Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function

Similar documents
Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks

Grid Interconnection Issues for Wind Generation

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

Mitigation of Voltage Fluctuations in Power System Using STATCOM

INTERSTATE TRANSMISSION VISION FOR WIND INTEGRATION

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

Grid Connection and Power Quality Optimization of Wind Power Plants

Impacts of the Decentralized Wind Energy Resources on the Grid

Integration of Wind Power Plants in The Electric Power System: A Case Study in Piauí Brazil

MAY 1, Variable Generation Integration Costs

Technical considerations for integration of distributed renewables on the grid

Slide 1. ABB August 23, 2016

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

Full electrical LNG-plant: Highest availability and energy efficiency trough overall system design

Grid Power Quality Improvement and Battery Energy Storage in Wind Energy System by PI and Fuzzy Based STATCOM Controller

Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks

Distribution Network Planning for Mumbai

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Distribution Information Exchange Code

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

Modeling of the Dynamic Behavior of the Island Power System of Cyprus

Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator

Refinement of Hydel power by implementing FACTS at Narangwal hydroelectric power plant

GRID CODE FOR ISOLATED SYSTEMS

Power Flow Control Scheme for Wind Energy Conversion System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

POTOMAC ELECTRIC POWER COMPANY

Joint DSO TSO reactive power management for an HV system considering MV systems support

EDF and Integration of Distributed Energy Resources

R2 TESTING GUIDELINE. PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013

A JOINT DSO-TSO REACTIVE POWER MANAGEMENT FOR AN HV SYSTEM CONSIDERING MV SYSTEMS SUPPORT

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016

Phasor measurement units gain credibility through improved test and calibration standards

Centralized wind power plant voltage control with optimal power flow algorithm

Cluster Design Toolbox. Cluster Design Workshop, 15/04/2016

International ejournals

Power quality improvement by using STATCOM control scheme in wind energy generation interface to grid

Power Plant Model Verification using PMUs

GRID CODE COMPLIANCE TESTING OF RENEWABLES NEW REQUIREMENTS AND TESTING EXPERIENCES

Collaborative Approach for Wind Power Plant Model Data and Validation

Information Document Protection System Information ID# R

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

Assessment of the Steady State Voltage Stability of the Ghanaian Transmission System with the Integration of Renewable Energy Sources

Peak Time Demand Management Using Distributed Solar Inverters

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS

RESEARCH ON THE VIRTUAL SYNCHRONOUS GENERATOR CONTROL STRATEGY OF GRID-CONNECTED PERMANENT-MAGNET DIRECT-DRIVEN WIND POWER SYSTEM

Standard TPL Transmission System Planning Performance Requirements

Value-based Transmission Investment and Operations. Marija Ilic Invited Panel, IEEE PES 2014 Washington DC

Contribution of PV Power Plants to Flicker Severity in Power Distribution Grids

Connection of generation plant to distribution networks. Guidance on completing the application form

Management System of Distribution Transformer Loading

4»IEEE POWER SYSTEMS .*ISK ASSESSMENT OF. Models, Methods, and Applications. Wiley. Ph.D., Fellow, IfE, CAE, EIC SECOND EDITION

8 th Annual Electric Power Industry Conference

Study on the Application of Advanced Power Electronics in Smart Grid

California Independent System Operator Corporation Fifth Replacement Tariff

INTERIM RESULTS. Wind energy sector in Brazil Developments and future outlook for Dutch parties. Larive - Your partner in emerging markets

Integration issues and simulation challenges of high penetration PV

Standard Development Timeline

DECISION 1 SCOPE AND CONSIDERATIONS... 2

Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers

DYNAMIC MODELLING AND SIMULATION OF A SIX WHEEL AUTOMATIC GUIDED VEHICLE

LARGE WIND FARM AGGREGATION AND MODEL VALIDATION MULUMBA PROSPER PANUMPABI THESIS

ENABLING FREQUENCY AND VOLTAGE REGULATION IN MICROGRIDS USING WIND POWER PLANTS

Active Distribution Networks

Research and Application Study on Accident-Based 3D Power Station Simulation Technology

EDP Investor Day. 5 years of IPO EDP in Brasil

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

Power-Flow Analysis of Large Wind Power Plant Collector Systems With Remote Voltage Control Capability

A Test System Model for Stability Studies of UK Power Grid

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

Wind Power Grid Interconnection:

N-1-1 AC Contingency Analysis as a Part of NERC Compliance Studies at Midwest ISO

H AND REPETITIVE CONTROL

MOD Data for Power System Modeling and Analysis

Public Utility District Number 1 of Snohomish County

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS

Bulk Power System Integration of Variable Generation - Program 173

Renewable energies. Wind energy solutions. Reliable innovation. Personal solutions.

Consequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis

Renewable energies. Wind energy solutions. Reliable innovation. Personal solutions.

Transmission Network Development &RES Integration December 2013


Spannungshaltung und Blindleistungsmanagement bei zunehmend dezentraler Stromerzeugung. Fabian Hinz.

Visualization for Shipboard Power Systems

The Derivation of Efficiency Equation of the Prototype of Pico Wind Turbine Produces the Electricity

A Research Reactor Simulator for Operators Training and Teaching. Abstract

Electrical Networks and Integration of Wind Energy

MAUI SMART GRID PROJECT

Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation

PRICE. Distribution Grid State Estimation

Comparison of Variable Speed Wind Turbine Control Strategies

Tutorial on Wind Generator Modeling and Controls

João Flavio Frossard André Ruzany José Antonio Pimenta Bueno André Gomes

Primary reserve studies for high wind power penetrated systems

POWER SYSTEM STABILITY GUIDELINES

Shunt Active Power Filter Wind Energy Conversion System

Transcription:

Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function Mariana B. Pereira 1, Sebastian A. Achilles 2, Nath Venkit 2 Energy Consulting General Electric 1 Av. Magalhães de Castro 4800, São Paulo-SP, 05502-001, Brazil 2 1 River Road, Schenectady-NY, 12345, USA mariana.bindapereira@ge.com, sebastian.achilles@ge.com, nath.venkit@ge.com ABSTRACT This paper presents the coordination of multiple voltage controllers in adjacent wind plants connected to João Câmara II substation in Rio Grande do Norte, Brazil. The parameter settings are estimated through dynamic simulations and confirmed with field tests. The methodology presented in this paper was used to calculate voltage regulator parameters like reactive power droop and regulator gains. A sensitivity analysis was done with dynamic simulations to verify satisfactory operation through different grid conditions. Complex field tests were performed to verify actual performance. Field tests confirmed that it was possible to coordinate 15 voltage controllers with the static voltage droop functionality, and to verify stable operation. Keywords: Voltage control, voltage droop, wind power generation 1 INTRODUCTION Wind power generation is significantly increasing its participation in the Brazilian electrical system. The regions with highest concentration of wind plants are the Northeast and South regions, where the wind conditions are very attractive. However, the existing transmission network is considerably stressed after the connection of the additional generation. Stability challenges may arise and have the power transfers limited below the transmission line thermal limits. The electrical system of João Câmara II (JC II) substation in Rio Grande do Norte state, with approximately 500MW of wind generation connected was considered for this study case. The system analyzed is described in Figure 1-1. The grid strength of JC II substation was evaluated in comparison with the wind generation. The three phase grid short circuit power level at the 34.5kV buses of the wind plants, without the contribution of the wind turbine generators (WTG) and nearby thermal generation for N-0 and N-1 conditions were calculated for relevant present and future grid conditions. The ratio of the grid short circuit power and the total MW of the wind plants, so called composite short circuit ratio (CSCR) [1], resulted in very low levels, even including the transmission upgrades.

Figure 1-1. Simplified One Line Diagram of João Câmara II System. Low levels of CSCR indicate the risk of system instability. This also indicates that the system voltages will change significantly with active power variations if the wind plants are operated on fixed reactive power. Hence, it is recommended to operate the wind plants connected to JC II substation on voltage control to improve system stability and reduce voltage variations during normal operation. There are approximately 500MW of wind generation connected to JC II substation, where 315MW are of wind plants equipped with GE s WTGs and the wind plant control system, so-called WindCONTROL (WC). There are 10 independently controlled wind plants composing União dos Ventos (UV) cluster, and 5 wind plants in Morro dos Ventos (MV) cluster. This results in 15 adjacent WCs. Adjacent voltage controllers (GE and non-ge) can interact causing reactive power circulation between wind plants or other forms of uneven reactive power generation. This results in an inefficient use of the available reactive power range and reduces the ability of the transmission system to reliably absorb the active power production from these plants. This interaction may also impact system and wind plant availability. In this extremely weak grid connection, efficient reactive power support is particularly relevant. It is possible to configure wind plant controllers to achieve a coordinated response. In this article, the methodology used to configure these 15 adjacent voltage controllers for a coordinated response is explained, and the results of field tests are presented to verify coordinated and stable operation. 2 COORDINATION METHODOLOGY 2.1 Steady State Performance All the GE equipped wind plants have a WC. In this application, the measurement signals for these WCs are taken from measurement devices (current transformers and power transformers) at 34.5kV substations. There is more than one WC per measurement location. It is not possible to have more than one WC controlling the same 34.5kV voltage without the risk of negative interactions. A configuration option is to enable and properly set the reactive power droop functionality in these controllers.

The reactive power droop feature in the WC displaces the effectively controlled node from the measurement point. That is, a droop set to a certain value X, moves the node of voltage control from the measurement point to an electrical distance X in the direction from the measurement point towards the wind turbines [2]. In this context, electrical distance is measured in the same unit as a reactance. There is a minimum electrical distance between voltage controlled nodes to reduce the risk of negative interactions between controllers. When this minimum electrical distance is not provided by the impedance of the electrical equipment, the reactive power droop feature can be utilized to ensure appropriate response of adjacent controllers. The common node is defined as the node in the system where the power of all the adjacent wind plants under study converges. In this case, the common node is the JC II 230kV bus. In order to obtain an even distribution of reactive power among WCs, the effective electrical distance between the common node and the controlled nodes has to be approximately the same for all WCs. The effective electrical distance (X EDeff ) is equal to the sum of the electrical distance (X ED ) between the common node and the point of measurement plus the reactive power droop setting. That is, X EDeff = X ED + droop (1) In the evaluated sites, there are unequal electrical distances from the 34.5kV substations and the common node (JC II 230kV). Reactive power droop is also used to compensate for differences in electrical distances. The steps to calculate reactive power droop setting of the WCs in all plants are: 1. Estimate X ED for each 34.5kV substation, considering equipment and line reactances. 2. Select the 34.5kV substation with larger X ED. Define droop setting in WCs connected to this substation to 10% in MVA base. 3. Estimate droop settings of other WCs such that the effective electrical distance, Eq. 1, is the same as for substation in item 2. Since the droop setting is in per-unit, all plants in the same substation are set to the same value. The droop settings for the wind plants not equipped with GE WTGs were also calculated, as if they also operate on voltage control mode. This is done for the sensitivity analysis purpose to investigate the condition that the fastest response is obtained. As more voltage controllers are in operation, faster is their response for a given group of settings. 2.2 Dynamic Performance The approach described in section 2.1 should improve reactive power sharing in steady state conditions. If dynamic responses of the different voltage controllers (GE and non-ge) are considerably different, there will be uneven reactive power sharing during transitions and wind plants are likely to temporarily operate at their reactive power limits. Therefore the dynamic response coordination is also recommended and is achieved by appropriately adjusting controller gains. The methodology to set the WC dynamic response is affected by WTG converter settings. GE s WTG converter has a turbine-level voltage control. The volt/var control loops of GE s WC and WTG can be simplified as shown in Figure 2-1 for a conceptual description of the tuning procedure [2]. The time constant of the droop term and the communication delay between WC and WTGs are neglected. The

time constant T Q represents the closed-loop response of the reactive power regulator at the WTGs. K p and K i are the WC proportional and integral gains respectively. The WC ratio K p /K i is normally selected to compensate the effect of T Q. The parameter V/Q depends on the stiffness of the electrical system. For strong systems the following approximation is valid [2]: V/Q X grid (2) Where X grid is the system impedance seen from the point of WC measurement into the utility system. Figure 2-1. Volt/var control loops of the WC and the WTGs. It is possible then to simplify Figure 2-1 and obtain Figure 2-2. Figure 2-2. Voltage Control Simplification. Then the bandwidth and time response to 80% of the final value can be easily calculated, though the equation: (3) V/Q and droop are selected depending on the considered operating conditions and number of parallel WCs. Equation 3 conceptually describes the approach to estimate the integral gain K i for a chosen time response, for high wind power production and assuming all plants in service. This operating condition has higher stability risks than operation with lower number of plants in service. In this particular weak application the WTGs have additional features that affect the volt/var response. Those aspects are considered in the definition of the settings. The transfer functions become slightly more complex, but the approach is as described above. Time simulations with the dynamic models of the GE WC and WTGs were performed in the software PSLF to verify and adjust estimated settings. In this

particular application with weak grid WTG settings, simulations are mandatory to estimate performance because of the complexity of the dynamics. After defining the integral gain K i, the response time with the selected settings in different operating conditions was estimated. Additional simulations were performed to check response time and overshoots for the following conditions: Controller reference step and capacitor bank switching Response of the WC in a single plant, all WCs of the plants connected to the same substation and all WCs in all substations N-0 and N-1 transmission conditions The WC voltage regulator gains were chosen considering that, in the future, the neighboring non-ge plants may operate with voltage control. This results in a slower response if the non-ge plants operate on power factor control, but mitigates the risk of oscillatory behavior if these are changed to voltage control mode in the future. Time simulations were performed for several initial conditions and dynamic events, trying to capture credible and critical conditions of operation, in order to verify the calculated settings. 3 SIMULATION RESULTS In this section, results of the sensibility analysis are presented [2]. Some of these simulations are later compared with the field test results. The setup used for the simulation tests presented in this paper considers all the wind turbines online, with 100% power generation, Extremoz load and SVC on with droop setting of 2%, the capacitor banks of União dos Ventos and Morro dos Ventos substations on. The WCs are in voltage control mode with weak grid WTG feature enabled in the field. 3.1 Individual Tests Figure 3-1 shows the simulation results of individually tested WCs, representing one WC per substation (Potiguares, Caiçara, União dos Ventos and Morro dos Ventos). This means that the referred WC is on, while all the others are turned off. The responses are stable and critically damped. Responses times are in the order of 150 seconds. 3.2 Group Tests Figure 3-2 shows the resulted simulations of group tested WCs of the wind plants of União dos Ventos and Morro dos Ventos clusters. For this test all 15 WCs of Potiguares, Caiçara, União dos Ventos and Morro dos Ventos substations are on. The responses are stable and critically damped, and the wind plants react to the same direction providing similar amount of reactive power, demonstrating its coordination. Responses are clearly faster than when testing individual plants and in the order of 40 seconds

Figure 3-1. Reactive Power Response to a 1% Voltage Step of Individually Tested WCs. Figure 3-2. Reactive Power Response to a 1% Voltage Step of Group Tested WCs of União dos Ventos and Morro dos Ventos Clusters.

4 FIELD TEST RESULTS Field tests were performed on the wind plants of Morro dos Ventos and União dos Ventos in April/May of 2014, to verify the operation of the voltage controllers [3-4]. The reactive power response of the voltage controllers was monitored to check for stability and coordination. 4.1 Individual Tests In the field, each WC of the 15 wind plants was tested individually during commissioning. Figure 4-1 shows the WC measurement trend captured during the application of a voltage step in the voltage reference signal of the WC of União dos Ventos 6 (UV 6) in Potiguares substation. The monitored signal is the Actual Reactive Power in green color, which presents a stable response. The response time to 80% of the final value was calculated and compared to the simulation values. This was done to all 15 WCs commissioned. Table 4-1 shows the comparison between measurement and simulation of one WC per substation. Figure 4-1. WC Trend of Individual Test in UV 6.

Table 4-1. Response Times of Reactive Power, Individual Tests. Wind Plant/Substation Response Time to 80% (s) Simulation Measurement MV 4 - Morro dos Ventos 47 50 UV 1 - Caiçara 54 57 UV 6 - Potiguares 75 75 UV 10 - União dos Ventos 32 29 4.2 Group Tests The WCs were also tested in groups in the field. The WCs of União dos Ventos, Caiçara and Potiguares substations were tested together, while the other WCs were off. A voltage step reference was sent to the WCs of these substations. The next table shows the recorded response times of all WCs of these substations during this test. Table 4-2. Response Times of Reactive Power, Group Test of União dos Ventos, Caiçara and Potiguares WCs. Wind Plant/Substation Response Time to 80% (s) Measurement UV 1 - Caiçara 33 UV 2 - Caiçara 29 UV 3 - Caiçara 23 UV 4 - Potiguares 18 UV 5 - Potiguares 34 UV 6 - Potiguares 17 UV 7 - Potiguares 27 UV 8 - União dos Ventos 26 UV 9 - União dos Ventos 29 UV 10 - União dos Ventos 20 Additionally, a capacitor switching event with the 15 WCs in operation was recorded. The capacitor bank in SE JC II had a block of 21.3 MVar maneuvered. Figure 4-2 shows the WC measurement trend of Morro dos Ventos 9 WC during the capacitor switch event. The monitored signal is the Actual Reactive Power in light blue color, which presents a stable response. Note that when the WCs of Morro dos Ventos and União dos Ventos are all in operation, the response to a voltage variation is faster than recorded response in the individually test. The controller gains were calculated as to give a reactive power response time of around 16s to 80% when all wind plants connected to JC II are under voltage control mode. This response time is in accordance to the tuning objectives for this operating condition and avoids risk of excessively fast/unstable response in other operating conditions, like N-1 or additional non-ge controllers on voltage control. Table 4-3 shows the recorded response times of all WCs of Morro dos Ventos during the capacitor switch event.

Table 4-3. Response Times of Reactive Power, Capacitor Switch of Morro dos Ventos WCs. Wind Plant/Substation Response Time to 80% (s) Measurement MV 1 - Morro dos Ventos 30 MV 3 - Morro dos Ventos 26 MV 4 - Morro dos Ventos 27 MV 6 - Morro dos Ventos 30 MV 9 - Morro dos Ventos 20 Figure 4-2. WC Trend of MV 9 for Capacitor Switch Test.

5 CONCLUSION Due to the weak grid condition of the transmission system of João Câmara II, voltage control operation of the wind plants reduces voltage instability risks and reduces the voltage fluctuations during normal operation. GE equipped wind plants have been configured to provide a coordinated voltage control response. The settings for voltage controller gains and droop were determined through a detailed methodology, and checked with dynamic simulations. The performance of the several controllers was also verified in the field, and it was observed that Morro dos Ventos and União dos Ventos voltage controllers had satisfactory and coordinated responses. Hence the method proposed for voltage coordination using droop function and dynamic coordination was validated even for this challenging system. REFERENCES [1] S. Achilles, E. Larsen, M. Shah, Integration of Wind Generation to Weak Grids, Cigré-Brasil, I Workshop Fontes Alternativas, March, 2012. [2] GE Energy, WindCONTROL Coordination Study: Wind Plants Connected to João Câmara 230kV, Rev 2, September, 2013. [3] GE Power and Water, Morro dos Ventos WindCONTROL Tests, May 20, 2014. [4] GE Power and Water, União dos Ventos WindCONTROL Tests, May 12, 2014. BIOGRAPHIES Mariana Binda Pereira Born in Brazil in 1983. Holds a degree in Master of Science in Renewable Energies from Oldenburg Universitaet in Germany, and a degree in Electrical Engineering from Universidade Federal do Espírito Santo in Brazil. She works for General Electric Company since September 2009, and joined GE Energy Consulting in 2012, as part of Latin American group, located in São Paulo, Brazil. She is currently Senior Engineer working mostly with interconnection studies of wind generation into the bulk power system, for diverse projects throughout the world. She is active in Brazilian working groups related to wind power integration. Sebastian Achilles Born in Argentina in 1972. He studied electrical engineering in the Universidad Nacional de La Plata and a masters in Electric Power Systems from Rensselaer Polytechnic Institute in Troy, NY. He leads the power system team from GE Energy consulting in Latin America. He is an IEEE and CIGRE member. He is a secretary of the CIGRE working group B4.62 on connection of wind farms to weak AC systems. Nath Venkit Born in India in 1969, he graduated with a Master s degree in Electrical Engineering from the Indian Institute of Science, Bangalore. He is the technical leader for the grid interfaces team for GE s Renewables business. He is based out of Schenectady NY and works with wind farm owners, consultants and grid authorities to ensure that the turbines and plant level controllers are designed and configured to meet the required grid interconnection specifications.