Concrete Pavement Preservation:

Similar documents
Tools and Tactics for Roadway Pavement Preservation: An Implementation Guide to Preserving High-Traffic-Volume Roadways

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments

550 Surface Treatments

IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction

Asphalt Pavement Maintenance and Rehabilitation Strategies

Concrete Pavement Preservation Guide

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

Alligator Cracking. Light. Medium. High

Pavement Management Systems

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

Maintaining your roads with Asphalt

Chapter 4 Portland Cement Concrete Pavement Guidelines and Policies Publication Edition Change 1 CHAPTER 4

Optimization of Concrete Maintenance to Extend Pavement Service Life

Pavement Preservation with Thin Lift Concrete Overlays. Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

Pavement Crack Treatment

Controlling Reflection Cracking in HMA Overlays of PCC Pavement. Gary L. Fitts, P.E. Sr. Field Engineer Asphalt Institute San Antonio, Texas

AMERICAN CONCRETE PAVEMENT ASSOCIATION

Concrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay

DOWEL BAR RETROFIT DO S AND DON TS

ACKNOWLEDGMENT OF SPONSORSHIP

Joint- and Crack-Sealing Challenges

12/11/ th Annual Illinois Bituminous Paving Conference December 11, 2013

Prevention of Transverse Bumps Over Crack Sealant During Asphalt Overlay Construction

PAVEMENT PRESERVATION GUIDELINES

THINLAY ASPHALT FOR PAVEMENT PRESERVATION

PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE

SHRP2 R21 Composite Pavement Systems Project Overview

Mechanistic-Empirical Pavement Design Guide

PAVEMENT MARKINGS. F. Grooves Cut for Pavement Markings, Symbols, and Legends

Deterioration of Concrete Roads

MNDOT PAVEMENT DESIGN MANUAL

3 Road Surface Guide. for 3M TM Stamark TM Pavement Marking Tapes

PORTLAND CEMENT CONCRETE OVERLAYS. C. Unbonded Concrete Overlays Over Concrete (with separation layer)

Session 11: Concrete Overlays

GUIDELINES FOR ASSESSING PAVEMENT PRESERVATION TREATMENTS AND STRATEGIES

General Information for Joints

SOM August 2009 Alaska

Pavement Preservation-ODOT Leading the Way

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction

Recommended Practices for Crack Sealing HMA Pavement

Design of Rigid Pavements

Section 504. MICRO-SURFACING

404-LVT (Low Volume Traffic) A new 404 specification for your lightly traveled roads

CONSTRUCTION BULLETIN

SECTION FLEXIBLE PAVING

SIDEWALK PROBLEMS AND REPAIR

INDOT Thin Concrete Overlay Initiatives. Tommy E. Nantung INDOT Division of Research and Development

Concrete Pavement Joint Design and Construction

The Role of Pavement Preservation in Asset Management

The Ultimate Stress Absorbing Membrane presented by

Polymer Concrete Patching Materials. Todd Donmyer P.E. Area Engineer District 61

Pavement Preservation

Surface Texture Issues Related to Concrete Pavements

Pay Schedule for Ride Quality

Australian Society for Concrete Pavements Concrete Pavements Conference 2017

Introduction to Pavement Overlays

Asphalt Rubber: The Arizona Experience. Julie Kliewer, Ph.D., PE Arizona Department of Transportation

PRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW

THIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION

ACKNOWLEDGMENT OF SPONSORSHIP

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

Curtis Bouteillier, Proform Management Inc. Wayne Gustafson, The City of Red Deer

PCC/AC Shoulder Joint Seal Evaluation

A. This Section includes resinous flooring systems with epoxy body coat(s).

Good Practices for Concrete Road Pavement Construction

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

E.V.A. EXPANSION JOINT SYSTEMS

2011 Regional Asphalt Meetings. Frequently Asked Questions

UNIFIED FACILITIES GUIDE SPECIFICATIONS

USER RESPONSIBILITY.1 CHAPTER 1: INTRODUCTION.3 CHAPTER 2: PAVEMENT DESIGN PROCEDURES.5 CHAPTER 3: PROJECT SCOPE.7 CHAPTER 4: DATA COLLECTION.

Special Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:

Mix Design & Construction -1-

FULL DEPTH RECLAMATION FOR CITIES AND COUNTIES. OTEC - October 27, 2015

Georgia DOT Micro-milling and Thin Overlay

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

Technical Information

Specialty Expansion Joint Systems

Concrete Distress Assessments and Solutions 2017 Municipal Streets Seminar November 15, 2017 Ames, Iowa

Life Cycle Cost Analysis July 2011 Materials Division Page 1 TABLE OF CONTENTS V. ASPHALT PAVEMENT CONSTRUCTION/RECONSTRUCTION...

Thin Asphalt Overlays for Pavement Preservation

Concrete pavements are noted and specified for their longevity and ease of

507 SLURRY SEAL AND MICRO-SURFACING 1 of 8 CATEGORY 500 PAVING SECTION 507 SLURRY SEAL SECTION 507 SLURRY SEAL AND MICRO-SURFACING

This specification refers to the following standards, specifications, or publications:

SD95-16-G1. SD Department of Transportation Office of Research. Rural Road Condition Survey Guide

Combining Preservation Treatments

SUDAS Revision Submittal Form

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

Bridge Deck Preservation Treatment Options

Designer Supplement: AS-2-15 Approach Slab Installation January 16, 2015

ARCHITECTURAL GUIDE SPECIFICATIONS - DESCRIPTIVE

CHAPTER 11 PAVEMENT TYPE DETERMINATION

Bump Formation & Prevention

TRANSVERSE CRACKING PROGRESSION IN ASPHALT SHOULDERS ADJACENT TO CONCRETE PAVEMENTS

MICHIGAN DEPARTMENT OF TRANSPORTATION LOCAL AGENCY PROGRAMS GUIDELINES FOR GEOMETRICS

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONSTRUCTION SPECIFICATION FOR KEYHOLE EXCAVATION AND PERMANENT REINSTATEMENT OF KEYHOLE CORES TABLE OF CONTENTS

AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS

Transcription:

Concrete Pavement Preservation: Concrete Pavement Surface Restoration and Joint and Crack (Re-)Sealing Presented by: Mark B. Snyder, Ph.D., P.E. representing the National Concrete Pavement Technology Center at Iowa State University Email: mbsnyder2@gmail.com 1

Primary Source Material http://www.cptechcenter.org/technicallibrary/documents/preservation_guide_2nd_ed_50 8_final.pdf 2

Concrete Pavement Preservation and Preventive Maintenance (A Webinar Series) Part 1 The Essentials: From Pavement Evaluation to Strategy Selection - March 15 Part 2 Partial- and Full-Depth Repair Methods April 15 Part 3 Tips and Techniques for Specialized Repair and Construction Methods September 27 Includes Slab Stabilization, Slab Jacking, Dowel Bar Retrofit, Cross-Stitching and Slot Stitching, Retrofit Edge Drains Part 4 Pavement Maintenance and Preservation Using Concrete Overlays October 25 Part 5 Concrete Pavement Surface Restoration and Joint/Crack (Re)Sealing November 1 Includes Diamond Grinding and Grooving

Webinar Part 1 - Highlights What is Preventive Maintenance? Planned strategy of cost effective treatments Applied to structurally sound pavements with significant remaining life Maintain or improve functional condition What is Pavement Preservation? Network level, long-term strategy for enhancing pavement performance Focus on extending pavement life and restoring functional condition Goals accomplished with a collection of preventive maintenance treatments and a few minor rehabilitation and routine maintenance treatments

Webinar Part 1 - Highlights Pavement Evaluation Determine causes of deterioration Develop appropriate alternatives Provides quantitative information for quantity estimates, LCCA As-built info, distress surveys, NDT, sampling Strategy Selection Treatment-Distress Matrix Concurrent Treatment Sequencing Distress Slab Stabilization Partial- Slab Depth Jacking Repair Full- Depth Repair Concrete Pavement Preservation Treatment Retrofitted Edge Drains Dowel Bar Retrofit Cross Stitching/ Diamond Diamond Slot Grinding Grooving Stitching Joint Resealing Corner breaks a Linear cracking b a Punchouts Crack Sealing Thin Concrete Overlay D-cracking c c Alkali-aggregate reaction Map cracking, crazing, scaling Joint seal damage c Joint spalling Blowup Pumping Faulting Bumps, settlements, heaves Polishing/Low Friction Distress-Treatment Matrix c Concurrent Treatment Sequencing

Slab Jacking 6

Slab Stabilization vs. Slab Jacking Slab Stabilization: Pressure insertion of grout/polyurethane to fill void beneath slab Slab Jacking: Pressure insertion of grout/polyurethane to raise slab (profile restoration) Grout or polyurethane 7

Partial-Depth Repairs

Benefits Restores slab integrity Improves ride quality Extends the service life Restores a welldefined uniform joint sealant reservoir

Partial-Depth Repair Types Fig. 5.1 on p. 5.2

Diamond Grinding and Grooving

9-12 Grinding vs. Grooving Diamond grinding Removal of thin layer of concrete surface to restore smoothness and friction Diamond grooving Creation of channels in concrete pavements to reduce hydroplaning potential Typically performed in localized areas

9-13 Surface Comparison Diamond Grinding Diamond Grooving

9-14 Other Surface Textures Optimized Texture for City Streets (OTCS) Similar to diamond grinding but reduced land heights/widths Next Generation Concrete Surface (NGCS) Manufactured, low-noise surface consisting of flush grinding and grooving Cold Milling Removal of concrete layer using carbide blades

9-15 Other Texture Comparisons NGCS OTCS Cold Milling

9-16 Diamond Grinding Grinding

9-17 Diamond Grinding Potential Performance Benefits Grinding Restored smoothness (by removing builtin roughness and joint/crack faulting) Improved friction Improved cross-slope Reduced noise Typical performance life: 14-17 years

Diamond Grinding Effect on Roughness Grinding Percent decrease in IRI (new pavement): 58% (avg) Test Area Lane 1 Lane 2 Lane 3 1 59% 56% 2 53% 3 64% 60% Source: 2003 ADOT Study 4 55% Expect higher decreases for older pavements (~70% average).

Diamond Grinding Effect on Friction Grinding Percent increase in friction (new, longitudinally tined pavement): 27% Test Area Lane 1 Lane 2 Lane 3 1 25% 15% 2 18% 3 41% 35% 4 26% Source: 2003 ADOT Study

9-20 Diamond Grinding Other Advantages Can be done lane-at-a-time under a moving operation Does not affect overhead clearances No new materials introduced Limited waste Aesthetically blends patching and other irregularities into consistent surface Grinding

9-21 Diamond Grinding Project Selection Grinding Structurally sound pavement Triggers: Average faulting > 0.08 in (higher for JRCP) IRI (Roughness) > 160 to 220 in/mi Wheelpath wear > 0.25 to 0.40 in Surface friction below agency standards Excessive noise levels Consider hardness of aggregate Consider need for associated treatments (e.g., LTR) Recommended Evaluation Procedures: Distress surveys Roughness and/or friction testing

9-22 Diamond Grinding Limitations Grinding Does not address structural or durability issues Hardness of aggregate affects costs, productivity, and performance life Roughness and deterioration will re-develop if causes are not addressed Full- and partial-depth repairs Dowel bar retrofit Slab stabilization Joint resealing?

9-23 Diamond Grinding Equipment Schematic Grinding Hydraulic Cylinder Grinding Machine Frame Trailing Bogies Depth-Control Wheels Subframe Grinding Head Leading Bogies Figure 9.15 on p. 9.14

Diamond Grinding Cutting Head Specifications Grinding Diamond blades mounted in series on cutting head Cutting head width from 48 to 50 in [1,220 to 1,270 mm] Spacing of 50 to 60 blades per ft [164 to 197 blades per meter]

9-25 Diamond Grinding Cutting Head and Blades Grinding Figure 9.1 on p. 9.2

9-26 Diamond Grinding Blade and Spacer Pairings Grinding Figure 9.4 on p. 190

9-27 Diamond Grinding Blade Spacing Grinding Parameter Range Hard Agg Soft Agg Groove Width 0.09 0.15 in 0.09 0.15 in 0.09 0.15 in Land Area 0.07 0.13 in 0.07 0.11 in 0.09 0.13 in Depth 0.04 0.12 in 0.04 0.12 in 0.04 0.12 in No. of Blades 50 60/ft 53 60/ ft 50 54/ft Table 9.1 on p. 9.3

9-28 Diamond Grinding Blade Spacing Effects Grinding Correct spacing critical to achieving proper texture Hard and largesized aggregates require tighter blade spacing 52 blades/foot 60 blades/foot

9-29 Diamond Grinding Construction Considerations Grinding Mobile single-lane closure Grind parallel to centerline Max 2-in overlap (1 inch or less preferred) Maintain cross-slope of adjoining passes Limit holidays Slurry removal

9-30 Diamond Grinding Grinding Process Grinding

Diamond Grinding Grinding After First Pass of Grinding Machine

9-32 Diamond Grinding Feather Pass at Curb and Gutter Grinding Fig. 9.17 on p. 9.16

9-33 Diamond Grinding Holidays Grinding Fig. 9.16 on p. 9.15

9-34 Diamond Grinding Slurry Handling Grinding Establish slurry handling schemes prior to project (on-site or off-site) On-Site Deposit on foreslopes Avoid wetland areas and natural streams or lakes Off-Site On-board vacuums and water tankers Deposit in settlement ponds

9-35 Diamond Grinding Grinding Machine Grinding

9-36 Diamond Grinding Trucks Collecting Slurry Grinding

9-37 Diamond Grinding Finished Product Grinding

9-38 Diamond Grinding Key Factors for Success Grinding Selection of proper candidate projects Proper design (blade spacing, transverse slope, and project layout) Conduct grinding parallel to the centerline Check that overlaps are within tolerances Monitor grinding depth Verify end product meets specification Smoothness testing Friction and/or texture measurements

9-39 Troubleshooting What is wrong here? Grinding Unground Areas ( Holidays )

9-40 Troubleshooting What is wrong here? Grinding Poor Vertical Match Between Passes

9-41 Diamond Grooving Grooving

9-42 Diamond Grooving Grooving Cutting parallel grooves into the pavement using diamond saw blades Longitudinal (more common) or transverse Benefits Reduced hydroplaning potential Reduced wet-weather crashes Reductions in splash and spray

Diamond Grooving Effect on Friction Grooving WET PCCP ACCIDENT RATE (ACC/MVK) 20 15 10 5 YEARS OF OPERATION 4 3 2 1 5 6 7 7½ 8 9 Fig. 9.4 on p. 9.6 10 20 30 40 50 MILLION VEHICLE PASSAGES/LANE

9-44 Diamond Grooving Project Selection Grooving High incidence of wet-weather crashes Generally performed at localized areas Pavements should be structurally and functionally sound

9-45 Diamond Grooving Orientation Grooving Longitudinal Decreased hydroplaning potential Improved curve tracking Easier to conduct under traffic Lateral squirm of vehicles Transverse Most direct channel for water drainage Significant braking traction Difficult to conduct under traffic Noise may be an issue Common for bridge decks and airports

9-46 Diamond Grooving Design Considerations Grooving Groove entire lane area (but allow for small areas with surface irregularities) Use recommended blade spacing Saw blade thickness: 0.125 in [3.2mm] Saw blade thickness 2.5 mm Diamond Grooving 0.75-in [19mm] spacing 19 mm Fig. 9.5 on p. 9.6 Minimum Depth: 0.125 in [3.2 mm] Maximum Depth: 0.25 in [6.4 mm] 3.2 mm min

9-47 Diamond Grooving Construction Considerations Grooving Groove dimensions Direction of grooving Disposal of slurry Procedures similar to diamond grinding

9-48 Diamond Grooving Equipment Head width: 1 to 6 ft [0.3 to 1.8 m] Blade spacing: 0.75 in [19 mm] Vacuum system to collect slurry Grooving

9-49 Diamond Grooving Longitudinal Grooving Grooving

9-50 Diamond Grooving Transverse Grooving Grooving Bridge Deck Airport

9-51 Diamond Grooving Key Factors for Success Selection of proper candidate projects Proper selection of groove dimensions Selection of grooving direction Grooving

9-52 NGCS NGCS

9-53 NGCS Description NGCS Manufactured concrete pavement surface Uses conventional grinding equipment in two-phase operation: Flush grinding Grooving Can also use single-pass equipment. Combines smoothness of diamond grinding and hydroplaning reduction of grooving into a low-noise surface New and rehabilitated pavements

9-54 NGCS Equipment Head Comparisons NGCS NGCS Head (first pass) Conventional Diamond Grinding Head

9-55 NGCS Construction NGCS

9-56 NGCS Future NGCS NGCS continues to be evaluated by a growing number of highway agencies Projects in at least 9 states Benefits of low noise but also increased smoothness, improved lateral stability, and reduction in hydroplaning potential

Joint Resealing and Crack Sealing

10-58 Joint Resealing & Crack Sealing Definition Placement of an approved sealant material in an existing joint or crack to reduce moisture infiltration and prevent intrusion of incompressibles

10-59 PCC Pavement Deterioration Influence of Moisture Infiltration Cracks/Joints + Moisture Infiltration Base/Subbase Softening Loss of Fines (Pumping) Corner Breaks Transverse Joint Faulting

10-60 PCC Pavement Deterioration Influence of Moisture Infiltration Cracks + Moisture Infiltration Deteriorated Cracks Breakdown of Existing Cracks

10-61 PCC Pavement Deterioration Influence of Incompressibles Cracks/Joints + Incompressible Material Joint Spalling Blow-Ups

10-62 Joint Resealing Guidelines and Project Selection Reseal when existing sealant no longer functional Pavement not severely deteriorated In conjunction with other preservation activities If joints were originally sealed, continue to keep those joints sealed

10-63 Joint Sealing Materials Material Type Specs Description Polymerized/ Rubberized Asphalt Table 10.1 on p. 213 ASTM D6690, Type I-IV (AASHTO M324) Silicone ASTM D5893, Type NS or SL Polysulfides, polyurethane Fed Spec SS-S- 200E, type M or H Thermoplastic I: Mod climates II-III: Most climates IV: Very cold climates Thermosetting NS: Non-sag SL: Self leveling Thermosetting Preformed ASTM D2628 Polychloroprene Backer Rod ASTM D5249 For hot- or coldapplied sealants

10-64 Desirable Sealant Properties Durability Extensibility Resilience Adhesiveness Cohesiveness Resistance to traffic, moisture, sunshine, and climatic variation Deformation without rupturing Recovery from deformation and resistance to stone intrusion Resistance to debonding at joint/crack wall during elongation Resistance to internal rupture during elongation

10-65 Sealant Material Selection Factors Climatic conditions Joint/crack characteristics and spacing/density Traffic level and percent trucks Material availability and cost Joint movement Tool for estimating joint movement: http://apps.acpa.org/apps/

10-66 Backer Rod Purpose: Achieves shape factor Prevents 3-sided adhesion Use closed-cell products Must be compatible with sealant type Diameter ~25% greater than joint width Use with caution in some cases Closed-Cell Backer Rod

10-67 Example Joint Reservoir 3 to 6 mm (0.125 to 0.25 in) recess Sealant Depth (D) Width (W) Backer Rod Sealant Shape Factor = W:D Fig. 10.4 on p. 216

10-68 Joint Reservoir Design Recommended Shape Factors Sealant Material Type Typical Shape Factor (W:D) Rubberized Asphalt 1:1 Silicone 2:1 Polysulfide and Polyurethane 1:1 Table 10.2 on p. 217

10-69 Joint Reservoir Design Sealant Configurations Recessed Flush-Filled Overbanded Sealant Backer Rod See ACPA Joint Noise Estimator tool at: apps.acpa.org Fig. 10.7 on p. 218

10-70 Construction: Joint Resealing Procedures 1. Old sealant removal 2. Joint refacing 3. Joint reservoir cleaning 4. Backer rod installation 5. New sealant installation

10-71 Construction: Joint Resealing Sealant Removal Joint Plow Joint Sawing

10-72 Construction: Joint Resealing Joint Refacing

10-73 Construction: Joint Resealing Cleaning the Joint Air blasting Water blasting Sandblasting Goal: clean, dry surface with newly exposed concrete (enhanced bond)

10-74 Construction: Joint Resealing Backer Rod Installation

10-75 Construction: Joint Resealing Installed Backer Rod

10-76 Construction: Joint Resealing Sealant Installation Hot-Poured Sealant Silicone Sealant

Longitudinal Joint Resealing 10-77

10-78 Construction: Joint Resealing Longitudinal PCC/PCC Joints Lane/lane or lane/shoulder joint Tied non-working joint Shape factor not needed Hot-applied thermoplastic sealant

10-79 Construction: Joint Resealing Longitudinal PCC/HMA Joints Very difficult joint to seal Vertical movements Horizontal movements Major entry point for water infiltration Joint reservoir: Minimum width and depth of 0.75 in [19mm] No backer rod required Hot-applied and silicone sealants Some agencies simply overband

10-80 Construction: Joint Resealing Sawed Longitudinal PCC/HMA Joint

10-81 Construction: Joint Resealing Sealed Longitudinal PCC/HMA Joints

10-82 Key Factors For Success Joint Resealing Selection of candidate projects Selection of proper material Proper reservoir design and joint shape factor Proper reservoir preparation Proper sealant application techniques Monitor opening to traffic

10-83 Troubleshooting What is wrong here? Too Much Applied Sealant

10-84 Troubleshooting What is wrong here? Dirt on Refaced Surfaces

Crack Sealing 10-85

10-86 Guidelines for Sealing Cracks Leave tight, narrow cracks alone Seal working transverse cracks Can seal cracks 0.5 in [13 mm] wide Use special crack sawing blades Same general joint resealing procedures apply to crack sealing

10-87 Construction: Crack Sealing Procedure 1. Crack sawing 2. Cleaning 3. Backer rod installation 4. Sealant installation

10-88 Construction: Crack Sealing Crack Sawing

10-89 Construction: Crack Sealing Sawed Crack

10-90 Construction: Crack Sealing Completed Crack Seal

Closure A complete surface restoration strategy may encompass many techniques Spall repair, grinding, grooving, joint resealing, etc. Strategy varies with individual project needs (surface defects, friction and hydroplaning issues, etc.) Surface restoration is an effective component of pavement preservation programs. 91

Acknowledgments American Concrete Pavement Association (ACPA) Dale Harrington and the National Concrete Pavement Technology Center (CPTech Center) Kurt Smith and Applied Pavement Technology, Inc. (ApTech) John Roberts and International Grooving and Grinding Association U.S. Federal Highway Administration (FHWA) and additional agencies, consultants and academics who contributed photographs and content. 92

Primary Source Material http://www.cptechcenter.org/technicallibrary/documents/preservation_guide_2nd_ed_50 8_final.pdf 93

Questions? Presented by: Mark B. Snyder, Ph.D., P.E. Representing the National Concrete Pavement Technology Center at Iowa State University Email: mbsnyder2@gmail.com 94