Drayton Management System Standard. Environmental Monitoring Program

Similar documents
Monthly Environmental Monitoring Report

Monthly Environmental Data May 2016

STRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan

WILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425

WILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425

Wambo Coal Environmental Management System

AUSTAR COAL MINE AIR QUALITY MANAGEMENT AND MONITORING PLAN

2.0 Description of Existing Mine Operations

Environment Protection Licence

Air Quality Monitoring Program. for the. Integra North Open Cut Coal Mine

AGL UPSTREAM INVESTMENTS PTY LTD GLOUCESTER GAS PROJECT

Operation Environmental Management Plan

Environment Protection Licence

Air Quality Monitoring Program

Drayton Management System Standard. Mine Closure Plan

Environmental Monitoring Results Summary

Mayo Renewable Power Killala Construction Works Monthly Environmental Report 010 April 2016

Bengalla Mining Company Pty Limited. Particulate Matter Control Best Practice Implementation Monitoring Programs

ENVIRONMENTAL MONITORING PROGRAMME

Environment Protection Licence

Appendix G Noise and Blasting Assessment

Environmental Noise Assessment

Hydrocarbon Management PROCEDURE

TABLE OF CONTENTS LIST OF FIGURES. Mt Arthur Coal Open Cut Modification Environmental Assessment

Environmental Protection Licence 2688

Moolarben Coal Complex Open Cut Optimisation Modification. Environmental Assessment ATTACHMENT 3. Stage 2 Project Approval (08_0135)

Ambient Air Quality Monitoring Baseline Report, Kirby Misperton A Wellsite, KM8 Production Well

Mt Arthur Coal. Annual Environmental Management Report FY16

WILPINJONG COAL NOISE MANAGEMENT PLAN

Environmental Assessment Chapter 8 Surface Water

aemc Wambo Coal Mine Independent Environmental Audit - June August 2011 Prepared for: Wambo Coal Pty Limited PMB 1 Singleton NSW 2330

2016 Annual Air Monitoring Results Summary

Alinta Cogeneration (Wagerup) Pty Ltd Alinta Wagerup Units 1 2

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

EMM. Mount Pleasant Project Construction Water Management Plan. Planning + Environment + Acoustics

Loy Yang B Environment Improvement Plan

Environment Protection Licence

Noise Management Plan

Section 75J of the Environmental Planning and Assessment Act 1979

NOISE Management Plan

Magino Project Environmental Impact Statement. Technical Support Document Environmental Monitoring Plan

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Airborne Pollutant Management Plan. November 2009

WEATHER MONITORING. Competitive rates available for long term hire. Hire rate Per week Per month

URANIUM MINING IN MALAWI BY PATRICK MEDIUS NYIRENDA ENVIRONMENTAL AFFAIRS DEPARTMENT, MINISTRY OF NATURAL RESOURCES, ENERGY AND MINING, MALAWI

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

Environment Protection Licence

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

Australian/New Zealand Standard

Bass Point Quarry. Environmental Management Strategy. Bass Point Quarry Environmental Management Strategy

Kurnell Refinery Conversion Project

Centennial Ivanhoe No2 Colliery. Environmental Monitoring Data

WAMBO COAL MINE MINING OPERATIONS PLAN

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES

Managing land contamination during the mine closure and rehabilitation process NSW Department of Industry Division of Resources & Energy

Report. PWCS Combined Environmental Compliance Audit /01/01. Prepared for: Port Waratah Coal Services. Prepared by URS Australia Pty Ltd

Construction Environmental Management Plan

Environment Protection Licence

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval

Environment Protection Licence

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

SHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY October, 2016

Evaluation of Void Water intercepted by Werris Creek Coal Mine Operations

Section 75O of the Environmental Planning and Assessment Act 1979

Environmental Management Strategy

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17

MINING LEASE No ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2012

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009

Dublin Airport Air Quality Monitoring Q1, Q2 2017

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS

MINING LEASE No ANNUAL ENVIRONMENTAL MANAGEMENT REPORT APRIL 2014

Annual Review

Murra Warra Wind Farm Project Environmental Management Plan

The assessment is based upon the design ore production of 95 million tonnes / annum.

Environment Protection Licence

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions.

Relevant legislation (Administering Authority Commonwealth legislation

WESTSIDE ENVIRONMENTAL MANAGEMENT PLAN

Subsidence Monitoring Program

Compliance Audit Report. Woodlawn Wind Farm

KKB Micro Testing Labs Pvt. Ltd., , 2 nd Floor, Tarun Plaza, NFC Main Road, Krishna Nagar Colony, Moula Ali, Hyderabad, Telangana

Annual Environmental Management Report

WILPINJONG COAL ENVIRONMENTAL MANAGEMENT STRATEGY

Section 75J of the Environmental Planning & Assessment Act 1979

Welcome to the H1 Software

Environment Protection Licence

Discipline Chemical Testing Issue Date Certificate Number T-3553 Valid Until Last Amended on - Page 1 of 9

Final Environmental Impact Assessment Report

Independent Environmental Audit

DEVELOPMENT CONSENT MODIFICATION Statement of Environmental Effects

10.0 AIR QUALITY AND CLIMATIC FACTORS

WAMBO COAL MINE MINING OPERATIONS PLAN

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

Environmental Guideline for Saskatchewan Asphalt Plants

ENVIRONMENTAL ASSESSMENT A3-1 INTEGRA COAL OPERATIONS PTY LTD. Glennies Creek Open Cut Coal Mine Report No. 642/03. Appendix 3

Hind Energy & Coal Beneficiation (India) Ltd.

Mount Arthur Coal Mine 2017 Independent Environmental Audit

Environment Protection Licence

Engineering Management Manual

Advice to decision maker on coal mining project

Transcription:

Anglo Coal (Drayton Management) Pty Ltd Drayton Management System Standard Author: Name Brooke York Title Environmental Officer Signature Date 10-10-2017 Reviewer: Name Matt Lord Title Environmental Superintendent Signature Date 10-10-2017 Authoriser: Name Darren Pisters Title Mining Engineering Manager Signature Date 10-10-2017 This document is controlled whilst it remains in the Drayton Intranet DOC # DRA_12-001_PRO_ Page 1 of 22

Anglo Coal (Drayton Management) Pty Ltd Revisions Issue Issue Date Author Reviewer Authoriser 1 June 2008 P Simpson P Forbes M Heaton 2 July 2013 L McGinnity P Forbes/J Benson C Robertson 3 June 2017 N Dobbins / B York (Hansen Bailey) M Lord D Pisters DOC # DRA_12-001_PRO_ Page 2 of 22

Distribution List Distributed to: General Manager s Office (current originals) Administration Central File (originals of previous versions) NSW Department of Planning and Environment Anglo American Website DOC # DRA_12-001_PRO_ Page 3 of 22

Anglo Coal (Drayton Management) Pty Ltd Table of Contents 1 PURPOSE... 5 2 SCOPE... 5 3 DEFINITIONS... 6 4 PROCEDURAL REQUIREMENT... 6 4.1 Responsibilities... 6 4.2 Audit / Review Schedule... 7 4.3 Records Management... 7 4.4 Revision Status... 7 4.5 References... 7 4.6 Monitoring Requirements... 8 4.7 Meteorological Monitoring... 14 4.8 Noise... 14 4.9 Air Quality... 14 4.10 Blasting Airblast Overpressure and Ground Vibration... 15 4.11 Surface Water... 16 4.12 Groundwater... 16 4.13 Rehabilitation... 16 4.14 Coal Transport... 16 4.15 Greenhouse and Energy Efficiency... 16 4.16 Waste... 16 4.17 Spontaneous Combustion... 17 4.18 QA / QC... 17 4.19 Reporting... 17 4.20 Statutory Requirements... 17 5 APPENDICES... 19 DOC # DRA_12-001_PRO_ Page 4 of 22

Document Information 1 PURPOSE The purpose of this management plan is to provide an overview of environmental monitoring conducted at Drayton, and to demonstrate compliance with condition S5.2 of the Project Approval 06_0202 requiring Drayton to have an. 2 SCOPE This procedure describes the various environmental monitoring requirements for the following environmental aspects: Meteorology; Noise; Air Quality; Blasting Airblast Overpressure and Ground Vibration; Surface water; Groundwater; Rehabilitation; Coal Transport; Greenhouse and Energy Efficiency; Waste; and Spontaneous Combustion. This monitoring program also assists Drayton in maintaining compliance with ISO14001 requirements, the Anglo American Metallurgical Coal SHECMS and the Anglo American (AA plc) Environment Way protocols. Active mining operations ceased at the site in September 2016. Monitoring will continue to be conducted as outlined in this document and reported in the Annual Environmental Management Report (AEMR). DOC # DRA_12-001_PRO_ Page 5 of 22

3 DEFINITIONS AEMR EPA SHE DP&E EPL TDS TSS TPH BTEX EC CCC TEOM L Aeq L A1 Annual Environment Management Report Environmental Protection Authority Safety, Health and Environment Department of Planning and Environment Environment Protection Licence Total Dissolved Solids (mg/l) Total Suspended Solids Total Petroleum Hydrocarbon benzene, toluene, ethylbenzene, and xylenes Electrical Conductivity (µs/cm) Community Consultative Committee Tapered Element Oscillating Microbalance Equivalent A-weighted continuous sound level One percentile A-weighted sound level 4 PROCEDURAL REQUIREMENT 4.1 Responsibilities Environmental Superintendent Ensuring all environmental monitoring is undertaken per Project Approval requirements; Ensuring all environmental monitoring is undertaken per the relevant Australian Standard or Approved Method; Ensuring all monitoring results are entered into the Envirosys database; Reviewing environmental processes and data collection; and Implementing the environmental monitoring program. Environmental Officer Undertaking environmental monitoring as required by the Project Approval; Ensuring that correct procedures are followed during sample collection; Entering all environmental monitoring results into the Envirosys database; Ensuring all environmental monitoring equipment is maintained and serviced as required; and DOC # DRA_12-001_PRO_ Page 6 of 22

Ensuring all environmental equipment is calibrated according to equipment specifications and Australian Standards. 4.2 Audit / Review Schedule This monitoring plan is to be reviewed at least every three years or as otherwise directed by the Director-General of DP&E. In accordance with Project Approval (06_0202), Drayton will commission an independent environmental audit to the satisfaction of Director-General of DP&E every three years. The audit will include an assessment of the adequacy of all management and monitoring plans. Where necessary, following the audit, this monitoring plan may be updated and action taken to improve environmental monitoring practices at Drayton. 4.3 Records Management All records of environmental monitoring must be kept on file at the Drayton mine site for the duration of the life of mine. 4.4 Revision Status June 2008 This version supersedes the 2003 Environmental Monitoring Procedure, and was updated per the requirements of the 2008 Project Approval. July 2013 Procedure reviewed and updated to reflect changes in organisational structure at Drayton and regulatory office reference changes February 2016 Procedure reviewed in line with recommendations from the 2015 Independent Environmental Audit conducted by AECOM, and updated with the current monitoring locations, and regulatory office references. June 2017 Minor wording changes and monitoring figure revised to include current ground and surface water monitoring locations. 4.5 References Environmental monitoring at Drayton is conducted in accordance with the following Regulatory and Corporate requirements: The Protection of the Environment Operations Act, 1997 (PoEO Act) administered by the EPA and the associated EPL (1323); Environmental Planning and Assessment Act, 1979 (EP&A Act) administered by the DP&E and associated project approval conditions (PA 06_0202, and DA 106-04-00); DOC # DRA_12-001_PRO_ Page 7 of 22

Drayton Mine Environmental Assessment 2007; Management plans required by PA 06_0202 and DA 106-04-00; Anglo Safety, Health, Community and Environment Management System (SHCEMS); Australian Standard 3580.9.8 2008 Methods for sampling and analysis of ambient air Method 9.8: Determination of suspended particulate matter PM10 continuous direct mass method using a tapered element oscillating microbalance analyser; Australian Standard 3580.9.3-2015 Methods For Sampling and Analysis of Ambient Air Determination of Suspended Particulate Matter Total Suspended Particulate Matter (TSP) High Volume Sampler Gravimetric Method; Australian Standard 3580.10.1 2003 Methods For Sampling and Analysis of Ambient Air Determination of Particulate Matter Deposited Matter Gravimetric Method; Australian Standard 5667.1 1998 Water quality - Sampling - Guidance on the design of sampling programs, sampling techniques and the preservation and handling of samples; Australian Standard 5667.6 1998 Water quality - Sampling - Guidance on sampling of rivers and streams; Australian Standard 5667.11 1998 Water quality - Sampling - Guidance on sampling of groundwaters; and Approved Methods for the Sampling and Analysis of Air Pollutants in New South Wales (EPA, 2006). 4.6 Monitoring Requirements This section describes the type, frequency and location of various environmental monitoring requirements as described in Schedule 3 of the Project Approval. Monitoring sites are shown in Figure 1 and Figure 2. Table 1: Overview of the Project Parameter Monitoring Sites Frequency Section Meteorological Temperature Relative Humidity Rainfall Wind Velocity Wind Direction Automatic Weather Station Continuous 4.7 DOC # DRA_12-001_PRO_ Page 8 of 22

Parameter Monitoring Sites Frequency Section Noise 1 Independent Attended Noise Compliance Monitoring L Aeq (15 mins) L 1 (1 min) Real Time Monitoring (Barn Owl) Air Quality Dust Deposition High Volume Air Sampling (TSP) TEOM (PM10) Location R16: Doherty Location R25: Kerr Location R35: Wilson Location R42: Smith Location R61: Skinner Location R72: Robertson Location R75:Sharman Location R76: Horder Lot 9 Antiene Balmoral Road 2130, 2157, 2175, 2197, 2208, 2230, 2235, 2247 Lot 22 Antiene Lot 9 Antiene Balmoral Road Monthly 4.8.1 Continuous 4.8.2 Monthly 4.9.1 24 hrs on a 6 day cycle 4.9.2 Continuous 4.9.3 E Samplers 1, 2, 3, 4 10 mins 4.9.4 Blasting Airblast Overpressure and Ground Vibration 2 Ground Vibration Airblast Overpressure Surface Water ph, EC, TDS, TSS, sodium, magnesium, calcium, potassium, chloride, sulphate and bicarbonates ph, EC, TDS, TSS, sodium, magnesium, calcium, potassium, chloride, sulphate and bicarbonates, TPH, BTEX Lot 24 Antiene De Boer monitor Sharman monitor Ash Dam Crest monitor Ash Dam Toe Monitor Lot 24 Antiene De Boer monitor Sharman monitor Ash Dam Crest monitor Ash Dam Toe Monitor 1969, 2081, 2114, 1609, SW13, 2221, 2109, 1895, V Notch. Every blast 4.10 Every blast 4.10 Monthly 4.11 OPC Dam Monthly 4.11 1 Attended Noise Monitoring - will be undertaken at the nearest location to the residence and shall be subject to consent of the resident. Attended noise monitoring may also be required at additional monitoring locations dependent upon requests received by landowners and/or residents. 2 Blasting - airblast and ground vibration levels may also be monitored at other residences dependent upon complaints received. These will be conducted using a portable monitor. Page 9 of 22 DOC # DRA_12-001_PRO_

Parameter Monitoring Sites Frequency Section ph, EC, TDS, TSS, sodium, magnesium, calcium, potassium, chloride, sulphate and bicarbonates Groundwater 3 Standing Water Level, field ph, field EC, field Salinity and field TDS ph, EC, TDS, TSS, sodium, magnesium, calcium, potassium, chloride, sulphate and bicarbonates Rehabilitation Flora: growth form, species name, Projected Foliage Cover (PFC) and minimum and maximum heights of each strata, Canopy cover and mid-storey cover (native and exotic) were recorded every five metres along the 50 m transect. Shrub cover, grass cover, other ground cover (herbs, forbs, sedges) and exotic ground cover Fauna: Hair funnel and remote camera, nocturnal survey, bird census, herpetogical survey, microchiropteran bats. Coal Transport Coal production and train movements Greenhouse and Energy Efficiency Diesel Electricity Explosives Fugitive Emissions Waste ES Void Quarterly 4.11 F1167, F1168, F1162, F1164, F1024, F1163, W1102, R4241, DS1, DS2, DS3 F1167, F1168, F1162, F1164, F1024, F1163, W1102, R4241, DS1, DS2, DS3 29 Flora sites 8 Fauna sites Rail Loadout Equipment usage and blasting Monthly 4.12 6 Monthly 4.12 Annually 4.13 Annually (coal production) Daily (train movements including date and time) 4.14 Monthly 4.15 3 Ground water bore monitoring of registered offsite bores will commence if bores re located and permission obtained from the resident land owner. Page 10 of 22 DOC # DRA_12-001_PRO_

Waste Oil Metal General Waste Recyclable Wastes Parameter Monitoring Sites Frequency Section Spontaneous Combustion Monthly Collection Waste data forms Monthly 4.16 Area and Intensity of Spontaneous Combustion areas Active Spontaneous Combustion areas Monthly 4.17 DOC # DRA_12-001_PRO_ Page 11 of 22

Figure 1: Drayton Environmental Monitoring Sites DOC # DRA_12-001_PRO_ Page 12 of 22

Figure 2: Rehabilitation Monitoring Sites DOC # DRA_12-001_PRO_ Page 13 of 22

4.7 Meteorological Monitoring An automatic weather station has been operational at Drayton since 1982. Temperature, relative humidity, wind speed, wind direction and rainfall are recorded on a five minute basis, with summaries being obtained hourly and daily. This station is operated in accordance with the requirements of the Approved Methods for the Sampling and Analysis of Air Pollutants in New South Wales (EPA, 2005). 4.8 Noise Drayton has a well-developed noise monitoring program that was established at the commencement of mining operations. This involves a combination of unattended real time monitoring and independent attended monitoring as detailed in the Noise Management Plan. All results from this monitoring are analysed and summarised in the AEMR and presented at the CCC meeting. 4.8.1 Independent Attended Noise Compliance Monitoring Monitoring is conducted at eight representative residential locations to quantify the overall ambient noise amenity criteria for the site as detailed in Table 1 and shown in Figure 1. This monitoring is conducted by a qualified acoustic consultant. The information obtained in attended monitoring is used to model noise levels at 23 other receivers listed in EPL1323. Results of any independent monitoring assessments are reported in the AEMR. Environment personnel can conduct attended noise monitoring at the request of a resident in the vicinity of Drayton, however this is indicative only and not included in compliance monitoring. 4.8.2 Real Time Noise Monitoring Real time noise monitoring stations (Barnowls) operate at Lot 9 Antiene and Balmoral Road conducting 24 hour directional noise monitoring. Current information relating to noise emissions is available to key personnel through a website should an enquiry be received. 4.9 Air Quality An Air Quality Management and Monitoring Plan has been in operation at Drayton since 1982. This details the monitoring of dust deposition, PM10 and TSP concentrations using a network of dust depositional gauges, TEOM and high volume air samplers. 4.9.1 Dust Deposition A network of eight dust depositional gauges exist in the Antiene area to assess air quality impacts on the Antiene subdivision, directly to the north of the mine lease and are collected on a monthly basis. These gauges have been in operation for over 20 years and have well established baseline levels to compare current ambient levels with. Dust depositional gauges locations are shown in Figure 1. Monitoring is undertaken per Australian Standard 3580.10.1-2003 and gauges are collected monthly and analysed for ash, combustible matter and insoluble solids. This information is DOC # DRA_12-001_PRO_ Page 14 of 22

reported in the AEMR, discussed at the CCC meeting and posted monthly on the Drayton website. 4.9.2 Total Suspended Particulates A high volume air sampler is used to monitor atmospheric suspended particulate matter having an approximate equivalent aerodynamic diameter of less than 50µm. This sampler has been in operation for several years and has established baseline levels with which to compare current ambient levels. The location of the HVAS is shown in Figure 1. This high volume air sampler is operated for 24hrs on a six day cycle with monitoring undertaken per Australian Standard 3580.9.3-2015. This information is reported in the AEMR and posted monthly on the Drayton website. 4.9.3 Particulate Matter PM10 Two TEOMs are used to monitor particulate matter less than 10 µm in size. Their location is shown in Figure 1. These samplers operate on a continuous basis per Australian Standard 3580.9.8-2008. This information is reported in the AEMR and posted monthly on the Drayton website. 4.9.4 Proactive and reactive monitoring Drayton maintains 4 E Samplers on site, located to the North, South, East and West of the pit (Figure 1), and an associated weather station. EnviroSuite software is used to provide alerts when: Unfavourable weather conditions are forecast at Drayton; and Real time dust monitors exceed predefined triggers. The E Samplers provide feedback of real time PM10 dust levels to the Drayton operation where employees can monitor the data and make operational decisions based on this real time data. 4.10 Blasting Airblast Overpressure and Ground Vibration A Blasting Management and Monitoring Plan is well established for the site, which includes real-time monitoring of airblast overpressure and ground vibration levels for all blasts. Drayton has been monitoring blasts in excess of 20 years and has an extensive database of airblast and ground vibration results. Ground vibration levels are monitored at the Ash Dam Levee Monitors to comply with NSW Dam Safety Committee requirements. Monitoring locations in relation to residences are shown in Figure 1. These permanent stations have been commissioned to represent levels in the Antiene estate. This information is reported in the AEMR, discussed at the CCC meetings and posted monthly on the Drayton website. In addition, supplementary airblast overpressure and ground vibration monitoring can be undertaken on an as needs basis utilising portable monitors. DOC # DRA_12-001_PRO_ Page 15 of 22

4.11 Surface Water A Water Management Plan has been in place at the Project since 1982. Monitoring locations are shown in Figure 1, and are monitored for the parameters given in Table 1. This includes monitoring of the ES Void tailings emplacement on a quarterly basis. Surface water quality monitoring and sample collection, storage and transportation are detailed in the Drayton Water Management Plan and undertaken per Australian Standard 5667-1998. All analysis is undertaken by a NATA accredited laboratory. The results from the surface water monitoring are discussed in the AEMR. 4.12 Groundwater A groundwater monitoring program has been in place since 1982. Monitoring locations are shown in Figure 1, and are monitored for the parameters given in Table 1. Groundwater monitoring and sample collection, storage and transportation are detailed in the Drayton Water Management Plan and undertaken as per Australian Standard 5667-1998. Analysis of these samples must be analysed by a certified NATA accredited laboratory. The results from this monitoring are discussed in the AEMR. 4.13 Rehabilitation Rehabilitation performance is monitored on an annual basis to assess vegetation establishment and to determine if there is a need for additional maintenance measures to be implemented. Figure 2 and Table 1 outline the monitoring locations and the parameters monitored. The results of this monitoring is discussed in the AEMR. 4.14 Coal Transport Records are kept regarding annual tonnages and coal tonnages transported from site on an annual basis. This includes recording total number of coal haulage train movements on a daily basis. Information is also received from Mt Arthur Coal regarding train numbers and coal tonnages transported along the Antiene Rail Spur. This information is reported every six months to the DP&E and in the AEMR. 4.15 Greenhouse and Energy Efficiency Anglo is a signatory to the Greenhouse Challenge and as such diesel, electricity and explosives are recorded on a monthly basis from which carbon dioxide (CO 2) equivalent emissions can be calculated. These parameters as well as fugitive gas emissions are reported in compliance with National Greenhouse and Energy Reporting (NGER) requirements. These CO 2 equivalent greenhouse gas emissions will be reported in the AEMR. 4.16 Waste Waste generation has been recorded at Drayton for several years and requirements are detailed in Drayton s Waste, Overburden and Hazardous Materials Management Plan. This practise shall continue, with any waste products removed from site being recorded and reported in the AEMR. DOC # DRA_12-001_PRO_ Page 16 of 22

4.17 Spontaneous Combustion An Open Cut Examiner inspects the mining area on a daily basis and observes for the presence of spontaneous combustion outbreaks. Spontaneous combustion is monitored on a monthly basis as outlined in the Drayton Spontaneous Combustion Management Plan. This monthly monitoring is a visual assessment of areas supported by the use of a thermal imaging camera. Monthly maps of areas affected are reported to the EPA, with six monthly reports of remediated areas also being provided. 4.18 QA / QC Monitoring instructions exist for the following monitoring requirements: Barn Owl (Noise) Data; Fallout (Depositional) Dust Monitoring; Groundwater Monitoring; Surface Water Monitoring; and TEOM (PM10). The procedures to be followed for other monitoring are contained within the relevant management plan. All samples to be sent to a NATA lab for analysis are accompanied by a Chain of Custody form. These are saved in the Drayton Environment filing system for future reference. All data received from the laboratory is uploaded into Envirosys, and filed electronically in the Drayton Environment filing system. Other data is managed as outlined in the relevant management plan. 4.19 Reporting Drayton prepares an AEMR that consolidates all environmental monitoring and reporting as required by this monitoring plan and referenced management Plans, the Project Approval Conditions and EPL1323. A copy of this management plan is made available to Drayton s Community Consultative Committee (CCC). In addition, the management plan is publicly available on Drayton s website: http://australia.angloamerican.com/our-operations/operating-sites-subpage/draytonenvironment In accordance with the Project Approval conditions and EPL requirements, a summary of the environmental monitoring results are made publicly available on the website and are updated monthly. 4.20 Statutory Requirements This plan has been developed in accordance with the requirements of the NSW DP&E for the Drayton Mine Extension (06_0202) issued in 2008. Conditions regarding Environmental Monitoring Program are as follows: DOC # DRA_12-001_PRO_ Page 17 of 22

Condition Condition Details Reference S5.2 The Proponent shall prepare and implement an Environmental Monitoring Program for the Project to the satisfaction of the Director-General. This program must be submitted to the Director-General within 6 months of this approval, and consolidate the various monitoring requirements in Schedule 3 of this approval into a single document, and be submitted to the Director-General concurrently with the submission of the relevant monitoring programs/plans. 4.5 DOC # DRA_12-001_PRO_ Page 18 of 22

5 APPENDICES Appendix 1: Regulatory Correspondence Document Reference 2017 DP&E Correspondence to Drayton Mine Where addressed 18/09/2017 Approval of received Appendix 2 b) vi) Update resulting from 2015 Independent Environmental Audit as follows: Updated so that it refers to the current network of surface and groundwater monitoring locations; The site should reconcile the EMP with updates to management plans as and when they occur The roles and responsibilities outlined in the Appendices should be reviewed for currency. Figure 1: Drayton Environmental Monitoring Sites and Table 1: Overview of the Project Environmental Monitoring Program Noted 4.1 DOC # DRA_12-001_PRO_ Page 19 of 22

DOC # DRA_12-001_PRO_ Page 20 of 22

DOC # DRA_12-001_PRO_ Page 21 of 22

DOC # DRA_12-001_PRO_ Page 22 of 22