPR beforehand Reclaiming too Deep Either going into the subgrade or little base to compact against Be aware of 50/50 blend thought process in design May not have structure or adequate rock or going into subgrade For SFDR higher oil demand, HMA 2% oil, Base 4.5% oil demand

MnDOT Inspectors Guide For FDR and SFDR On Grading and Base Website Eleven Pages Quick Read Preliminary Responsibilities Coring, GPR, & DCP Choosing Method Mix Design Equipment Requirements Weather Pre-meeting with Contractor Inspector Responsibilities Field Tests Depth Checks and Gradation Ball and Tire Test Compaction Tests Foaming Tests Common Problems 25