Sand, Stone & Bajri Mining Project Applicant: Shri Ashish Kumar, M/s Ashish Stone Crusher. Form-1 FORM-1 SRUSHTI SEWA, NAGPUR 1

Similar documents
Annex F Scoping Checklist

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

Form -1. [Vide Notification dated 1 st December 2009] FOR PROPOSED. COSTAL ROAD AT DRONAGIRI, NAVI MUMBAI Precast RCC Bridges On Holding Ponds-

A 'N 'E B 'N 'E C 'N 'E D 'N 'E

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

Revised FORM - I & PRE-FEASIBILITY REPORT

FORM-1. Sr. No 1 Name of the Project Harbour Heights 2 S. No. in the Schedule 8(b) Townships and Area Development projects.

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

FORM I GROUP HOUSING PROJECT GH-03C, SECTOR-144 NOIDA, UP. For. M/s GULSHAN HOMES AND INFRASTRUCTURE PVT.LTD ENVIRONMENT CONSULTANT

Centrade At Plot No. 1, Sector 140, NOIDA Noida, U.P FORM- I

Sector D 1,Kanpur Road Yojna

FORM I I. BASIC INFORMATION S. No. Proposed Mixed Use Development Project SPR Binny 2 S. no. in the schedule 8 (b) 1 Name of the project

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17.

Sandipbhai Shankarbhai Patel

Jayendrasinh Bharatsinh Jadeja

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

REVISED APPENDIX I. (See paragraph - 6) FORM - 1

FORM- I. Behrampur Gurgaon. Gurgaon, Haryana

(See paragraph 6) FORM - 1

APPENDIX I. (See paragraph - 6) FORM Existi ng capacity/area etc. 1,1O,OOO Tonnes/ Area 4.8O8 Hects. I. Bhatbhera Tehsil.

APPENDIX I (See Paragraph 6) FORM 1

3 SCOPING 3.1 DEVELOPMENT OF SCOPING PROCESS Need for Scoping

Proposed Group Housing Project ATS Rhapsody At Plot No. GH 12/1, Sector -01, Greater Noida (U.P.) APPENDX (See paragr FORM 1

Prepared by. Regd. Office: January, 2013

EIA Notification of LESSEE TANT

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

Form-I for Amendment of Environmental Clearance for Meja TPP (2x660MW) Meja Urja Nigam Pvt. Limited

SCHEDULE. FORM A (Rule 3(1)) THE CERTIFICATE OF ENVIRONMENTAL CLEARANCE RULES 2001 APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL CLEARANCE

M/s Aura Buildwell Pvt. Ltd. 1

"RAMA WORLD desh. PHASE # 2" ZODIAC DEALER PRIVATE LIMITED

APPLICATION FOR ENVIRONMENTAL CLEARANCE

M/s. SREE BALAJI NIRMAN & ESTATES

FORM -1 CAPITAL CITY COMMERCIAL PROJECT. Plot No. 2B, Sector 94, Noida, District: Gautam Budh Nagar, Uttar Pradesh

Proposed Office Building at Plot no: 11 & 12 Sector 127, Noida, U.P.

Submitted to. Expert Appraisal Committee (EAC), Mumbai Maharashtra. May 2017

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

FORM 1 & 1 A. Proposed Residential Project. Sr. No. 25/2/2A Kondhwa Bk. Tal. Haveli Dist. Pune. M/s. ANISHKA DEVELOPERS PVT. LTD.

Bangalore Development Authority T. Chowdaiah Road Kumara Park West Bangalore

KOTHAGUDEM THERMAL POWER STATION (KTPS) STAGE VII (1X800 MW)

Affordable Group Housing At Village Devlawas, Sector 27, Rewari, Haryana FORM 1

Dr. NARLA TATA RAO THERMAL POWER STATION (Dr. NTTPS) STAGE V (1X800 MW)

Environmental Information Worksheet

FORM-I CORPORATE OFFICE FILM CITY PROJECT FC 24C, SECTOR-16A, FILM CITY, NOIDA, UTTAR PRADESH FOR. M/s WINDSOR CORPORATE TOWERS PVT LTD PREPARED BY

Project Proponent: M/S FAITH BUILDTECH PVT. LTD. EIA Consultant:

Form-1; Form-1A and Conceptual Plan

FORM-1, PRE FEASIBILITY REPORT ENVIRONMENT MANAGEMENT PLAN FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EIA for Proposed Redevelopment Activities of Cochin Port Trust at Cochin Port, Willingdon Island In Ernakulam District, Kerala UPDATED FORM-1

Environmental Impact Assessment of Hydroelectric Power Plant LEEZA MALIK (2013CEP2080) TUSHAR SINGLA (2011MT50623)

GRANULES INDIA LIMITED SY. NO. 533, 535 & 536, BONTHAPALLY VILLAGE, JINNARAM MANDAL, MEDAK DISTRICT, TELANGANA FORM I

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

Environmental Assessment Matrix

Florida Department of Environmental Protection. Bureau of Mining and Minerals Regulation. Regulation of Mines. Howard J. Hayes, Program Administrator

Environmental Management Plan (EMP)

PROJECT FEASIBILITY REPORT

Summary of Preparatory Study

Prepared by: Vardan Environet, Gurgaon

Application for Gas Exploration and Production

Wetland Permit Application

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

CMPDI. 4.6 Mine Closure Plan

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

Regulatory Requirements for Site Approval Permit of Nuclear Power Plants

Expansion in. Environment Clearance Application. Shopping Mall. Mall of India

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Hubert Enviro care systems Pvt. Ltd.

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

PRE-FEASIBILITY REPORT

STANDARD OPERATING PROCEDURE

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

Appendix 3 The World Bank s New Operational Manual

CHAPTER 3 POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

Federal Regulation. Copyright 2011 Gary A. Robbins. All rights reserved.

LIFELINE ROAD NETWORK IMPROVEMENT PROJECT ENVIRONMENTAL MANAGEMENT PLAN FOR SMALL SCALE ROAD REHABILITATION

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

Conservation and Reclamation INFORMATION LETTER. Environmental Protection Guidelines for Oil Production Sites - Revised January 2002

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

Sec Abandonment of Certain Oil/Gas Land Uses. (Added by Ord. 4551, 9/21/04)

Guidance on use of Disposal and Recovery Codes (Waste Management Act, 1996 as amended)

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

7. NATURAL HAZARDS 7.1 SECTION INTRODUCTION

Base Metal and Iron Ore Mining

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres )

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

Proposed New 18 CFR Part Hydraulic Fracturing in Shale and Other Formations:

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

Chapter 10 Natural Environment

General Permit No.: OHR Page 53 of 146

Erosion & Sedimentation Control Policy

TWIN PLATTE NATURAL RESOURCES DISTRICT

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

Transcription:

FORM-1 SRUSHTI SEWA, NAGPUR 1

FORM 1 (I) Basic Information S.. Item Details 1. Name of the project/s Sand, Stone and Bajri Mining Project 2. Serial. in the schedule 1(a) Mining of Mineral 3. Proposed capacity /area /length /tonnage to be handled/command area/lease area/number of wells to be drilled 4. New/Expansion/Modernization New The area of the proposed mine is 10.54 Ha (125-01 Bighas) and the proposed production will be 101250 TPA of Sand, Stone & Bajri. 5. Existing Capacity/Area etc. Area: 10.54 Ha (125-01 Bighas) Capacity: 101250 TPA 6. Category of Project i.e. A or B Category B2 7. Does it attract the general condition? If yes, please specify. 8. Does it attract the specific condition? If yes, please specify. 9. Location Pillar Co-ordinates A Latitude: 30 29'49"N Longitude: 77 40'39"E B Latitude: 30 29'40"N Longitude: 77 40'56"E Plot/Survey/Khasra. Khasra. 250/228/4/3 & 250/228/4/4 Mouza/ Mohal Tehsil District State 10. Nearest railway station/airport along with distance in km. 11. Nearest Town, city, District Headquarters along with distance in kms. Mauza Bangran Paonta Sahib Sirmour Himachal Pradesh Dehradun Railway Station is about 40 km in SE direction. Airport: Jolly Grant Airport, Dehradun is about 50 km in SE direction. Town: Paonta is about 7 Km in SW direction. District Head Quarter: Nahan is about 40 Km in West direction. 12. Village Panchayats, Zilla Parishad, Panchayat-Phoolpur SRUSHTI SEWA, NAGPUR 2

Municipal Corporation, Local body (complete postal addresses with telephone nos. to be given) Village-Bangran P.O.-Bangran Tehsil-Paonta Sahib District-Sirmour Himachal Pradesh 13. Name of applicant Shri Ashish Kumar 14. Registered Address S/o Shri Anand Kumar, 15. Address for correspondence Name Designation (Owner/Partner/CEO) Address 186/10, P.O. Devinagar, Tehsil Paonta Sahib, District Sirmour, Himachal Pradesh Shri Ashish Kumar Owner S/o Shri Anand Kumar, 186/10, P.O. Devinagar, Tehsil Paonta Sahib, District Sirmour, Himachal Pradesh Pin Code 173025 E-mail Telephone. 9418089511 Fax. -- 16. Details of Alternative Sites examined, if any. Location of these sites should be shown on a Toposheet. 17. Interlinked Projects 18. Whether separate application of interlinked project has been submitted? 19. If yes, date of submission -- stonecrusherashish@gmail.com alternate site has been examined for proposed project as the lease has been granted for this particular site only. 20. If no, reason t Applicable (The stone crusher does not come under the SRUSHTI SEWA, NAGPUR 3

21. Whether the proposal involves approval/ clearance under: if yes, details of the same and their status to be given. (a)the Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (C) The C.R.Z tification, 1991? 22. Whether there is any Government Order/Policy relevant/relating to the site? purview of the EIA notification) 23. Forest land involved (hectares) 24. Whether there is any litigation pending against the project and /or land in which the project is propose to be set up? (a) Name of the Court (b) Case. (c) Orders/directions of the Court, if any and its relevance with the proposed project. (II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S.. Information/Checklist confirmation Yes/ 1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) quantities /rates, wherever possible) with The area is river bed and mined out pit will be completely filled during rainy season hence there would be no change in the topographical features and land use pattern. SRUSHTI SEWA, NAGPUR 4

1.2 Clearance of existing land, vegetation and buildings? There is no built-up structure in the lease area. So no clearance of existing land and vegetation is required. 1.3 Creation of new land uses? The mining lease area is confined only to the perennial Giri River, and the area will remain as river after mining. 1.4 Pre-construction investigations e.g. Pre-construction investigation has been bore houses, soil testing? performed. 1.5 Construction works? Yes Construction of check dam is proposed at vulnerable locations. 1.6 Demolition works? demolition work has been proposed. 1.7 Temporary sites used for construction Yes Local people will be hired for excavation works or housing of construction purpose; hence no permanent housing will be workers? required. However provision for temporary rest shelters will be made. 1.8 Above ground buildings, structures or -- earthworks including linear structures, cut and fill or excavations 1.9 Underground works including mining -- or tunneling? 1.10 Reclamation works? Yes Plantation in consultation with the experts will be raised, based on the characteristics of soil, topography and climatic conditions. Check Dams Check Dams has been proposed at some vulnerable points to protect banks. 1.11 Dredging? dredging will be done. 1.12 Offshore structures? t required for this project. 1.13 Production and manufacturing production and manufacturing process is processes? involved at the site. 1.14 Facilities for storage of goods or The applicant intends to mine Sand, Stone materials? and Bajri from the lease area. The stone, after being sieved would be sold for construction SRUSHTI SEWA, NAGPUR 5

industry depending upon the market demand. 1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes The Silt/Sand-clay Mixture which has been shown as the waste material shall not be dumped at the land of mining lease area, as the same shall be screened at the crusher site and the silt which shall be socked is also saleable, which is used for filling works. 1.16 Facilities for long term housing of operational workers? Workers will be hired/ employed locally from the nearby villages for the mining activity. Thus no housing facility will be developed near mine site. 1.17 New road, rail or sea traffic during construction or operation The site already has sufficient approach roads hence it is not proposed to construct new roads. 1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc? t required for the operation of this project. 1.19 Closure or diversion of existing There would be no closure or diversion of transport routes or infrastructure existing routes, which would change the leading to changes in traffic traffic movements. movements? 1.20 New or diverted transmission lines or pipelines? t required for the operation of this project. 1.21 Impoundment, damming, culverting, t required for the operation of this project. realignment or other changes to the hydrology of watercourses or aquifers? 1.22 Stream crossings? stream crossings are involved. 1.23 Abstraction or transfers of water from ground or surface waters? Yes The project requires 2.0 KLD as daily water demand. 1.5 KLD water will be required for dust suppression and about 0.5 KLD water will be required for drinking & domestic purpose. SRUSHTI SEWA, NAGPUR 6

1.24 Changes in water bodies or the land surface affecting drainage or run-off? 1.25 Transport of personnel or materials for construction, operation or decommissioning? 1.26 Long-term dismantling or decommissioning or restoration works? 1.27 Ongoing activity during decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either temporarily or permanently? --- -- There will be no change in the land surface affecting drainage or run-off as mining will be limited within river bed. In the operation phase Sand, Stone and Bajri will be excavated manually and loaded directly into tractor-trolley to the Stone Crusher and then finished product transported to local markets. Mostly local people will be deployed locally to carry out the mining operations. So no influx of people will be seen. 1.29 Introduction of alien species? Yes The vehicles used for transportation of 1.30 Loss of native species or genetic diversity? 1.31 Any other actions? -- minerals have chances of carrying spores/seeds which is not native to lease area. As such no loss of native species or genetic diversity is expected. 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): S.. Information/checklist confirmation Yes/ quantities /rates, wherever possible) with 2.1 Land especially undeveloped or The activity will be done in the proposed agricultural land (ha) 2.2 Water (expected source & competing users) unit: KLD Yes mine lease area. The total mine lease area is situated in Giri river, and hence no agricultural land is involved. The project requires 2.0 KLD as daily water demand. 1.5 KLD water will be required for dust suppression and about 0.5 KLD water will be required for drinking & domestic SRUSHTI SEWA, NAGPUR 7

purpose. 2.3 Minerals (MT) There will be no mineral/material is required 2.4 Construction material stone, aggregates, sand/ soil (expected source MT) 2.5 Forests and timber (source MT) -- 2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW) 2.7 Any other natural resources (use appropriate standard units) for the operation of the project. During construction of dams Stone, Yes -- Aggregates, and Sand is required. The demand will be full filled by project itself. Diesel will be required for operation of tractor and electricity for crusher operation. 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S.. Information/Checklist confirmation Yes/ 3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by changing living conditions? 3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc., quantities/rates, wherever possible) with This project operation will not involve any hazardous materials. As such there will be no change in occurrence of disease however poisonous bites may affect the health of the workers which can be prevented by anti-venom injections. Proposed project will provide employment to the nearby villagers and hence is going to uplift the living standard of the people. It will not affect the welfare of people. This project will not affect the vulnerable groups of people. 3.5 Any other causes Yes Accidents may occur, which may be avoided by taking due care & precautions as SRUSHTI SEWA, NAGPUR 8

transportation is one of the major activities of this project. 4. Production of solid wastes during construction or operation or decommissioning (MT/month) S.. Information/Checklist confirmation Yes/ quantities/rates, wherever possible) with 4.1 Spoil, overburden or mine wastes Yes About 937.5 MT/month Waste will be 4.2 Municipal waste (domestic and or commercial wastes) 4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes generated during mine life. Waste contains Silt/ Sand-Clay Mixture which does not have any market value. Very insignificant quantity of domestic waste will be generated by the labors at site. Hazardous wastes (as per Hazardous Waste Management Rules) will be generated. 4.4 Other industrial process wastes There is no industrial process involved in the project. 4.5 Surplus product The entire mined out product will be sold to 4.6 Sewage sludge or other sludge from effluent treatment the consumer. There is no effluent treatment plant in the proposed project. 4.7 Construction or demolition wastes construction or demolition work involved. 4.8 Redundant machinery or equipment There will be no redundancy of machineries, as the mining is manual and the machineries involved are simple hand tools. 4.9 Contaminated soils or other materials contamination of soil or other material will be involved. 4.10 Agricultural wastes There is no agricultural waste involved. 4.11 Other solid wastes other solid waste is generated. 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.. Information/Checklist confirmation Yes/ 5.1 Emissions from combustion of fossil Yes fuels from stationary or mobile sources quantities/rates, wherever possible) with There will be emissions due to burning of fuels from vehicles used for transportation of minerals from site to the crusher. SRUSHTI SEWA, NAGPUR 9

5.2 Emissions from production processes Yes Dust emission is expected during excavation of the mineral from the stream bed but in a very minimal quantity. 5.3 Emissions from materials handling including storage or transport 5.4 Emissions from construction activities including plant and equipment 5.5 Dust or odors from handling of materials including construction materials, sewage and waste Yes Yes Dust emission is expected during handling of minerals i.e. during loading and transportation. construction activity is involved in this project. Dust emission is expected during handling of minerals i.e. during loading and transportation. 5.6 Emissions from incineration of waste There will be no incineration of any waste. Hence no emission is expected. 5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) There will be no burning of waste. 5.8 Emissions from any other sources Yes Stone and Bajri will be sent to the crusher unit. Emission of dust is expected from the crusher unit. 6. Generation of ise and Vibration, and Emissions of Light and Heat S.. Information/Checklist confirmation Yes/ 6.1 From operation of equipment e.g. engines, ventilation plant, crushers 6.2 From industrial or similar processes -- 6.3 From construction or demolition -- quantities/rates, wherever possible) with Yes Mining will be done manually. ise generation is expected from the proposed crusher unit and from operation of tractor. 6.4 From blasting or piling Blasting and Piling is not proposed for the mining process. 6.5 From construction or operational traffic Yes ise will be generated only from vehicular movement during transportation. 6.6 From lighting or cooling systems Mining will be carried out during day time only and in open area. Thus there is no need SRUSHTI SEWA, NAGPUR 10

for lighting and cooling systems. 6.7 From any other sources Yes ise generation is expected from the proposed crusher unit which lies outside the lease area. 7. Risks of contamination of land or water from release of pollutants into ground or into sewers, surface waters, groundwater, coastal waters or the sea: S.. Information/Checklist confirmation Yes/ 7.1 From handling, storage, use or spillage of hazardous materials 7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) 7.3 By deposition of pollutants emitted to air into the land or into water -- Yes 7.4 From any other sources -- 7.5 Is there a risk of long term build up of pollutants in the environment from these sources? quantities/rates, wherever possible) with hazardous material will be used at the project site. Only dust emission is expected into air due to movement of vehicles. However dust suppression will be done by sprinkling of water. Only dust will be generated, which would be suppressed by water sprinkling. Hence there is no risk of long term build up of pollutants in the environment. 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S.. Information/Checklist confirmation Yes/ 8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances -- quantities/rates, wherever possible) with 8.2 From any other causes Yes Risk of accidents are expected: 1. During transportation. 2. During loading of minerals into tractors. Efforts will be made to minimize the SRUSHTI SEWA, NAGPUR 11

8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes accidents ensuring due care and operations and will try to maintain the vehicle movement at slow speed. The mine lease area lies in Seismic Zone IV which is prone to earthquakes. However there is no built-up structure within the lease area which would affect the mining. 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S.. Information/Checklist confirmation Yes/ quantities/rates, wherever possible) with 9.1 Lead to development of supporting Yes Proposed project will result in development facilities ancillary development or development stimulated by the project which could have impact on the environment e.g. Supporting infrastructure (roads, power supply, etc.) waste or waste water treatment, Housing development Extractive industries Supply industries Other 9.2 Lead to after-use of the site, which could have an impact on the environment of living standards of the surrounding area by increasing direct and indirect employment opportunities in the region. The site will not be used for any other purpose other than mining, which would create any impact on the environment. 9.3 Set a precedent for later developments Yes A better after use scenario, which is likely to 9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects increase aesthetic beauty of the area by doing plantation. major industries except few mines of mineral are located in the 10 km area. Thus there is likelihood of cumulative effect due to the transportation of mineral. SRUSHTI SEWA, NAGPUR 12

A better planned and executed project has to yield a better result individually; which in turn has to give better cumulative effect also. (III) Environmental Sensitivity S.. Areas Name / Identity 1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or underground waters Asan Barrage Conservation Reserve Giri River Yamuna River Nil -- Nil -- 5 State, National boundaries Interstate boundary 6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas of H.P. and Uttarakhand SH-01 NH-72 B 7 Defense installations Nil --- Aerial distance (within 15 km) Proposed project location boundary About 5 km away in SW direction Project itself lies on this River. About 5 km away in South direction. About 4.5 km away from the proposed lease area. About 0.5 km in rth direction. About 3.0 km in West direction. 8 Densely populated or built-up area Paonta Sahib Vikasnagar Dakpatthar Phoolpur About 7 km in SW direction. About 10 km in SE direction. About 11.5 km in East direction. About 1 km in SW direction. SRUSHTI SEWA, NAGPUR 13

9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) 10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Puruwala Bangran Naraingarh Kanshipur About 1.5 km in NE direction. About 1 km in NW direction. About 4 km in SW direction. About 3 km in SW direction. Paonta Sahib About 7 km in SW direction. Vikasnagar About 10 km in SE direction. Dakpatthar About 11.5 km in East direction. Phoolpur About 1 km in SW direction. Puruwala About 1.5 km in NE direction. Bangran About 1 km in NW direction. Naraingarh About 4 km in SW direction. Kanshipur About 3 km in SW direction. Giri River Project itself lies on this River. Yamuna River About 5 km away in SE to SW direction. Nil -- Earthquake The mine area lies in Seismic Zone IV, which is prone to earth quakes. SRUSHTI SEWA, NAGPUR 14