REPUBLIC OF UZBEKISTAN

Similar documents
STATE JOINT-STOCK COMPANY "UZBEKENERGO" Current state of electricity industry and prospects of energy system modernization

Use of renewable energy sources in Uzbekistan

Energy Efficiency Policy in Uzbekistan

Chapter 1. Uzbekistan s energy sector

Figure 1. Energy balance of Uzbekistan.

State Agency on Energy Efficiency and Energy Saving of Ukraine. State policy on renewable energy in Ukraine

THEME Country profile Current state of energy sector Outlook of energy demand and supply The energy policy Documents and its implementation. Short ter

Development of renewable energy sector in the Kyrgyz Republic

PREPARATORY SURVEY (F/S) FOR TASHKENT THERMAL POWER COGENERATION PLANT CONSTRUCTION PROJECT AND MASTER PLAN STUDY IN THE REPUBLIC OF UZBEKISTAN

CHAPTER VI Infrastructure and Public Services

ERAV Electricity Regulatory Authority of Vietnam

Content Sri Lanka At a Glance Energy reserves Current Energy Policy and Measures Past Energy Demand and Supply Outlook of energy Demand and Supply Ene

Implementation of UNFCCC in Armenia: ongoing activities in the context of climate change mitigation measures

Nuclear energy development in the Republic of Armenia. IAEA, Amsterdam June

Energy Resources and Security of Supply in Serbia

CMD projects in the Kyrgyz Republic Hydropower

IX. INITIATIVES FOR E-COMMERCE CAPACITY-BUILDING OF SMEs IN UZBEKISTAN

Content Introduction Institutional Arrangement Energy Policy Documents Energy Statistics Legal and Policy Efforts for Hydropower Development Problems

SECTOR ASSESSMENT (SUMMARY): ENERGY

REPUBLIC OF ARMENIA. Flag. Map. Coat of Arms. Republic of Armenia. Tatever Ropeway. Yerevan /Capital/ Cross-stone

The Potential for Renewable Energy in India

DECADES Tool to Make Comparative Assessment of Electricity Generation in Indonesia 1

EXPERIENCE OF KYRGYZ REPUBLIC: ENERGY SECTOR S SERVICES

Agricultural reform in Uzbekistan

CBM AND CMM DEVELOPMENT IN MONGOLIA NEW POLICIES TO STIMULATE CLEAN ENERGY PROJECTS

Cooperation in the Energy Sector

Taiwan Power Market Outlook to 2030 Market Trends, Regulations and Competitive Landscape. GDPE0646ICR / Published April 2013

Preliminary Findings of the Gap Analysis for Central Asia

Energy situation in Astana

Member State Perspectives

PV AND OTHER RENEWABLES THE FINANCIAL ADVANTAGE

Bioenergy in Ukraine: state of the art, prospects, barriers

MONGOLIA S PERSPECTIVE ON GREEN DEVELOPMENT

Development and Financing of Renewable Energy Projects in India

AZERBAIJAN COUNTRY PROFILE 83

PROPOSAL IMPLEMENTATION OF STATE S SHARE OF JSC «NAVOIYAZOT» FOR STRATEGIC INVESTORS

General Overview Area km2 Population-3,5 mln Situated south-east of Europe Density of population 121.9/km2 Economy- based on sevices 75% agricul

REFERENCE CODE GDPE0683ICR PUBLICATION DATE AUGUST 2013 PERU POWER MARKET OUTLOOK TO MARKET TRENDS, REGULATIONS AND COMPETITIVE LANDSCAPE

Contents. Introduction. Introduction. First Power Plant based on AC Tesla s s principles 1900! Recent Energy Sector Development

Research on China's power industry investment in Kazakhstan. Gao Yang

Energy from Renewable Sources Act

Economic Growth (in % to previous year)

Introductory presentation from the National Agency for Energy Regulation (ANRE)

The content of country report 1) General information about Turkmenistan 2) Current Energy Policy and Measures of Turkmenistan 3) Past energy demand an

Portugal Energy efficiency report

CASE STUDY How Uzbekistan is Becoming a Solar Energy Powerhouse

CHALLENGES AHEAD AND WAY FORWARD: Fostering Renewable Energy Deployment in Mongolia

UKRAINE RENEWABLE ENERGY NEWSLETTER ISSUE # July In This Issue. I. Legal and Regulatory Developments. II.

MEMO 27 June District heating and combined heat and power in China

Update of the Power Sector Master Plan of Azerbaijan

The Danish Road to Energy Self-Sufficiency

An Outlook of Renewable Energy Development in Malaysia

Renewable Energy Development in Cambodia. Institute of Technology of Cambodia

China's Green Growth Strategy: Industry Policy or Green Environment Policy?

The Lebanese Experience in Energy Efficiency and Renewable Energy

State Programme for Water Resources Management and Kazakhstan s Transition to Green Economy

Best Practices and Experiences on Thailand s Energy Policy for Sustainable Development

A Green light for renewable energy in Ukraine: Results and forecast for enterprises and energy market operation using a green tariff NERC

sustainable Energy Deployment in Egypt

Energy sector in Mongolia. Contents Brief of energy sector Energy sector policy Future trend

Jawaharlal Nehru National Solar Mission Building Solar India Ministry of New and Renewable Energy Government of India

Renewable Energy Plan in Thailand Karnnalin Theerarattananoon

I SUBSIDIARIES I. 1-1 pzzzgq. "Uzbekenergo" State Joint Stock company I. Board of Directors. Executive Board. - management. Hydro CHP.

Co-Benefit Approach in JICA

Renewable Energy Sources Policies of India. Author- Miss. Rucha Korhale BE-Instrumentation, Lecturer, V.P.M s Polytechnic, Thane.

Jawaharlal Nehru National Solar Mission

Fossil Fuel Consumption: United States and China

Comparative Legal Aspects of Renewable Energy Sources in the Russian Federation and China Ekaterina M. KOLOGERMANSKAYA

Electricity prices are changing.

Democratic Socialist Republic of Sri Lanka Commercial Capital: Colombo Administrative Capital: Sri Jayawardenapura Kotte

Solar Energy-An overview

Croatia Energy efficiency report

PROSPECTS OF SOLAR ENERGY IN NORTH EASTERN REGION OF INDIA

Uruguayan Energy matrix change Wind & PV development. Stuttgart - Germany June, 2013

Current Status of Energy in Viet Nam: Tran Thuc

Uzbek Commodity Exchange. Professional Development in Government Procurement

Reality and Prospects of Wind Power in Syria

Vietnam Renewable Energy development project to 2030 with outlook to 2050

RenovAr PROJECT ON ARGENTINA Ministry of Energy and Mining Argentina Republic

INTRODUCTION OF RENEWABLE ENERGY SECTOR IN MONGOLIA AND THEIR POLICY ENVIRONMENT

SECTOR ASSESSMENT (SUMMARY): ENERGY

COMPLEX PROJECT FOR THE DEVELOPMENT OF BROWN COAL DEPOSITS KARA-KECHE AND MIN- KUSH (AK-ULAK SECTION)

Uzbekistan Towards 2030: Transition to the Resource-efficient Growth Model DRAFT

Potential For Local Manufacturing of Solar Thermal Systems in Egypt

Renewable Energy Policies Case Study For Jordan

PREPARATORY SURVEY (F/S) FOR TASHKENT THERMAL POWER COGENERATION PLANT CONSTRUCTION PROJECT AND MASTER PLAN STUDY IN THE REPUBLIC OF UZBEKISTAN

Group 8. Energy System Integration: New Zealand Case Study, 2030 & 2050 Futures.

Development of Renewable Energies in Tunisia

ENERGY AND WATER STATISTICS 2016

Renewable Energy - A technology overview and the new Feed in Tariffs. Jos Mister Energy Saving Trust

Workshop on the Polices and Schemes for Financing Energy Efficiency in Buildings Belgrade, June, 2013

Baseline survey. INOGATE Partner Countries Institutional and Regulatory Frameworks in Sustainable Energy

Shivee Energy integrated energy complex

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

A. M. Monsurul Alam Director. Department of Environment Ministry of Environment and Forests

Strategic outlook of Heat pump development in China

Renewable energy in Belarus

Renewable Heat Incentive Schemes. Neil Witney Renewable Heat Premium Payment

Tin Zaw Myint Energy Planning Department (EPD), Ministry of Energy (MOE), Myanmar.

Renewable energy (RE) is any energy source that naturally replenishes and cannot be exhausted. Renewable energies include:

Transcription:

REPUBLIC OF UZBEKISTAN ENERGY POLICY Ministry of Economy of Uzbekistan

Contents * Uzbekistan: General Information * Current energy policy. * Energy demand and supply (statistics) * Outlook of energy policy, demand and supply 2

LOCATION

4 Area: 447.8 thous.sq.km Population: above 30 mln.

Main trends of social economic development of Uzbekistan Sustained high rates of economic growth (7-9% per annum on average) Growth rate of industry production (in % to the previous year) 14 12 10.8 12,1 12.7 10 8 6 9.1 8.3 63 6.3 7.7 8.8 4 2 0 2006 2007 2008 2009 2010 2011 2012 2013 for the period of independence, the volume of industrial production has development of GDP based on grown more than 3 times during purchase power parity has increased 1990-2012 3.5 times

Main trends of social economic development of the Republic of Uzbekistan (in % to previous year) Forecast # Indicators 2013 2014 Average rates until 2030 1. GDP growth rate 108.00 108.11 107.0-108.00-108 0 2. Inflation rate (end of period) 6.8 6-7 5-6 3. Industry production growth rate 108.8 108.3 108-109 4. Agriculture production growth rate 106.0 105.8 105-106 5. Investment growth rate 109.3 109.5 109-112 6. Decreasing of Energy intensity of Economy 15.3 115.0 110-115

Government support for development of the economy For the years of Independence the aggregate g tax burden decreased by almost 3 times. Moreover the Government provides additional tax incentives for exporters, small business enterprises and companies engaged in new investments and starting production of new goods and products Taxes Tax rates in 1992-2009 Tax rates in 2013 Legal entities income tax 45% 9% Individual income tax 13%-60% 8%-22% Value added tax 30% 20% Single social payment 40% 25% Single tax payment for small enterprises 15,2% 6% (in industry - 5%)

Factors assuring sustainable economic development of the Republic of Uzbekistan during 2014-2030 2030 1. Retaining macroeconomic stability, domestic and external balance of the economy; 2. Active industrial policy, aimed for structural changes, rapid growth of the share of processing industry with the production of high value added goods; 3. Implementation of modern innovative technologies, including environment-friendly and energy-saving; 4. Modernization and development of the industrial infrastructure, particularly transport, power industry, water use and sewer systems, as well as means of communication;

State joint stock company "Uzbekenergo" is the governing body in the power energy and coal industries - the major structural components of the economy. The company includes 54 enterprises and organizations. The installed capacity of power plants of "Uzbekenergo" is 12.5 million kw. The Thermal Power Plants of totalt capacity about 11,0 mln. kw is the base of the Power System of Uzbekistan. The power units of capacity from 150 to 800 MW each are set up at 5 big Thermal Power Plants These are such a big Thermal Power Plants as Talimardjan, Syr-darya, Novo-Angren, Tashkent and Navoiy TPP s generating over 85% of electric power.

Structure of Installed Capacities of Power Plants in Uzbekistan The installed capacities of power plants in Uzbekistan (MW), total including: 1. SJSC Uzbekenergo including: Thermal power plants (TPP) Hydro power plants (HPP) 12,945.0 12,467.0 11,048.0 1,419.7 2. Power plants which are not in jurisdiction 478.5 of SJSC Uzbekenergo

Structure of Fuel Consumption by Thermal Power Plants Black oil 2.0% Coal 7.0% Underground gas 0.2% Natural gas 90.8%

* Construction 0.5% Transport services sector 29% 2.9% 9.3% Population 25.4% Agriculture 21.8% Industry 40.1

Current Energy policy and measures

* Government strategy in the energy policy *Forcing the energy efficiency policy *Development p of technology based on ecologically friendly energy; *Energy efficiency i as a part of national forecasts; *Priority to the development of RES. *Growth of energy resources commercial export

* Law on Energy, 2009 *Legal g framework *Article 20 of the Law On rational energy usage (1997) *Decree of the President of the Republic of Uzbekistan dated March 01, 2013 no. 4512 "On measures for further development of alternative energy sources *The Resolution of the President of the Republic of Uzbekistan March 01, 2013 no. 1929 "On creation of the International Institute for Solar Energy *Draft Law of the Republic of Uzbekistan On renewable energy sources - to be presented to the Parliament. *Program of epensesdecreasing expenses and cost reduction in industrial enterprises. *Decree of the Cabinet of Ministers of 25.07.2011 2011 211 Improving energy efficiency of industrial enterprises" supported by International Development Association

ENERGY SECTOR Development Stages 1-stage: (1991-1996) 1996) Energy independence d and reorientation of the fuel-energy market to achieve society s priority social goals. 2-stage: (1997-2002) - Introduction of market management mechanisms; incentives for domestic and foreign investment into sector. 3-stage: (2003-present) Raising energy efficiency and introduction of renewable energy sources

Main measures on Energy Policy *Program of expenses decreasing and cost reduction in industrial enterprises *Project Improving energy efficiency of industrial enterprises supported by International Development Association (WB) *Preferential loans and incentives on tax and customs payments for modernization and re-equipment production by new energy-efficient technology *Incentives for organizing the domestic production energyefficient goods *Works on gradually equipping (starting from 2015) households and new constructing houses (ADB) with energy-efficient devices and boilers 17 of domestic production

Program for Priority Development of Power Industry till 2015 No Power Industry Sector Quantity of Projects Capacity/ Length 1 Thermal Power Plants 15 2,639 MW 2 Hydro Power Plants 10 83.45 MW 3 Power Networks 110-500 kv 4 Power Distribution Networks 0.4-35 kv 9 933.4 km, 2,099 MW 1 25.1 thousand km, 4,057 transformers, 58 substations (35 kv) 5 Electricity Consumption Metering System Introduction 4 4.5 million electricity meters 6 Others 8 Production of composite materials, current transformers, electricity meters, LED lamps, diesel oil synthesis and repair companies modernization

* No Name of project Capacity MW Sources of funding 1 Construction of CCGT unit at Navoi TPP 478 MW CCGT unit UFRD loans 2 Introduction of gas turbine technology at Tashkent CHPP 27 MW GTU NEDO grant (with CDM component) 3 Expansion of Talimardjan TPP with construction of two CCGT units 4 Installation of gas expansion machines at Syrdarya and Talimardjan TPPs with expansion of 220kV open switchyard at the above plants 5 Transfer of generating units No 1-5 of Novo-Angren TPP to all-the-year-round coal burning with modernization of Angren coal strip mine (first stage) 6 Construction of generating unit with heat extraction for high-ash coal burning at Angren TPP 7 Reconstruction of cooling towers No 1 and No 2 and 220kV open switchyard at Navoi TPP 2 х 450 MW CCGT units 20 - UFRD, ADB, JICA UFRD loan Loans of UFRD and Exim Bank (China) 130-150 Chinese loan for SCO countries - Own funds 8 Full-scale modernization of two generating units at 50 UFRD loan Syrdarya TPP Total 1,625

* Construction of combined cycle gas turbine in the Navoi TPP The aim of the project is to provide reliable and quality supply of heat and electrical energy to consumers in South- West power center, Navoi free industrial and economic zone and reduce unit cost of energy resources for production and decrease the environmental impact of the HPP. Capacity: 478 MW. Output of electrical energy: 3,4 3,5 billion kwh annually. Project implementation period: 2009-2012. The total cost: 468 million USD. Sources of finance: Own funds of SJSC Uzbekenergo 131,98 million USD; Loans of the Fund of Reconstruction and Development of the Republic of Uzbekistan 351 million USD; Loans of commercial banks 46,8 million USD.

Expansion of Talimarjan TPP with construction of 2 combined cycle generators with capacity of 450 MW each Capacity: 2х450 MW. Output t of electrical l energy: 6,8 7,0 billion kwh annually. Project implementation period: 2013-2016. The total cost: 1280 million USD. Sources of finance: Own funds of SJCS «Uzbekenergo» 380 million USD Loaned finance (ADB, JICA) 650 million USD Fund of Reconstruction and Development of Republic of Uzbekistan 250 million USD.

Energy demand and supply (statistics)

During the economic reform years, the Power Industry s enterprises annually generate up to 48bln.kW/h of electric power and more than 10 mln. Gcal of thermal power that fully meet the economic and population demand of the country.

billion.kwh Power energy demand and supply 56.0 54.0 52.0 50.0 48.0 46.0 44.0 42.0 40.0 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013*

Outlook of energy policy demand and supply

Outlook of changing the structure of power energy capacities up to 2030 th y. 2013 Y. 54.9 BILLION KWH

* According to the estimate of total hydroelectric potential of 656 rivers with confluents having overall water-producing area of 83,369369 km 2 : 1.Total theoretical hydroelectric potential of river flow in the country is 88.5 billion kwh. 2. Total technical hydroelectric potential is 21.09 billion kwh, including: 6.85 billion kwh at operating HPPs; 3.06 billion kwh at canal drop structures; 1.36 billion kwh at irrigation reservoirs; 9.82 billion kwh on rivers. 3 Presently it is used 6 27 billion kwh of technical potential including: 3. Presently it is used 6.27 billion kwh of technical potential, including: 5.17 billion kwh generated by HPPs in SJSC Uzbekenergo system; 1.1 billion kwh generated by HPPs in the system of the Ministry of Agriculture and Water Resources of the Republic of Uzbekistan.

The total potential of solar radiation in the Republic of Uzbekistan is estimated to be in the range from 525 billion kwh up to 760 billion kwh 20

Construction of 100MW Solar Photovoltaic Power Plant in Construction of 100MW Solar Photovoltaic Power Plant in Samarkand Province

* The site is located 4 km north of Sazagan settlement

The project implementation is to be done in accordance with the Decree of the President of the Republic of Uzbekistan dated 01.03.2013, 4512 "On measures for further development of alternative ti energy sources. It s being implemented by SJC Uzbekenergo jointly with Chinese partners in Free industrial economic zone Navoi. Its capacity is at the first stage will be 50 MW solar panels per year. In the future it is planned to reach capacity of 100 MW per year. Currently project documentation and JV agreements are being finalized.

Technical potential of biogas production In Uzbekistan Ube 8,9 bln. cubic. m. / year Resource of biogas in comparison with the production o of natural a gas in the republic 10% 6 bln. cubic. m. / year methane 60-65 bln. cubic. m./year methane production in the republic

UNDP Project "Promotion of Biogas Technology in Uzbekistan Technical characteristics Power 300 m 3 tonnes in a year Volume 120 tonnes in a year Biofertilisers 2800 tonnes in a year Loadings 5-7 tonnes manure daily Electric power 20 kwt*h

In accordance with the Decree of the President of the Republic of Uzbekistan dated 01.03.2013, 4512 "On measures for further development of alternative energy sources, on the 25 th of July, 2013, by the Cabinet of Ministers of Uzbekistan was approved The list of experimental and pilot projects on the implementation of solar and biogas energy in 2013-20182018 years. It includes projects for installation of: biogas units with the total cost of more than 14 mln. USD, PV units with the totalt cost of more than 100 mln USD.

THANK YOU FOR ATTENTION!